Time
SCHEDULE OF ACTIVITIES F
Land on lease
20 Days 20 Days 20
Land on lease
Company Registration
INTIAL GESTA
Company Registration
Approval & Sanction Lo
8/12/2019 Neera
2/32
8/12/2019 Neera
3/32
Sr. No.
Particulars Quantity Unit Cost Value of
Raw
material Sr. No.
Particulars Quantity
1
Freshly
tapped
Neera
600,000 8 4,800,000 1
Freshly
tapped
Neera
600,000
2
Preservativ
es and
Nutrients
840,000 2
Preservativ
es and
Nutrients
3 Packaging 5,040,000 3 Packaging
Total 10,680,000 Total
Sr. No.
Particulars Quantity Unit Cost Value of
Raw
material Sr. No.
Particulars Quantity
1
Freshly
tapped
Neera
600,000 10.65 6,388,800 1
Freshly
tapped
Neera
600,000
2
Preservativ
es and
Nutrients
1,286,400 2
Preservativ
es and
Nutrients
3Packaging
7,680,000 3Packaging
Total 15,355,200 Total
Raw Materials For 1st year Raw Materials Fo
Raw Materials For 4th year Raw Materials Fo
8/12/2019 Neera
4/32
8/12/2019 Neera
5/32
totaltransport
cost
incurred
1,800,000
2,100,000
2,400,000
2,700,000
3,000,000
8/12/2019 Neera
6/32
SR no Particulars Units
1 Building
Land 4000
Civil works Process area 1500
Laboratory 150
Office area 150
Storage area 1000Utility area 500
Workers amenity 200
TOTAL 3500
TOTAL
2 Plant and Machinery
Quick Chiller @2500lt,4deg C 1
Filter(Microfilter ) 1
Storage tank 2500lt 1
Industrial Centrifuge 300lph 1
Interim storage tank 2500lt 1
Pasteurisation unit 300lph,150degC 1Measurement instruments 5
Refrigirator,500ltr 3
Automatic filling machine 1
Cap sealing machine 1
Batch coding machine 1
Electronic weighting machine 1
Diesel [email protected] KVA 1
TOTAL 19
3 Office Furniture
4 Pumps,pipes and fittings
5 Installation and labour
6 Miscellaneous Design,SS utensils,Exhaust fans
Electric fittings
7 Preliminary Expenses
8 Initial working capital exp
Total Capital Expenditure
8/12/2019 Neera
7/32
Unit price Total cost
175 700,000.00
1000 1,500,000.00
1000 150,000.00
1000 150,000.00
1000 1,000,000.001000 500,000.00
1000 200,000.00
3,500,000.00
4,200,000.00
400000 400,000.00
200000 200,000.00
200000 200,000.00
800000 800,000.00
200000 200,000.00
300000 300,000.0010000 50,000.00
30000 90,000.00
500000 500,000.00
300000 300,000.00
200000 200,000.00
25000 25,000.00
700000 700,000.00
3,965,000.00
50,000.00
200,000.00
300,000.00
500,000.00
300,000.00 Gross Block
9,215,000
1,691,117.54
11,206,117.54
8/12/2019 Neera
8/32
Serial
NumberLabour Number Unit Cost
Total Cost
(Per
Month)
Total Cost
(Per
Annum
Year 1)
Unit Cost
YR 2
Total Cost (Per
Annum Year 2)
Unit Cost
YR 3
1
Plant
supervisor 1 10,000 10,000 120,000 11000 132,000 12000
2Machineoperator 5 10,000 50,000 600,000 11000 660,000 12000
3 Chemist 1 10,000 10,000 120,000 11000 132,000 12000
4
Neera
Tappers 40 10,000 400,000 4,800,000 11000 5,280,000 12000
Sub Total 47 5,640,000 6,204,000
8/12/2019 Neera
9/32
Total Cost (Per
Annum Year 3)
Unit Cost
YR 4
Total Cost (Per
Annum Year 4)
Unit Cost
YR 5
Total Cost
(Per
Annum
Year 5)
144,000 13000 156,000 14000 168,000
720,000 13000 780,000 14000 840,000
144,000 13000 156,000 14000 168,000
5,760,000 13000 6,240,000 14000 6,720,000
6,768,000 7,332,000 7,896,000
8/12/2019 Neera
10/32
Sr NoMachine
Name
Number
of
machines
(HP)
connecte
d
kW/Units
per hour
Total
working
hours per
day
Rate per
unit for
1st year
Cost per
day for
1st year
Working
days per
year
1Quick
Chiller 1 0.75 0.5595 8 6.5 29.094 300
2 Filter 1 0.25 0.1865 8 6.5 9.698 300
3Industrial
centrifuge 1 15 11.19 8 6.5 581.880 300
4 Pasteurisa
tion unit 1 1.5 1.119 8 6.5 58.188 300
5
Auotomat
ic Filling
m/c 1 2.5 1.865 8 6.5 96.980 300
6
Cap
sealing
M/c 1 2 1.492 8 6.5 77.584 300
7
batch
coding
M/c 1 0.25 0.1865 8 6.5 9.698 300
8
Refrigrato
r 500Ltr 3 4.5 3.357 8 6.5 174.564 300
TOTAL 26.75
8/12/2019 Neera
11/32
Total cost
incurred
in 1st
year
Rate per
unit for
2nd year
Total cost
incurred
in 2nd
year
Rate per
unit for
3rd year
Total cost
incurred
in 3rd
year
Rate per
unit for
4th year
Total cost
incurred
in 4th
year
Rate per
unit for
5th year
Total cost
incurred
in 5th
year
8,728 7.0 9,339 7.5 10,071 8.0 10,776 8.5 11,414
2,909 7.0 3,113 7.5 3,357 8.0 3,592 8.5 3,805
174,564 7.0 186,783 7.5 201,420 8.0 215,519 8.5 228,276
17,456 7.0 18,678 7.5 20,142 8.0 21,552 8.5 22,828
29,094 7.0 31,131 7.5 33,570 8.0 35,920 8.5 38,046
23,275 7.0 24,904 7.5 26,856 8.0 28,736 8.5 30,437
2,909 7.0 3,113 7.5 3,357 8.0 3,592 8.5 3,805
52,369 7.0 56,035 7.5 60,426 8.0 64,656 8.5 68,483
311,306 333097 359199 384343 407092
8/12/2019 Neera
12/32
Serial
Number Labour Units Unit Cost
Total Cost
(Per Month)
Total Cost (Per
Annum Year 1)
1 Watchman 1 5,000.00 5,000.00 60,000.00
2 Salesman 2 7,000.00 14,000.00 168,000.00
3 Selling & marketing exp. 3,352,160.00
4 Project manager 1 20,000.00 20,000.00 240,000.00
5 Office supplies 2,500.00 30,000.00
6 Insurance 20,000.00
7 Maintenance cost 15,000.00
8 Office Assistant 1 10,000.00 10,000.00 120,000.00
9 Director's salary 4 25,000.00 100,000.00 1,200,000.00
Total 5,205,160.00
8/12/2019 Neera
13/32
Total Cost (Per
Annum Year 2)
Total Cost (Per
Annum Year 3)
Total Cost (Per
Annum Year 4)
Total Cost (Per
Annum Year 5)
66,000.00 72,600.00 79,860.00 87,846.00
184,800.00 203,280.00 223,608.00 245,968.80
3,591,600.00 3,831,040.00 3,831,040.00 4,070,480.00
264,000.00 290,400.00 319,440.00 351,384.00
33,000.00 36,300.00 39,930.00 43,923.00
20,000.00 20,000.00 20,000.00 20,000.00
16,500.00 18,150.00 19,965.00 21,961.50
132,000.00 145,200.00 159,720.00 175,692.00
1,320,000.00 1,452,000.00 1,597,200.00 1,756,920.00
5,627,900.00 6,068,970.00 6,290,763.00 6,774,175.30
8/12/2019 Neera
14/32
Depreciation as per companies act 2013
Particular Rate Cost
1st
year(2015) 2nd year 3rd year 4th year
Civil work 10.00% 3,500,000.00 350,000.00 315,000.00 283,500.00 255,150.00
Plant & Machinery 13.91% 3,965,000.00 551,531.50 474,813.47 408,766.91 351,907.44
Office Furniture 18.10% 50,000.00 9,050.00 7,411.95 6,070.39 4,971.65
Depreciation 7,515,000.00 910,581.50 797,225.42 698,337.30 612,029.08
Depreciation as per IT act
Particular Rate Cost
1st
year(2015) 2nd year 3rd year 4th year
Civil work 10.00% 3,500,000.00 350,000.00 315,000.00 283,500.00 255,150.00
Plant & Machinery 15.00% 3,965,000.00 594,750.00 505,537.50 429,706.88 365,250.84
Office Furniture 10.00% 50,000.00 5,000.00 4,500.00 4,050.00 3,645.00
Depreciation 949,750.00 825,037.50 717,256.88 624,045.84
8/12/2019 Neera
15/32
5th year
229,635.00
302,957.11
4,071.78
536,663.89
5th year
229,635.00
310,463.22
3,280.50
543,378.72
8/12/2019 Neera
16/32
Particulars Percentage Amount
Owner's Capital 30% of FA 2,764,500
Term loan 70% of FA 6,450,500
Total 9,215,000
Working capital financing
1st year 2nd year 3rd year
Particulars
Cash credit 1,268,338 899,475 0
Owner's contribution 422,779 899,475 1,904,007
Total 1,691,118 1,798,950 1,904,007
Total capital expenditure
generated 10,906,118
Fixed assests financing
8/12/2019 Neera
17/32
fixed assest
financing 2,764,500
PreliminaryExpenses 100,000
WC financing 422,779
Total 3,587,279
4th year 5th year
0 0
1,963,394 1,983,636
1,963,394 1,983,636
Total of Owner's Capital
8/12/2019 Neera
18/32
Serial Number Particulars Period(days) Year 1(70 % Capacity)
1 Current Assets
Raw Material 1 35,600
Finished Goods 7 509,518
Debtors 15 1,680,000
Total 2,225,118
2 Current Liabilities
Creditors 15 534,000Total 534,000
Net Working Capital Requirement 1,691,118
Bank finance(maximum 75%) at 14% 1,268,338
Owner's contribution(25%) 422,779
Interest on working capital 14% 177,567
8/12/2019 Neera
19/32
Year 2(75% Capacity) Year 3(80% Capacity) Year 4(80% Capacity) Year 5(85% Capacity)
40,700 46,272 51,184 58,310
568,750 631,815 759,970 759,970
1,800,000 1,920,000 1,920,000 2,040,000
2,409,450 2,598,087 2,731,154 2,858,280
610,500 694,080 767,760 874,644610,500 694,080 767,760 874,644
1,798,950 1,904,007 1,963,394 1,983,636
899,475 - - -
899,475 1,904,007 1,963,394 1,983,636
125,926 - - -
8/12/2019 Neera
20/32
8/12/2019 Neera
21/32
8/12/2019 Neera
22/32
Particulars
Amount per
year 1 (in
Rs.)
Amount per
year 2 (in
Rs.)
Amount per
year 3 (in Rs.)
Opening Stock of Raw Materials 0 0 0
Add Purchase of Raw Material 10,680,000 12,210,000 13,881,600
Add Purchasing Expenses on Raw Material 1,800,000 2,100,000 2,400,000Less Closing Stock of Raw Materials 0 0 0
RAW MATERIAL CONSUMED 12,480,000 14,310,000 16,281,600
Add Direct Wages 5,640,000 6,204,000 6,768,000
PRIME COST 18,120,000 20,514,000 23,049,600
Add Factory Overheads 311,306 333,097 359,199
Add opening WIP 0 0 0
Less Closing WIP 0 0 0
WORKS COST/Factory cost 18,431,306 20,847,097 23,408,799
Add Administration Overheads 0 0 0
COST OF PRODUCTION 18,431,306 20,847,097 23,408,799Add Opening Stock of Finished Goods 0 509,518 568,750
Less Closing Stock of Finished Goods 509,518 568,750 631,815
COST OF GOODS SOLD 17,921,788 20,278,347 22,776,984
Add SGA 5,205,160 5,627,900 6,068,970
COST OF SALES 23,126,948 25,906,247 28,845,954
SALES 33,521,600 35,916,000 38,310,400
Cost Sheet
8/12/2019 Neera
23/32
8/12/2019 Neera
24/32
Total per unit Total per unit
R.M. 10,680,000 6.372 12,210,000 6.799
Labour 5,640,000 3.365 6,204,000 3.455
Electricity 311,306 0.186 333,097 0.185Overheads 5,205,160 3.106 5,627,900 3.134
Total variable cost 21,836,466 13.028 24,374,997 13.573
S.P. 20.000 20.000
Contribution 11,685,134 6.972 11,541,003 6.427
Total Contribution
Fixed Cost
BEP (Period)
Particulars
9,989,060 8,923,667
11,685,134.20 11,541,002.79
MARGIN
Year 1 Year 2
8/12/2019 Neera
25/32
Total per unit Total per Unit Total per Unit
13,881,600 7.247 15,355,200 9.132 17,492,880 8.595
6,768,000 3.533 7,332,000 4.122 7,896,000 3.880
359,199 0.188 384,343 0.21 407,092 0.2006,068,970 3.168 6,290,763 3.536 6,774,175 3.328
27,077,769 14.136 29,362,306 17.003 32,570,148 16.003
20.000 20.000 20.000
11,232,631 5.864 5,740,253 2.997 8,134,653 3.997
10 months 6 days
7,971,629 7,118,480 6,351,639
11,232,631.00 5,740,252.50 8,134,652.50
AL COSTING
Year 3 Year 4 Year 5
8/12/2019 Neera
26/32
Term Loan Interest
6,450,500 12.00%
Year Interest Loan yet to be repaid Principal repayment
1 774,060 5,160,400 1,290,1002 619,248 3,870,300 1,290,100
3 464,436 2,580,200 1,290,100
4 309,624 1,290,100 1,290,100
5 154,812 - 1,290,100
Year Short term loan ( Interest rate Interest payment
1 1,268,338 14% 177,567
2 899,475 14% 125,926
8/12/2019 Neera
27/32
8/12/2019 Neera
28/32
Year 5
6,196,826.70
536,663.89
5,660,162.80
8/12/2019 Neera
29/32
SR.NO PARTICULARS Year 1 Year 2 Year 3
1 INCOME
Sales 33,521,600 35,916,000 38,310,400
NET SALES 33,521,600 35,916,000 38,310,400
2 EXPENDITURE
Raw Materials 10,680,000 12,210,000 13,881,600
Tranportation 1,800,000 2,100,000 2,400,000
Wages 5,640,000 6,204,000 6,768,000
Power 311,306 333,097 359,199
SGA 5,205,160 5,627,900 6,068,970
Total 23,636,466 26,474,997 29,477,769
3 PROFIT BEFORE INTEREST, DEP and TAX. 9,885,134 9,441,003 8,832,631
Depreciation 910,582 797,225 698,337PROFIT BEFORE INTEREST and TAX. 8,974,553 8,643,777 8,134,294
4 less: Interest on term loan 774,060 619,248 464,436
less: Interest on WC 1,268,338 899,475 0
5 PROFIT BEFORE TAX 6,932,155 7,125,054 7,669,858
Tax(32.4%) 2,246,018 2,308,518 2,485,034
6 PROFIT AFTER TAX 4,686,136 4,816,537 5,184,824
7 DIVIDEND 0 179,364 358,728
8 DDT (@15%) 0 26,905 53,809
9 TRANSFER TO RESERVES AND SURPLUS 1,171,534 1,204,134 1,296,206
10 To Net Profit 3,514,602 3,406,134 3,476,081
PROJECTED PROFIT AND LOSS ACCOUNT
8/12/2019 Neera
30/32
Year 4 Year 5
38,310,400 40,704,800
38,310,400 40,704,800
15,355,200 17,492,880
2,700,000 3,000,000
7,332,000 7,896,000
384,343 407,092
6,290,763 6,774,175
32,062,306 35,570,148
6,248,094 5,134,653
612,029 536,6645,636,065 4,597,989
309,624 154,812
0 0
5,326,441 4,443,177
1,725,767 1,439,589
3,600,674 3,003,587
179,364 179,364
26,905 26,905
900,169 750,897
2,494,237 2,046,422
8/12/2019 Neera
31/32
Particulars Amount
Total equity (Rs.) 3,587,279 % of face value
Face value of each share (Rs.) 1 Dividend per promoter
Total shares 3,587,279 Total dividend payout
Number of promoters 4
Shares per promoter 896,820
SHAREHOLDING PATTERN
8/12/2019 Neera
32/32
Year 1 Year 2 Year 3 Year 4 Year 5
0% 5% 10% 5% 5%
- 44,841 89,682 44,841 44,841
- 179,364 358,728 179,364 179,364
DIVIDEND PAYOUT