NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

Embed Size (px)

Citation preview

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    1/28

    NICMAR PGPM 24

    Page 1 of 28 SUBMITTED BY : SOMDATT

    PROJECT MANAGEMENT I POWER PLANTS & ENGINEERING

    1. Course No. : PGPPM - Module 56

    2. Course Title : Project ManagementI Power Plants & Engineering

    3. Assignment No. : PGPM 24

    4. Date of Dispatch : 3thSeptember. 2014

    5. Last Date of Receipt : 5thSeptember. 2014 (At CODE Office)

    Project ManagementI Power Plants & Engineering

    Submitted By :-

    Name : SOMDATT

    Registration No. : 213-10-31-11813-2154

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    2/28

    NICMAR PGPM 24

    Page 2 of 28 SUBMITTED BY : SOMDATT

    1.0 INTRODUCTION

    Energy is an essential input for the economic development of a country in improving the

    quality of life of its people. For meeting the growing energy needs of the society at a

    reasonable cost, power development in India started at the end of the 19th century. Tocontribute significantly to the overall energy availability in the country, sustained attention is

    being given to develop and promote non-conventional, alternate and renewable sources of

    energy as also for the development of nuclear energy.

    Today the installed power generation capacity in the country has increased from 1,400 MW in

    1947 to 1,04,917.50 MW at the end of 2001-02 comprising 26,261.22 MW hydro, 74,428.82

    MW thermal (including gas and diesel), 1,507.46 MW wind and 2720 MW nuclear. In spite

    of this increase in installed capacity, the energy shortage in India is of the order of

    approximately 9 per cent. The peak shortage of power averages almost 15 per cent.

    The per capita consumption of the power in the country is only 350 units much below the

    consumption levels in development countries. In order to provide power to all by 2012,

    additional capacity of 100,000 MW will have to be set up in the next decade. Capacity

    addition plans for 41,110 MW have been finalized State-wise and project wise for the Tenth

    Plan period (2002-07). In the central sector, State sector and private sector the capacity

    addition would be 22,832 MW, 11,157 MW and 7,121 MW respectively. For the year 2002-

    03, a capacity addition programme of 4109.10 MW has been fixed. The power generation

    during 2001-02 was 515.271 BUs comprising 422.001 BUs thermal, 73.992 BUs hydro and

    19.278 BUs nuclear. The target of power generation for 2002-03 has been fixed at 545.552

    BUs. The plant load factor has shown a steady improvement over the years and has improved

    from 52.8 per cent in 1990-91 to 69.9 percent in 2001-02.

    To achieve the target of providing power to all by 2012, the Center has initiated a number of

    steps with the help of the States. These include a programme initiated by the power Ministry

    for accelerated and planned hydro development after an overall assessment and prioritization

    with a view to harness an unharnessed estimated hydro potential of more than 150,000 MW

    and attain the ideal hydro thermal mix ratio of 40:60 which is presently 25:70. In central

    sector, various hydro schemes with a capacity of over 28000 MW are under different stages of

    development.

    The outlay for power sector during the Xth Plan period was enhanced to about Rs. 143,000

    crore which is approximately 214 per cent higher than IX plan Outlay.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    3/28

    NICMAR PGPM 24

    Page 3 of 28 SUBMITTED BY : SOMDATT

    For a phased development of National Power Grid a number of schemes have been planned

    such as interconnections link to the northern, western, southern and eastern regions in

    addition to the existing interconnections. Today the inter-regional power transfer capacity is

    4,850 MW. It has been planned to enhance to the level of 30,000 MW by 2012 through

    various interregional links along with transmission highways. United load dispatch centers are

    being commissioned for northern and southern regions to help regulate the respective grids.

    The government is pursuing reform measured expeditiously. The Central Electricity

    Regulatory Commission, formed under the previsions of Electricity Commission Act, 1998

    has been made fully functional. The commission has passed orders on availability-based tariff

    and has also notified terms and conditions for determination.

    2.0 INDIAS ENERGY SECTOR

    Energy has been universally recognized as one of the most important inputs for economic

    growth and human development. There is a strong two-way relationship between economic

    development and energy consumption. On one hand, growth of an economy, with its global

    competitiveness, hinges on the availability of cost-effective and environmentally benign

    energy sources, and on the other hand, the level of economic development has been observed

    to be reliant on the energy demand.

    2.1 An Overview

    The energy intensity of India is over twice that of the matured economies, which are

    represented by the OECD (Organization of Economic Co-operation and Development)

    member countries. Indias energy intensity is also much higher than the emerging

    economiesthe Asian countries, which include the ASEAN member countries as well as

    China. However, since 1999, Indias energy intensity has been decreasing and is expected to

    continue to decrease.

    The indicator of energyGDP (gross domestic product) elasticity, that is, the ratio of growth

    rate of energy to the growth rate GDP, captures both the structure of the economy as well as

    the efficiency. The energyGDP elasticity during 19532001 has been above unity. However,

    the elasticity for primary commercial energy consumption for 19912000 was less than unity

    (Planning Commission 2002). This could be attributed to several factors, some of them being

    demographic shifts from rural to urban areas, structural economic changes towards lesser

    energy industry, impressive growth of services, improvement in efficiency of energy use, and

    inter-fuel substitution.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    4/28

    NICMAR PGPM 24

    Page 4 of 28 SUBMITTED BY : SOMDATT

    The energy sector in India has been receiving high priority in the planning process. The total

    outlay on energy in the Tenth Five-year Plan has been projected to be 4.03 trillion rupees at

    2001/02 prices, which is 26.7% of the total outlay. An increase of 84.2% is projected over the

    Ninth Five-year Plan in terms of the total plan outlay on energy sector. The Government of

    India in the mid-term review of the Tenth Plan recognized the fact that under-performance of

    the energy sector can be a major constraint in delivering a growth rate of 8% GDP during the

    plan period. It has, therefore, called for acceleration of the reforms process and adoption of an

    integrated energy policy.

    In the recent years, the government has rightly recognized the energy security concerns of the

    nation and more importance is being placed on energy independence. On the eve of the 59th

    Independence Day (on 14 August 2005), the President of India emphasized that energy

    independence has to be the nations first and highest priority, and India must be determined to

    achieve this within the next 25 years.

    2.2 Demand and supply scenario

    In the recent years, Indias energy consumption has been increasing at one of the fastest rates

    in the world due to population growth and economic development. Primary commercial

    energy demand grew at the rate of six per cent between 1981 and 2001 (Planning Commission

    2002). India ranks fifth in the world in terms ofprimary energy consumption,accounting for

    about 3.5% of the world commercial energy demand in the year 2003. Despite the overall

    increase in energy demand,per capita energy consumption in India is still very low compared

    to other developing countries.

    India is well-endowed with both exhaustible and renewable energy resources. Coal, oil, and

    natural gas are the three primary commercial energy sources. Indias energy policy, till th e

    end of the 1980s, was mainly based on availability of indigenous resources. Coal was by far

    the largest source of energy. However, Indias primary energy mix has been changing over a

    period of time.

    Despite increasing dependency on commercial fuels, a sizeable quantum of energy

    requirements (40% of total energy requirement), especially in the rural household sector, is

    met by non-commercial energy sources, which include fuelwood, crop residue, and animal

    waste, including human and draught animal power. However, other forms of commercial

    http://www.eia.doe.gov/pub/international/iealf/tablee1.xlshttp://www.eia.doe.gov/pub/international/iealf/tablee1c.xlshttp://www.eia.doe.gov/pub/international/iealf/tablee1c.xlshttp://www.eia.doe.gov/pub/international/iealf/tablee1.xls
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    5/28

    NICMAR PGPM 24

    Page 5 of 28 SUBMITTED BY : SOMDATT

    energy of a much higher quality and efficiency are steadily replacing the traditional energy

    resources being consumed in the rural sector.

    Resource augmentation and growth in energy supply has not kept pace with increasing

    demand and, therefore, India continues to face serious energy shortages. This has led to

    increased reliance on imports to meet the energy demand.

    2.3 Coal

    India now ranks third amongst thecoalproducing countries in the world. Being the most

    abundant fossil fuel in India till date, it continues to be one of the most important sources for

    meeting the domestic energy needs. It accounts for 55% of the countrys total energy

    supplies. Through sustained increase in investment,production of coal increased from about

    70 MT (million tonnes) (MoC 2005) in early 1970s to 382 MT in 2004/05. Most of the coal

    production in India comes from open pit mines contributing to over 81% of the total

    production while underground mining accounts for rest of the national output (MoC 2005).

    Despite this increase in production, the existing demand exceeds the supply. India currently

    faces coal shortage of 23.96 MT. This shortage is likely to be met through imports mainly by

    steel, power, and cement sector (MoC 2005). India exports insignificant quantity of coal to

    the neighbouring countries. The traditional buyers of Indian coal are Bangladesh, Bhutan, and

    Nepal.

    The development of core infrastructure sectors like power, steel, and cement are dependent on

    coal. About 75% of the coal in the country is consumed in the power sector (MoC 2005).

    2.4 Power

    Access to affordable and reliable electricity is critical to a countrys growth and prosperity.

    The country has made significant progress towards the augmentation of its power

    infrastructure. In absolute terms, theinstalled power capacity has increased from only 1713

    MW (megawatts) as on 31 December 1950 to 118 419 MW as on March 2005 (CEA

    2005).The all India gross electricity generation,excluding that from the captive generating

    plants, was 5107 GWh (gigawatt-hours) in 1950 and increased to 565 102 GWh in 2003/04

    (CEA 2005).

    Energy requirement increased from 390 BkWh (billion kilowatt-hours) during 1995/96 to 591

    BkWh (energy) by the year 2004/05, and peak demand increased from 61 GW (gigawatts) to

    88 GW over the same time period. The country experienced energy shortage of 7.3% and

    peak shortage of 11.7% during 2003/04. Though, the growth inelectricity consumption over

    http://coal.nic.in/anx05063.pdfhttp://coal.nic.in/anx05069.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab124.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab124.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab125.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab125.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab124.pdfhttp://indiabudget.nic.in/es2004-05/chapt2005/tab124.pdfhttp://coal.nic.in/anx05069.pdfhttp://coal.nic.in/anx05063.pdf
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    6/28

    NICMAR PGPM 24

    Page 6 of 28 SUBMITTED BY : SOMDATT

    the past decade has been slower than the GDPs growth, this increase could be due to high

    growth of the service sector and efficient use of electricity.

    Per capita electricity consumption rose from merely 15.6 kWh (kilowatt-hours) in 1950 to

    592 kWh in 2003/04 (CEA 2005). However, it is a matter of concern that per capita

    consumption of electricity is among the lowest in the world. Moreover, poor quality of power

    supply and frequent power cuts and shortages impose a heavy burden on Indias fast-growing

    trade and industry.

    2.5 Oil and Natural Gas

    The latest estimates indicate that India has around 0.4% of the worlds proven reserves of

    crude oil. The production of crude oil in the country has increased from 6.82 MT in 1970/71to 33.38 MT in 2003/04 (MoPNG 2004b). The production of natural gas increased from 1.4

    BCM (billion cubic metres) to 31.96 BCM during the same period. The quantity of crude oil

    imported increased from 11.66 MT during 1970/71 to 81 MT by 2003/04. Besides, imports of

    other petroleum products increased from 1 MT to 7.3 MT during the same period. The exports

    of petroleum products went up from around 0.5 MT during 1970/71 to 14 MT by 2003/04.

    The refining capacity, as on 1 April 2004, was 125.97 MTPA (million tonnes per annum).

    The production of petroleum products increased from 5.7 MT during 1970/71 to 110 MT in

    2003/04.

    Indias consumption of natural gas has risen faster than any other fuel in the recent years.

    Natural gas demand has been growing at the rate of about 6.5% during the last 10 years.

    Industries such as power generation, fertilizer, and petrochemical production are shifting

    towards natural gas. Indias natural gas consumption has been met entirely through domestic

    production in the past. However, in the last 4/5 years, there has been a huge unmet demand of

    natural gas in the country, mainly required for the core sectors of the economy. To bridge this

    gap, apart from encouraging domestic production, the import of LNG (liquefied natural gas)is being considered as one of the possible solutions for Indias expected gas shortages.

    Several LNG terminals have been planned in the country. Two LNG terminals have already

    been commissioned: (1) Petronet LNG Terminal of 5 MTPA (million tonnes per annum) at

    Dahej, and (2) LNG import terminal at Hazira. In addition, an in-principle agreement has

    been reached with Iran for import of 5 MTPA of LNG.

    http://petroleum.nic.in/petstat.pdfhttp://petroleum.nic.in/petstat.pdf
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    7/28

    NICMAR PGPM 24

    Page 7 of 28 SUBMITTED BY : SOMDATT

    2.6 Renewable Energy Sources

    Renewable energy sources offer viable option to address the energy security concerns of a

    country. Today, India has one of the highest potentials for the effective use of renewable

    energy. India is the worlds fifth largest producer of wind power after Denmark, Germany,

    Spain, and the USA. There is a significant potential in India for generation of power from

    renewable energy sources, small hydro, biomass, and solar energy. The country has an

    estimated SHP (small-hydro power) potential of about 15 000 MW. Installed combined

    electricity generation capacity of hydro and wind has increased from 19 194 MW in 1991/92

    to 31 995 MW in 2003/04, with a compound growth rate of 4.35% during this period (MoF

    2005). Other renewable energy technologies, including solar photovoltaic, solar thermal,

    small hydro, and biomass power are also spreading. Greater reliance on renewable energy

    sources offers enormous economic, social, and environmental benefits.

    The potential for power production from captive and field-based biomass resources, using

    technologies for distributed power generation, is currently assessed at 19 500 MW including

    3500 MW of exportable surplus power from bagasse-based cogeneration in sugar mills

    (MNES 2005).

    2.7 Future scenario

    Increasing pressure of population and increasing use of energy in different sectors of the

    economy is an area of concern for India. With a targeted GDP growth rate of 8% during the

    Tenth Five-year Plan, the energy demand is expected to grow at 5.2%. Driven by the rising

    population, expanding economy, and a quest for improved quality of life, the total primary

    energy consumption is expected to about 412 MTOE (million tonnes oil equivalent) and 554

    MTOE in the terminal years of the Tenth and Eleventh Plans, respectively (Planning

    Commission 1999).

    The International Energy Outlook 2005 (EIA 2005b) projects,Indias gas consumption to

    grow at an average annual rate of 5.1%, thereby reaching 2.8 trillion cubic feet by 2025 with

    the share of electric power sector being of 71% by that time. Coal consumption is expected to

    increase to 315 MT over the forecast period. In India, slightly less than 60% of the projected

    growth in coal consumption is attributed to the increased demand of coal in the electricity

    sector while the industrial sector accounts for most of the remaining increase. The use of coal

    for electricity generation in India is expected to increase by 2.2% per annum during 200225,

    thus requiring an additional 59 000 MW of coal-fired capacity. Oil demand in India is

    expected to increase by 3.5% per annum during the same time.

    http://mnes.nic.in/frame.htm?publications.htmhttp://www.eia.doe.gov/oiaf/aeo/aeoref_tab.htmlhttp://www.eia.doe.gov/oiaf/aeo/aeoref_tab.htmlhttp://mnes.nic.in/frame.htm?publications.htm
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    8/28

    NICMAR PGPM 24

    Page 8 of 28 SUBMITTED BY : SOMDATT

    It is quite apparent that coal will continue to be the predominant form of energy in future.

    However, imports of petroleum and gas would continue to increase substantially in absolute

    terms, involving a large energy import bill. There is, therefore, an urgent need

    toconserve energy and reduce energy requirements by demand-side management and by

    adopting more efficient technologies in all sectors.

    3.0 POWE SECTOR : PRESENT SCENARIO

    3.1 Generation

    India has the fifth largest generation capacity in the world with an installed capacity of 152

    GW as on 30 September 2009, which is about 4 percent of global power generation. The top

    four countries, viz., US, Japan, Chinaand Russia together consume about 49 percent of thetotal power generated globally. The average per capita consumption of electricity in India is

    estimated to be 704 kWh during 2008-09. However, this is fairly low when compared to that

    of some of the developed and emerging nations such US (~15,000 kWh) and China (~1,800

    kWh). The world average stands at 2,300 kWh. The Indian government has set ambitious

    goals in the 11th plan for power sector owing to which the power sector is poised for

    significant expansion. In order to provide availability of over 1000 units of per capita

    electricity by year 2012, it has been estimated that need-based capacity addition of more than

    100,000 MW would be required. This has resulted in massive addition plans being proposed

    in the sub-sectors of Generation Transmission and Distribution

    3.2 Transmission

    The current installed transmission capacity is only 13 percent of the total installed generation

    capacity. With focus on increasing generation capacity over the next 8-10 years, the

    corresponding investments in the transmission sector is also expected to augment. The

    Ministry of Power plans to establish an integrated National Power Grid in the country by

    2012 with close to 200,000 MW generation capacities and 37,700 MW of inter-regional

    power transfer capacity. Considering that the current inter-regional power transfer capacity of

    20,750 MW, this is indeed an ambitious objective for the country.

    3.3 Distribution

    While some progress has been made at reducing the Transmission and Distribution (T&D)

    losses, these still remain substantially higher than the global benchmarks, at approximately 33

    percent. In order to address some of the issues in this segment, reforms have been undertakenthrough unbundling the State Electricity Boards into separate Generation, Transmission and

    http://petroleum.nic.in/conserv.htmhttp://petroleum.nic.in/conserv.htm
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    9/28

    NICMAR PGPM 24

    Page 9 of 28 SUBMITTED BY : SOMDATT

    Distribution units and privatization of power distribution has been initiated either through the

    outright privatization or the franchisee route; results of these initiatives have been somewhat

    mixed. While there has been a slow and gradual improvement in metering, billing and

    collection efficiency, the current loss levels still pose a significant challenge for distribution

    companies going forward.

    4.0 GROWTH OF POWER SECTOR

    The power sector has registered significant progress since the process of planned development

    of the economy began in 1950. Hydro -power and coal based thermal power have been the

    main sources of generating electricity. Nuclear power development is at slower pace, which

    was introduced, in late sixties. The concept of operating power systems on a regional basiscrossing the political boundaries of states was introduced in the early sixties. In spite of the

    overall development that has taken place, the power supply industry has been under constant

    pressure to bridge the gap between supply and demand.

    Power development is the key to the economic development. The power Sector has been

    receiving adequate priority ever since the process of planned development began in 1950. The

    Power Sector has been getting 18-20% of the total Public Sector outlay in initial plan periods.

    Remarkable growth and progress have led to extensive use of electricity in all the sectors ofeconomy in the successive five years plans. Over the years (since 1950) the installed capacity

    of Power Plants (Utilities) has increased to 89090 MW (31.3.98) from meagre 1713 MW in

    1950, registering a 52d fold increase in 48 years. Similarly, the electricity generation

    increased from about 5.1 billion units to 420 Billion units 82 fold increase. The per capita

    consumption of electricity in the country also increased from 15 kWh in 1950 to about 338

    kWh in 1997-98, which is about 23 times. In the field of Rural Electrification and pump set

    energisation, country has made a tremendous progress. About 85% of the villages have been

    electrified except far-flung areas in North Eastern states, where it is difficult to extend the grid

    supply.

    In December 1950 about 63% of the installed capacity in the Utilities was in the private sector

    and about 37% was in the public sector. The Industrial Policy Resolution of 1956 envisaged

    the generation, transmission and distribution of power almost exclusively in the public sector.

    As a result of this Resolution and facilitated by the Electricity (Supply) Act, 1948, the

    electricity industry developed rapidly in the State Sector.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    10/28

    NICMAR PGPM 24

    Page 10 of 28 SUBMITTED BY : SOMDATT

    In the Constitution of India "Electricity" is a subject that falls within the concurrent

    jurisdiction of the Centre and the States. The Electricity (Supply) Act, 1948, provides an

    elaborate institutional frame work and financing norms of the performance of the electricity

    industry in the country. The Act envisaged creation of State Electricity Boards (SEBs)for

    planning and implementing the power development programmes in their respective States.

    The Act also provided for creation of central generation companies for setting up and

    operating generating facilities in the Central Sector. TheCentral Electricity

    Authorityconstituted under the Act is responsible for power planning at the national level. In

    addition the Electricity (Supply) Act also allowed from the beginning the private licensees to

    distribute and/or generate electricity in the specified areas designated by the concerned State

    Government/SEB.

    During the post independence period, the various States played a predominant role in the

    power development. Most of the States have established State Electricity Boards. In some of

    these States separate corporations have also been established to install and operate generation

    facilities. In the rest of the smaller States and UTs the power systems are managed and

    operated by the respective electricity departments. In a few States private licencees are also

    operating in certain urban areas.

    From, the Fifth Plan onwards i.e. 1974-79, the Government of India got itself involved in a

    big way in the generation and bulk transmission of power to supplement the efforts at the

    State level and took upon itself the responsibility of setting up large power projects to develop

    the coal and hydroelectric resources in the country as a supplementary effort in meeting the

    countrys power requirements. TheNational thermal Power Corporation

    (NTPC)and National Hydro-electric Power Corporation (NHPC)were set up for these

    purposes in 1975. North-Eastern Electric Power Corporation (NEEPCO)was set up in

    1976 to implement the regional power projects in the North-East. Subsequently two more

    power generation corporations were set up in 1988 viz. Tehri Hydro Development

    Corporation (THDC)andNathpa Jhakri Power Corporation (NJPC). To construct,

    operate and maintain the inter-State and interregional transmission systems theNational

    Power Transmission Corporation (NPTC)was set up in 1989. The corporation was

    renamed as POWER GRIDin 1992.

    The policy of liberalisation the Government of India announced in 1991 and consequent

    amendments in Electricity (Supply) Act have opened new vistas to involve private efforts and

    investments in electricity industry. Considerable emphasis has been placed on attracting

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    11/28

    NICMAR PGPM 24

    Page 11 of 28 SUBMITTED BY : SOMDATT

    private investment and the major policy changes have been announced by the Government in

    this regard which are enumerated below:

    The Electricity (Supply) Act, 1948 was amended in 1991 to provide for creation of private

    generating companiesfor setting up power generating facilities and selling the power in

    bulk to the grid or other persons.

    Financial Environment for private sector units modified to allow liberal capital structuring

    and an attractive return on investment. Up to hundred percent (100%) foreign

    equityparticipation can be permitted for projects set up by foreign private investors in the

    Indian Electricity Sector.

    Administrative & Legal environment modified to simplify the procedures for clearances ofthe projects.

    Policy guidelines for private sector participation in the renovation & modernisationof

    power plants issued in 1995.

    In 1995, the policy for Mega power projectsof capacity 1000 MW or more and supplying

    power to more than one state introduced. The Mega projects to be set up in the regions

    having coal and hydel potential or in the coastal regions based on imported fuel. The Mega

    policy has since been refined andPower Trading Corporation (PTC)incorporated

    recently to promote and monitor the Mega Power Projects. PTC would purchase power

    from the Mega Private Projects and sell it to the identified SEBs.

    In 1995 GOI came out with liquid fuel policypermitting liquid fuel based power plants to

    achieve the quick capacity addition so as to avert a severe power crisis. Liquid fuel linkages

    (Naphtha) were approved for about 12000 MW Power plant capacity. The non-traditional

    fuels like condensate and orimulsion have also been permitted for power generation.

    GOI has promulgated Electricity Regulatory Commission Act, 1998 for setting up of

    Independent Regulatory bodies both at the Central level and at the State level viz.

    The Central Electricity Regulatory Commission (CERC)and the State Electricity

    Regulatory Commission (SERCs) at the Central and the State levels respectively. The

    main function of the CERC are to regulate the tariff of generating companies owned or

    controlled by the Central Government, to regulate the tariff of generating companies, other

    than those owned or controlled by the Central Government, if such generating companies

    enter into or otherwise have a composite scheme for generation and sale of electricity in

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    12/28

    NICMAR PGPM 24

    Page 12 of 28 SUBMITTED BY : SOMDATT

    more than one State to regulate the inter-state transmission of energy including tariff of the

    transmission utilities, to regulate inter-state bulk sale of power and to aid & advise the

    Central Government in formulation of tariff policy. The CERC has been constituted on

    24.7.1998.

    The main functions of the SERC would be to determine the tariff for electricity wholesale

    bulk, grid or retail, to determine the tariff payable for use by the transmission facilities to

    regulate power purchase and procurement process of transmission utilities and distribution

    utilities, to promote competition, efficiency and economy in the activities of the electricity

    industries etc. Subsequently, as and when each State Government notifies, other regulatory

    functions would also be assigned to SERCs.

    The Electricity Laws (Amendment) Act, 1998passed with a view to make transmission as

    a separate activity for inviting greater participation in investment from public and private

    sectors. The participation by private sector in the area of transmission is proposed to be

    limited to construction and maintenance of transmission lines for operation under the

    supervision and control of Central Transmission Utility (CTU)/State Transmission Utility

    (STU). On selection of the private company, the CTU/STU would recommend to the

    CERC/SERC for issue of transmission licence to the private company.

    The Electricity Laws (Amendment) Act, 1998 provides for creation of Central and StateTransmission utilities. The function of the Central Transmission Utilityshall be to

    undertake transmission of energy through inter-state transmission system and discharge all

    functions of planning and coordination relating to inter-state transmission system with State

    Transmission Utilities, Central Government, State Governments, generating companies etc.

    Power Grid Corporation of India Limited will be Central Transmission Utility.

    The function of the State Transmission Utilityshall be to undertake transmission of

    energy through intra-state transmission system and discharge all functions of planning andcoordination relating to intra-state transmission system with Central Transmission Utility,

    State Governments, generating companies etc.

    5.0 INVESTMENT IN POWER SECTOR

    5.1 Investment Opportunities in Thermal Power Development

    70% of the country's total installed capacity and more than 80% of the total electricity

    generation is contributed by thermal power.

    Coal continues to be the main source of for thermal generation.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    13/28

    NICMAR PGPM 24

    Page 13 of 28 SUBMITTED BY : SOMDATT

    The major thrust in thermal generation could be fructified through significant jump in

    unit size and steam parameters resulting in higher efficiencies and better economics.

    The largest unit size in the country at present is 500 MW and 600 MW super critical

    units are in the pipeline. The projected future unit size is 800-1000 MW with still

    higher super critical parameters which will have low cost of generation, higher

    efficiency and are environment friendly.

    With the identification of new gas sources and availability in international market,

    there is renewed thrust in gas based combined cycle plants. Such CCGT plants are

    increasingly becoming techno-economical viable with advancements in efficient gas

    turbine technologies and their environmental benefits.

    The post Electricity Act 2003 scenario provides for the opportunity for any generating

    company to establish, operate and maintain a thermal generating station without the

    need of a license, thus providing a free hand in setting up of a thermal generating

    plant.

    Strong supportive factors conducive to investment opportunity such a vibrant strong

    and stable economy, low cost indigenous fuel, availability of skilled manpower,

    indigenous power plant manufacturing capability, presence of independent power

    producers and power sector reforms initiatives as confidence building measures for

    prospective investors.

    Thrust to R&M / life extension activities with large investment potential forimproving the performance of old thermal power stations. The 10 Plan (2002-07) is

    targeted towards 57 units (14270 MW) for R&M works and 106 units (10413 MW)

    with anticipated total cost of more than Rs.10000 crores.

    5.2 Investment Opportunities in Hydro Power Development

    The 10 Plan program envisages capacity addition of 14393 MW from hydel projects

    in the total capacity addition of 41110.

    The Govt. has initiated advance action for taking up new hydro projects. A 50,000

    hydro initiative has been launched and pre feasibility reports for 162 projects

    prepared. In the second phase of this programme, DPRs for about 30,000 MW are

    under preparation for eventual implementation through both public & private sector

    agencies.

    Govt. would take up for execution, all the CEA cleared projects and take steps to up

    date and obtain clearance for pending DPRS.

    Survey and investigations for new green field sites.

    Restart and activate the pending hydro projects for want of funds/inter state issues.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    14/28

    NICMAR PGPM 24

    Page 14 of 28 SUBMITTED BY : SOMDATT

    Promoting small and mini hydel projects by simple design of turbines, generators and

    the civil works and in a shorter period.

    5.3 Investment Opportunities in Transmission Schemes

    The high capacity inter-regional transmission links, forming the back bone of the National

    Power Grid would require an investment of the order of Rs. 40,000 crores of which about

    50% would be needed during the Tenth Plan period and the balance during the Eleventh Plan

    period. Simultaneously, strengthening of the regional system for meeting the increased

    transmission needs on account of increased inter-regional transactions as well as for

    evacuation, transmission and dispersal of power from generation resources within the regions

    would have to be continued and the transmission and distribution system in the State sector

    would also need to be strengthened. The requirement of funds for transmission and

    distribution system in the country corresponding to the programme of 1,00,000 MW of

    generation addition in the next ten years has been estimated to be of the order of Rs.3,00,000

    Crores as per the following break-up:

    X Plan XI Plan XII Plan

    National Grid System including Inter-Regional and Regional Transmission System

    40,000 50,000 90,000

    States Transmission System20,000 20,000 40,000

    Sub-transmission and Distribution System80,000 90,000 1,70,000

    Total 1,40,000 1,60,000 3,00,000

    5.4 Investment Opportunities in Private Sector Participation in Transmission

    Schemes

    The Government made enabling provision for private sector participation in transmission

    sector way back in 1998 by amending the then existing Electricity Act 1948. Generation of

    electricity was opened for private sector in 1991.

    In the newly enacted Electricity Act 2003, any private player can seek license from the

    Appropriate Commission to carry out business in transmission of electricity.

    Government of India envisages two routes for private sector participation in transmission

    ventures. IPTC routeprovides 100% fund mobilization by private entrepreneurs as I n d e

    p e n d e n t P r i v a t e Transmission Company. And JVC route -provides formulation of a

    Joint Venture Company (JVC) with CTU/STU by selecting a private investor as joint venture

    partner.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    15/28

    NICMAR PGPM 24

    Page 15 of 28 SUBMITTED BY : SOMDATT

    To start with, Central Electricity Regulatory Commission granted transmission license on 13-

    11-2003 to M/s Powerlinks Transmission Limited, a joint venture company of the Power Grid

    Corporation of India Limited and Tata Power. This Joint Venture (JV) project is first of its

    kind in India and is being promoted by Government of India as a pilot project under its policy

    of encouraging private sector participation in transmission of electricity.

    As a first project to be undertaken under the IPTC route, the Government has already

    identified the Bina-Nagda-Dehgam 400kV Double Circuit transmission line of about 700 KM

    route length to be taken up for private sector participation.

    Opportunity of massive investment in Transmission exists and it is envisaged that upto Rs.

    9,000 crores can be invested by the private sector by the end of Xth Five Year Plan.

    5.5 Investment Opportunities in Distribution Schemes

    Accelerated Power Development Reform Programme:

    The Distribution Sector could not grow with the required pace due to paucity of funds and

    therefore,Distribution Reforms were initiated by the Government. MoUs and MoAs were

    signed with the States for linking the support of Government of India through APDRP which

    is ambitious plan for upgradation and strengthening of sub-transmission and distribution

    system with the objective of reducing the AT&C losses to around15%.

    Six Level Intervention Strategy:In order to achieve commercial viability Ministry of Power has formulated six level

    intervention strategy that encompasses initiatives at National level, State level, SEB/Utility

    level, Distribution Circle level, Feeder level and the consumer level.

    Anti-Theft Measures:

    Several States viz. Andhra Pradesh, Karnataka, Madhya Pradesh, Uttar Pradesh, West Bengal,

    Maharashtra, Kerala and Gujarat have taken number of initiative to curb the theft of power

    which have shown improvement in collection of revenue by the SEBs/Utilities.

    The Electricity Act, 2003 provides a legal framework for making theft of electricity a

    cognizable offence. Under Section 135 of the Electricity Act, 2003, whoever dishonestly taps

    lines or cables or service wires, tampers, damages or destroys meters etc. shall be punishable

    with imprisonment for a term which may extend to three years or with fine or with both.

    100% Metering Programme:

    A programme of 100% metering has been taken up by States subsequent to PowerMinisters/Chief Ministers conference held on 26.2.2000. As on 30th September, 2004, 95%

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    16/28

    NICMAR PGPM 24

    Page 16 of 28 SUBMITTED BY : SOMDATT

    and 87% metering have been achieved in respect of 11 kV feeders and consumer feeders

    respectively.

    Consumer Care Centre:

    To address consumer grievances various States have taken initiatives by setting up consumer

    care centres and these centers are effectively operating at Hyderabad, Vadodara, Bangalore,

    Faridabad, Delhi and almost all States are taking steps for implementing the consumer care

    centres for large towns of the States

    5.6 Future Investment Requirement

    Even after investment made by the Union Government through APDRP in ST&D system, the

    distribution sector needs further investment considering the growth rates of various segmentsof the distribution system the projections by the end of 2006-07 are as follows:

    Line Ckt km

    66kV 46947

    33kV 346336

    11kV 2270984

    LV 4486176

    An investment of Rs. 86357 crores was assessed by the Working Group on Power at the

    beginning of the Tenth Plan. However the same has gone to Rs. 1,00,000/- crore as on today

    for the entire 10th Plan period (2002-07).

    Research And Development (R&D) And New Technologies:

    According to the National Perspective Plan on R&D in Indian Power Sector up to 2015,distribution sector was identified as the key area for taking up the Research and Development

    (R&D) in this sector. The identified areas are:

    High voltage distribution system (HVDS)

    Demand side management

    Custom power devices

    Compact transformation devices

    Distribution automation

    Metering

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    17/28

    NICMAR PGPM 24

    Page 17 of 28 SUBMITTED BY : SOMDATT

    Quality of Power Supply and Customer Satisfaction:

    With the enactment of the Electricity Act, 2003 the emphasis has been given on providing

    quality and interruption free supply to customers. Keeping this objective in view Central

    Electricity Authority (CEA) has started monitoring of reliability index, average tripping permonth in respect of 11 kV feeders in respect of towns having population of more than 8 lakhs.

    This will facilitate in bench marking various indices for the annual frequency and duration of

    tripping. Various State Electricity Regulatory Commissions (SERCs) are also in the process

    of making regulations for standard of performance in compliance to various provisions of the

    Electricity Act, 2003.

    Regulation on Installation and Operation of Meters:

    In compliance to provision of Section 55 of the Electricity Act, 2003, CEA is making

    regulation on installation and operation of meters. This will facilitate in uniformity of

    approach for location of meters, selecting type of meters and their specification, new

    investment opportunities.

    The Finance Minister of India Sh. Pranab Mukherjee in an article on march 01, 2009

    mentioned that :

    With the countrys power requirement expected to touch 8,00,000 MW by 2031-32, India

    would need an investment of Rs6,00,000 crore,

    This investment is possible only by attracting foreign direct investment and public-private

    participation in the power sector, He said at a function to lay the foundation stone for the

    1,000 MW Tuticorin power project of NLC Tamilnadu Power Ltd, a joint venture of the

    Neyveli Lignite Corporation and Tamil Nadu Electricity Board.

    Claiming that despite odds, the power sector in the country had made a turnaround, he said Itis time we move ahead and improve our performance by joining together. We should ensure

    the power shortage is the story of the past and the people got quality power at a competitive

    price, he said.

    The government should make efforts to generate power through various sources by fixing

    targets, he added.

    At present, the energy shortage in the country was estimated at 10% and it touches 13%

    during peak seasons. There are states, where the energy shortage is 25%.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    18/28

    NICMAR PGPM 24

    Page 18 of 28 SUBMITTED BY : SOMDATT

    This is a serious impediment in the way of industrial development and economic process. So

    we need a crash project for capacity building and eliminate power shortage by 2012, hesaid.

    6.0 CURRENT PROBLEM IN POWER SECTOR

    As the Indian power sector is embarking on increasing the generation and transmission

    capacities, key challenges lie ahead which also resulted the historical underperformance.

    6.1 Project ExecutionNeeds to be expedited

    India has historically failed to meet its power sector targets by a significant margin and with

    tremendous opportunities ahead, the power sector continues to be affected by the shortfall

    both on generation as well as transmission side. For example, for the current installed capacity

    of around 152 GW, the inter-regional transmission capacity is only about 20 GW (13 percent

    of the installed capacity).

    The various proposals in generation and transmission are currently under different

    implementation stages. However, the power sector in India has been plagued with a set of

    problems for meeting the planned targets. Although measures have been defined by the

    policymakers and stakeholders in a sense of complacency that the issues will indeed be

    resolved and India will plug the supply deficit of power to resolve the same but looking at the

    past record, it can be estimated that the resolution measures may not be implemented.

    The biggest indicator of a poor track record is the inability to meet targets on the power

    generation capacity additions. Variance with the target has been as high as 50 percent in the

    past.

    For the 10th Five year plan various reasons have been identified for slippage. They range

    from inadequate preparedness of projects, shortage of equipment to the delay in financial

    closure. The shortage of equipment by BHEL has been identified as a major cause of delay in

    the timely completion of the power generation projects.

    The target for the current 11th Plan is ambitious, at 78,700 MW, but the first 2 years have

    already seen a slippage.

    6.2 Fuel Availability

    While additional gas supply from KG Basin has eased shortage to a limited extend, supply

    constraints for domestic coal remain and are expected to continue going forward.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    19/28

    NICMAR PGPM 24

    Page 19 of 28 SUBMITTED BY : SOMDATT

    Consequently, public and private sector entities have embarked upon imported coal as a

    means to bridge the deficit. This has led to some Indian entities to take upon the task of

    purchasing, developing and operating coal mines in international geographies. While this is

    expected to secure coal supplies it has again thrown upon further challenges. For example, the

    main international market for coal supply to IndiaIndonesia, poses significant political and

    legal risks in the form of changing regulatory framework towards foreign companies.

    Similarly, coal evacuation from mines in South Africa is constrained by their limited railway

    capacity and the capacity at ports is controlled by a group of existing users making it difficult

    for a new entrant to ensure reliable evacuation9. In this case it is essential to manage the risk

    of supply disruption by different options like diversification of supply, due diligence on

    suppliers, unambiguous contracting and strict monitoring among others.

    The failure to achieve the planned target from the captive coal blocks presents itself as a

    major challenge to the power sector, as only 24 blocks have become operational out of the

    total 210. Experts believe that the non-operational status of majority of these blocks is

    attributed to land acquisition (R&R) issues, permit delays and infrastructure problems10. In

    addition, the developers who have been given the charge of captive blocks are not putting

    diligent efforts to expedite the mining operations due to their lack of experience in coalmine

    development.

    Coal is the mainstay of the power production in India and is expected to remain so in the

    future. Additional power generation is likely to require incremental amount of coal

    transportation by Indian Railways within the country and increasing unloading at ports in

    India for imported coal. In both cases India currently faces capacity shortage. Hence, a project

    developer has to account for and manage its logistics chain in a manner that minimizes

    disruption to its fuel supply. In many cases this is likely to involve self development of

    relevant supply infrastructure which poses additional project execution complexity for the

    developer. For example, some imported coal based power plants are also forced to set up anunloading jetty for coal carrying shipping vessels. This has to be ensured before the

    commissioning of a power plant which requires an alternate set of project execution skills in

    the port sector.

    6.3 Equipment Shortage

    Equipment shortages have been a significant reason for India missing its capacity addition

    targets for the 10th five year plan. While the shortage has been primarily in the core

    components of Boilers, Turbines and Generators, there has been lack of adequate supply of

    Balance of Plant (BOP) equipment as well. These include coal-handling, ashhandling plants,

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    20/28

    NICMAR PGPM 24

    Page 20 of 28 SUBMITTED BY : SOMDATT

    etc. Apart from these, there is shortage of construction equipment as well. The Working

    Group on Power for 11th Plan has outlined the requirement for construction equipment for

    Hydro and Thermal power plants.

    To alleviate supply shortage of equipment two measures are being adoptedenhancement of

    domestic equipment manufacturing capability by establishing JVs between Indian and foreign

    suppliers and second measure is procuring equipment directly from international markets. In

    both cases equipment sourcing needs to be managed effectively throughout the procurement

    cycle. For instance, it may be a challenge for new project owners to select a reliable supplier,

    monitor its performance and ensure the quality of supply on a sustained basis. Also, the

    timelines for availability of additional domestic equipment supply has not been clearly

    defined.

    6.4 Land Acquisition and Environment Clearance

    Land Acquisition poses an increasingly significant challenge in the Indian Power sector.

    Power plants and utilities face major constraints and delays regarding the availability of land

    and obtaining the requisite environment and other clearances for the projects. The new Bill

    relating to land acquisition has continued to face political opposition. While it provides for

    acquisition by project development agencies to the extent of 70 percent of the land required

    for a project, with the balance to be obtained by the Government. In addition, it has beenreported that in some cases, even after land owners were asked to sell and handover their land

    in Public Interest, the project was not completed for several years due to other delays, a fact

    that eroded the credibility of both the industry and the government. Consequently there is a

    significant mismatch of expectations from the Project Affected Persons (PAP). Stakeholders

    or other land owners may collectively object of the project execution. In such cases, it is

    essential to proactively manage the environment and stakeholders expectations.

    6.5 Financial

    Rapid build up of the generation capacity is being aided by setting up of Ultra Mega Power

    Projects (UMPPs) each of which is 4000 MW. However, the execution of the Ultra Mega

    Power Projects (UMPP) is a significant challenge as India has not witnessed an execution of

    such a large scale power project before. Furthermore, with each UMPP costing above INR

    16,000 Crore, financing such a large project is a critical constraint for any developer. In

    addition, considering the high financial stake involved through private investments, delay in

    payments may put severe pressure on developers/suppliers to meet the performance

    commitments.

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    21/28

    NICMAR PGPM 24

    Page 21 of 28 SUBMITTED BY : SOMDATT

    6.6 Manpower Shortage

    There is a general consensus that shortage of talent in the construction sector is a long term

    problem and is likely to continue to push up project costs and risks. The flow of talent into

    construction and power sector has been gradually drying up as candidates have sought an

    alternativeand often more lucrativecareer options. The Government, which is the biggest

    buyer of the capital projects, has also not done enough to address this challenge. The

    education system is often not delivering the required number of specialists across project

    management, engineering, estimating, surveying and contract management. Facing a

    desperate game of catch up, the industry needs a genuine collaboration between project

    owners, contractors and governments to attract more school leavers and graduates. Companies

    should also seek to stay in touch with changing employee aspirations. By encouraging

    diversity in its employment practices and by offering greater flexibility in working hours, the

    sector can reach out to a wider potential audience that perhaps would not previously have

    considered such a career. Investment in existing employees is also crucial in order to offer

    better-defined career structures, with a greater focus on training and higher salaries where

    possible.

    6.7 Schedule Dependency on Transmission Lines

    Significant enhancement in construction activity is likely to be required to meet the 11th plan

    target of additional transmission capacity. A significant portion of this enhancement is likely

    to be in the North Eastern region, Sikkim and Bhutan, which have difficult terrain reducing

    the margin of error for project execution. Additional transmission capacity is required to

    evacuate power from surplus regions to supply to deficit regions and to enable electricity

    trading. This is essential to meet the target of Power for all. Hence, the criticality ofimplementing transmission projects cannot be ignored. In this context, it is imperative to

    establish sound project management principles to the sector to help ensure timely completion

    of projects. From the perspective of power generation projects, it is critical for project specific

    transmission projects to be set up before the commissioning of the plant to enable timely

    evacuation of power. This adds another scheduling constraint for the project.

    The most important cause of the problems being faced in the power sector is the irrational and

    unremunerative tariff structure. Although the tariff is fixed and realized by SEBs, the State

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    22/28

    NICMAR PGPM 24

    Page 22 of 28 SUBMITTED BY : SOMDATT

    Governments have constantly interfered in tariff setting without subsidizing SEBs for the

    losses arising out of State Governments desire to provide power at concessional rates to

    certain sectors, especially agriculture. Power Supply to agriculture and domestic consumers is

    heavily subsidized. Only a part of this subsidy is recovered by SEBs through cross

    subsidization of tariff from commercial and industrial consumers. The SEBs, in the process,

    have been incurring heavy losses. If the SEBs were to continue to operate on the same lines,

    their internal resources generation during the next ten years will be negative, being of the

    order of Rs.(-) 77,000 crore. This raises serious doubts about the ability of the States to

    contribute their share to capacity addition during the Ninth Plan and thereafter. This

    highlights the importance of initiating power sector reforms at the earliest and the need for

    tariff rationalization.

    7.0 DEMAND SUPPLY GAP

    It is evident that the deficit in power availability in India is a significant impediment to the

    smooth development of the economy. In this context, bridging the gap in demand and supply

    has become critical and consequently, large projects are being undertaken in different

    segments of the sector; Generation, Transmission and Distribution. As India has not

    witnessed such a large scale of implementation before, there is a need to review and enhance

    project execution capabilities to help ensure targets are met.

    This strongly necessitates employing a comprehensive project management structure to

    address the major challenges of the power sector projects and to be able to deliver them as per

    the planned targets. Historical records also indicate the presence of a weak project

    management structure which does not assess all the key project aspects.

    As discussed initially, the overall intent of this paper is to highlight the opportunities and

    challenges of the power sector, and the project management drivers that are required toaddress these challenges.

    The table below summarizes the key implementation challenges and drivers for successfully

    achieving the implementation of power generation plans.

    KeyChallenges

    Measures beingadopted

    Resulting Issues Drivers fordetermining success

    Addition ofsignificantgenerationcapacity

    UMPP Technical and financialcapability to execute suchlarge projects

    Risk Increase manifold

    Project execution

    Cost / Cash flowmanagement

    Risk Managementstrategy and planning

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    23/28

    NICMAR PGPM 24

    Page 23 of 28 SUBMITTED BY : SOMDATT

    Ensuring fuelavailability andquality

    Purchase anddevelopment ofcoal mines abroad

    Risk in operating in differentgeographies, Eg. Politicalrisks

    Uncertainties in logistics

    operation

    Risk managementthrough effectivecontracting, supplydiversification, etc

    Control over supply

    infrastructure

    Plant equipmentshortage

    Procurement fromabroad

    Setting up of newsupply units

    Vendor reliability

    Execution timelines

    Robust procurementmanagement, vendormonitoring

    Project scheduling

    Land acquisitionandenvironmentclearances

    Speeding upprocesses

    Inadequate communicationwith stakeholders resulting inmismatch of expectationsfrom project affected person

    Environment andstakeholdersmanagement

    Manpowershortage

    Enhance training Resource planning andmanagement

    8.0 STRATEGIES TO ACHIEVE POWER FOR ALL BY ALTERNATESOURCES OF ENERGY

    (i) Biomass as a Source of Energy

    The term biomass refers to all organic matter generated through photosynthesis and other

    biological processes. The ultimate source of this renewable biomass is the inexhaustible solarenergy which is captured by plants through photosynthesis. It includes both terrestrial as well

    as aquatic matter such as wood, herbaceous plants, algae, aquatic plants and residues, like

    straw, husks, corncobs, cow dung, saw-dust, wood shavings and other wastes like disposable

    garbage, night soil, sewage solids, industrial refuse etc. In spite of all these biomass resources

    available in India, they are not being properly utilized. In fact, a large amount of it is disposed

    off by burning in open fields causing serious air pollution.

    In order to utilise these resources properly, biomass should be converted to energy which can

    meet a sizeable percentage of the country's demands for fuel as well as energy. Three main

    approaches can be adopted for generation and proper utilization.

    1. Collection ofagricultural and forest residues to produce fuels, organic manures and

    chemical feed stock.

    2. Collection of urban and industrial wastes as fuel in boilers and as a feedstock for

    producing methane and some liquid fuels.

    http://www.world-agriculture.com/http://www.world-agriculture.com/
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    24/28

    NICMAR PGPM 24

    Page 24 of 28 SUBMITTED BY : SOMDATT

    3. Growth of some specific energy plants for use as energy feed stock and cultivation of

    commercial forestry, aquatic and marine plants for different products.

    By a number of processes, the collected wastes can be converted into solid, liquid and

    gaseous fuels. The technologies include thermal, thermo-chemical and bio-chemical

    conversions. The actual processes in these technologies are combustion, pyrolysis,

    gasification, alcoholic fermentation, liquefaction etc.

    The main products of conversion technologies are energy (thermal, steam, electricity), solid

    fuels (charcoal, combustibles) and synthetic fuels (methanol, methane, hydrogen gas etc.).

    These can be used for different purposes like cooking, lighting, heating, water pumping,

    electricity generation and as industrial and transport fuels.

    Depending on the nature and availability of these wastes and organic residues they can be

    utilized in different manners as described here.

    1. Fuel biomass

    By some processes and procedures, biomass products like fuel gas, liquid fuels, gaseous fuels

    etc. are obtained, which are given here

    Biomass from plants or animal origin are directly burnt for cooking and other purposes.

    Municipal and sewage wastes, industrial wastes and agricultural wastes are converted to

    energy which can meet the demand for energy in rural sector.

    Paddy straw and rice husk can be profitably converted to fuel gas by thermal

    decomposition (Combustion)

    Ethanol, which is used as a liquid fuel can be produced from carbohydrates by alcoholic

    fermentation.

    When wood and agricultural residues are heated in the absence of air (pyrolysis), charcoal

    is the resultant product which can be used as a fuel more advantageously than wood.

    By the process of gasification, gas is evolved which can be used as a fuel for engines.

    Biogas, which is popular in rural areas is produced by anaerobic fermentation from farm

    wastes.

    2. Feed biomass

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    25/28

    NICMAR PGPM 24

    Page 25 of 28 SUBMITTED BY : SOMDATT

    Conventionally, crop residues are used as cattle-feed. However, some of them with high

    percentage of lignin or non-digestible constituents need certain treatments such as soaking in

    water, alkali/alcohol to make their use as a fuel. The oil-cakes of various crop seed like

    cotton, rubber, tobacco etc. can also be used as a feed after extraction of toxic materials.

    3. Organic fertilizer biomass

    Dry fermented slurry can be used as a direct organic fertilizer for crop land.

    4. Fibre biomass

    The fibrous agricultural wastes and residues are being profitably utilised for making pulp for

    cheap grade paper.

    5. Chemical biomass

    Highly siliconous agricultural residues like rice husk and rice straw can be converted into

    useful chemicals like morphous silicon, silicate products and solar grade silicon. Furfural an

    another chemical can be produced from biogases, cotton seed hulls, corn-cobs, flax fibres, oat

    hulls etc., which is used as a solvent for some petroleum products.

    (ii) Wind as a source of Energy

    Today, people are realizing that wind power "is one of the most promising new energy

    sources" that can serve as an alternative to fossil fuel-generated electricity.

    With today's technology, wind energy could provide 20% of America's electricity (or about

    the amount nuclear power provides) with turbines installed on less than 1% of its land area.

    And within that area, less than 5% of the land would be occupied by wind equipment-the

    remaining 95% could continue to be used for farming or ranching. By the year 2020, 10

    million average American homes may be supplied by wind power, preventing 100 millionmetric tons of CO2 emissions every year. Lessening our dependence on fossil fuels is critical

    to the health of all living things, and wind energy can do just that.

    The 3 billion kWh of electricity produced by America's wind machines annually displace the

    energy equivalent of 6.4 million barrels of oil and avoid 1.67 million tons of carbon

    emissions, as well as sulfur and nitrogen oxide emissions that cause smog and acid rain. In

    other words, "more wind power means less smog, acid rain, and greenhouse gas emissions".

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    26/28

    NICMAR PGPM 24

    Page 26 of 28 SUBMITTED BY : SOMDATT

    Windmills may have been around for almost 1500 years, but it was not imagined that wind

    power would become affordable enough to compete with fossil fuels. Indeed it has. In fact,

    many utility services around the world offer wind-generated electricity at a premium of 2 to 3

    cents per kWh. If a household used wind power for 25% of its needs, it would spend only $4

    or $5 dollars per month for it and the price is still dropping.

    Compare this to 4.8 to 5.5 cents per kWh for coal or 11.1 to 14.5 cents per kWh for nuclear

    power. Wind energy is therefore "cheaper than any other new electric generation except

    natural gas.[which] emits one pound of greenhouse gases for every kilowatt-hour of

    electricity it generates." The success of this energy is in part due to the fact that its costs have

    gone "down by more than 80% since the early 1980s." Even lower prices are expected, as

    "industry analysts see the cost dropping by an additional 20 percent to 40 percent by 2005".

    Wind power is now the world's fastest growing energy source and has also become one of the

    most rapidly expanding industries, with sales of roughly $3 billion in 2008. Major offshore

    developments are likely in northern European waters in the early part of the next century.

    This will be the next major step for this technology and will result in a dramatic increase in

    decentralized electricity generation. Offshore wind has the potential to deliver substantial

    quantities of energy at a price that is cheaper than most of the other renewable energies, as

    wind speeds are generally higher offshore than on land.

    As of 1999, global wind energy capacity topped 10,000 megawatts, which is approximately

    16 billion kilowatt-hours of electricity. That's enough to serve over 5 cities the size of Miami,

    according to the American Wind Energy Association. Five Miamis may not seem significant,

    but if we make the predicted strides in the near future, wind power could be one of our main

    sources of electricity. "With today's technology, wind energy could provide 20% of America

    's electricity (or about the amount nuclear power provides) with turbines installed on less than

    1% of its land area. And within that area, less than 5% of the land would be occupied by windequipment the remaining 95% could continue to be used for farming or ranching." By the year

    2010, 10 million average American homes may be supplied by wind power, preventing 100

    million metric tons of CO 2 emissions every year.

    Lessening our dependence on fossil fuels is critical to the health of all living things, and

    wind energy can do just that. "The 3 billion kWh of electricity produced by America's wind

    machines annually displace the energy equivalent of 6.4 million barrels of oil and avoid 1.67

    million tons of carbon emissions, as well as sulfur and nitrogen oxide emissions that cause

  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    27/28

    NICMAR PGPM 24

    Page 27 of 28 SUBMITTED BY : SOMDATT

    smog and acid rain." In other words, "more wind power means less smog, acid rain, and

    greenhouse gas emissions."

    (iii) Mini and micro hydroelectric projects.

    Water flowing downstream is a powerful force. Water is a renewable resource, constantly

    recharged by the global cycle of evaporation and precipitation. The heat of the sun causes

    water in lakes and oceans to evaporate and form clouds. The water then falls back to Earth as

    rain or snow, and drains into rivers and streams that flow back to the ocean. Flowing water

    can be used to power water wheels that drive mechanical processes. And captured by turbines

    and generators, like those housed at many dams around the world, the energy of flowing

    water can be used to generate electricity.

    (iv) Solar power

    Solar energy is the energy derived from thesun through the form ofsolar radiation.Solar

    powered electrical generation relies onphoto voltaics andheat engines.A partial list of other

    solar applications includes space heating and cooling throughsolar

    architecture,daylighting,solar hot water,solar cooking,and high temperature process heat for

    industrial purposes.

    Solar technologies are broadly characterized as either passive solar or active solar depending

    on the way they capture, convert and distribute solar energy. Active solar techniques includethe use of photovoltaic panels and solar thermal collectors to harness the energy. Passive solar

    techniques include orienting a building to the Sun, selecting materials with favorable thermal

    mass or light dispersing properties, and designing spaces that naturally circulate air.

    (v) Nuclear power

    Many researchers consider that harnessing the energy of the atom in fission reactions is the

    most important alternative energy resource that we have, for the simple fact of the immense

    power that it can generate.

    Nuclear power plants are especially "clean-burning" and their efficiency is quite staggering.

    Nuclear power is produced at 80% efficiency, meaning that the energy created by the fission

    reactions is almost equal to the energy put into producing the fission reactions to begin with.

    There is not a lot of waste material created by nuclear fission-although, due to the fact that

    there is no such thing as producing energy without also creating some measure of waste, there

    is some. The apprehensions of people such as environmentalists regarding using nuclear

    power as an alternative energy source are based on this waste, which are radioactive gases

    that must be contained.

    http://en.wikipedia.org/wiki/Sunhttp://en.wikipedia.org/wiki/Solar_radiationhttp://en.wikipedia.org/wiki/Solar_powerhttp://en.wikipedia.org/wiki/Solar_powerhttp://en.wikipedia.org/wiki/Photovoltaicshttp://en.wikipedia.org/wiki/Heat_enginehttp://en.wikipedia.org/wiki/Solar_architecturehttp://en.wikipedia.org/wiki/Solar_architecturehttp://en.wikipedia.org/wiki/Daylightinghttp://en.wikipedia.org/wiki/Solar_hot_waterhttp://en.wikipedia.org/wiki/Solar_cookinghttp://en.wikipedia.org/wiki/Solar_cookinghttp://en.wikipedia.org/wiki/Solar_hot_waterhttp://en.wikipedia.org/wiki/Daylightinghttp://en.wikipedia.org/wiki/Solar_architecturehttp://en.wikipedia.org/wiki/Solar_architecturehttp://en.wikipedia.org/wiki/Heat_enginehttp://en.wikipedia.org/wiki/Photovoltaicshttp://en.wikipedia.org/wiki/Solar_powerhttp://en.wikipedia.org/wiki/Solar_powerhttp://en.wikipedia.org/wiki/Solar_radiationhttp://en.wikipedia.org/wiki/Sun
  • 8/11/2019 NICMAR PGPM-24 SOMDATT - (213-10-31-11813-2154)

    28/28

    NICMAR PGPM 24

    The radiation from these gases lasts for an extremely long time, so it can never be let out once

    contained and stored. However, the volume of this waste gas generated by the nuclear power

    plants is small in comparison to the volume of NOx (nitrous oxide-that is, air pollution) that is

    attributable to one day's worth of rush-hour commuter traffic in Los Angeles. Whereas the

    radiation is certainly the more deadly by far of the two waste products, the radiation is also by

    far the simpler of the two to contain and store. In spite of the concerns of the

    environmentalists, nuclear power is actually environmentally friendly alternative power, and

    the risk of the enclosed radiation getting out is actually lower than you would expect. With a

    relatively low volume of waste material created, it should not be a difficult thing at all for

    storage and disposal solutions for the long-term to be formulated as technology advances.

    The splitting of an atom produces energy in the forms of both heat and light. Atomic power

    plants control the fission reactions so that they don't lead to the devastating explosions that are

    generated by atomic and hydrogen bombs. There is hardly any chance of an atomic power

    plant exploding similar to a nuclear bomb, as the specialized conditions and the pure

    Plutonium utilized to unleash an atomic bomb's vicious force just simply don't exist inside a

    nuclear power plant. The risk of a "meltdown" is very low. Although this latter event has

    changed a couple of times, when one considers that there are over 430 nuclear reactors spread

    out across 33 nations around the world, and that nuclear reactors have been used since the

    early 1950s, these are rare incidents, and the events akin to that which have taken place were

    the fault of outdated materials which should have been properly maintained. Indeed, if nuclear

    energy could become a more broadly accepted form of alternative energy, there would be

    little question of their upkeep being maintained. Presently, six states in America generate

    more than half of all their electrical energy needs by way of nuclear power, and the media are

    not filled with grim horror stories of the power plants regularly having difficulties.