5
Project: K. D. Malaviya National Oil Museum 1 84934617.xls K. D. MALAVIYA NATIONAL OIL MUSEUM FAULT LEVEL CALCULATION 1 SCOPE : Calculations for Source Impedance (Zs) :  The equivalent impedence for 500 MVA a fault level is 2.18 Ohms 500 MVA/ (3 x 33kV )  3 Calculations for cable A:  System : 33kV  At Supply point (I.e. outoging of State Electricity Board Circuit Breaker) 8.75KA sqrt 3 x 33 k V Assuming conductor area to be A mm² and time duration of 1 sec I sc = 0 .094 A/ sqrt t  8.75 = 0.094 A/ sqrt t A = 8.75 x 1 /0.094 = 93.08mm²  The said cable should cater to normal full load current corresponding to 0.8MVA at 33kV I.e 14.00Amp From the cable manufacturer's data table 3C x 120 mm² cable is necessary to satisfy conditions (a) and (b) for XLPE (E) cable : 4 Impeden ce of cable A ( Za) : Length of Cable 'A' is about 20 Mtrs. Impedence of cable A = (0.253 ) x 20 / 1000 Za = 0.0051 Ohms Therefore total impedence at the owner's 33kV V.C.B panel is = Za + Zs = = 2.1780 + 0.0051 = 2.1805 Ohms Selected size for Cable B is 3C X 120mm²  The building has one vertical electric shafts. Through there rising mains will be run for normal and emergency loads. The A.H.U.s and distribution boards on any floor will be connected to rising main with suitable plug-in-units/breakers.  The sizing of L.T. cables has been done using the fact that circuit breakers will interrupt fault current in 8 c.p.s ( I.e. 0.16 secs) and compensation required for temperature and bunching of cables in cable trays. The sizing of H.T cables is done on the basis of available data of fult level at site (500 MVA) The block diagram is Zs = 33 kV/ 3 I = 500 MVA = Supply Co’s C.B Owner’s VCB Main L T Panel A B B INCOMER 33kV Cable 3 Panel 33kV VCB Panel 33kV Cable 400kVA X’mer

NOMElec_FaultlevelCalc_20041005

  • Upload
    zipdash

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

8/3/2019 NOMElec_FaultlevelCalc_20041005

http://slidepdf.com/reader/full/nomelecfaultlevelcalc20041005 1/5

Project: K. D. Malaviya National Oil Museum 1

K. D. MALAVIYA NATIONAL OIL MUSEUM

FAULT LEVEL CALCULATION

1 SCOPE :

Calculations for Source Impedance (Zs) :

 The equivalent impedence for 500 MVA a fault level is

2.18 Ohms

500 MVA/ (3 x 33kV )  

3 Calculations for cable A:  

System : 33kV  

At Supply point (I.e. outoging of State Electricity Board Circuit Breaker)8.75KA

sqrt 3 x 33 kV

Assuming conductor area to be A mm² and time duration of 1 sec

I sc = 0 .094 A/ sqrt t  

8.75 = 0.094 A/ sqrt t

A = 8.75 x 1 /0.094 = 93.08mm²

 The said cable should cater to normal full load current corresponding to 0.8MVA at 33kV

I.e 14.00Amp

From the cable manufacturer's data table 3C x 120 mm² cable is necessary to satisfy conditions

(a) and (b) for XLPE (E) cable :

4 Impedence of cable A ( Za) :

Length of Cable 'A' is about 20 Mtrs.

Impedence of cable A = (0.253 ) x 20 / 1000

Za = 0.0051 Ohms

Therefore total impedence at the owner's 33kV V.C.B panel is

= Za + Zs =

= 2.1780 + 0.0051 = 2.1805 Ohms

Selected size for Cable B is 3C X 120mm²

 The building has one vertical electric shafts. Through there rising mains will be run for normal andemergency loads. The A.H.U.s and distribution boards on any floor will be connected to rising main withsuitable plug-in-units/breakers.

 The sizing of L.T. cables has been done using the fact that circuit breakers will interrupt fault current in 8c.p.s ( I.e. 0.16 secs) and compensation required for temperature and bunching of cables in cable trays. Thsizing of H.T cables is done on the basis of available data of fult level at site (500 MVA) The block diagram

Zs = 33 kV/ 3

I = 500 MVA =

SupplyCo’sC.B

Owner’sVCB

MainLTPanel

A

B

BINCOMER  33kV

Cable

3 Panel 33kV

VCB Panel

33kV

Cable400kVA

X’mer

8/3/2019 NOMElec_FaultlevelCalc_20041005

http://slidepdf.com/reader/full/nomelecfaultlevelcalc20041005 2/5

Project: K. D. Malaviya National Oil Museum 2

K. D. MALAVIYA NATIONAL OIL MUSEUM

FAULT LEVEL CALCULATION

8/3/2019 NOMElec_FaultlevelCalc_20041005

http://slidepdf.com/reader/full/nomelecfaultlevelcalc20041005 3/5

Project: K. D. Malaviya National Oil Museum 3

K. D. MALAVIYA NATIONAL OIL MUSEUM

FAULT LEVEL CALCULATION

5Impedence of cable B ( Zb) :

Length of Cable 'B' is about 20 Mtrs.

Impedence of cable B = (0.253) x 20 / 1000Zb = 0.0051 Ohms

Therefore total impedence at the Transformer

Z t = (Za + Zs + Zb )

Z t = 2.1780 + 0.0025 +.0051 = 2.1856 Ohms

6 Impedence of Transformer ( Z tr) :

Assuming transformer impedence to be 5% is V² x X% , Where V is the secondary voltage

 

MVA

0.0215 Ohms

  400 X1000 X100

(HV)²

(33000)²

Z eq = 0.00034 + 0.0215 = 0.0218 Ohms

Zeq = 0.0218 Ohms

7Fault level calculation :

Z eq

10.99KA

0.02Isc = 10.99 kA

So, we are considering that the maximum fault level as 11KA.

 The impedence at the secondary side of the transformer is the sum of equivqlent impedence of StateElectricity Boards network, the cable 'A', the cable 'B' (all reflected on secondry side) plus impedence of thtransformer

Z tr = (V)² x Z% =

Z tr = (415)² x 5 =

 Total impedence on secondarysideZ eq = (LV)² x.Z t + Z tr

Z eq = (415)² x2.1856+0.0215

Zeq = 0.00016 x 2.1856 +

0.0215

 The fault current at the secondarycurrent of the transformer is

Isc = 415/sqrt 3

Isc = 415/sqrt 3 =

8/3/2019 NOMElec_FaultlevelCalc_20041005

http://slidepdf.com/reader/full/nomelecfaultlevelcalc20041005 4/5

19

AHU RISER PIU 1 AHU-GRA-DB Gr-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 2 AHU-GRB-DB Gr-AHU Rm-B  YFY 1 4C X 16

AHU RISER PIU 3 AHU-BANK-DB Gr-AHU Rm-Bank  YFY 1 4C X 16

AHU RISER PIU 4 AHU-01A 01-AHU Rm-A  YFY 1 4C X 10AHU RISER PIU 5 AHU-01B 01-AHU Rm-B  YFY 1 4C X 10

AHU RISER PIU 6 AHU-02A 02-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 7 AHU-02B 02-AHU Rm-B  YFY 1 4C X 10

AHU RISER PIU 8 AHU-03A 03-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 9 AHU-03B 03-AHU Rm-B  YFY 1 4C X 10

AHU RISER PIU 10 AHU-04A 04-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 11 AHU-04B 04-AHU Rm-B  YFY 1 4C X 10

AHU RISER PIU 12 AHU-04-DB 04-Elect. Rm-01  YFY 1 4C X 16

AHU RISER PIU 13 AHU-05A 05-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 14 AHU-05B 05-AHU Rm-B  YFY 1 4C X 10AHU RISER PIU 15 AHU-06A 06-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 16 AHU-06B 06-AHU Rm-B  YFY 1 4C X 10

AHU RISER PIU 17 AHU-07A 07-AHU Rm-A  YFY 1 4C X 10

AHU RISER PIU 18 AHU-07B 07-AHU Rm-B  YFY 1 4C X 10

AHU RISINGMAIN 400 A

8/3/2019 NOMElec_FaultlevelCalc_20041005

http://slidepdf.com/reader/full/nomelecfaultlevelcalc20041005 5/5

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWGSq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWGSq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG

Sq.mm 2 8 SWG