44
E nergy S ystems NT series introduction UPS training June 2006 Markus Schwab

NT series introduction UPS training June 2006 Markus Schwab

  • View
    219

  • Download
    5

Embed Size (px)

Citation preview

Page 1: NT series introduction UPS training June 2006 Markus Schwab

E n er gy S ystem s

NT series introductionUPS training June 2006

Markus Schwab

Page 2: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 2

E n er gy S ystem s NT-series UPS Introduction

Features: Online double conversion UPS

20-200kVA models

Very compact size to save floorspace

Up to 4 units parallelable for capacity or redundancy

Very wide input voltage range for fewer switching to battery and longer battery life

100% unbalanced and computer load suitability

Redundant auxiliary power and redundant static switch control

Intelligent charger design to extend battery lifetime

Hot-Standby function is available

Reduced charger capacity when run from generator source

Soft start to smoothly load a generator

Page 3: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 3

E n er gy S ystem s

Features: User-friendly graphic LCD display

Programmable status dry contacts

RS232 & RS485 communication ports

Optional SNMP interface

Local and remote Emergency Power Off ( EPO ) function

Multi-CPU digital control to minimize the number of components

Intelligent Multi-Speed cooling fan control (less dust and noise, longer life)

Manual & scheduled battery test and battery replacement warning

Built-in SRAM saves up to 500 historical records and event logs

Smart software package with 3-phase functions included

Page 4: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 4

E n er gy S ystem s

Optional features: 12-Pulse rectifier to reduce input current distortion

Single phase output models (20 and 30kVA)

Output transformers for special voltage ratings

Battery Start Function

Page 5: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 5

E n er gy S ystem s

NT-Series 20kVA - 200kVA

General data:

Technology: On-Line

Input / Output: 3-phase / 3-phase

Cabinet type: Tower

Rating: 20, 30, 40, 50, 60, 80100, 120 , 160, 200kVA

Input nominal: 3-phase 380//400/415VAC

Input range: 305 - 499VAC

Input power factor: >0,75

Input frequency: 50/60Hz (auto-selectable)

Output voltage: 3-phase: 380/400/415V1-phase: 220/230/240VAC

Output power factor: 0,8

Output waveform: Pure sine wave

Overload: < 110% - 60 min.< 125% - 10 min.< 150% - 30 sec.

Page 6: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 6

E n er gy S ystem s

NT-Series 20kVA - 200kVA

Temperature range: 0°C - 40°C

Audible noise: 65dBA

Crest factor: 3:1

Input current THD: 6-pulse (standard) 34%12-pulse (optional) 14%

Software: UPSentry included

Battery

Battery: External 29 x 12V

Communication

Front: Graphical Interface with LED indicators

Interface1: RS232 (D-Sub Connector)

Interface 2: SNMP card (optional)

Interface 3: RS485

Page 7: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 7

E n er gy S ystem sStandards

CE approval

EMC EN50091-2 Class A for restricted use IEC62040-2 Class C3

Safety IEC62040-1-2 Restricted access UPS systems ESD IEC 1000-4-2 Level 4 Contact: 8KV Air: 15KV

RS IEC 1000-4-3 Level 3 Field strength: 10V/M

EFT IEC 1000-4-4 Level 4 AC Port: 4KV I/O Port: 2KV

Surge IEC 1000-4-5 Level 4 Input Port: 4KV

CS IEC 1000-4-6 Level 3 Strength: 10Vrms

Page 8: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 8

E n er gy S ystem s

UPS configurations

Page 9: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 9

E n er gy S ystem s

1 2 3 4

A

B

C

D

4321

D

C

B

A

Load

BY PASS

RESERVE

RECTIFIER

OUTPUT

STATIC SWITCH

INVERTER

BATTERY

RECTIFIER

Single unit configuration

Page 10: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 10

E n er gy S ystem s

1 2 3 4

A

B

C

D

4321

D

C

B

A

Load

UPS 1

UPS 2

Parallel configuration

Same bypass

mains

Load

Mains 1

Mains 2

Page 11: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 11

E n er gy S ystem s

1 2 3 4

A

B

C

D

4321

D

C

B

A

Load

UPS 1

UPS 2

Hot standby

Page 12: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 12

E n er gy S ystem sCommon Battery

1 2 3 4

A

B

C

D

4321

D

C

B

A

Load

UPS 1

UPS 2

Note: For capacity increase only, not for n+1 redundancy

Page 13: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 13

E n er gy S ystem s

Hot-Standby ( Common Battery )

1 2 3 4

A

B

C

D

4321

D

C

B

A

Load

UPS 1

UPS 2

Page 14: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 14

E n er gy S ystem sRedundant auxiliary supply

When one DC/DC converter fails, the UPS still normally supplies the load and alarms.

Page 15: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 15

E n er gy S ystem s

1. EPO switch

2. Rectifier ok

3. Reserve input ok

4. Maintenance bypass on

5. Load on battery

6. Inverter operating

7. Load on reserve

8. Output ok

9. Load on inverter

10. Inverter On/Off (with for 3sec. )

11. Display navigation

12. LCD screen

Control panel

Page 16: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 16

E n er gy S ystem s

Advantages of parallel operation: Enhance system reliability (redundancy) Increase power rating Easy capacity extension (on site) Cost advantage (do expansion when needed only)

Parallel operation

Page 17: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 17

E n er gy S ystem s

100%

50% 50%

66% 66% 66%

75% 75% 75% 75%

N + 1 Redundancy

+ ++

Capacity for

n+1 redundancy

Page 18: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 18

E n er gy S ystem s

UPS-1UPS-1-

UPS-2UPS-2-

UPS-NUPS-N-

I1

I2

IN

VL

LoadLoad

-

-

I1

I2

IN

VL

Load sharing ( 3%) Precise voltage

regulation ( 1% )CommunicationEvery unit can be

master Fault isolation

Requirement of UPS Parallel Operation

Page 19: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 19

E n er gy S ystem s

O/P CharacteristicCondition: AC MODE O/P FULL R LOAD

CH1: R Phase O/P Voltage 100V/DIV

CH2: S Phase O/P Voltage 100V/DIV

CH3: T Phase O/P Voltage 100V/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (1)

Measurements taken with four sets 80kVA in parallel

Page 20: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 20

E n er gy S ystem s

O/P CharacteristicCondition: ON LINE MODEI/P: 600KW Generator SourceO/P: 75% R LOAD

CH1: R Phase I/P Voltage 100V/DIV

CH2: R Phase O/P Voltage 100V/DIV

CH3: R Phase I/P Current 200A/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (2)

Page 21: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 21

E n er gy S ystem s

Transfer time TestCondition: Inverter Bypass O/P FULL R LOAD

CH1: R Phase I/P Voltage 100V/DIV

CH2: R Phase O/P Voltage 100V/DIV

CH3: R Phase I/P Current 200A/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (3)

Page 22: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 22

E n er gy S ystem s

Transfer time TestCondition: Main Power Failure AC Backup Mode O/P FULL R LOAD

CH1: R Phase I/P Voltage 100V/DIV

CH2: R Phase O/P Voltage 100V/DIV

CH3: R Phase I/P Current 200A/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (4)

Page 23: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 23

E n er gy S ystem s

O/P SHORT CIRCUITCONDITION: Backup Mode(T PhaseN)FULL R LOAD

CH1: UPS1 O/P Current 200A/DIV CH2: UPS2 O/P Current 200A/DIV

CH3: UPS3 O/P Current 200A/DIV

CH4: UPS4 O/P Current 200A/DIV

At short circuit in AC mode the UPS will switch to bypass to blow the load fuse faster

Parallel Test Waveform (5)

Page 24: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 24

E n er gy S ystem s

Rectifier Soft StartI/P: 600KW Generator SourceO/P: 75% LOAD

CH1: R Phase I/P Voltage 100V/DIV

CH2: R Phase O/P Voltage 100V/DIV

CH3: R Phase I/P Current 200A/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (6)

Page 25: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 25

E n er gy S ystem s

Load Sharing Test, load stepCondition: ON LINE MODEI/P: 600KW Generator SourceO/P: R LOAD (0%100%)

CH1: UPS1 R Phase O/P Current 50A/DIV

CH2: UPS2 R Phase O/P Current 50A/DIV

CH3: UPS3 R Phase O/P Current 50A/DIV

CH4: UPS4 R Phase O/P Current 50A/DIV

Parallel Test Waveform (7)

Page 26: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 26

E n er gy S ystem s

Load Sharing TestCondition: ON LINE MODEI/P: 600KW Generator SourceO/P: R LOAD (0%50%100%0%)

CH1: UPS1 R Phase O/P Current 50A/DIV

CH2: UPS2 R Phase O/P Current 50A/DIV

CH3: UPS3 R Phase O/P Current 50A/DIV

CH4: UPS4 R Phase O/P Current 50A/DIV

Parallel Test Waveform (8)

Page 27: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 27

E n er gy S ystem s

LOAD STEPCONDITION: Nominal LineR LOAD (100%0%)

CH1: R Phase O/P Voltage 100V/DIV

CH2: S Phase O/P Voltage 100V/DIV

CH3: T Phase O/P Voltage 100V/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (9)

Page 28: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 28

E n er gy S ystem s

LOAD STEPCONDITION: Nominal LineR LOAD (0%100%)

CH1: R Phase O/P Voltage 100V/DIV

CH2: S Phase O/P Voltage 100V/DIV

CH3: T Phase O/P Voltage 100V/DIV

CH4: R Phase O/P Current 200A/DIV

Parallel Test Waveform (10)

Page 29: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 29

E n er gy S ystem s

Phase Shift Method ( 12-PULSE Rectifier )

Active Filter (in development)

UPS Input Harmonic Improve Methods

Page 30: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 30

E n er gy S ystem s

100 KVA UPS

Volts = 223.6 Vac

Amps = 173.9A

PF = 0.765

A thd = 11.54%

AH05 = 1.700%

AH07 = 1.099%

AH011= 8.236%

AH013 = 1.894%

12 - Pulse Rectifier Input Current Waveform

Page 31: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 31

E n er gy S ystem s

+

-

+

-

S1

S2

S3

S4

S5

S6

vSa vSb vSc

iSaiSbiSc

iLaiLbiLc

iAPFaiAPFbiAPFc

Block diagram of active filter

Page 32: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 32

E n er gy S ystem s

I / P THD=2.9%I / P THD=2.9%

vvSaSa

iiLaLa

iiAPFaAPFa

iiSaSa

I / P THD=2.9%I / P THD=2.9%

vvSaSa

iiLaLa

iiAPFaAPFa

iiSaSa

Current waveform with active filter

Page 33: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 33

E n er gy S ystem s

6-Pulse and 12-Pulse Harmonic Curve

Page 34: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 34

E n er gy S ystem s

Generally speaking:

If the UPS rectifier is 6-PULSE configuration, then the generator capacity must be 2 times of the UPS capacity.

If the UPS rectifier is 12-PULSE configuration, then the generator capacity must be 1.5 times of the UPS capacity.

Generator CapacityGenerator Capacity

Page 35: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 35

E n er gy S ystem s

Battery Management System

BatteryManagement

System

Battery voltage Battery currentBattery parameterLoad conditionUser settings

Battery Charge VoltageBattery Test ResultBattery CapacityBattery Remaining TimeBattery Low WarningBattery Leakage Warning Battery Installation dateBattery Next replacement dateBattery Replace Warning

Page 36: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 36

E n er gy S ystem s

0 ~ T1 : constant current charge

T1 ~ T2 : constant voltage charge -> automatic boost charge

T2 ~ : constant voltage charge -> float charge

Parameters can be set by the user

Battery charging method

Page 37: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 37

E n er gy S ystem s

0 ~ T1 : battery floated

T1 : start battery test -> manually -> scheduled

T1 ~ T2 : discharge time

T2 : finish discharge test, battery return to floated

If the battery voltage is lower than the test voltage, the test is stopped and an alarm is generated

Battery test

Page 38: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 38

E n er gy S ystem s

Battery Ground Fault Detect

The battery ground will be connected to separate ground terminal at the UPS, large currents to ground can be detected.

Page 39: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 39

E n er gy S ystem s

Width (mm) Depth (mm) Height (mm)600 800 1400800 830 1700

1200 830 1700

Battery(AH) Width (mm) Depth (mm) Height (mm)

NT BBU 1 40 1 600 800 1400NT BBU 2 40 1 600 800 1700NT BBU 3 40 2 900 800 1700NT BBU 4 100 1 970 800 1700

Every battery string with 29 pieces 12V batteries in series.

DimensionKVA

100/120160/200

NT Cabinet

DimensionBatterystring

NT Battery Cabinet

20/30/40/50/60/80

NT dimensions

Page 40: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 40

E n er gy S ystem s NT series Runtime table

Example: 60KVA 30 min – NT BBU1*4 (40AH*4>152AH)

100KVA 30 min – NT BBU4*3 (100AH*3> 250AH)

KVA TIME 10mins 15mins 30mins 1Hour 2Hours 4Hours 8Hours

20KVA 25 34 51 85 151 279 484

30KVA 37 51 77 128 226 419 727

40KVA 48 68 101 169 299 552 958

50KVA 60 85 127 211 373 690 1198

60KVA 72 101 152 254 448 828 1437

80KVA 96 134 200 345 591 1093 1895

100KVA 120 167 250 418 739 1366 2369

120KVA 144 200 301 502 886 1639 2843

160KVA 192 268 401 669 1182 2185 3790

200KVA 240 334 502 836 1477 2731 4738

UNIT : AH

Page 41: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 41

E n er gy S ystem s Thermal simulationScalar Show Vector Show

Unit=ft/min

T max LI1=117 0C

X

Y

Z

Page 42: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 42

E n er gy S ystem s

1

Dynamic Animation Display (100X Displacements)

U2

U3

U1

Seismic Simulation for UPS 60K- Vibration in Z Direction and Response Deflections

Page 43: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 43

E n er gy S ystem s

1

Seismic Simulation for UPS 60K- Vibration in Z Direction and Response Deflections

(5X Displacements)

(Green color mesh is the original shape of structure)

Page 44: NT series introduction UPS training June 2006 Markus Schwab

© 2023年4月18日 Delta Energy Systems 44

E n er gy S ystem s

Thanks