Tabel 3.2 Ongkos Material No Nama barang TOKO Harga (Rp) Satuan kuantit as Jumlah harga (Rp) 1 Mesh 10 CV. DUA PUTRA PETIR 70.00 0 m 2 1 70.000 2 Mesh 20 CV. DUA PUTRA PETIR 100.0 00 m 2 1 100.000 3 Bantalan PD. ABOI JAYA 25.00 0 Kg 6 150.000 4 Bahan poros S40C 25.00 0 Kg 4 100.000 5 Puli penggerak 100.0 00 Unit 1 30.000 6 Puli yang digerakan 100.0 00 Unit 1 50.000 7 Bantalan 20 mm 20.00 0 Unit 2 40.000 8 Pasak 10x8 bahan S40C 1000 Unit 5 5.000 15 Baud + ring 10 x 50 mm 2.100 Unit 15 31.500 16 Baud + ring 6 x 100 mm 1.500 Unit 5 7.500 17 V-belt 50.00 0 Unit 1 50.000

Onkos Material Tabel

  • Upload
    faruq

  • View
    213

  • Download
    0

Embed Size (px)

DESCRIPTION

ongkos material

Citation preview

Page 1: Onkos Material Tabel

Tabel 3.2

Ongkos Material

No Nama barang TOKOHarga

(Rp)Satuan kuantitas

Jumlah harga

(Rp)

1 Mesh 10 CV. DUA

PUTRA PETIR

70.000 m2 1 70.000

2 Mesh 20 CV. DUA

PUTRA PETIR

100.000 m2 1 100.000

3 Bantalan PD. ABOI

JAYA

25.000 Kg 6 150.000

4 Bahan poros S40C 25.000 Kg 4 100.000

5 Puli penggerak 100.000 Unit 1 30.000

6 Puli yang digerakan 100.000 Unit 1 50.000

7 Bantalan ∅20 mm 20.000 Unit 2 40.000

8 Pasak 10x8 bahan

S40C

1000 Unit 5 5.000

15 Baud + ring ∅ 10 x

50 mm

2.100 Unit 15 31.500

16 Baud + ring ∅ 6 x

100 mm

1.500 Unit 5 7.500

17 V-belt 50.000 Unit 1 50.000

18 Motor listrik 700.000 Unit 1 700.000

Total Ongkos Material (Cm) 1.334.000

Tabel 3.3 Ongkos Peralatan

No Nama mesin/

peralatan

Harga

sewa (Rp)

satuan Lama pakai

(jam)

Jumlah

harga (Rp)

1 Bubut konvensional

lengkap

15.000 Per jam 4 60.000

2 Las listrik lengkap 20.000 Per jam 22 440.000

3 Bor konvensional 15.000 Per jam 6 90.000

Page 2: Onkos Material Tabel

lengkap

4 Mesin gergaji 10.000 Per jam 5 50.000

Total ongkos mesin dan peralatan (C p) 640.000