Upload
juliana-willis
View
221
Download
6
Embed Size (px)
Citation preview
PACMAN Workshop
OUTLINE
IntroductionESR 3.1 Challenges
- Stability budget and Precision Mechanical Design- Precision Assembly of MBQ and BPM - System Integration
Done and UndergoingFuture
CERN 03/02/2015by
Iordan Doytchinov
“If you grasp the principles – myths fall & Ideas take-off” David Lentink
(TUDELFT) TED Conference Amsterdam
(“ خليفة (“Khalifa Tower" ,برج– Dubai 2010
Babylon tower by Tobias Verhaecht (1561 – 1631)
CLIC Challenge
2
200m
2m
CLIC alignment Challenge:
Calibrate and pre-align all critical components to allow maximum error of 17µm (diameter of a cylinder) over 200
meters length of sliding window of assembled components
17µmNever done before. Needed for ~50km future colliders!
2 meter section of the Accelerator
Steps AS structures and BPM
MBQ
Zero of components to fiducials [µm] 5 10Fiducials to sensor interface on support [µm] 5 5
Sensor interface to sensor zero [µm] 5 5Sensor measurement w.r.t straight reference [µm] 5 5
Stability knowledge of the straight reference [µm] 10 10
Total: Error fromperfect alignment (as uncorrelated uncertainties) U [µm] 14 17
The PACMAN system targets
3
Girders Alignment Budget CLIC
Physicists requirements for CLIC to operate
Pre-alignment PACMAN Uncertainty budget [µm] @BPM 6.78
@MBQ 11.8
Mechanical Stability for PACMAN system
yX
Z
+
Where
Uncertainty Sphere with Diameter Uc(y) of 6.78µm for
BPM and 11.8µm for MBQ
y
X
Z
Real time RF or Magnetic Centre
Real time RF Centre
Real time Magnetic centreStretched wire
Coordinate centre of Reference System by 3x
ceramic balls
5
+
Mechanical Stability for PACMAN system
= (vision sensor) + (CMM@L1)]
=
¿𝟏
= (Head Change) +
𝟎 .𝟐𝟓µ𝒎 @L=0.5m
@L=0.5m
= 43.4384
= 6.59 µm
0.89
1.64 1
𝑼 𝟐 (𝑭𝒊𝒆𝒍𝒅 𝑴𝒆𝒂𝒔𝒖𝒓𝒆 )=𝑐𝑒𝑚2 𝑈 2 (𝐸𝑙𝑒𝑐𝑡𝑟𝑜𝑛𝑖𝑐 𝑠𝑈𝑛𝑐𝑒𝑟𝑡𝑎𝑖𝑛𝑡𝑦 )+𝒄𝒎𝒆𝟏
𝟐 𝑼 𝟐 (𝒎𝒆𝒄𝒉𝒂𝒏𝒊𝒄𝒂𝒍 𝑬𝒓𝒓𝒐𝒓𝒔 𝑫𝒓𝒊𝒇𝒕 )
[1] Stability of Optical Elements in the NIF Target Area Building [David J. Trummer, Richard J. Foley, Gene S. Shaw]
𝟔 .𝟕𝟖𝟐µ𝒎
Mechanical Stability for PACMAN system
=
Uncertainty Input Only Rotation (Θz+αx) OROnly Translation ( + ) Σ = sqrt(Rot^2 +
Translation^2)U(structural) ? OR ? ?U(Thermal Transient) ? OR ? ?U(Contingency) ? OR ? ? TOTAL: U(Mechanical Errors Drift) 2.99µrad – 0.618 arcs OR 5-6µm 5-6µm
m
5-6µm
m
m
Translation or rotation on Y axis irrelevant for magnetic or RF field alignment
α
Assembly of MBQ and BPM
8
DesignManufac
turing
Hard/expensive to optimise
Measurement + evaluation
Magnetic measurement
Assembly stage+ jig/tooling
The problem: Mechanical Uncertainties Correlated to Magnetic uncertainty
How the assembly cycle and correlated uncertainties can be deterministically controlled? - Integrate CAD,CAM, CMM, Magnetic measurement into one cycle? Use information real time at assembly?
9
PACMAN ESR 3.1 Assembly of MBQ and BPM
10
BPM mechanical Centre
Magnet mechanical centre
Volumetric assembly tolerance zone cylinder
Match the real-time RF and Magnetic centres to required accuracy for error compensation
[2] 0.3mm Distance from the centre [mm]
[2] Design of the 15GHz BPM Test Bench for the CLIC Test Facility to perform precise stretched wire RF measurements: Silvia Zorzettiy, Luca Fanucciy, Natalia Galindo Mu~noz and Manfred Wendt
Assembly accuracy desired = Linear_region_size - [(Magnetic measurement uncertainty) +(RF measurement uncertainty)] = 0.54mm
Vacuum enabling enabling interface to butterfly vessel!Electrical connectors feed-troughConfined spaceHigh assembly repeatability,Mechanical and thermal transient stability (critical assembly!)
PACMAN ESR 3.1 Sub-System Integration to Final system
ESR 3.1
Other PhD
Researchers
Monitoring sub-systems specification and their development for any
integration issues!
Magnetic Measurement
None-Contact CMM Head/Micro
triangulation - Wire Localization
BPM Measurement
RF Cavity Measurement
Need Requirements Need Requirements
‘Cli
en
ts’
Integrated system requirements
Need Requirements
Activities done so far and undergoing:
12
Technical trainings (metrology, tolerancing, CATIA, ANSYS, etc.)
System Integration studies
Magnet assembly studies (on existing MBQ prototypes)
Mechanical error budget studies
Initial Literature survey
Industrial survey and relations (GD&T analysis software's) 3dcs, sigmetrix, KOTEM
Link with QVI/KOTEM technologies and Metrosage on possible future collaboration
BPM/MBQ connector 1st conceptual design
Planning for first Integration Thermal vs Vibrations VS Magnetic Issues experiment
Future plans
13
Complete literature survey for 1 year Review at Cranfield University
DMP secondment?
Thermal vs. Vibrations vs. Magnet centre shift issues experiments
BPM/MBQ precision connector design/manufacture + evaluation
Further magnet assembly test
Further uncertainty estimation investigation
Further system integration investigation
More development in: Investigation relationship between real component shape and corelated magnetic
errors. (possible collaboration with KOTEM)- Further specific literature survey in the area
- assembly method including GD&T software and real-time data- assembly jig design
Thank you for your attention,
Any questions?
14
“Errors, like straws, upon the surface flow; He who would search for pearls, must dive
below.”
― John Dryden, All for Love
BPM Concept
15