Upload
brett-harrison
View
218
Download
1
Embed Size (px)
Citation preview
Page 1D.Goutte FINUPHY Funchal 2005
GANIL 2005GANIL 2005
Page 2D.Goutte FINUPHY Funchal 2005
GANIL 2010GANIL 2010
Page 3D.Goutte FINUPHY Funchal 2005
Fusion reactions Fusion reactions (with n-rich beams)(with n-rich beams)
Fission productsFission products(with converter)
N = Z N = Z ISOL (thick target)
TransfermiumsTransfermiumsIn-Flight (Z=106,108)
High Ex fission productsHigh Ex fission products(without converter)
Primary beams : Primary beams : deuteronsdeuterons heavy ionsheavy ions
Light Light Radioactive Radioactive NucleiNuclei(very high intensity)
Page 4D.Goutte FINUPHY Funchal 2005
with 1014 fissions/second
Page 5D.Goutte FINUPHY Funchal 2005
CIME Cyclotron RNB (fission-fragments)
E < 6-7 MeV/u
Production Cave
C converter+UCx target
> 1013 fiss./s
SC - LINACE = 14.5 AMeV
HI A/Q=3E = 40 MeV - 2H
Low energy RNB
ECRIS-HI 1mA
“SILHI-deut.” 5mA
High Intensity HI
Page 6D.Goutte FINUPHY Funchal 2005
Modification périmètre INB 113
Page 7D.Goutte FINUPHY Funchal 2005
Multi-Faisceaux
2
3
54
séparateur
1+/n+
New direct linesCIME salles G1-G2
LIRAT 1
SPIRAL2 : 40 MeV D+ onto ECS
Standard GANIL3) stable beam/RIB at
50-100 A.MeV (CSS ’s)4) 1 A.MeV stable (IRRSUD)
5) 8-10 A.MeV stable (SME)
1) Low energy RIB (LIRAT)2) 6 A.MeV RIB CIME VAMOS / EXOGAM
Example (5 beams)
Page 8D.Goutte FINUPHY Funchal 2005
…………… 2001 2002 2003 2004 2005 2006 2007 2008
APS
SPIRAL 2 APD
Construction phase
LinagChoiceOption
PreliminaryStudies
End ofAPD
2009
« Green Light » from the Minister of Research First BeamFirst Beam
Page 9D.Goutte FINUPHY Funchal 2005
Accélérateur
Sources+LEBT RFQ MEBT
RFQ 1
source D+
QWR (12 mod x 1 cav) QWR (7 mod x 2 cav)
88 MHz =0.07
ion sources(1/3,1/6)
max Eacc = 6.5 MV/m
88 MHz =0.12
RFQ 2
micro-phoenix : mai 2003SILHI : juillet 2004
proto : fin juin 2004tests Catane : sept. 2004
simulations start-to-end : sept 2004
proto : nov 2004tests : dec 2004, janv 2005
Page 10D.Goutte FINUPHY Funchal 2005
SILHI-like source (DAPNIA)
• Based on SILHI source 2.45 GHz (135mA)• Adaptation to Spiral2 : permanent magnets optimisation of the extraction system
achieved : 4.2 mA deuteron achieved with extraction hole of 3 mm
Large fraction of impurities (30%)experiments for reduction of impurity content
Source deutons
source & HV column assembly
measured emittance ~ 0.1 mm.mrad
Page 11D.Goutte FINUPHY Funchal 2005
A-PHOENIX Source
• Based on the Phoenix source• New version 28 GHz, 60 kV
Next step ...• HT superconducting coils• Compact hexapole• Optimised for heavy elements
Source ions stables
Page 12D.Goutte FINUPHY Funchal 2005
10e-610e-510e-410e-310e-210e-1
TraceWin - CEA/DSM/DAPNIA/SACM
Position ( m )80706050403020100
Part
icle
den
sit
y p
rob
ab
ilit
y (
mm
)
80
75
70
65
60
55
50
45
40
35
30
25
20
15
10
5
0
Beam Dynamics
Study of opticsfrom source to target D-beam distribution (H&V)
Beam size 90%, 99%, 99.9%, etc
LEBT RFQ MEBT SC1 SC2 HEBT
LEBT RFQ MEBT SC1 SC2 HEBT
scrapers in LEBT and MEBTfor beam halo reduction
Page 13D.Goutte FINUPHY Funchal 2005
Sept. 2004 : tests at INFN-LNS (Catane)
design : 40 kW for 110 kV vane voltage
power achieved = 50 kW (power meas., X rays)
10 hours of operation at 40kW
50
60
70
80
90
100
110
120
130
140
10 15 20 25 30 35 40 45 50 55
kW read on the Bird
Me
as
ure
d k
V w
ith
X-r
ay
s
Theoretical curve based on Q0
Measured datas
datas after sept 21--> water problem ?
X error bar : +/-5%Y error bar : estimated from measurement
RFQ power tests
concept validatednext step : power test at Grenoblefor vane displacement measurement
Page 14D.Goutte FINUPHY Funchal 2005
Cavity prototypes
Low-betaprototypeACCEL
High-betaprototypeZANON
Page 15D.Goutte FINUPHY Funchal 2005
1,0E+07
1,0E+08
1,0E+09
1,0E+10
0 1 2 3 4 5 6 7 8 9 10
Eacc (MV/m)
Qo
Mesures dans CV1 :Mesures dans CV1 :Tbain = 4.21 KTbain = 4.21 Kf = 87.788 MHzf = 87.788 MHzEacc,max=9.5 MV/mEacc,max=9.5 MV/mQo @6.5 MV/m > 10Qo @6.5 MV/m > 1099
Pin,max = 22 WPin,max = 22 WLimite = Limite = T° couvercle ? T° couvercle ?
= Pertes joint ?= Pertes joint ?
Prochain test :Prochain test :Joint HélicoflexJoint HélicoflexRefroidissement couvercleRefroidissement couvercleChimie BCPChimie BCP
Corps cavité : 200 mmCorps cavité : 200 mmCouvercle : 10 mmCouvercle : 10 mm
Joint Cuivre+IndiumJoint Cuivre+IndiumRinçage HP 60 barsRinçage HP 60 barsSéchage à 45° pdt 1 nuitSéchage à 45° pdt 1 nuit
Resultats tests décembre = 0.07
Page 16D.Goutte FINUPHY Funchal 2005
Tuning system for the low cavity :deformation in the direction perpendicular to the beam axis
Intertank normal-conducting section
Low beta family cryostat High beta family cryostat
Warm QpolesDiagnostic box
Cryomodules
Page 17D.Goutte FINUPHY Funchal 2005
4K 80K level
Losses in cryomodules
450 W 1110 W
Losses in transfer lines
120 W 480 W
Power required for cryo. system
900 W 2000 W
Helium production 10 l/h
• LHe produced in 1 cold box, stored in a 3000 l tank + 1000 l tank for external users
• 2 compressors of 80 g/s• 60 K He supplies the thermal shields• Connection of each cryostat to the main
transfer line via a connecting box (5 circuits)allows for individual cryostat isolation
• He bath pressure p = ± 1 mbar (cavity requir.)
Cryogenic plant
IPN
Page 18D.Goutte FINUPHY Funchal 2005
Transfer tube in tantalum (2000°C)
Tantalum oven
Cooled chamber
UCx pellets
Convertisseur et Cible UCx
la roue et les tuiles de carbone
cible dans le four
Etude mécanique : Achevée fin Août 2004Test :Novembre 2004
Page 19D.Goutte FINUPHY Funchal 2005
servicecap
shieldingblock
CTISconfin.boxes
highly radioactive and contaminated secondary vacuumfor converter & TIS compartments: each volume equipped with its dedicated pumping system
10-7mbar10-5mbar
10-6m
bar
converter TIS
vacuum-tight tank
vac. pumpsvac.pump
tankpump
input valve
outputvalve
primarypump insulator
Production station
supplypipe
gasket
Calculs récents d’activation (SPR Saclay) : DED > 6 mSv/h atténuation neutrons insuffisante
Page 20D.Goutte FINUPHY Funchal 2005
pumping system
valve actuator
converter shielding
HV cables
target – ion source
beam optics
converter
connectors
Plug details
TargetSource
TIS
Tank housing production and LE plugscut-away of the production plug
Page 21D.Goutte FINUPHY Funchal 2005
Target Oven
assembly of 1st oven prototypetests and temperature measurementsfrom mid-november 2004
efficient release of radioactive elements high temperature ~ 2200°fission reactions power deposition ~ 500 Wextra power provided by the Ta oven(chosen at Oak-Ridge) 10-20 kW
IPN
Page 22D.Goutte FINUPHY Funchal 2005
Hot cell
purposes of the hot cell :
disassembling & replacement of irradiated components after cooling
waste management : sorting, characterisation & conditioning (packaging) of waste
Examples of components :
walls and lower part of the plug ;
electric and fluid connections ;
target/ion-source unit (<100 Kg) – which can be totally or partially disassembled so that the source may be re-used with another target ;
converter unit, including the 1 m diameter carbon wheel and the cooling screens
beam line elements (extraction element, steerers, lens, profilers, deflector)
electric cables
input-output gate valves
chamber, magnet & coils of separator & charge breeder
plug loaded throughthe top of the hot cell
LPC-Caen : études préliminaires
Page 23D.Goutte FINUPHY Funchal 2005
Separator
2 solutions studied + 1 simplified versionmust be able to switch mass of interest to the required channel
Brama type (Broad Range Acceptance Mass Analyser)
based on Elbek-type magnet & electrostatic sliding deflectors
Wien filter type decoupling of the functions :
mass separation by a Wien filter, located in a plug close to ISmass purification performed by two independent spectrometers
Ion Source
EQTWien Filter
Charge Breeder
Low EnergyExperiment
DI
Mass Identification
DI
DI DI
DI
DI
ES
slit
slit
X double focusEQT: electrostatic quad tripletES: electrostatic deflectorDI: magnetic dipole
EQ WFEQ EQ
10 cm
A = 140
A = 90
Page 24D.Goutte FINUPHY Funchal 2005
Construction Cost
SUB-SYTEMS COUT PLAFOND (k€)
LINAC - DRIVER 26 671
TARGET ION SOURCE STATION 6 649
SECONDARY BEAM LINES 9 540
CONVENTIONAL FACILITIES 35 139
INTEGRATED CONTROL SYSTEMS 2 206
DIRECT LINES G1/G2 2 640
TOTAL CAPITAL COST 82 844
STAFF COST 35 000
CONSTRUCTION COST 117 844
CONTINGENCY (15%) 17 677
20 M€ « Europe »
117,8 M€ 32,6 M€ Region32,6 M€ CNRS32,6 M€ CEA
Page 25D.Goutte FINUPHY Funchal 2005
Construction Cost
20 M€ « Europe »20 M€ « Europe »
« Construction … » instrument of FP7 (up to 20 % of the total cost ?)
Contributions from « partners » ….(UK, GSI, INFN, Dubna, Poland, Bulgaria, India, … )
already several M.O.U. signed but detailed discussion will start really only after the French « green light »