Analisa Harga Satuan Pekerjaan
Citation preview
BTN : PEKERJAAN BETON
1 m3 - Cor beton K.125 ( manual )
Pasir beton 0,5070 m3
Split pecah mesin 2/3 0,7160 m3
Semen PC 50 kg 5,0000 zak
Pekerja 1,8000 hr
Tukang batu 0,4750 hr
mandor 0,2858 hr
Alat bantu 2,5000 set
JUMLAH
DIBULATKAN
1 m3 - Cor beton K. 175 ( manual )
Pasir beton 0,5070 m3
Split pecah mesin 2/3 0,7160 m3
Semen PC 50 kg 9,0000 zak
Pekerja 1,8000 hr
Tukang batu 0,4858 hr
mandor 0,2608 hr
Alat bantu 2,5000 set
JUMLAH
DIBULATKAN
1 m3 - Cor beton K. 225 ( manual )
Pasir beton 0,5070 m3
Split pecah mesin 2/3 0,7160 m3
Semen PC 50 kg 11,0000 zak
Pekerja 1,8000 hr
Tukang batu 0,2608 hr
mandor 0,5858 hr
Alat bantu 2,5000 set
JUMLAH
DIBULATKAN
1 m3 - Cor beton K. 250 ( manual )
Pasir beton 0,4000 m3
Split pecah mesin 2/3 0,7400 m3
Semen PC 50 kg 11,8000 zak
Pekerja 1,8000 hr
Tukang batu 0,2620 hr
mandor 0,6270 hr
Alat bantu 2,5000 set
JUMLAH
DIBULATKAN