Development, design and urban planning project of residential area in Segorbe (Spain)
LIDAR Technology
Natural-Scale Profile Points Cloud Surface
Getting the topographic information from LIDAR Technology and modelling the surface with Civil 3D
Big problem with the heavy grade, 40 meters of elevation’s difference
Necessary a Study of Solutions to find the best option
Main features: 11.298 m2 of green space Preserve existing forest Good from urban area Difficult development High volume of dirt moving Big occupancy rate Stability slope problems
Development, design and urban planning project of residential area in Segorbe (Spain)
Design 1 Roads System
Plots
Service Areas
Development, design and urban planning project of residential area in Segorbe (Spain)
Design 2
Main features: 57.935 m2 of green space Don’t preserve part of existing forest Bad access from urban area Easy development Minimum dirt moving Small occupancy rate No stability slope problems
Roads System
Plots
Service Areas
Main features: 17.887 m2 of green space Don’t preserve existing forest Good access from urban area Difficult development Maximum dirt moving High occupancy rate Stability slope problems
Development, design and urban planning project of residential area in Segorbe (Spain)
Design 3 Roads System
Plots
Service Areas
Main features: 20.050 m2 of green space Don’t preserve existing forest Good access from urban area Difficult development Maximum dirt moving High occupancy rate Stability slope problems
Development, design and urban planning project of residential area in Segorbe (Spain)
Design 4 Roads System
Plots
Service Areas
Main features: 6.601 m2 of green space Don’t preserve part of existing forest Good access from urban area Difficult development Minimum dirt moving Medium occupancy rate No stability slope problems
Development, design and urban planning project of residential area in Segorbe (Spain)
Design 5 Roads System
Plots
Service Areas
Development, design and urban planning project of residential area in Segorbe (Spain)
Due to the high elevation difference between the North and South side of the area, the development is concentrated in the South flat part.
To reduce the dirt moving, roads have been designed based on the contour lines, being a complex system of parks and roads.
Design 5
Development, design and urban planning project of residential area in Segorbe (Spain)
Pedestrian Road Northern Perimeter Road Internal Roads
Northern Perimeter Road: Double direction's road with double sidewalk and ditch in the external side to collect the mountain runoff water
Internal Road: Single direction’s roads with a car park line and double sidewalk Pedestrian Road: Four pedestrian roads to give pedestrian access to the houses
Development, design and urban planning project of residential area in Segorbe (Spain)
The grade line has been designed 1 meter under the surface line considering the aggregate material of the platform
Longitudinal section: The cut and fill of the road and the dirt moving
Cross Sections: Let analyse how the road evolves every 20 meters
Longitudinal Section Northern Perimeter Road
Cross Sections
Road Axis
Development, design and urban planning project of residential area in Segorbe (Spain)
Collector 4
Collector 1
Collector 2
General Collector
Collector 3
Concrete Stormtank
Drainage net Runoff areas
Drain Section CYPE computation net
Collector 1 The drainage system has
been calculated with CYPE software
The manholes have been designed from the ground slope, keeping in mind the water speeds and the minimum tube diameters
Development, design and urban planning project of residential area in Segorbe (Spain)
Sewer net Drain Section
Civil 3D computation net
Collector 3 Sewer system has been
calculated with Civil 3D software
Sewer and drainage system are a separate system
Network 2
Network 1
General Water System
Network 1
General Water System
It is the highest point in the Sewer System
General Water System
Network 1 The clean water system has been
calculated with CYPE software. This system guarantees a 30 mca
pressure in the highest point of the sewer system
There are designed the irrigation connexions for green areas
Development, design and urban planning project of residential area in Segorbe (Spain)
Development, design and urban planning project of residential area in Segorbe (Spain)
Medium and Low Voltage
Power Substation
Roads Lighting System
Lighting System in Central Park
Underground medium and low voltage lines
Separate lighting system to guarantee lighting supply in case of breakdown
Special lighting design for parks and gardens using different luminaries depending on the situation
Medium voltage
Low voltage
Parks Lighting System
Development, design and urban planning project of residential area in Segorbe (Spain)
Central Park
Central Park Eastern Park
Small Landscaped Areas
Green Spaces
There are two big parks, Central and Eastern Park, and ten small landscaped areas to connect the roads
Central Park This park has 4 platforms in a different level to solve the roads connection problem
Platform 1: Connection zone between zone 2 and 4 with a ramp and stairs Platform 2: The biggest area with playground and sport zone Platform 3: A promenade with benches, trees and special lighting Platform 4: A landscape area with a characteristic garden design
1 2
4 3
Development, design and urban planning project of residential area in Segorbe (Spain)
Eastern Park Small Landscaped Areas
Eastern Park This park has 4 platforms in a different level to give access from the road with high slope
Platform 1: Leisure zone with barbecues and tables Platform 2: Area with playground and benches without direct access to the road Platform 3: Area with playground and benches with direct access to the road Platform 4: Closed landscape area with the power substation building
1
2
4
3
Ten small landscaped areas which connect different levels roads
There are two zones, the highest one is a extension of the sidewalks with a fountain and benches
The medium zone is an landscaped area. Both are connected with ramps and stairs substation building
Development, design and urban planning project of residential area in Segorbe (Spain)
Resume Euros % Dirt Moving 208,606.15 5.37 Roads System 672,133.06 17.29 Sewer System 367,976.34 9.46 Drainage System 667,140.45 17.16 Stormtanks 8,026.87 0.21 Water System 175,345.33 4.51 Power System 295,912.71 7.61 Lighting System 216,166.27 5.56 Telecom System 49,035.24 1.26 Green Spaces 1,086,433.24 27.94 System of signs 25,225.53 0.65 Quality Control 25,262.22 0.65 Waste Management 58,636.24 1.51 Health and Safety 31,966.21 0.82
Estimated Cost 3,887,865.86
Percentage of costs
Economic Ratios 40 €/ m2 gross
255 €/ m2 parcel 167 €/ m2 roof
It is needed a work outline of 14 months, calculated with Microsoft Project
The budget has been estimated with Presto Software, being a total amount of 3,887,865.86 €
There is an important cost for green spaces due to urban furniture and special luminaries
The economics ratios give us an idea how much we will spend to buy a parcel in this urban area
Universidad Politécnica de Valencia Escuela Técnica Superior de Ingenieros de Caminos
Canales y Puertos
Santiago Garnes Simón Civil Engineer
Tutors: José Sergio Palencia Jiménez - María Carmen Castro Bugallo
January 2011 - January 2013