TÜREK 2018 - “Montaj ve Lojistik Zincirinde Doğru Kararlar Almak Neden Önemli” - “Why is it important to take the right decision on logistic and installation” Istanbul, Total Enerji Servis Hizmetleri Tic. Ltd. Sti. 06/11/2018 – Ali Sarigoz

PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

TÜREK 2018- “Montaj ve Lojistik Zincirinde Doğru Kararlar AlmakNeden Önemli” - “Why is it important to take the right decision on logistic and installation”

Istanbul, Total Enerji Servis Hizmetleri Tic. Ltd. Sti.06/11/2018 – Ali Sarigoz

Page 2: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13/11/2018 2Total Enerji Servis Hizmetleri Tic. Ltd. Sti. - TUREK TWEC 2017

• TES Ltd. established in 2009 in Istanbul/Turkey by Ali Sarigoz

• Active player within the Turkish and international market for more than 9 years

• High class experience within consultancy, start-up, transportation, crane erection, manpower and installation

• TES Ltd. offers its specialist services in the whole Mediterranean, Caucasus, Balkans, Middle East,South America, Caribbean, North Africa and Asia

• TES Ltd. has partnership agreements with companies from abroad, with their headquarters overseas

• TES Ltd. is NOT ONLY dealing with installation works, but offers maintenance after installation, as well as consultancy

• TES Ltd. stands for professional work - SAFETY, QUALITY, ECONOMIC

- Introduction of TES Ltd.

Company Profile

Page 3: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13/11/2018 Total Enerji Servis Hizmetleri Tic. Ltd. Sti. - TUREK TWEC 2017 3

- Geography

Turkey - Map

Page 4: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

Logistic ports

Aegean ports: Izmir, Aliaga,

Marmara ports: Tekirdag, Hadimkoy

Mediterranean ports: Adana, Mersin, Iskenderun

Black sea ports: Samsun, Ordu

Production facilitiesMaramara Region: Tower productions

Anatolia Region: Tower production

Aegean Region Tower. Blade and Nacelle production.

Project locationsMarmara region: Bandirma, Canakkale, Yalova, Kocaeli etc.

Trakya region: Tekirdag, Edirne, Catalca etc.

Aegean Region: Izmir, Bodrum, Marmaris etc.

Anatolian Region: Eskisekir, Ankara, Sivas, Yozgat etc.

Sout East Region: Hatay, Iskenderun, Mersin etc.

Black Sea Region: Ordu. Samsun etc.

13 November 2018 Ali Sarigoz 4

Logistic from ports, production facilities to project locations

Page 5: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

• Logistics is important to bring the full wind turbine to the project location.• For installation of heavy material to be delivered on site. (crane and transport

material.)• Coordination from production/ports to site.• Permits for transport on public and private roads.• Permits for work on site.

– Longest pieces is approx. 75m long.– Heaviest pieces is approx. 90-120 ton.– Width of the widest pieces is starting from 3.4 – 5.2 m– Height of pieces is approx. 5.5 – 5.7m

13 November 2018 Ali Sarigoz 5

Why is Logistics and installation important?

Page 6: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 6

• Check out the depth of berth for selection of the correct vessel and equipment

planning for unloading.

Logistic starting point from port of unloading of cargo.

Page 7: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 7

Port unloading operations.

Page 8: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 8

- 74m long blade.

Road surveys

Page 9: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 9

- Clearance of transport for abnormal high transportation.

Road surveys cont’d

Page 10: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 10

- Bigger turning radius for long section parts.

Road surveys cont’d

Page 11: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 11

- Long pieces on public mountain road

Road surveys cont’d

Page 12: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 12

- Transport through town, where it may be needed to demolish buildings.

Road surveys cont’d

Page 13: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

• When a project location has been selected for the wind farm.– Why at this stage?

• Wind turbine components is becoming bigger and heavier, were detailed study is needed as the grid connection for wind farm.

• Importance to start logistics planning at this early stage is due to the fact that cost improvements can be made, as well as applications for modifications on public roads and private areas can be submitted.

– Why so early?• Because wind projects are build on windy mountains, where these roads are normally hilly, and curves

too narrow.

– We can modify it !!• Yes this can be possible, but you have to get approval first check bridges load capacity, environmental

protected area, private property passages etc., then next to calculate the cost for modifications. Some times cost can be covered, but to expensive to affect the earning of project or get approval.

13 November 2018 Ali Sarigoz 13

- At what point should you start the logistic planning?

Logistics Planning

Page 14: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

• Investment made until licensing procedure will be lost.– Wind measurement.

– Cost of the land.

– Establishment cost for project.

• Time spend for no project realization.– Which can vary from project to project.

13 November 2018 Ali Sarigoz 14

- What are the effects of Logistical risks on projects?

Risk Management

Page 15: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 15

• Access to wind farm location to be selected for detailed design of internal roads.

– Wind farm roads design to be done during the development of project.

– Detailed design for road and crane pads for safe installation.

• Selection of crane and right transport material.

• Environmental approval for clearing the turbine locations.

– Application for building permit with the final design of roads and crane pads.

– In case of restricted space for storage area, other locations to be arranged and designed for delivery of the cargo to site.

– Plan the correct logistics for delivery of components to turbine locations.

- What considerations to be had for Wind farm installations?

Installation Planning

Page 16: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 16

• Difficult to get building permit• Additional cost for construction of installation areas and roads.• Acquisition of private property at the site area.• Unsafe installation, which increases risk of accidents for installation teams and equipment.• Damage of turbine parts, causing delays.

– Damaged part to be replaced, where some parts can be long-lead items.

• Delays to the project installation programme.• If any commitment for generation of energy from the windfarm at specific date, which can

penalize the owner towards authorities.• Loss of project permits.

- What are the impacts of incomprehensive installation planning?

Installation Planning

Page 17: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 17

Examples of installation areas

Page 18: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 18

Examples of installation areas

Page 19: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 19

Operation on installation area

Page 20: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

13 November 2018 Ali Sarigoz 20

• Advantage to negotiate with sub-contractors.• Adherence to project completion and commitment to programme.• Correct application for building permits with minor modifications of design.• Better alignment with the local community and authorities.• Increase safety during construction. • Etc.With the above considerations, the following benefits could be achieved:

• Saving money on project development and construction.• Saving time for project execution.

SUCCES FULL PROEJCT EXECUTION

- What are the benefits of detailed preparation of logistics and installation planning?

Detailed Planning

Page 21: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

Questions…

13 November 2018 Ali Sarigoz 21

Page 22: PowerPoint PresentationPowerPoint Presentation Author: hasan.sarigoz Created Date: 11/13/2018 1:18:59 PM

Ali SarigozManaging DirectorTLF: +90 216 680 02 13-14GSM: +90 532 522 80 75Email: [email protected]: www.tes-ltd.com

Thank you!