Presentation Marintek

  • Upload
    nhsosx

  • View
    229

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 Presentation Marintek

    1/29

    1MARINTEK

    LNG as fuel for marine applicationexperiences / challenges

    Per Magne Einang

    Research Director

    MARINTEK

    www.marintek.com

    CIMAC Circle NorShipping 2009

  • 8/8/2019 Presentation Marintek

    2/29

    2MARINTEK

    Natural gas as fuel for ships - experience

    The first LNG ferry Glutra 2000

    Two Supply Vessels 2003

    Two new supply vessels on order

    Series of five LNG car ferries 2007

    Ten new ferries on ordered

    Three military vessels on order

  • 8/8/2019 Presentation Marintek

    3/29

    3MARINTEK

    Bergensfjord In service January 2007

  • 8/8/2019 Presentation Marintek

    4/29

    LNG ferry Bergensfjord

    Main dimensions and capacities: Overall length 130 m

    Breath 19 m

    Draught max 4, 6 m

    Cars (pcu) 212

    Passengers 590

    Service speed 21 knots

    LNG storage: 2 x 125 m

    3

    LNG

    4MARINTEK

  • 8/8/2019 Presentation Marintek

    5/29

    Bergensfjord General arrangements

    5MARINTEK

  • 8/8/2019 Presentation Marintek

    6/296MARINTEK

    Bergensfjord - Gas engines installed

    Rolls-Royce K-type

    Lean Burn gas engines

    2 KVGS 16G4 3535 kW each

    2 KVGS 12G4 2650 kW each

    Total power installed: 12370 kW

  • 8/8/2019 Presentation Marintek

    7/297MARINTEK

    0

    0,1

    0,2

    0,3

    0,4

    g/kWh

    MDO 1% S natural gas

    0

    2

    4

    6

    g/kWh

    MDO 1% S natural gas

    SO2

    Particulates

    Exhaust emission -Natural gas vs MDO

    Source: Rolls-Royce Marine 0

    6

    12

    18

    g/kWh

    MDO 1% S natural gas

    0

    200

    400

    600

    800

    g/kWh

    MDO 1% S natural gas

    CO2

    NOx

    Sulphur emission is eliminated

    Particulate matters is close to zero

    CO2 is reduced by 26%Due to unburned methane the net reductionof greenhouse gases is somewhat lower

    NOx is reduced by 80-90%

  • 8/8/2019 Presentation Marintek

    8/298MARINTEK

    The LNG ferry at berth

  • 8/8/2019 Presentation Marintek

    9/299MARINTEK

    LNG bunkering station at ferry berth

    Capacity bunkering station:

    2x 500m3

    LNG

    LNG transferred by pump

    Filling time for the large

    LNG ferries about two

    hours

    Refuelled every third night

  • 8/8/2019 Presentation Marintek

    10/2910MARINTEK

    Bunkering LNG ferry

  • 8/8/2019 Presentation Marintek

    11/2911MARINTEK

    R&D program LNG fuelled ships (2006-08)Example RoRo Freight ship (fixed rout in Baltic sea)

    Requirements from ship operator:

    Same classification of engine room as for diesel or HFO operation

    Mechanical drive

    Increased building cost should be justified by lower operating cost (meainglower fuel cost and tax reduction, avoid exhaust gas cleaning)

    Cost level (preliminary)

    Building cost Heavy fuel operation: about 25 mill

    Additional cost for LNG propulsion (gas only): about 2 mill (+8%)

  • 8/8/2019 Presentation Marintek

    12/2912MARINTEK

    LNG powered RoRo freight ship (gas only)

    Two ships under construction for delivery in 2010-11

  • 8/8/2019 Presentation Marintek

    13/2913MARINTEK

    Rules and regulations - Gas fuelled ships

    Examples from the IMO work Provisions for gas fuelled ships

    Different engine room arrangements

    Inherently safe engine room Double piping to gas engine

    No special requirements

    ESD (Emergency Shut Down) protected engine room

    Minimum two separate engine rooms

    Redundant systems

    Increased ventilation

    Gas detection

    Minimum of ignition sources

  • 8/8/2019 Presentation Marintek

    14/2914MARINTEK

    Main Gas engineRolls Royce B35:40V12P-G marine

    Arrangement with double walled piping on main gas supply and pre-chamber gas

    Gas dangerous area

  • 8/8/2019 Presentation Marintek

    15/29

    15MARINTEK

    Gas dangerous area

  • 8/8/2019 Presentation Marintek

    16/29

    Main gas engineRolls-Royce Bergen B35:40 V 12Spark ignited lean-burn gas engine

    Rolls-Royce Bergen

    Gas engine B35:40-V12

    Power: 5250 kW

    Efficiency: 48%

    NOx: 1,2 g/kWh

    16MARINTEK

  • 8/8/2019 Presentation Marintek

    17/29

    17MARINTEK

    7

    9

    11

    13

    15

    17

    0 10 20 30 40 50 60 70 80 90 100

    Engine Load [%]

    Spec.ener

    gycons.

    [MJ/kWh]

    Generator load

    Propeller load

    Mechanical vs electric driveLean Burn gas engine

    Thermal efficiency:

    Power output/fuel input kWh/9 MJ 103

    W3600s/9*106

    Ws3600/9000*100% 40%

    Based on measured data from Rolls-Royce Bergen

  • 8/8/2019 Presentation Marintek

    18/29

    New concepts and design

    Four small costal bulk carries

    designed or considered

    Two oil product tankers designed

    or considered

    18MARINTEK

  • 8/8/2019 Presentation Marintek

    19/29

    19MARINTEK

    Development of a new LNG storage system (IMO A tank)

  • 8/8/2019 Presentation Marintek

    20/29

    20MARINTEK

    Development of a new LNG storage system (IMO A tank)Design of 450 m3 LNG fuel tank with complete secondary barrier

  • 8/8/2019 Presentation Marintek

    21/29

    21MARINTEK

    What about availability of LNG and price?

    Small scale receiving terminals in Norway (2006)

  • 8/8/2019 Presentation Marintek

    22/29

    22MARINTEK

    Small scale receiving terminals in Norway (2006)

    Receiving LNG terminals LNG receiving terminals in

    operation (read) and underconstruction (blue)

    Total number of 26 terminals Wide span in size

    100m3 - 3500m3 LNG

    Source of LNGLocal production (marked P)

    Karmy 20000 ton/year

    Kollsnes1 40000 ton/year

    Kollsnes2 80000 ton/year

    Tjelbergodden 10000 ton/year

    Total 150000 ton/year

  • 8/8/2019 Presentation Marintek

    23/29

    23MARINTEK

    Small receiving terminal at an aluminum plant

    LNG ship 1000m3 LNG

    G N LNG l 2 f 2009

  • 8/8/2019 Presentation Marintek

    24/29

    24MARINTEK

    Gasnor New LNG vessel 2. quarter of 2009

  • 8/8/2019 Presentation Marintek

    25/29

    25MARINTEK

    Lyse gasLNG i RisavikaStavanger

    Capasity (train 1) 300 000 Ton/year (train 2 300 000 ton/year)

    Starting 4. quarte 2010 (train 1)

  • 8/8/2019 Presentation Marintek

    26/29

    26MARINTEK

    Nordic LNG (Lyse Gas and Skaugen)

    Logistic solutions with ships

    6 multi gas (LNG, Ethylene, LPG) carriers of 10 000 cbm and two of 12 000 cbm

  • 8/8/2019 Presentation Marintek

    27/29

    27MARINTEK

    Price level LNG vs Marin Diesel Oil (MDO)

    LNG and MGO prices vs Crude oil price on energy basis

    0

    200

    400

    600

    800

    1000

    1200

    20 30 40 50 60 70 80 90 100

    Brent crude oil price [$/barrel]

    Fuelp

    rices[$/ton]

    LNG small scaleLNG import Japan

    MGO market price

    At high crude oil price LNG has a significant price margin to

    Marin Diesel Oil (MDO)

    S i

  • 8/8/2019 Presentation Marintek

    28/29

    28MARINTEK

    Summing up

    Natural gas (LNG) as fuel is an alternative for low emissionsin short sea shipping

    Gas engine and LNG technology are available

    LNG as fuel can compete with Marin Diesel Oil not with Lowsulphur heavy fuel

    LNG fuelled ships will have a higher building cost due to theLNG storage and bunkering system

    Competitiveness can be improved by reduction of costsrelated to the LNG system

    Reduction in the level of cost is possible due to simplifying

    rules and regulations, general product developments andcompetition

    LNG is available today from small scale production plants.Small LNG ships can take LNG from import terminals

  • 8/8/2019 Presentation Marintek

    29/29

    29MARINTEK

    Tank you for your attention

    [email protected]