Upload
nhsosx
View
229
Download
0
Embed Size (px)
Citation preview
8/8/2019 Presentation Marintek
1/29
1MARINTEK
LNG as fuel for marine applicationexperiences / challenges
Per Magne Einang
Research Director
MARINTEK
www.marintek.com
CIMAC Circle NorShipping 2009
8/8/2019 Presentation Marintek
2/29
2MARINTEK
Natural gas as fuel for ships - experience
The first LNG ferry Glutra 2000
Two Supply Vessels 2003
Two new supply vessels on order
Series of five LNG car ferries 2007
Ten new ferries on ordered
Three military vessels on order
8/8/2019 Presentation Marintek
3/29
3MARINTEK
Bergensfjord In service January 2007
8/8/2019 Presentation Marintek
4/29
LNG ferry Bergensfjord
Main dimensions and capacities: Overall length 130 m
Breath 19 m
Draught max 4, 6 m
Cars (pcu) 212
Passengers 590
Service speed 21 knots
LNG storage: 2 x 125 m
3
LNG
4MARINTEK
8/8/2019 Presentation Marintek
5/29
Bergensfjord General arrangements
5MARINTEK
8/8/2019 Presentation Marintek
6/296MARINTEK
Bergensfjord - Gas engines installed
Rolls-Royce K-type
Lean Burn gas engines
2 KVGS 16G4 3535 kW each
2 KVGS 12G4 2650 kW each
Total power installed: 12370 kW
8/8/2019 Presentation Marintek
7/297MARINTEK
0
0,1
0,2
0,3
0,4
g/kWh
MDO 1% S natural gas
0
2
4
6
g/kWh
MDO 1% S natural gas
SO2
Particulates
Exhaust emission -Natural gas vs MDO
Source: Rolls-Royce Marine 0
6
12
18
g/kWh
MDO 1% S natural gas
0
200
400
600
800
g/kWh
MDO 1% S natural gas
CO2
NOx
Sulphur emission is eliminated
Particulate matters is close to zero
CO2 is reduced by 26%Due to unburned methane the net reductionof greenhouse gases is somewhat lower
NOx is reduced by 80-90%
8/8/2019 Presentation Marintek
8/298MARINTEK
The LNG ferry at berth
8/8/2019 Presentation Marintek
9/299MARINTEK
LNG bunkering station at ferry berth
Capacity bunkering station:
2x 500m3
LNG
LNG transferred by pump
Filling time for the large
LNG ferries about two
hours
Refuelled every third night
8/8/2019 Presentation Marintek
10/2910MARINTEK
Bunkering LNG ferry
8/8/2019 Presentation Marintek
11/2911MARINTEK
R&D program LNG fuelled ships (2006-08)Example RoRo Freight ship (fixed rout in Baltic sea)
Requirements from ship operator:
Same classification of engine room as for diesel or HFO operation
Mechanical drive
Increased building cost should be justified by lower operating cost (meainglower fuel cost and tax reduction, avoid exhaust gas cleaning)
Cost level (preliminary)
Building cost Heavy fuel operation: about 25 mill
Additional cost for LNG propulsion (gas only): about 2 mill (+8%)
8/8/2019 Presentation Marintek
12/2912MARINTEK
LNG powered RoRo freight ship (gas only)
Two ships under construction for delivery in 2010-11
8/8/2019 Presentation Marintek
13/2913MARINTEK
Rules and regulations - Gas fuelled ships
Examples from the IMO work Provisions for gas fuelled ships
Different engine room arrangements
Inherently safe engine room Double piping to gas engine
No special requirements
ESD (Emergency Shut Down) protected engine room
Minimum two separate engine rooms
Redundant systems
Increased ventilation
Gas detection
Minimum of ignition sources
8/8/2019 Presentation Marintek
14/2914MARINTEK
Main Gas engineRolls Royce B35:40V12P-G marine
Arrangement with double walled piping on main gas supply and pre-chamber gas
Gas dangerous area
8/8/2019 Presentation Marintek
15/29
15MARINTEK
Gas dangerous area
8/8/2019 Presentation Marintek
16/29
Main gas engineRolls-Royce Bergen B35:40 V 12Spark ignited lean-burn gas engine
Rolls-Royce Bergen
Gas engine B35:40-V12
Power: 5250 kW
Efficiency: 48%
NOx: 1,2 g/kWh
16MARINTEK
8/8/2019 Presentation Marintek
17/29
17MARINTEK
7
9
11
13
15
17
0 10 20 30 40 50 60 70 80 90 100
Engine Load [%]
Spec.ener
gycons.
[MJ/kWh]
Generator load
Propeller load
Mechanical vs electric driveLean Burn gas engine
Thermal efficiency:
Power output/fuel input kWh/9 MJ 103
W3600s/9*106
Ws3600/9000*100% 40%
Based on measured data from Rolls-Royce Bergen
8/8/2019 Presentation Marintek
18/29
New concepts and design
Four small costal bulk carries
designed or considered
Two oil product tankers designed
or considered
18MARINTEK
8/8/2019 Presentation Marintek
19/29
19MARINTEK
Development of a new LNG storage system (IMO A tank)
8/8/2019 Presentation Marintek
20/29
20MARINTEK
Development of a new LNG storage system (IMO A tank)Design of 450 m3 LNG fuel tank with complete secondary barrier
8/8/2019 Presentation Marintek
21/29
21MARINTEK
What about availability of LNG and price?
Small scale receiving terminals in Norway (2006)
8/8/2019 Presentation Marintek
22/29
22MARINTEK
Small scale receiving terminals in Norway (2006)
Receiving LNG terminals LNG receiving terminals in
operation (read) and underconstruction (blue)
Total number of 26 terminals Wide span in size
100m3 - 3500m3 LNG
Source of LNGLocal production (marked P)
Karmy 20000 ton/year
Kollsnes1 40000 ton/year
Kollsnes2 80000 ton/year
Tjelbergodden 10000 ton/year
Total 150000 ton/year
8/8/2019 Presentation Marintek
23/29
23MARINTEK
Small receiving terminal at an aluminum plant
LNG ship 1000m3 LNG
G N LNG l 2 f 2009
8/8/2019 Presentation Marintek
24/29
24MARINTEK
Gasnor New LNG vessel 2. quarter of 2009
8/8/2019 Presentation Marintek
25/29
25MARINTEK
Lyse gasLNG i RisavikaStavanger
Capasity (train 1) 300 000 Ton/year (train 2 300 000 ton/year)
Starting 4. quarte 2010 (train 1)
8/8/2019 Presentation Marintek
26/29
26MARINTEK
Nordic LNG (Lyse Gas and Skaugen)
Logistic solutions with ships
6 multi gas (LNG, Ethylene, LPG) carriers of 10 000 cbm and two of 12 000 cbm
8/8/2019 Presentation Marintek
27/29
27MARINTEK
Price level LNG vs Marin Diesel Oil (MDO)
LNG and MGO prices vs Crude oil price on energy basis
0
200
400
600
800
1000
1200
20 30 40 50 60 70 80 90 100
Brent crude oil price [$/barrel]
Fuelp
rices[$/ton]
LNG small scaleLNG import Japan
MGO market price
At high crude oil price LNG has a significant price margin to
Marin Diesel Oil (MDO)
S i
8/8/2019 Presentation Marintek
28/29
28MARINTEK
Summing up
Natural gas (LNG) as fuel is an alternative for low emissionsin short sea shipping
Gas engine and LNG technology are available
LNG as fuel can compete with Marin Diesel Oil not with Lowsulphur heavy fuel
LNG fuelled ships will have a higher building cost due to theLNG storage and bunkering system
Competitiveness can be improved by reduction of costsrelated to the LNG system
Reduction in the level of cost is possible due to simplifying
rules and regulations, general product developments andcompetition
LNG is available today from small scale production plants.Small LNG ships can take LNG from import terminals
8/8/2019 Presentation Marintek
29/29
29MARINTEK
Tank you for your attention