Upload
fady-ezzat
View
15
Download
0
Embed Size (px)
Citation preview
Name: Fady Ibrahim Aziz
Course: Practical Training(CENG 497)
Instructor: Dr. Mohamed Salama
12 September 20161
Company: Orascom for Construction Industries (OCI)
Project: Grand Heights
Department: Quality Control and Technical Office
Duration: 5 Weeks
Presentation Outline:
-Project Parties
-Project Information
-Managerial and Site Terms
12 September 20162
-Managerial and Site Terms
-Tasks Assigned in QC department
-Tasks Assigned in Technical Office Department
- Internship Benefits
Project Main Parties:
- Client: KUWADICO ( Kuwait Wadi Al-Nile Development Company)
- Project Management: EGYCAN (Egyptian Canadian Project Managers)
- Consultant: IDG (Integrated Development Group)
12 September 20163
- Consultant: IDG (Integrated Development Group)
- Contractor: OCI (Orascom for Construction Industries)
Project Information:
- Location: 6th October City-Giza
- Scope: Construction of 2-Floor Villas of around 15 Types
- Handover: Core and Shell
12 September 20164
- Handover: Core and Shell
- Project Capital Cost: +400M L.E
- Project Phases: 1) Infrastructure2) C1(Yellow)3) C2 (Green)4) C3
Managerial and SiteTerms
- Material Submittal
- Project Quality Plan (PQP)
- Material Inspection Request (MIR)
12 September 20165
- Internal Inspection Request (IIR)
- External Inspection Request (EIR)
- Inspection and Testing Plan (ITP)
- Method Statement
- Non-Confirmance Report (NCR)
- Key Performance Indicator (KPI)
Civil Work
12 September 20166
Shop Drawing for Slab Reinforcement Slab Reinforcement matching Shop Drawing
Civil Work:
Formwork Structure
12 September 20167
Steel Formwork Wooden Formwork
Civil Work:
Foundation Work Inspection
12 September 20168
PC Foundations RC Foundations
Civil Work:
Column Work Inspection
12 September 20169
Column Formwork Column Reinforcement
Civil Work:
Beam and Slab Work Inspection
12 September 201610
Slab and Beam Formwork Slab and Beam Reinforcement
Civil Work:
Stairs Work Inspection
12 September 201611
Stairs Formwork Stairs Reinforcement
Civil Work:
Slab On Grade (SOG) Work Inspection
12 September 201612
Slab On Grade Reinforcement Pouring Slab On Grade
Architectural Work
12 September 201613
Concrete Masonary Units (CMU) Silty Clay Bricks
Architectural Work:CMU First Course Inspection
12 September 201614
First Course on Edges and Door Opening First Course bonded with Mortar
Architectural Work:Full Height Inspection
12 September 201615
Checking the Height of Window Sill Checking Window Dimensions and Level
Architectural Work:Inspection of Verticality and Horizontality of Building Elements
12 September 201616
Thread Balance to Check Verticality Water Bubble Balance to Check Horizontality
Architectural Work:Galvanized Steel Sheets
12 September 201617
Steel Sheets out of Masonry Units for Bond CMU First Course Bonded with Column
Architectural Work:Unification of Surface Level Inspection
12 September 201618
Metal Bar to Check Equality of Surface Level
Architectural Work:
Inspection of Angle Between Surfaces’ Edges
12 September 201619
Right-Angle Ruler
Architectural Work:Botomine Isolation
12 September 201620
Isolation under SOG to protect from Humidity during Backfill
Technical Office Experience
12 September 201621
Structural Shop Drawing Calculation Sheet
Miscellaneous Work
12 September 201622
Concrete Compressive Strength Test Inspection Chamber and House Connections
Miscellaneous Work:
- Project Planning and Scheduling
- Project Cost Control and Monitoring
- Reviewing Shop Drawings and Performing Bar List
12 September 201623
- Reviewing Shop Drawings and Performing Bar List
- Lab Testing Procedures for Concrete and Soil
- Water and Waste Water Pipes between Villas and Main Network System
Internship Benefits:
- Proper Site Inspection
- Formwork Design
- Translating Design Drawings into Shop Drawings.
12 September 201624
- Translating Design Drawings into Shop Drawings.
- Identifying the importance of Coordination between Architect, Structural Engineer and MEP Engineer.
- Identifying some constructability problems that might arise from design.
- Having Brief ideas about Quality Assurance, Planning and Cost Control.
Thanks OCI & AUC
12 September 201625
SalamaStructural Engineers
12 September 201626
Engineers (SSE)
Duration: 4 -5 Weeks
Al Jawharah Tower
Presentation Outline:
- Scope of Work
- Projects I have worked on
- Tasks Assigned
12 September 201627
- Tasks Assigned
- Internship Benefits
Scope of Work:
- Assigning Structural Systems for Different Projects.
- Modeling of Reinforced Concrete Structures using Structural Softwares1- ETABS for 3D Model to study lateral loads2- SAFE and S-Concrete for 2D Model to analyze Slabs and Rafts
12 September 201628
2- SAFE and S-Concrete for 2D Model to analyze Slabs and Rafts3- CSICOL to design Columns and Walls4- SAP2000 to model Steel and Reinforced Concrete Structures
- Structural Design of Reinforced Concrete and Steel Structures.
- Producing Framing Plans and Structural Detailing Drawings.
Projects I have Worked on:
- Qatar Industrial Manufacturing Center Tower (QIMC Tower)
- Gemstone Tower (UAE)
- Al Khail Cooling Building (UAE)
12 September 201629
- Al Khail Cooling Building (UAE)
- Mirdif Cooling Building (UAE)
- Saudi-German Hospital (UAE)
Projects I have Worked on:
12 September 201630QIMC Tower Gemstone Tower
Tasks Assigned:
Selection of Structure System
- Coordination with the Architect to Identify Slab Edge and Newly Proposed Columns.
- Identifying Wall Patricians of different Thicknesses.
12 September 201631
Saudi-German Hospital
Thicknesses.
- Using Steel Sections for Large Spans.
- Reasonable Balance between Design Safety, Functionality and Most Economic Solutions.
Tasks Assigned:
Slabs Analysis and Design
- Serviceability Short-term deflection.
- Serviceability Long-term deflection.
- Punching Shear Analysis.
12 September 201632
QIMC Slab
- Punching Shear Analysis.
- Thermal Contraction and Expansion Analysis.
- Eccentric Section Analysis for the combination between Thermal Axial Loads and Moments.
Tasks Assigned:Raft Analysis and Design
- Check Pile Capacity (End Bearing and Friction) against Compression.
- Check Pile Capacity (Friction) against Tension taking into consideration Uplift Forces.
12 September 201633
QIMC Raft
Tension taking into consideration Uplift Forces.
- Check Raft Capacity for Columns Punching Shear.
- Check Raft Settlement and Differential Settlement.
- Raft Structural Design
Tasks Assigned:3D Model and Design
- Assigning RC Structural Members
- Assigning Gravity and Lateral Loads
- Serviceability Check for Inter-story Drift
12 September 201634
GEMSTONE Tower
- Serviceability Check for Inter-story Drift
- Performing Modal Analysis
- Checking the Performance of Outrigger Belts in MEP Floors.
Tasks Assigned:Structure Design of RC & Composite
Sections
- Analyzing Composite Sections for P-M2-M3.
- Submitting Reports if Safe Sections.
12 September 201635
Composite Wall
- Initiating Engineering Solutions in case it is unsafe.
- Structure Design of RC Structure Walls.
- Structure Design of RC Columns
Tasks Assigned:Producing AutoCAD Drawings
- Framing Plans.
- Loading Plans.
12 September 201636
Gemstone 10th Floor Framing Plan
- Columns, Walls and Beam Schedules.
- Slabs and Beams Reinforcement Detailing.
- Vertical Elements Reinforcement Detailing.
Internship Benefits:
- Using Modern Structural Softwares.
- Being Able to Read Wind Tunnel Test Report and Understand it.
- Deal with ACI 318-14, UBC 97 and AISC 360-10.
12 September 201637
- Deal with ACI 318-14, UBC 97 and AISC 360-10.
- Being Able to Model and Design High-Rise Buildings.
- Being Able to Produce Construction Design Drawings.
- Being Able to Select Optimum Basement Construction Method.
Geotechnical and Structural Engineering
Consultant (GSEC)
12 September 201638
Duration: 8 Weeks
Telecom Tower Profile
Presentation Outline:
- Scope of Work
- Tasks Assigned
- Internship Benefits
12 September 201639
- Internship Benefits
Scope of Work:
- Structural Analysis and Design of Green Field and Roof Top Telecom Towers using RISAtower and tnxtower.
- Structural Analysis and Design of Steel Grillage and Steel Masts using SAP2000.
12 September 201640
SAP2000.
- Structural and Geotechnical Analysis and Design of RC Buildings using ETABS.
Tasks Assigned:Structure Design of GF and RF
Telecom Towers
- Receiving Surveying Documents for Tower Profile and existing devices.
12 September 201641
GF Telecom Tower
- Assigning Wind Speed, Tower Profile and devices.
- If Tower is safe, Structural Report is submitted with Future Loads.
- If Tower is unsafe, a Retrofitting Proposal is submitted.
Tasks Assigned:Structure Design Steel Grillage
- Assigning Tower Base Reactions
- Applying all Wind Load Cases following TIA-
12 September 201642
Steel Grillage
- Applying all Wind Load Cases following TIA-222-G.
- If Tower is safe, Structural Report is submitted with Future Loads.
- If Tower is unsafe, a Retrofitting Proposal is submitted.
Tasks Assigned:Structure Design Steel Masts
- Calculating Wind Loads on main pipe and devices manually.
- Drawing Mast Profile with Side arms on
12 September 201643
Steel Mast after Retrofit
- Drawing Mast Profile with Side arms on SAP2000.
- If Tower is safe, Structural Report is submitted with Future Loads.
- If Tower is unsafe, a Retrofitting Proposal is submitted.
Tasks Assigned:Structure Design of RC
Mosque Minaret
- Assigning Wind Loads on Vertical Elements.
- Modeling of Stairs and Dome.
12 September 201644
Mosque Minaret
- Structure Design of Minaret and Support Columns.
Tasks Assigned:Structure Design of RC
Mosque Minaret
- Assigning Structural Systems in coordination with the Architect.
- Full Structural Model with Gravity and Lateral
12 September 201645
Church Service Building
- Full Structural Model with Gravity and Lateral Loads.
- Structure Design of all Structural Elements.
- Foundation Structure Design for Raft on Piles.
- Producing Framing Plans and Design Drawings.
Internship Benefits:
- Using Modern Structural Softwares.
- Dealing with New Category regarding Antenna Structures Industries.
- Being independently responsible for Designing a whole Structure.
12 September 201646
- Being independently responsible for Designing a whole Structure.
- Being Able to Produce Construction Design Drawings.
- Being Able to Develop my Skills in Steel Structures.
Thank You
12 September 201647
Thank You