Proposed NWC General Works and Major Works Proposed NWC General Works and Major Works Business Plan ProcessBusiness Plan Process
• Repairs and maintenance costing over £50k per project covering:
- Reservoirs- Embankments and Culverts- Dredging- Water Supply- Major moving structures
• Centrally prioritised and delivered through the national framework contract (May Gurney)
• Responsibility of the Operations/Technical Director
• National average spend - £25m per annum
Explanation – Major WorksExplanation – Major Works
• Day to day maintenance, repairs and risk management
- Minor repairs costing less than £50,000 (e.g. lock gates)- Planned Preventative Maintenance- Vegetation Management-Customer Service – lockkeepers, sanitary stations, signage, etc.-Inspections
• Planned and delivered locally through the direct labour force and contract under the direction of the Waterway Manager
• Responsibility of the Operations/Technical Director
• National Average Spend - £55m per annum
Explanation – General WorksExplanation – General Works
Stage 1 – Setting of National Targets & Priorities
• Executive Directors consider macro income and expenditure forecasts
• Finance Director issues target allocations to Directors
October
Stage 1 – Setting of National Targets & Priorities
Stage 2 – Setting of Directorate Targets & Priorities
• Operations/Technical Director confirms national standards, performance targets/priorities for General and Major Works
• Operations/Technical Director issues target allocations to national Major Works team and each Waterway Manager
October
Stage 2 – Setting Operations Targets & Priorities
Stage 3 – Preparing draft Major Works Plan
• National Team – adjust existing 2/3 year plan in light of target allocations
• Meet with waterways to explain and discuss national and local priorities
• Needs and views of Local Partnership fed into process by Waterway Manager
• Programme prepared that addresses priorities and is deliverable within financial year
• Programme submitted - to waterways for information/comment
- to Operations/Technical Director for approval
November - December
Stage 3 – Preparing draft Major Works Plan
Stage 3 – Preparing draft General Works Plan
• Waterway Manager discusses local needs/priorities with Local Partnership and local management team
• Liaises with Operations/Technical Director and other Waterway Managers on national priorities etc.
• Waterway Manager submits local business plan including commentary on risks to Operations/Technical Director for approval
November - December
Stage 3 – Preparing draft General Works Plan
Stage 4 – Preparation of draft National Plan for Trustees
• Operations/Technical Director considers Major and General Works Plans, agrees modifications and adjustments in light of comments and feedback
• Submits Major and General Works Programme budgets to Finance Director
• Finance Director consolidates all plans into a draft National Business Plan
• Draft National Business Plan submitted to Trustees for comment
January
Stage 4 – Preparation of draft National Plan for Trustees
Stage 5 – Revisions/Refinements to National & Local Plans
• Executive reconsiders Local and National Plans in light of feedback from Trustees
• Operations/Technical Director reconsiders GW and MW Plans in light of Trustees feedback and LWP comments
• LWP invoke right to meet Operations/Technical Director if major concerns remain in respect of Business Plan
February - March
Stage 5 – Revisions/Refinements to National & Local Plans
Stage 5 – Approval of National & Local Plans
• Executive adjusts National Plan and resubmits to Trustees
• LWP Chairmen have right to submit comments directly to Trustees
• Trustees consider final draft Plan for approval
• Executive confirm National and draft Plans to business (or continue review of Plan until Trustees approval received)
March
Stage 5 – Approval of National & Local Plans
Steady State Allocation - £125mSteady State Allocation - £125m
Steady State Comparison
2011/12 Business
Plan £'000
Steady State Model £'000
Variance £'000
%
Steady State Direct Cost: Repair, PPM and Inspections: Intermediate Repairs (aqueducts; bridges; locks; bank protection) 13,860 13,317 (543) 104.1 PPM (bridges; locks; sluices; weirs) 3,771 7,140 3,369 52.8 Inspections (Annual; Principal; Length; Reservoirs) 2,370 2,265 (105) 104.6 20,001 22,722 2,721 88 Amenity/Customer Service/Other: Vegetation 6,245 11,553 5,308 54.1 Facilities 1,719 2,939 1,220 58.5 Litter and antisocial behaviour 1,609 2,154 545 74.7 Water control 1,319 1,422 103 92.8
Other (volunteering; manning structures; towpath management; fencing; access management etc.)
9,298 16,997 7,699 54.7
20,190 35,065 14,875 58 Total Steady State Direct Costs 40,191 57,787 17,596 70 Steady State Indirect Costs:
People not directly attributable to specific works (includes 20% operational staff as productivity rate set at 80%)
9,598 16,366 6,768 58.6
Operational Plant, Craft and Equipment (maintenance; fuel; depreciation) 5,162 8,802 3,640 58.6 Operational Buildings (repair; insurance; utilities; depreciation) 1,661 2,832 1,171 58.6 Total Steady State Indirect Costs 16,421 28,000 11,579 58.6 Total Steady State Costs (excl Major Works) 56,612 85,787 29,175 66.0
Minor Works Steady State Comparison
Average Steady State Spend by Waterway 2011/12 - £5.2m
Average Steady State Spend by Waterway 2011/12 - £5.2m
Operational Focus 2011/12 - £56.6mOperational Focus 2011/12 - £56.6m
BW HQ and Central Services
HQ & Central HQ & Central Service cost Service cost supporting supporting Operations - Operations -
£21.8m£21.8m
Total HQ Total HQ and Central and Central
Service Service cost - cost -
£30.9m£30.9m
HQ and Central Services
Major Works 4 year planned expenditure Major Works 4 year planned expenditure
Major Works focus Year 1 and 2
Year 12011/12£16.2m
Major Works focus Year 1 and 2
• Operations focus to manage risk, prioritise expenditure, increase productivity and efficiency to deliver effective customer service
• Open to suggestions for improving best value for waterways from local/national stakeholders
Explanation – General WorksOverview