18
Proposed NWC General Works and Major Works Proposed NWC General Works and Major Works Business Plan Process Business Plan Process

Proposed NWC General Works and Major Works Business Plan Process

  • Upload
    gene

  • View
    22

  • Download
    0

Embed Size (px)

DESCRIPTION

Proposed NWC General Works and Major Works Business Plan Process. Explanation – Major Works. Explanation – Major Works. Repairs and maintenance costing over £50k per project covering : Reservoirs Embankments and Culverts Dredging Water Supply Major moving structures - PowerPoint PPT Presentation

Citation preview

Page 1: Proposed NWC General  Works and Major Works   Business Plan Process

Proposed NWC General Works and Major Works Proposed NWC General Works and Major Works Business Plan ProcessBusiness Plan Process

Page 2: Proposed NWC General  Works and Major Works   Business Plan Process

 • Repairs and maintenance costing over £50k per project covering:

- Reservoirs- Embankments and Culverts- Dredging- Water Supply- Major moving structures

• Centrally prioritised and delivered through the national framework contract (May Gurney)

• Responsibility of the Operations/Technical Director

• National average spend - £25m per annum 

Explanation – Major WorksExplanation – Major Works

Page 3: Proposed NWC General  Works and Major Works   Business Plan Process

 • Day to day maintenance, repairs and risk management

- Minor repairs costing less than £50,000 (e.g. lock gates)- Planned Preventative Maintenance- Vegetation Management-Customer Service – lockkeepers, sanitary stations, signage, etc.-Inspections

• Planned and delivered locally through the direct labour force and contract under the direction of the Waterway Manager

• Responsibility of the Operations/Technical Director

• National Average Spend - £55m per annum

Explanation – General WorksExplanation – General Works

Page 4: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 1 – Setting of National Targets & Priorities

• Executive Directors consider macro income and expenditure forecasts

• Finance Director issues target allocations to Directors

October

Stage 1 – Setting of National Targets & Priorities

Page 5: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 2 – Setting of Directorate Targets & Priorities

• Operations/Technical Director confirms national standards, performance targets/priorities for General and Major Works

• Operations/Technical Director issues target allocations to national Major Works team and each Waterway Manager

October

Stage 2 – Setting Operations Targets & Priorities

Page 6: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 3 – Preparing draft Major Works Plan

• National Team – adjust existing 2/3 year plan in light of target allocations

• Meet with waterways to explain and discuss national and local priorities

• Needs and views of Local Partnership fed into process by Waterway Manager

• Programme prepared that addresses priorities and is deliverable within financial year

• Programme submitted - to waterways for information/comment

- to Operations/Technical Director for approval

November - December

Stage 3 – Preparing draft Major Works Plan

Page 7: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 3 – Preparing draft General Works Plan

• Waterway Manager discusses local needs/priorities with Local Partnership and local management team

• Liaises with Operations/Technical Director and other Waterway Managers on national priorities etc.

• Waterway Manager submits local business plan including commentary on risks to Operations/Technical Director for approval

November - December

Stage 3 – Preparing draft General Works Plan

Page 8: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 4 – Preparation of draft National Plan for Trustees

• Operations/Technical Director considers Major and General Works Plans, agrees modifications and adjustments in light of comments and feedback

• Submits Major and General Works Programme budgets to Finance Director

• Finance Director consolidates all plans into a draft National Business Plan

• Draft National Business Plan submitted to Trustees for comment

January

Stage 4 – Preparation of draft National Plan for Trustees

Page 9: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 5 – Revisions/Refinements to National & Local Plans

• Executive reconsiders Local and National Plans in light of feedback from Trustees

• Operations/Technical Director reconsiders GW and MW Plans in light of Trustees feedback and LWP comments

• LWP invoke right to meet Operations/Technical Director if major concerns remain in respect of Business Plan

February - March

Stage 5 – Revisions/Refinements to National & Local Plans

Page 10: Proposed NWC General  Works and Major Works   Business Plan Process

Stage 5 – Approval of National & Local Plans

• Executive adjusts National Plan and resubmits to Trustees

• LWP Chairmen have right to submit comments directly to Trustees

• Trustees consider final draft Plan for approval

• Executive confirm National and draft Plans to business (or continue review of Plan until Trustees approval received)

March

Stage 5 – Approval of National & Local Plans

Page 11: Proposed NWC General  Works and Major Works   Business Plan Process

Steady State Allocation - £125mSteady State Allocation - £125m

Page 12: Proposed NWC General  Works and Major Works   Business Plan Process

Steady State Comparison

 

2011/12 Business

Plan £'000

Steady State Model £'000

Variance £'000

%

Steady State Direct Cost: Repair, PPM and Inspections: Intermediate Repairs (aqueducts; bridges; locks; bank protection) 13,860 13,317 (543) 104.1 PPM (bridges; locks; sluices; weirs) 3,771 7,140 3,369 52.8 Inspections (Annual; Principal; Length; Reservoirs) 2,370 2,265 (105) 104.6           20,001            22,722            2,721               88     Amenity/Customer Service/Other: Vegetation 6,245 11,553 5,308 54.1 Facilities 1,719 2,939 1,220 58.5 Litter and antisocial behaviour 1,609 2,154 545 74.7 Water control 1,319 1,422 103 92.8

Other (volunteering; manning structures; towpath management; fencing; access management etc.)

9,298 16,997 7,699 54.7

          20,190            35,065          14,875               58     Total Steady State Direct Costs           40,191            57,787          17,596               70  Steady State Indirect Costs:

People not directly attributable to specific works (includes 20% operational staff as productivity rate set at 80%)

9,598 16,366 6,768 58.6

Operational Plant, Craft and Equipment (maintenance; fuel; depreciation) 5,162 8,802 3,640 58.6 Operational Buildings (repair; insurance; utilities; depreciation) 1,661 2,832 1,171 58.6 Total Steady State Indirect Costs           16,421            28,000          11,579           58.6  Total Steady State Costs (excl Major Works)           56,612            85,787          29,175           66.0 

Minor Works Steady State Comparison

Page 13: Proposed NWC General  Works and Major Works   Business Plan Process

Average Steady State Spend by Waterway 2011/12 - £5.2m

Average Steady State Spend by Waterway 2011/12 - £5.2m

Page 14: Proposed NWC General  Works and Major Works   Business Plan Process

Operational Focus 2011/12 - £56.6mOperational Focus 2011/12 - £56.6m

Page 15: Proposed NWC General  Works and Major Works   Business Plan Process

BW HQ and Central Services

HQ & Central HQ & Central Service cost Service cost supporting supporting Operations - Operations -

£21.8m£21.8m

Total HQ Total HQ and Central and Central

Service Service cost - cost -

£30.9m£30.9m

HQ and Central Services

Page 16: Proposed NWC General  Works and Major Works   Business Plan Process

Major Works 4 year planned expenditure Major Works 4 year planned expenditure

Page 17: Proposed NWC General  Works and Major Works   Business Plan Process

Major Works focus Year 1 and 2

Year 12011/12£16.2m

Major Works focus Year 1 and 2

Page 18: Proposed NWC General  Works and Major Works   Business Plan Process

 

• Operations focus to manage risk, prioritise expenditure, increase productivity and efficiency to deliver effective customer service

• Open to suggestions for improving best value for waterways from local/national stakeholders

Explanation – General WorksOverview