Page 1: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp
Page 2: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp
Page 3: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PT PP (Persero) Tbk. Divisi EPC

PROYEK :

Pada hari ini : Kamis

Tanggal : 24-Nov-16

Bertempat di : PP Plaza

Telah diadakan negosiasi terhadap penawaran : PT. Schneider Indonesia

No : 007/VII/PP-CGN/16

Tanggal : 26-Sep-16

1. Pekerjaan : Field Transmitter

2. Spesifikasi : As Per TBE, AVL

Garansi 12 bulan dari material on site

3. Waktu pengiriman : DDP Site Gresik

End of February 2016

4. Harga

:

5. Cara pembayaran : TT 90 hari/ SKBDN Ussance 90 hari

- 5% Engineering Approval

- 10% Fabrication Progress

- 10% Factory Acceptance

- 70% Material On Site

- 5% Retention 12bulan (counter warranty bond - bank)

6. Lingkup supplier : Supply, pengiriman DDP Gresik

7. Lingkup PT. PP (Persero) : Instalasi

8. Lampiran yang merupakan bagian dari Berita Acara ini :

TBE

Jakarta, 24 November 2016

Dinni Ika Irham________________________

BERITA ACARA NEGOSIASI

DENGAN SUPPLIER

Final Submission via E-Proc 29 Nov 2016

PT. Schneider Indonesia Pihak PT. PP (Persero)

Lamp.1 QSHE/DVEPC/AB/W/001

Page 4: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

1.0 GENERAL1.1 BIDDER'S QUOTATION NUMBER By Vendor PP EPC-Gresik Gas Cogen-Dt.23.9.2016-PT & PDT

1.2 DELIVERY To be specified (Unit : Month) Estimated Shipment: 8 - 10 Weeks ARO, TBC upon PO

1.3 VALIDITY To be specified (Unit : Month) 30 calendar days

1.4 FOB To be specified (Unit : Month) DDP Gresik, Indonesia

1.5 TERMS OF PAYMENT Engineering Approval 5 %Fabrication Progress 20 %Factory Acceptance 20 %Material On Site 30 %

After Installation Complete 10 %Site Acceptance Test 10 %

Retention 5 %

Engineering Approval 5 %Fabrication Progress 10 %Factory Acceptance 10 %Material On Site 70 %

Retention 5 % (Counter Bank Guarantee)

1.6 COMPLIANCE LIST TO SPECIFICATION Vendor to confirm YES

1.7 DEVIATION LIST Vendor to confirm NO

2.0 SCOPE OF SUPPLY

FIELD INSTRUMENT YES YES

MISCELLANEOUS EQUIPMENT YES YES

SPARE PARTS FOR 2 YEARS YES YES

FABRICATION & INSTALLATION YES YES

3.0 SCOPE OF WORK

3.1 PROJECT SERVICES YES Included

3.2 ENGINEERING SERVICES (BASIC & DETAILED)YES Included

3.3 PROJECT DOCUMENTATION YES Included

3.4 COMMISSIONING SUPPORT & SAT YES Included

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 1 of 37

TBE Sheet 13 Dec 2016

Page 5: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

3.5 PROJECT SERVICES YES Included

4.0 GENERAL REQUIREMENT

4.1 Domestic Contents List and Percentage YES Included4.2 Sub Supplier and Standardization YES Included4.3 Document to be submitted with Proposal YES Included4.4 Construction Work Volume for Package Item YES Included

5.0 TECHNICAL REQUIREMENT

5.1 Level Switch (06-LS-426)Model Standard Manufature Standard Manufature Service Waste Water Sump Pit-1 Waste Water Sump Pit-1

Line/Equipment 01-CQ-06427 01-CQ-06427

P&ID GGCP-04-P0-PI-002-PP 1 of 3 GGCP-04-P0-PI-002-PP 1 of 3

Pressure Max / Min 2kg/cm2g/0-0.25kg/cm2g 2kg/cm2g/0-0.25kg/cm2g

Temperature Max / Min 27 C 27 C

Type Displacer Displacer

Material 316 SS 316 SS

Power Supply 110 VAC 110 VAC

5.2 Level Switch (06-LS-427) Standard Manufature Model Standard Manufature Waste Water Sump Pit-2Service Waste Water Sump Pit-2 01-CQ-06429

Line/Equipment 01-CQ-06429 GGCP-04-P0-PI-002-PP 1 of 3

P&ID GGCP-04-P0-PI-002-PP 1 of 3 2kg/cm2g/0-0.25kg/cm2g

Pressure Max / Min 2kg/cm2g/0-0.25kg/cm2g 27 C

Temperature Max / Min 27 C Displacer

Type Displacer 316 SS

Material 316 SS 110 VAC

Power Supply 110 VAC

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 2 of 37

TBE Sheet 13 Dec 2016

Page 6: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.3 Level Switch (07-LS-464)Model Standard Manufature Standard Manufature Service Storage Service Water Tank-1 Storage Service Water Tank-1Line/Equipment 01-CU-07465 01-CU-07465P&ID GGCP-04-P0-PI-009-PP GGCP-04-P0-PI-009-PPPressure Max / Min 2kg/cm2g/0-1.65kg/cm2g 2kg/cm2g/0-1.65kg/cm2g

Temperature Max / Min 27 C 27 CType Guided Radar Level Guided Radar LevelMaterial Carbon Steel Carbon Steel

Power Supply 110 VAC 110 VAC

5.4 Level Switch (07-LS-465)Model Standard Manufature Standard Manufature Service Storage Portable Water Tank-2 Storage Portable Water Tank-2

Line/Equipment 01-CU-07466 01-CU-07466

P&ID GGCP-04-P0-PI-009-PP GGCP-04-P0-PI-009-PP

Pressure Max / Min 2kg/cm2g/0-1.65kg/cm2g 2kg/cm2g/0-1.65kg/cm2g

Temperature Max / Min 27 C 27 C

Type Guided Radar Level Guided Radar Level

Material Carbon Steel Carbon Stee;

Power Supply 110 VAC 110 VAC

5.5 Level Switch (07-LS-466)Model Standard Manufature Standard Manufature Service Storage Portable Water Tank Storage Portable Water Tank

Line/Equipment 01-CU-07468 01-CU-07468P&ID GGCP-04-P0-PI-009-PP GGCP-04-P0-PI-009-PPPressure Max / Min 2kg/cm2g/0-1.65kg/cm2g 2kg/cm2g/0-1.65kg/cm2gTemperature Max / Min 27 C 27 CType Guided Radar Level Guided Radar LevelMaterial Carbon Steel Carbon Steel

Power Supply 110 VAC 110 VAC

5.6 Temperature Gauge (04-TG-302)

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 3 of 37

TBE Sheet 13 Dec 2016

Page 7: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Model Standard Manufature Standard Manufature Service Cooling Water Return Cooling Water ReturnLine/Equipment 8"-CWR-1A-006 8"-CWR-1A-006P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PPPressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.7 Temperature Gauge (04-TG-301)Model Standard Manufature Standard Manufature Service Cooling Water Supply Cooling Water SupplyLine/Equipment 8" CWS-1A-005 8" CWS-1A-005P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PPPressure Max / Min 8 Kg/Cm2g / 12 Kg/cm2g 8 Kg/Cm2g / 12 Kg/cm2gTemperature Max / Min 32 C / 70 C 32 C / 70 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.8 Temperature Gauge (04-TG-305)Model Standard Manufature Standard Manufature Service Cooling Water Return from Air Compressor Cooling Water Return from Air CompressorLine/Equipment 2"-CWR-1A-001-PP 2"-CWR-1A-001-PPP&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PPPressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.9 Temperature Gauge (04-TG-306)Model Standard Manufature Standard Manufature Service Cooling Water Return from Dearator Cooling Water Return from Dearator

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 4 of 37

TBE Sheet 13 Dec 2016

Page 8: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 3"-CWR-1A-002 3"-CWR-1A-002P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PPPressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5,10 Temperature Gauge (04-TG-307)Model Standard Manufature Standard Manufature Service Cooling Water from PB Area Cooling Water from PB AreaLine/Equipment 1"-CWR-1A-022 1"-CWR-1A-022P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PPPressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.11 Temperature Gauge (04-TG-308)Model Standard Manufature Standard Manufature Service Cooling Water Return from HRSG Cooling Water Return from HRSGLine/Equipment 3"-CWR-1A-003-PP 3"-CWR-1A-003-PPP&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PPPressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.12 Temperature Gauge (04-TG-309)Model Standard Manufature Standard Manufature Service Cooling Water Return From GTG Cooling Water Return From GTGLine/Equipment 6"-CWR-1A-004 6"-CWR-1A-004P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 5 of 37

TBE Sheet 13 Dec 2016

Page 9: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Pressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2gTemperature Max / Min 42 C / 80 C 42 C / 80 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 100 C 0 C - 100 C

5.13 Temperature Gauge (04-TG-310)Model Standard Manufature Standard Manufature Service Cooling Water Return from SWAS Cooling Water Return from SWAS

Line/Equipment 2"-CWR-1A-005 2"-CWR-1A-005

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/Cm2g / 5 Kg/cm2g 2 Kg/Cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C / 80 C 42 C / 80 C

Type Heavy Duty Bimetalic Heavy Duty Bimetalic

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Measuring Range 0 C - 100 C 0 C - 100 C

5.14 Temperature Gauge (26-TG-951)Model Standard Manufature Standard Manufature Service MP Steam Header MP Steam HeaderLine/Equipment 14-MPS-3A-003-H-135 14-MPS-3A-003-H-135P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PPPressure Max / Min 51 Kg/Cm2g / 54,5 Kg/cm2g 51 Kg/Cm2g / 54,5 Kg/cm2gTemperature Max / Min 425 C / 460 C 425 C / 460 CType Heavy Duty Bimetalic Heavy Duty BimetalicProcess Connection 1/2" NPTM 1/2" NPTMMaterial SS 316 SS 316Measuring Range 0 C - 700 C 0 C - 700 C

5.15 Temperature Gauge (26-TG-960)Model Standard Manufacture Standard Manufature

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 6 of 37

TBE Sheet 13 Dec 2016

Page 10: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Service From BFW Pump Boiler From BFW Pump Boiler

Line/Equipment 6"-LPS-1A-001-H-100 6"-LPS-1A-001-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Heavy Duty Bimetalic Heavy Duty Bimetalic

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Measuring Range 0 C - 500 C 0 C - 500 C

5.16 Temperature Gauge (26-TG-961)Model Standard Manufacture Standard Manufature Service From BFW Pump HRSG From BFW Pump HRSG

Line/Equipment 6"-LPS-1A-002-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Heavy Duty Bimetalic Heavy Duty Bimetalic

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Measuring Range 0 C - 500 C 0 C - 500 C

5.17 Temperature Gauge (26-TG-962)Model Standard Manufacture Standard Manufature Service To BFW Pump Boiler From BFW Pump HRSG

Line/Equipment 3''-MPS-3A-010-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Heavy Duty Bimetalic Heavy Duty Bimetalic

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 7 of 37

TBE Sheet 13 Dec 2016

Page 11: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Measuring Range 0 C - 500 C 0 C - 500 C

5.18 Temperature Gauge (26-TG-963)Model Standard Manufacture Standard Manufature Service To BFW Pump HRSG From BFW Pump HRSG

Line/Equipment 3''-MPS-3A-009-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Heavy Duty Bimetalic Heavy Duty Bimetalic

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Measuring Range 0 C - 500 C 0 C - 500 C

5.19 Temperature Element (04-TE-304)Model Standard Manufature Standard Manufature Service Cooling Water Supply Line Cooling Water Supply Line

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 8 Kg/cm2g / 12Kg/cm2g 8 Kg/cm2g / 12Kg/cm2g

Temperature Max / Min 32 C / 70 C 32 C / 70 C

Type 3-Wire RTD 3-Wire RTD

Connection Wire 1/2" NPTM 1/2" NPTM

Mounting Thread to Well 1/2" NPTF 1/2" NPTF

Material PT-100 PT-100

Resistance 100 Ω at 0 C 100 Ω at 0 C

Temperature Range -200 C - 600 C -200 C - 600 C

5,20 Temperature Element (04-TE-303)Model Standard Manufature Standard Manufature Service Cooling Water Return Line Cooling Water Return Line

Line/Equipment 8"-CWS-1A-006 8"-CWS-1A-006

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 8 of 37

TBE Sheet 13 Dec 2016

Page 12: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 2 Kg/cm2g / 5Kg/cm2g 2 Kg/cm2g / 5Kg/cm2g

Temperature Max / Min 42 C / 80 C 42 C / 80 C

Type 3-Wire RTD 3-Wire RTD

Connection Wire 1/2" NPTM 1/2" NPTM

Mounting Thread to Well 1/2" NPTF 1/2" NPTF

Material PT-100 PT-100

Resistance 100 Ω at 0 C 100 Ω at 0 C

Temperature Range -200 C - 600 C -200 C - 600 C

5.21 Temperature Element (26-TE-953)Model Standard Manufature Standard Manufature Service MP Steam to Amurea II MP Steam to Amurea II

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 51 Kg/cm2g / 54,5Kg/cm2g 51 Kg/cm2g / 54,5Kg/cm2g

Temperature Max / Min 386 C / 440 C 386 C / 440 C

Type Thermocouple type K Thermocouple type K

Connection Wire 1/2" NPTM 1/2" NPTM

Mounting Thread to Well 1/2" NPTF 1/2" NPTF

Material SS 316 SS 316

Wire Configuration 2 Wire 2 Wire

Measurement Range -200 C - 1350 C -200 C - 1350 C

5.22 Temperature Element (26-TE-952)Model Standard Manufature Standard Manufature Service MP Steam to Amurea II MP Steam to Amurea II

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 51 Kg/cm2g / 54,5Kg/cm2g 51 Kg/cm2g / 54,5Kg/cm2g

Temperature Max / Min 425 C / 460 C 425 C / 460 C

Type Thermocouple type K Thermocouple type K

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 9 of 37

TBE Sheet 13 Dec 2016

Page 13: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Connection Wire 1/2" NPTM 1/2" NPTM

Mounting Thread to Well 1/2" NPTF 1/2" NPTF

Material SS 316 SS 316

Wire Configuration 2 Wire 2 Wire

Measurement Range -200 C - 1350 C -200 C - 1350 C

5.23 Temperature Element (26-TE-957)Model Standard Manufature Standard Manufature Service LP Steam to Dearator Package Boiler LP Steam to Dearator Package Boiler

Line/Equipment 10"-LPS-1A-003-H-85 10"-LPS-1A-003-H-85

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 7,5Kg/cm2g 4 Kg/cm2g / 7,5Kg/cm2g

Temperature Max / Min 250 C / 280 C 250 C / 280 C

Type Thermocouple type K Thermocouple type K

Connection Wire 1/2" NPTM 1/2" NPTM

Mounting Thread to Well 1/2" NPTF 1/2" NPTF

Material SS 316 SS 316

Wire Configuration 2 Wire 2 Wire

Measurement Range -200 C - 1350 C -200 C - 1350 C

5.24 Temperature Indicator Transmitter (04-TT-303)Model Standard Manufature RTT80-T1LLATKZZ-L1WFService Cooling Water Return Line Cooling Water Return Line

Line/Equipment 8"-CWR-1A-006 8"-CWR-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C / 80 C 42 C / 80 C

Type Smart Transmitter Smart Transmitter

Elec. Connection 1/2 NPTF 1/2 NPTF

Enclosure Material Die-Cast Alumunium Aluminum

Power 24 VDC (2 Wired System) 24 VDC (2 Wired System)

Calib. Range 0 C - 100 C 0 C - 100 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 10 of 37

TBE Sheet 13 Dec 2016

Page 14: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.25 Temperature Indicator Transmitter (04-TT-304)

Model Standard Manufature RTT80-T1LLATKZZ-L1WF

Service Cooling Water Supply Line Cooling Water Return Line

Line/Equipment 8"-CWS-1A-005 8"-CWR-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 8 Kg/cm2g / 12 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 32 C / 70 C 42 C / 80 C

Type Smart Transmitter Smart Transmitter

Elec. Connection 1/2 NPTF 1/2 NPTF

Enclosure Material Die-Cast Alumunium Aluminum

Power 24 VDC (2 Wired System) 24 VDC (2 Wired System)

Calib. Range 0 C - 100 C 0 C - 100 C

5.26 Temperature Indicator Transmitter (26-TT-952)

Model Standard Manufature RTT80-T1LLKTKZZ-L1WF

Service MP Steam Header MP Steam Header

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 54,5 Kg/cm2g / 51 Kg/cm2g 54,5 Kg/cm2g / 51 Kg/cm2g

Temperature Max / Min 460 C / 425 C 460 C / 425 C

Type Smart Transmitter Smart Transmitter

Elec. Connection 1/2 NPTF 1/2 NPTF

Enclosure Material Die-Cast Alumunium Die-Cast Alumunium

Power 24 VDC (2 Wired System) 24 VDC (2 Wired System)

Calib. Range 0 C - 700 C 0 C - 700 C

5.27 Temperature Indicator Transmitter (26-TT-953)

Model Standard Manufature RTT80-T1LLKTKZZ-L1WF

Service MP Steam to Amurea II MP Steam to Amurea II

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 11 of 37

TBE Sheet 13 Dec 2016

Page 15: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Pressure Max / Min 54,5 Kg/cm2g / 51 Kg/cm2g 54,5 Kg/cm2g / 51 Kg/cm2g

Temperature Max / Min 440 C / 368 C 440 C / 368 C

Type Smart Transmitter Smart Transmitter

Elec. Connection 1/2 NPTF 1/2 NPTF

Enclosure Material Die-Cast Alumunium Die-Cast Alumunium

Power 24 VDC (2 Wired System) 24 VDC (2 Wired System)

Calib. Range 0 C - 700 C 0 C - 700 C

5.28 Temperature Indicator Transmitter (26-TT-957)

Model Standard Manufature RTT80-T1LLKTKZZ-L1WF

Service LP Steam to Dearator Boiler Package LP Steam to Dearator Boiler Package

Line/Equipment 10"-LPS-1A-003-H-85 10"-LPS-1A-003-H-85

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 7,5 Kg/cm2g / 4 Kg/cm2g 7,5 Kg/cm2g / 4 Kg/cm2g

Temperature Max / Min 280 C / 250 C 280 C / 250 C

Type Smart Transmitter Smart Transmitter

Elec. Connection 1/2 NPTF 1/2 NPTF

Enclosure Material Die-Cast Alumunium Die-Cast Alumunium

Power 24 VDC (2 Wired System) 24 VDC (2 Wired System)

Calib. Range 0 C - 400 C 0 C - 400 C

5.29 Thermowell (04-TW-302)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Supply Cooling Water Supply

Line/Equipment 8" CWS-1A-006 8" CWS-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 5 Kg/Cm2g / 2 Kg/cm2g 5 Kg/Cm2g / 2 Kg/cm2g

Temperature Max / Min 80 C / 42 C 80 C / 42 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 6,25" / 4,5" 6,25" / 4,5"

Material SS 316 SS 316

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 12 of 37

TBE Sheet 13 Dec 2016

Page 16: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Bore Size 0,260" 0,260"

5,30 Thermowell (04-TW-303)

Model Standard Manufature TT-2CA404520

Service Cooling Water Return Line Cooling Water Return Line

Line/Equipment 8"-CWR-1A-006 8"-CWR-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 5 Kg/Cm2g / 2 Kg/cm2g 5 Kg/Cm2g / 2 Kg/cm2g

Temperature Max / Min 80 C / 42 C 80 C / 42 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPTM 1/2" NPTM

Stem / Insertion Length 6,25" / 4,5" 6,25" / 4,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.31 Thermowell (04-TW-301)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Supply Cooling Water Supply

Line/Equipment 8" CWS-1A-005 8" CWS-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 12 Kg/Cm2g / 8 Kg/cm2g 12 Kg/Cm2g / 8 Kg/cm2g

Temperature Max / Min 70 C / 32 C 70 C / 32 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 6,25" / 4,5" 6,25" / 4,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.32 Thermowell (04-TW-304)

Model Standard Manufature TT-2CA404520

Service Cooling Water Supply Line Cooling Water Supply Line

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 13 of 37

TBE Sheet 13 Dec 2016

Page 17: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 8 Kg/cm2g / 12 Kg/cm2g 8 Kg/cm2g / 12 Kg/cm2g

Temperature Max / Min 32 C / 70 C 32 C / 70 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPTM 1/2" NPTM

Stem / Insertion Length 6,25" / 4,5" 6,25" / 4,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.33 Thermowell (04-TW-305)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Return from Air Compressor Cooling Water Return from Air Compressor

Line/Equipment 2"-CWR-1A-001 2"-CWR-1A-001

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 3,25" / 1,5" 3,25" / 1,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.34 Thermowell (10-TW-306)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Return from Dearator Cooling Water Return from Dearator

Line/Equipment 3"-CWR-1A-002 3"-CWR-1A-002

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 3,75" / 2" 3,75" / 2"

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 14 of 37

TBE Sheet 13 Dec 2016

Page 18: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.35 Thermowell (10-TW-307)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water from PB Area Cooling Water from PB Area

Line/Equipment 1"-CWR-1A-022 1"-CWR-1A-022

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 2,25" / 0,5" 2,25" / 0,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.36 Thermowell (10-TW-308)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Return from HRSG Cooling Water Return from HRSG

Line/Equipment 3"-CWR-1A-003 3"-CWR-1A-003

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 3,75" / 2" 3,75" / 2"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.37 Thermowell (10-TW-309)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Return from GTG Cooling Water Return from GTG

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 15 of 37

TBE Sheet 13 Dec 2016

Page 19: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 6"-CWR-1A-004 6"-CWR-1A-004

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 5,25" / 3,5" 5,25" / 3,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.38 Thermowell (10-TW-310)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service Cooling Water Return from SWAS Cooling Water Return from SWAS

Line/Equipment 2"-CWR-1A-005 2"-CWR-1A-005

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 2 Kg/cm2g / 5 Kg/cm2g 2 Kg/cm2g / 5 Kg/cm2g

Temperature Max / Min 42 C - 80 C 42 C - 80 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 3,25" / 1,5" 3,25" / 1,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.39 Thermowell (26-TW-951)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service MP Steam Header MP Steam Header

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 51 Kg/cm2g / 54,5 Kg/cm2g 51 Kg/cm2g / 54,5 Kg/cm2g

Temperature Max / Min 425 C - 460 C 425 C - 460 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 16 of 37

TBE Sheet 13 Dec 2016

Page 20: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Stem / Insertion Length 9,25" / 7,5" 9,25" / 7,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5,40 Thermowell (26-TW-952)

Model Standard Manufature TT-2CA407520

Service MP Steam Header MP Steam Header

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 51 Kg/cm2g / 54,5 Kg/cm2g 51 Kg/cm2g / 54,5 Kg/cm2g

Temperature Max / Min 425 C / 460 C 425 C / 460 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPTM 1/2" NPTM

Stem / Insertion Length 9,25" / 7,5" 9,25" / 7,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.41 Thermowell (26-TW-953)

Model Standard Manufature TT-2CA407520

Service MP Steam to Amurea II MP Steam to Amurea II

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 51 Kg/cm2g / 54,5 Kg/cm2g 51 Kg/cm2g / 54,5 Kg/cm2g

Temperature Max / Min 386 C / 440 C 386 C / 440 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPTM 1/2" NPTM

Stem / Insertion Length 9,25" / 7,5" 9,25" / 7,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.42 Thermowell (26-TW-957)

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 17 of 37

TBE Sheet 13 Dec 2016

Page 21: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Model Standard Manufature TT-2CA404520

Service LP Steam to Dearator Boiler Package LP Steam to Dearator Boiler Package

Line/Equipment 10"-LPS-1A-003-H-85 10"-LPS-1A-003-H-85

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 7,5 Kg/cm2g 4 Kg/cm2g / 7,5 Kg/cm2g

Temperature Max / Min 250 C / 280 C 250 C / 280 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPTM 1/2" NPTM

Stem / Insertion Length 6,25" / 5,5" 6,25" / 5,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.43 Thermowell (26-TW-960)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service From BFW Pump Boiler From BFW Pump Boiler

Line/Equipment 6"-LPS-1A-001-H-100 6"-LPS-1A-001-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 5,25" / 3,5" 5,25" / 3,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.44 Thermowell (26-TW-961)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service From BFW Pump HRSG From BFW Pump HRSG

Line/Equipment 6"-LPS-1A-002-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 18 of 37

TBE Sheet 13 Dec 2016

Page 22: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 5,25" / 3,5" 5,25" / 3,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.45 Thermowell (26-TW-962)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service To BFW Pump Boiler To BFW Pump Boiler

Line/Equipment 3''-MPS-3A-010-H-100 3''-MPS-3A-010-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 5,25" / 3,5" 5,25" / 3,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

5.46 Thermowell (26-TW-963)

Model Standard Manufature 50-W-U LENGTH-HT-260-S-XDQ-W5

Service To BFW Pump HRSG To BFW Pump HRSG

Line/Equipment 3''-MPS-3A-009-H-100 3''-MPS-3A-009-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 4 Kg/cm2g / 8 Kg/cm2g 4 Kg/cm2g / 8 Kg/cm2g

Temperature Max / Min 304,5 C / 420 C 304,5 C / 420 C

Type Solid Drilled from Bar Stock Solid Drilled from Bar Stock

Process Connection 1/2" NPT 1/2" NPT

Stem / Insertion Length 5,25" / 3,5" 5,25" / 3,5"

Material SS 316 SS 316

Bore Size 0,260" 0,260"

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 19 of 37

TBE Sheet 13 Dec 2016

Page 23: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.47 Pressure Gauge (06-PG-426A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Sump Pump-1 (01-GA-06428-A-M) Discharge Sump Pump-1 (01-GA-06428-A-M) Discharge

Line/Equipment 3"-WW-1A-006 3"-WW-1A-006

P&ID GGCP-04-P0-PI-002-PP (sheet 1 of 3) GGCP-04-P0-PI-002-PP (sheet 1 of 3)

Pressure Max / Min 7.5 kg/cm2 / 5 kg/cm2 7.5 kg/cm2 / 5 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-12 kg/cm2g 0-12 kg/cm2g

5.48 Pressure Gauge (06-PG-426B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Sump Pump-1 (01-GA-06428-B-M) Discharge Sump Pump-1 (01-GA-06428-B-M) Discharge

Line/Equipment 3"-WW-1A-035 3"-WW-1A-035

P&ID GGCP-04-P0-PI-002-PP (Sheet 1 of 3) GGCP-04-P0-PI-002-PP (Sheet 1 of 3)

Pressure Max / Min 7 kg/cm2 / 5 kg/cm2 7 kg/cm2 / 5 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-12 kg/cm2g 0-12 kg/cm2g

5.49 Pressure Gauge (06-PG-427A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Sump Pump-2 (01-GA-06430-A-M) Discharge Sump Pump-2 (01-GA-06430-A-M) Discharge

Line/Equipment 1"-WW-1A-010 1"-WW-1A-010

P&ID GGCP-04-P0-PI-002-PP (Sheet 1 of 3) GGCP-04-P0-PI-002-PP (Sheet 1 of 3)

Pressure Max / Min 7,5 kg/cm2 / 5 kg/cm2 7,5 kg/cm2 / 5 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 20 of 37

TBE Sheet 13 Dec 2016

Page 24: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-12 kg/cm2g 0-12 kg/cm2g

5,50 Pressure Gauge (06-PG-427B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Sump Pump-2 (01-ga-06430-B-M) Discharge Sump Pump-2 (01-ga-06430-B-M) Discharge

Line/Equipment 1"-WW-1A-038 1"-WW-1A-038

P&ID GGCP-4-P0-PI-002-PP (sheet 1 of 3) GGCP-4-P0-PI-002-PP (sheet 1 of 3)

Pressure Max / Min 7,5 kg/cm2 / 5 kg/cm2 7,5 kg/cm2 / 5 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

Type Direct reading, Bourdon Type Direct reading, Bourdon Type

Process Connection 1/2 NPTM 1/2 NPTM

Material 316 SS 316 SS

Measuring Range 0-12 kg/cm2g 0-12 kg/cm2g

5.51 Pressure Gauge (08-PG-476A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Demin Feed PB Pump 01-GA-08477-A-M Discharge Demin Feed PB Pump 01-GA-08477-A-M

Line/Equipment 6"-DW-1SSA-004 6"-DW-1SSA-004

P&ID GGCP-04-P0-PI-003-PP (sheet 1 of 13) GGCP-04-P0-PI-003-PP (sheet 1 of 13)

Pressure Max / Min 16 kg/cm2 / 12,27 kg/cm2 16 kg/cm2 / 12,27 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2 NPTM 1/2 NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5.52 Pressure Gauge (08-PG-476B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Demin Feed PB Pump 01-GA-08477-BM Discharge Demin Feed PB Pump 01-GA-08477-BM

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 21 of 37

TBE Sheet 13 Dec 2016

Page 25: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 6"-DW-1SSA-006 6"-DW-1SSA-006

P&ID GGCP-04-P0-PI-003-PP (Sheet 1 of 13) GGCP-04-P0-PI-003-PP (Sheet 1 of 13)

Pressure Max / Min 16 kg/cm2 / 12,27 kg/cm2 16 kg/cm2 / 12,27 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5.53 Pressure Gauge (08-PG-477A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Feed HRSG Pump 01-GA-08478-A-M Discharge Feed HRSG Pump 01-GA-08478-A-M

Line/Equipment 4"-DW-1SSA-008 4"-DW-1SSA-008

P&ID GGCP-04-P0-PI-003-PP (sheet 1 of 13) GGCP-04-P0-PI-003-PP (sheet 1 of 13)

Pressure Max / Min 18 kg/cm2 / 14,22 kg/cm2 18 kg/cm2 / 14,22 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon type Direct Reading, Bourdon type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-25 kg/cm2g 0-25 kg/cm2g

5.54 Pressure Gauge (08-PG-477B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Feed HRSG Pump 01-GA-08478-B-M Discharge Feed HRSG Pump 01-GA-08478-B-M

Line/Equipment 4"-DW-1SSA-010 4"-DW-1SSA-010

P&ID GGCP-04-P0-PI-003-PP (Sheet 1 of 13) GGCP-04-P0-PI-003-PP (Sheet 1 of 13)

Pressure Max / Min 18 kg/cm2 / 14,22 kg/cm2 18 kg/cm2 / 14,22 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Discharge Feed HRSG Pump 01-GA-08478-B-M Discharge Feed HRSG Pump 01-GA-08478-B-M

Process Connection Direct Reading, Bourdon type Direct Reading, Bourdon type

Material 316 SS 316 SS

Measuring Range 0-25 kg/cm2g 0-25 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 22 of 37

TBE Sheet 13 Dec 2016

Page 26: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.55 Pressure Gauge (10-PG-533)Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Instrument Air Distribution Header Instrument Air Distribution Header

Line/Equipment 2"-IA-1AG-005 2"-IA-1AG-005

P&ID GGCP-04-P0-PI-006-PP GGCP-04-P0-PI-006-PP

Pressure Max / Min 11,5 kg/cm2 / 8 kg/cm2 11,5 kg/cm2 / 8 kg/cm2

Temperature Max / Min 70 C / 40 C 70 C / 40 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2 0-20 kg/cm2

5.56 Pressure Gauge (04-PG-301A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Make Up Cooling Pump 01-ga-04301-A-M Discharge Make Up Cooling Pump 01-ga-04301-A-M

Line/Equipment 1 1/2" -RW-1A-006 1 1/2" -RW-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 5,3 kg/cm2 / 3 kg/cm2 5,3 kg/cm2 / 3 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.57 Pressure Gauge (04-PG-301B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Make Up Cooling Pump 01-GA-04301-B-M Discharge Make Up Cooling Pump 01-GA-04301-B-M

Line/Equipment 1 1/2"-RW-1A-005 1 1/2"-RW-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 5,3 kg/cm2 / 3 kg/cm2 5,3 kg/cm2 / 3 kg/cm2

Temperature Max / Min 60 C / 27 C 60 C / 27 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 23 of 37

TBE Sheet 13 Dec 2016

Page 27: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2 " NPTM 1/2 " NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.58 Pressure Gauge (04-PG-303 A)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Disharge Circulating CW Pump 01-GA-04307-A-M Disharge Circulating CW Pump 01-GA-04307-A-M

Line/Equipment 8"-CWS-1A-002 8"-CWS-1A-002

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 11,5kg/cm2 / 8 kg/cm2 11,5kg/cm2 / 8 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5.59 Pressure Gauge (04-PG-303 B)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Discharge Circulating CW Pump 01-GA-04307-B-M Discharge Circulating CW Pump 01-GA-04307-B-M

Line/Equipment 8"-CWS-1A-04 8"-CWS-1A-04

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 11,5kg/cm2 / 8 kg/cm2 11,5kg/cm2 / 8 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5,60 Pressure Gauge (04-PG-306)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Distribution Header Cooling Water Distribution Header

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 24 of 37

TBE Sheet 13 Dec 2016

Page 28: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 8"-CWS-1A-04 8"-CWS-1A-04

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 11,5kg/cm2 / 8 kg/cm2 11,5kg/cm2 / 8 kg/cm2

Temperature Max / Min 60 C / 32 C 60 C / 32 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5.61 Pressure Gauge (04-PG-307)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling water return from air compressor plant Cooling water return from air compressor plant

Line/Equipment 2"-CWR-1A-001 2"-CWR-1A-001

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2 / 2 kg/cm2 5 kg/cm2 / 2 kg/cm2

Temperature Max / Min 72 C / 42 C 72 C / 42 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.62 Pressure Gauge (04-PG-308)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Return from Dearator of Boiler Cooling Water Return from Dearator of Boiler

Line/Equipment 3"-CWR-1A-002 3"-CWR-1A-002

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2 / 2 kg/cm2 5 kg/cm2 / 2 kg/cm2

Temperature Max / Min 72 C / 42 C 72 C / 42 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 25 of 37

TBE Sheet 13 Dec 2016

Page 29: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.63 Pressure Gauge (04-PG-309)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Return from HRSG Cooling Water Return from HRSG

Line/Equipment 3"-CWR-1A-003 3"-CWR-1A-003

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2 / 2 kg/cm2 5 kg/cm2 / 2 kg/cm2

Temperature Max / Min 72 C / 42 C 72 C / 42 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2 " NPTM 1/2 " NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.64 Pressure Gauge (04-PG-310)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Return from GTG Cooling Water Return from GTG

Line/Equipment 6"-CWR-1A-004 6"-CWR-1A-004

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2 / 2 kg/cm2g 5 kg/cm2 / 2 kg/cm2g

Temperature Max / Min 72 C / 42 C 72 C / 42 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2 " NPTM 1/2 " NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.65 Pressure Gauge (04-PG-311)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Return from SWAS Cooling Water Return from SWAS

Line/Equipment 2"-CWR-1A-005 2"-CWR-1A-005

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2g / 2 kg/cm2 5 kg/cm2g / 2 kg/cm2

Temperature Max / Min 72 C / 42 C 72 C / 42 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 26 of 37

TBE Sheet 13 Dec 2016

Page 30: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2 NPTM 1/2 NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.66 Pressure Gauge (04-PG-312)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service Cooling Water Return from PB Area Cooling Water Return from PB Area

Line/Equipment 1"-CWR-1A-022 1"-CWR-1A-022

P&ID GGCP-04-P0-PI-008-PP GGCP-04-P0-PI-008-PP

Pressure Max / Min 5 kg/cm2 / 2 kg/cm2 5 kg/cm2 / 2 kg/cm2

Temperature Max / Min 72 C / 42 C 72 C / 42 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.67 Pressure Gauge (26-PG-952)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service MP Steam Header MP Steam Header

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 61 kg/cm2g / 51 kg/cm2g 61 kg/cm2g / 51 kg/cm2g

Temperature Max / Min 460 C / 425 C 460 C / 425 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-100 kg/cm2g 0-100 kg/cm2g

5.68 Pressure Gauge (26-PG-953)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service LP Steam Header LP Steam Header

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 27 of 37

TBE Sheet 13 Dec 2016

Page 31: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 10"-LPS-1A-003-H-85 10"-LPS-1A-003-H-85

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 7,5 kg/cm2g / 4 kg/cm2g 7,5 kg/cm2g / 4 kg/cm2g

Temperature Max / Min 280 C / 250 C 280 C / 250 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.69 Pressure Gauge (26-PG-960)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service LP Steam from Steam Turbine of BFW Pump Boiler LP Steam from Steam Turbine of BFW Pump Boiler

Line/Equipment 6"-LPS-1A-001-H-100 6"-LPS-1A-001-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 8 kg/cm2 / 4 kg/cm2 8 kg/cm2 / 4 kg/cm2

Temperature Max / Min 420 C / 304,5 C 420 C / 304,5 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5,70 Pressure Gauge (26-PG-961)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service LP Steam from Steam Turbine of BFW Pump Boiler LP Steam from Steam Turbine of BFW Pump Boiler

Line/Equipment 6"-LPS-1A-002-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 8 kg/cm2 / 4 kg/cm2 8 kg/cm2 / 4 kg/cm2

Temperature Max / Min 420 C / 302 C 420 C / 302 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 28 of 37

TBE Sheet 13 Dec 2016

Page 32: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.71 Pressure Gauge (26-PG-962)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service LP Steam from Steam Turbine of BFW Pump Boiler LP Steam from Steam Turbine of BFW Pump Boiler

Line/Equipment 6"-LPS-1A-002-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 8 kg/cm2 / 4 kg/cm2 8 kg/cm2 / 4 kg/cm2

Temperature Max / Min 420 C / 302 C 420 C / 302 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.72 Pressure Gauge (26-PG-963)

Model Standard Manufature 60-1379-SSL-04L-XC4-NH-OS-SG

Service LP Steam from Steam Turbine of BFW Pump Boiler LP Steam from Steam Turbine of BFW Pump Boiler

Line/Equipment 6"-LPS-1A-002-H-100 6"-LPS-1A-002-H-100

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 8 kg/cm2 / 4 kg/cm2 8 kg/cm2 / 4 kg/cm2

Temperature Max / Min 420 C / 302 C 420 C / 302 C

Type Direct Reading, Bourdon Type Direct Reading, Bourdon Type

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.73 Pressure Indicator Transmitter (12-PT-707)

Model Standard Manufature IGP10ST22E1ZZ000-M2L1T

Service Metering Skid Discharge Outlet Gas to HRSG Metering Skid Discharge Outlet Gas to HRSG

Line/Equipment 2"-FG-1A-005 2"-FG-1A-005

P&ID GGCP-04-P0-PI-001-PP (sheet 2 of 2) GGCP-04-P0-PI-001-PP (sheet 2 of 2)

Pressure Max / Min 9 kg/cm2g / 4,92 kg/cm2g 9 kg/cm2g / 4,92 kg/cm2g

Temperature Max / Min 15,6 -48,9 C 15,6 -48,9 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 29 of 37

TBE Sheet 13 Dec 2016

Page 33: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 1/2"NPTM 1/2"NPTM

Material SS 316 SS 316

Power Supply 24 VDC, 4-20 mA HART Protocol 24 VDC, 4-20 mA HART Protocol

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.74 Pressure Indicator Transmitter (12-PT-708)

Model Standard Manufature IGP10ST22E1ZZ000-M2L1T

Service Metering Skid Discharge outlet gas to Package Boiler Metering Skid Discharge outlet gas to Package Boiler

Line/Equipment 4"-FG-1A-006 4"-FG-1A-006

P&ID GGCP-04-P0-PI-001-PP (Sheet 2 of 2) GGCP-04-P0-PI-001-PP (Sheet 2 of 2)

Pressure Max / Min 9 kg/cm2g / 4,92 kg/cm2g 9 kg/cm2g / 4,92 kg/cm2g

Temperature Max / Min 15,6 - 48,9 C 15,6 - 48,9 C

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Power Supply 24 VDC, 4-20 mA HART Protocol 24 VDC, 4-20 mA HART Protocol

Measuring Range 0-100 kg/cm2g 0-100 kg/cm2g

5.75 Pressure Indicator Transmitter (10-PIT-526)

Model Standard Manufature IGP10ST22E1ZZ000-M2L1T

Service Instrument Air Receiver Tank Discharge Outlet Instrument Air Receiver Tank Discharge Outlet

Line/Equipment 2"-IA-1AG-005 2"-IA-1AG-005

P&ID GGCP-04-P0-PI-006-PP (Sheet 2 of 3) GGCP-04-P0-PI-006-PP (Sheet 2 of 3)

Pressure Max / Min 11,5 kg/cm2g / 8 kg/cm2g 11,5 kg/cm2g / 8 kg/cm2g

Operating Temperature 40 C 40 C

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Power Supply 24 VDC, 4-20 mA HART Protocol 24 VDC, 4-20 mA HART Protocol

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 30 of 37

TBE Sheet 13 Dec 2016

Page 34: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.76 Pressure Indicator Transmitter (04-PT-305)

Model Standard Manufature IGP10ST22E1ZZ000-M2L1T

Service Circulation CW Pump Discharge Line Circulation CW Pump Discharge Line

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 12 kg/cm2g / 8 kg/cm2g 12 kg/cm2g / 8 kg/cm2g

Operating Temperature 32 C 32 C

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 1/2" NPTM 1/2" NPTM

Material SS 316 SS 316

Power Supply 24 VDC, 4-20 mA HART Protocol 24 VDC, 4-20 mA HART Protocol

Measuring Range 0-20 kg/cm2g 0-20 kg/cm2g

5.77 Pressure Indicator Transmitter (26-PT-951)

Model Standard Manufature IGP10S-T22E1ZZ000-M2L1T

Service MP Steam Header MP Steam Header

Line/Equipment 14"-MPS-3A-003-H-135 14"-MPS-3A-003-H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 53 kg/cm2g / 51 kg/cm2g 53 kg/cm2g / 51 kg/cm2g

Operating Temperature 425 C 425 C

Type 32 C 32 C

Process Connection Diaphragm, Smart Transmitter Diaphragm

Material 1/2" NPTM 1/2" NPT

Power Supply SS 316 SS 316

Measuring Range 24 VDC, 4-20 mA HART Protocol HART & 4-20 Ma

5.78 Pressure Indicator Transmitter (26-PT-959)

Model Standard Manufature IGP10ST22E1ZZ000-M2L1T

Service Low Pressure Steam Header Low Pressure Steam Header

Line/Equipment 4"-LPS-1A-005-H-85 4"-LPS-1A-005-H-85

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Pressure Max / Min 6 kg/cm2g / 4 kg/cm2g 6 kg/cm2g / 4 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 31 of 37

TBE Sheet 13 Dec 2016

Page 35: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Operating Temperature 306,8 C 306,8 C

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 3/4" NPTM 1/2" NPT

Material SS 316 SS 316

Power Supply 24 VDC, 4-20 mA HART Protocol 24 VDC, 4-20 mA HART Protocol

Measuring Range 0-10 kg/cm2g 0-10 kg/cm2g

5.79 Pressure Switch (08-PSL-478)

Model Standard Manufature ZT2181.00

Service Discharge Demin Feed Package Boiler Pump Discharge Demin Feed Package Boiler Pump

Line/Equipment 6"-DW-1SSA-004 6"-DW-1SSA-004

P&ID GGCP-04-P0-PI-003-PP (sheet 1 of 13) GGCP-04-P0-PI-003-PP (sheet 1 of 13)

Pressure Max / Min 16,5 kg/cm2g / 12,27 kg/cm2g 16,5 kg/cm2g / 12,27 kg/cm2g

Operating Temperature 32 C 32 C

Type Bourdon Bourdon

Process Connection 1/2" NPTM, bottom 1/2" NPTM, bottom

Material 316 SS 316 SS

Power Supply 24 VDC (two wire system, dry contact) 24 VDC (two wire system, dry contact)

Adjustable Range 0-20 kg/cm2g 0-20 kg/cm2g

5,80 Pressure Switch (08-PSL-479)

Model Standard Manufature ZT2181.00

Service Discharge Demin Feed HRSG Pump Discharge Demin Feed HRSG Pump

Line/Equipment 4"-DW-1SSA-008 4"-DW-1SSA-008

P&ID GGCP-04-P0-PI-003-PP GGCP-04-P0-PI-003-PP

Pressure Max / Min 17,5 kg/cm2g / 14,22 kg/cm2g 17,5 kg/cm2g / 14,22 kg/cm2g

Operating Temperature 32 C 32 C

Type Bourdon Bourdon

Process Connection 1/2" NPTM, bottom 1/2" NPTM, bottom

Material 316 SS 316 SS

Power Supply 24 VDC (two wire system, dry contact) 24 VDC (two wire system, dry contact)

Adjustable Range 0-25 kg/cm2g 0-25 kg/cm2g

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 32 of 37

TBE Sheet 13 Dec 2016

Page 36: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

5.81 Pressure Switch (04-PSL-302)

Model Standard Manufature ZT2181.00

Service Discharge Make-Uo Cooling Tower Pump Discharge Make-Uo Cooling Tower Pump

Line/Equipment 1 1/2"-RW-1A-006 1 1/2"-RW-1A-006

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Pressure Max / Min 5,5 kg/cm2g / 3 kg/cm2g 5,5 kg/cm2g / 3 kg/cm2g

Operating Temperature 27 C 27 C

Type Bourdon Bourdon

Process Connection 1/2" NPTM, bottom 1/2" NPTM, bottom

Material 316 SS 316 SS

Power Supply 24 VDC (two wire system, dry contact) 24 VDC (two wire system, dry contact)

Adjustable Range 0-10 kg/cm2g 0-10 kg/cm2g

5.82 Pressure Switch (10-PSHL-534)

Model Standard Manufature ZT2181.00

Service Instrument Air Distribution Header Instrument Air Distribution Header

Line/Equipment 2"-IA-1AG-005 2"-IA-1AG-005

P&ID GGCP-04-P0-PI-006-PP GGCP-04-P0-PI-006-PP

Pressure Max / Min 11,5 kg/cm2 / 8 kg/cm2 11,5 kg/cm2 / 8 kg/cm2

Operating Temperature 70 C / 40 C 70 C / 40 C

Type Bourdon Bourdon

Process Connection 1/2" NPTM, bottom 1/2" NPTM, bottom

Material 316 SS 316 SS

Power Supply 24 VDC (two wire system, dry contact) 24 VDC (two wire system, dry contact)

Adjustable Range 0-10 kg/cm2g 0-10 kg/cm2g

5.83 Flow Transmitter (04-FT-302)

Model Standard Manufature IDP10S-T22C21ZZ-M2L1T

Service Circulating CW Pump Discharge Line Circulating CW Pump Discharge Line

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 33 of 37

TBE Sheet 13 Dec 2016

Page 37: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Flow Max / Min 300 m3/hr / 280 m3/hr 300 m3/hr / 280 m3/hr

Operating Temperature 32 C 32 C

Type Diaphragm, Smart Transmitter Diaphragm

Process Connection 1/2" NPTM 1/2" - 14 NPT

Material 316 SS 316 SSPower Supply 24 VDC (Two Wired System), 4-20 Ma DC, HART Protocol 10.5 to 42.4 Vdc, 4-20 ma, HART ProtocolMeasuring Range 0-400 m3/hr 0-400 m3/hr

5.84 Flow Transmitter (04-FT-307)

Model Standard Manufature IDP10S-T22C21ZZ-M2L1T No datasheet provided, using data from 04-FT-302

Service Circulating CW Pump Discharge Line Circulating CW Pump Discharge Line

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Flow Max / Min 300 m3/hr / 280 m3/hr 300 m3/hr / 280 m3/hr

Operating Temperature 32 C 32 C

Type Diaphragm, Smart Transmitter Smart Transmitter

Process Connection 1/2" NPTM 1/2" NPT

Material 316 SS 316 SS

Power Supply 24 VDC (Two Wired System), 4-20 Ma DC, HART Protocol HART & 4-20 Ma

Measuring Range 0-400 m3/hr 0-400 m3/hr

5.85 Flow Transmitter (10-FT-534)

Model Standard manufacture IDP10S-T22C21ZZ-M2L1T No datasheet provided, using data from 04-FT-302

Service MP Steam to Amurea II MP Steam to Amurea II

Line/Equipment 2"-IA-1AG-005 2"-IA-1AG-005

P&ID GGCP-04-P0-PI-006-PP GGCP-04-P0-PI-006-PP

Design Pressure 11,5 kg/cm2g 11,5 kg/cm2g

Flow 600 Nm3/hr 600 Nm3/hr

Operating Pressure 8 kg/cm2g 8 kg/cm2g

Design Temperature 70 C 70 C

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 34 of 37

TBE Sheet 13 Dec 2016

Page 38: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Operating Temperature 40 C 40 C

Type Diaphragm, Smart Transmitter Diaphragm, Smart Transmitter

Process Connection 1/2" NPTM 1/2" NPTM

Material 316 SS 316 SS

Power Supply 24 VDC (Two Wired System), 4-20 Ma DC, HART Protocol24 VDC (Two Wired System), 4-20 Ma DC, HART Protocol

Measuring Range 0-600 m3/hr 0-600 m3/hr

5.86 Flow Indicator (10-FI-536)

Model Standard Manufacture As per manufacturer's part numberPak, merupakan item baru, tolong confirm apakah

bisa mensupply item rotary flow indicatorService Instrument Air Distribution Header Instrument Air Distribution Header

Line/Equipment 2"-IA-1AG-005 2"-IA-1AG-005

P&ID GGCP-04-P0-PI-006-PP GGCP-04-P0-PI-006-PP

Flow Max / Min 11,5 kg/cm2 / 8 kg/cm2 16 kg/cm2

Operating Temperature 70 C / 40 C 70 C / 40 C

Type Rotary Flow Indicator Rotary sight flow indicator

5.87 Flow Element (04-FE-302)

Model Standard Manufature ZT4601.00

Service Circulating Cooling Water Pump Discharge Header Circulating Cooling Water Pump Discharge Header

Line/Equipment 8"-CWS-1A-005 8"-CWS-1A-005

P&ID GGCP-04-P0-PI-007-PP GGCP-04-P0-PI-007-PP

Flow Rate Max / Min 300 m3/hr, 0 m3/hr 300 m3/hr, 0 m3/hr

Operating Temperature 32 C 32 C

Operating Pressure 8 kg/cm2G 8 kg/cm2G

Type Differential Pressure, Squere Edge Concentric Differential Pressure, Squere Edge Concentric

Tap Size 1/2" 1/2"

Material 316 SS 316 SS

5.88 Flow Element (26-FE-952)

Model Standard Manufature ZT4601.00

Service Steam Distribution System Steam Distribution System

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 35 of 37

TBE Sheet 13 Dec 2016

Page 39: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

Line/Equipment 14-MPS-3A-003H-135 14-MPS-3A-003H-135

P&ID GGCP-04-P0-PI-010-PP GGCP-04-P0-PI-010-PP

Flow Rate Max / Min 160 ton/hr / 0 ton/hr 160 ton/hr / 0 ton/hr

Operating Temperature 386 C 386 C

Operating Pressure 46,5 kh/cm2G 46,5 kh/cm2G

Type Differential Pressure, Squere Edge Concentric Differential Pressure, Squere Edge Concentric

Tap Size 1/2" 1/2"

Material 316 SS 316 SS

6.0 DOCUMENTATION

6.1

1) Deviation and Clarification List YES No

2) Complete B.O.M YES Included

3) System Configuration Diagram YES Included

4) Dimensional Outline Drawing with Loading DataYES No5) List of Spare Parts for Construction & PrecommissiningYES Included6) List of Spare Parts for Start-up & CommissiningYES Included7) List of Spare Parts for Two (2) Years OperationYES Included8) List of Consumables YES Included9) List of Special Tools YES No10) Power Consumption List and Heat Dissipation ListYES Yes11) Technical Leaflet and/or Catalogue YES Included

7.0

7.1 Field Instrument

At Vendor shop & site

(1) Training of Engineers in all aspects of system configurationYES Included

(2) Training of technicians in all aspects of system maintenanceYES Included

(3) Training of operators in all aspects if system operationYES Included

8.0

TRAINING

TEST AND INSPECTION

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 36 of 37

TBE Sheet 13 Dec 2016

Page 40: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-005-PP DCS & ESD Friday, November 18, 2016

Rev.0

VENDOR / SUPPLIER RESPONSE

PT. SCHNEIDER ELECTRIC INDONESIA

TECHNICAL BID EVALUATION TABULATION SHEET FOR FIELD INSTRUMENT

NO DESCRIPTION Specification & Requirements REMARKS

8.1 TYPICAL ACCEPTANCE TEST Required Included

8.2 PRE-FAT (PRE-FACTORY ACCEPTANCE TEST)Required Included8.3 FAT (FACTORY ACCEPTANCE TEST) YES Included

8.4 YES Included

8.5 SAT (SITE ACCEPTANCE TEST) YES Included

8.6 SITE SUPERVISION YES Included

CONCLUSION OF TECHNICAL EVALUATION A

9.0

TOTAL BUDGET To be specified (exclude VAT 10%)

DISCOUNT

COMMERCIAL

IFAT (INTEGRATED FACTORY ACCEPTANCE TEST) AT VENDOR'S SHOP

NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 37 of 37

TBE Sheet 13 Dec 2016

Page 41: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

1 of 7

9/29/2016Rev.: 0

Quotation No.: QPCI6W0025.R0 Validity: 60 days

To: PT PP (Persero) TbkSubject: GRESIK GAS COGENERATION PLANT PROJECTFinal User: PT PUPUK INDONESIA ENERGIEquipment: Electronic TransmittersPlace of Delivery:Time of Delivery/Shipment: 20~24 Weeks from receipt of Firm Purchase order and clear specifications.

This is just an estimated lead time and can be shorten after conclusion of the order.Terms of Payment: 20% DP upon drawing submission

75% upon delivery.5% on Submission of Final documents.Payments 2nd and 3rd shall be made via Wire transfer, Net 30 days from receipt of Invoice.

PT.YOKOGAWA INDONESIA.

Tri Cahyani

Fairry C.

Item Description Q'ty (Nos.) Amount (IDR)

1. Pressure and Differential Pressure Transmitters 20

2. Temperature Transmitters 7

3. Calibration Certificates [QIC]; @ USD12.5/Tag. 27

4. Engineering; Documentation and Project Management 1 Lot

5. Packing and delivery charges 1 Lot

6. Training, commisioning as per diem rate

Total Qty / Amount (IDR), FOB SINGAPORE : 1 Lot 0

Optional Offer:7. overseas Witness Inspection @ USD2,500 per-diem 18. Special tools, hart communicator 1

NOTE : EXCLUDE VAT 10%

PRICE QUOTATION SUMMARY

PT.Yokogawa Indonesia Plaza Oleos 3rd Fl Suite A, Jl.Simatupang no.53 A Jakarta Selatan 12520 Indonesia.

Page 42: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

ABC Development Complex Project Pressure Transmitter Yokogawa Engineering Asia Pte LtdOffer Ref#:YEA PCI-QT-2015-000C Rev.: 0Dtd: 3-June-2015

2 of 7

'1. Pressure and Differential Pressure Transmitters

Min Oper Max Unit Oper Unit Fluid SG Cal. Min

Cal. Max Cal. UOM Process Conn. Conn. Location Element Type Element Material Wetted Part

Material Filled Fluid Output Signal Accuracy Housing Mounting bracket

Electrical Connection

Power Supply

Maximum Overpressure

Process Connection Rating Diaphragm

Material

Upper Housing Material

Lower Housing Material

Fill Fluid Capillary Material Capillary Type

Capillary Length

Flushing Connection

Flushing Ring, Qty and Model

Diaphragm Seal Model

Hydrostatic Testing Calibration Certification Manifold

TypeManifold Material

Processconnector Diaphragm

1 12-PT-706 Natural Gas Supply GGCP-04-P0-PI-001-PP (Sht. 1 8”-FG-2A-007 PIPE MOUNTING

22.15 26 Kg/Cm2 15.6 - 48.9degC

0 40 Kg/Cm21/2 NPTM Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% Cast aluminum alloy 316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A No Yes No 2 way 316 SS 4-20 mA HART Protocol 0.5 to 10 MPa (72.5

to 1450 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A 1

2 12-DPT-702A Fuel Gas Scrubber GGCP-04-P0-PI-001-PP (Sht. 1 01-HD-12702-A PIPE MOUNTING22.15 26 Kg/Cm2 15.6 - 48.9

degC0 1 Kg/Cm2

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% Cast aluminum alloy 316SST 2-inch

pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 Kpa (20 to 2000 inH2O) 316L SST Hastelloy C-

276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting flat type (for horizontal type)

FM Explosionproof Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

3 12-PDT-702B Fuel Gas Scrubber GGCP-04-P0-PI-001-PP (Sht. 1 01-HD-12702-B PIPE MOUNTING22.15 26 Kg/Cm2 15.6 - 48.9

degC0 1 Kg/Cm2

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% Cast aluminum alloy 316SST 2-inch

pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 Kpa (20 to 2000 inH2O) 316L SST Hastelloy C-

276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting flat type (for horizontal type)

FM Explosionproof Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

4 12-LT-701A Fuel Gas Scrubber GGCP-04-P0-PI-001-PP (Sht. 1 01-HD-12702-A PIPE MOUNTING22.15 26 Kg/Cm2 27

degC densate D0.8490 800 mmH2O

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 1 to 100 Kpa (4 to

400 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 M EJA110E EJA110E-JMS4G-917DJ/FF1/D3/HE/M11/A 1

5 12-LT-701B Fuel Gas Scrubber GGCP-04-P0-PI-001-PP (Sht. 1 01-HD-12702-B- PIPE MOUNTING22.15 26 Kg/Cm2 27

degC densate D0.8490 800 mmH2O

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 1 to 100 Kpa (4 to

400 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 M EJA110E EJA110E-JMS4G-917DJ/FF1/D3/HE/M11/A 1

6 12-PT-701A Gas Metering Skid Stream A GGCP-04-P0-PI-001-PP (Sht. 2 8”-FG-2A-013 PIPE MOUNTING

21.4 25 Kg/Cm2 15.6 - 48.9degC

0 40 Kg/Cm21/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 316L SST Hastelloy C-

276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A/M15 1

7 12-FT-701A Gas Metering Skid Stream A GGCP-04-P0-PI-001-PP (Sht. 2 8”-FG-2A-013 PIPE MOUNTING

21.4 25 Kg/Cm2 15.6 - 48.9degC

0 400 InH2O1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% Cast aluminum alloy 316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

8 12-PT-701B Gas Metering Skid Stream B GGCP-04-P0-PI-001-PP (Sht. 2 8”-FG-2A-002 PIPE MOUNTING

21.4 25 Kg/Cm2 15.6 - 48.9degC

0 40 Kg/Cm21/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 0.5 to 10 MPa (72.5

to 1450 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A/M15 1

9 12-FT-701B Gas Metering Skid Stream B GGCP-04-P0-PI-001-PP (Sht. 2 8”-FG-2A-002 PIPE MOUNTING

21.4 25 Kg/Cm2 15.6 - 48.9degC

0 400 InH2O1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

10 07-LIT-468 Filtered Water Tank GGCP-04-P0-PI-003-PP 01-FI-07462 PIPE MOUNTING1 2 Kg/Cm2 27

degC0 20000 mmH2O

2” RF Flange, ANSI 150# Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 5 to 500kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA210E EJA210E-JHS5G-912DN-WA12C2WW00-B/FF1/HE/A 1

11 08-LIT-479 Condensate Tank GGCP-04-P0-PI-003-PP 01-FJ-08476 PIPE MOUNTING1.5 2 Kg/Cm2 44

degC0 20000 mmH2O

2” RF Flange, ANSI 150# Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 5 to 500kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA210E EJA210E-JHS5G-912DN-WA12C2WW00-B/FF1/HE/A 1

12 12-PT-551 Fire Water System GGCP-04-P0-PI-005-PP 8”-FW-1A-015 PIPE MOUNTING9 13.1 Kg/Cm2 27

degC0 20 Kg/Cm2

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 0.5 to 10 MPa (72.5

to 1450 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A/M15 1

13 10-PIT-534 Outlet Instrument Air Receiver GGCP-04-P0-PI-006-PP 2”-IA-1AG-005 PIPE MOUNTING

7 10 Kg/Cm2 40degC

0 20 Kg/Cm21/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 0.5 to 10 MPa (72.5

to 1450 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A/M15 1

14 04-PT-305 Circulating CW Pump GGCP-04-P0-PI-007-PP 8”-CWS-1A-005 PIPE MOUNTING16 20.3 Kg/Cm2 32

degC0 30 Kg/Cm2

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 0.5 to 10 MPa (72.5

to 1450 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 C EJA530E EJA530E-JCS7N-017DL/FF1/HE/D4/A/M15 1

15 04-FT-302 Circulating CW Pump GGCP-04-P0-PI-007-PP 8”-CWS-1A-005 PIPE MOUNTING16 20.3 Kg/Cm2 32

degC0 100 InH2O

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

16 26-PT-951 MP Steam Header GGCP-04-P0-PI-010-PP 14”-MPS-3A-003-H-135 PIPE MOUNTING51 61 Kg/Cm2 425

degC0 100 Kg/Cm2

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 5 to 50 MPa (720 to

7200 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 D EJA530E EJA530E-JDS7N-017DL/FF1/HE/D4/A/M15 1

17 26-PT-953 MP Steam Header to PKG Existing GGCP-04-P0-PI-010-PP 10”-MPS-3A-005-H-125 PIPE MOUNTING

0 40 54 Kg/Cm2 417degC

0 80 Kg/Cm21/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 5 to 50 MPa (720 to

7200 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 D EJA530E EJA530E-JDS7N-017DL/FF1/HE/D4/A/M15 1

18 26-PT-954 MP Steam Header to PKG Existing GGCP-04-P0-PI-010-PP 10”-MPS-3A-005-H-125 PIPE MOUNTING

0 51 61 Kg/Cm2 425degC

0 100 InH2O1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 2 way 316 SS 4-20 mA HART Protocol 5 to 50 MPa (720 to

7200 psi) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 D EJA530E EJA530E-JDS7N-017DL/FF1/HE/D4/A/M15 1

19 26-FT-951 MP Steam Header to PKG Existing GGCP-04-P0-PI-010-PP 10”-MPS-3A-005-H-125 PIPE MOUNTING

0 40 54 Kg/Cm2 417degC

0 200 InH2O1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART

PROTOCOL) 0.025% ASTM CF-8M stainless steel

316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

20 26-FT-952 MP Steam to Amurea II GGCP-04-P0-PI-010-PP 14”-MPS-3A-003-H-135 PIPE MOUNTING0 51 56 Kg/Cm2 380-420

degC0 300 InH2O

1/2 NPTF Pipeline Diaphragm SS 316L ASTM CF-8M Silicone 4 - 20 mA (HART PROTOCOL) 0.025% ASTM CF-8M

stainless steel316SST 2-inch pipe mounting 1/2" NPTF 24 VDC 1.5 time max N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Yes Yes No 5 way 316 SS 4-20 mA HART Protocol 5 to 500 kPa (20 to

2000 inH2O) 316L SST Hastelloy C-276 YES 1/2 NPT Female YES 316SST 2-inch pipe mounting FM Explosionproof

Approval IP66/67 H EJA110E EJA110E-JHS4G-912DJ/FF1/HE/M11/D4/A 1

YOKOGAWA OFFER

Item No. Tag Number Service P&ID No. Line No Mounting

Pressure Temperature TRANSMITTER DIAPHRAGM SEAL

CUSTOMER SPECIFICATIONS

Degrees of Protection

OPTIONS

Output signal Measurementspan (capsule)

Wetted parts material

Surge Protection Electrical connection Integral

Indicator Mounting bracket Explosion Protected type

Unit PriceIDR

Total PriceIDR RemarksCapsule

Code Base Model Model Code Qty

Page 43: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

'2. Temperature Transmitters

Element type

Line No Temperature Element Insertion Length (S)

Thermowell Length (S) Output Signal Electrical

ConnectionPower Supply

1 12-TT-701A Temperature Gas Metering Skid Stream A GGCP-04-P0-PI-001-PP (2 of 2) 8”-FG-2A-013 Pt100 PIPE MOUNTING0 100 °C

RTD, Pt-100, 3 Wire 6.26 4.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

2 12-TT-701B Temperature Gas Metering Skid Stream B GGCP-04-P0-PI-001-PP (2 of 2) 8”-FG-2A-002 Pt100 PIPE MOUNTING0 100 °C

RTD, Pt-100, 3 Wire 6.26 4.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

3 04-TT-301 Cooling Water Supply GGCP-04-P0-PI-007-PP 8”-CWS-1A-005 Pt100 PIPE MOUNTING 0 110 °C RTD, Pt-100, 3 Wire 6.26 4.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

4 04-TT-303 Cooling Water Return GGCP-04-P0-PI-007-PP 8”-CWR-1A-006 Pt100 PIPE MOUNTING 0 120 °C RTD, Pt-100, 3 Wire 6.26 4.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

5 26-TT-952 MP Steam Header GGCP-04-P0-PI-010-PP 14”-MPS-3A-003-H-135 TC PIPE MOUNTING 0 1372 °C TC type K 9.25 7.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

6 26-TT-953 MP Steam to Amurea II GGCP-04-P0-PI-010-PP 14”-MPS-3A-006-H-135 TC PIPE MOUNTING 0 700 °C TC type K 9.25 7.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

7 26-TT-957 LP Steam to Deaerator Boiler Package GGCP-04-P0-PI-010-PP 10”-LPS-1A-003-H-85 TC PIPE MOUNTING 0 1372 °C TC type K 6.26 4.5 4 - 20 mA (HART PROTOCOL) 1/2NPTF 24 VDC Aluminum No Yes No FM IP66/67 YTA710 YTA710-JA1A2DJ/FU1 1

Total Qty / Amount (IDR), FOB Singapore: 7 0

Total PriceIDR Remarks

Calibration Range

Base Model Model CodeDegrees of Protection

Amplifier Housing material

Surge Protection

Integral Indicator

Explosion Protected

typeQty

TRANSMITTER

Unit PriceIDR

CUSTOMER SPECIFICATIONS

Item No. Tag Number Service P&ID No. Mounting Mounting bracket

Page 44: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

JORDAN COVE LNG PROJECT Two Years Spares Yokogawa Engineering Asia Pte LtdOffer Ref#:YEA FIA-QT-2016-031C

Rev.: 0Dtd: 21-Jun-2016

1 HART COMMUNICATOR YHC5150 YHC5150X 1 1 7,500 7,500

Total Qty / Amount (IDR),FOB SINGAPORE : 1 7,500

No. Instrument Description Base Model Proposed Model Total Qty Total Qty Unit PriceIDR

Total PriceIDR Remarks

Page 45: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

General Terms And Conditions of Sale for our quotation

The conditions stated below shall constitute a part of the agreement resulting from an order for the whole or any partof the apparatus covered by this quotation unless expressly excepted herein. The word “YIN” used herein shall mean and represent PT. YOKOGAWA INDONESIA. The words " Purchaser" used herein shall mean PT PP (Persero) Tbk

* ACCEPTANCEAll orders based on this proposal shall be subject to the approval and acceptance of YIN as to price, quantity, delivery and other conditions not stated herein.

* SCOPE OF SUPPLY AND WORKNo equipment nor service other than expressly stated in and covered by this proposal is included in the scope of supply of YIN.

* PRICE3.1) All price pertaining to an order shall be based on YIN written quotation.3.2) All quoted prices are in US Dollars unless specified otherwise in the quotation.

* TERMS OF VALIDITYIf an extension of validity period is required, the purchaser shall make this request in writing to YIN. YIN reserves the right to alter this proposal whether in whole or in part, upon such request.Validity shall be 60 days from this proposal date.

* SPECIFICATION CHANGES AND CANCELLATIONSUpon confirmation of order, no addition to or modification of any of the specification shall be binding upon YIN unless made in writing and signed by a duly authorised officer of YIN.

Any change from the original specification on which YIN quotation is based shall be documented and advised to YIN in the form of a revision of Purchase Order. All charges by Purchaser are binding only if accepted by YIN.

5.1) Additional cost due to such specification change shall be quoted by YIN within 30 days after receipt of revision of order.5.2) The following table indicates the rate of cancellation charges at various stages of progress of factory orders.

* Time of Cancellation Rate

Prior to start of engineering 10%

After the start of engineering but prior to release of production 30%

After release of production but prior to completion of manufacture 60%

After completion of manufacture but prior to shipping 100%

Whenever there are item in this proposal that are subcontracted by YIN to a third party, the termsinvolving changes in specification and for cancellation between YIN and the third party shall apply to the purchaser.

* TYPING ERRORS

YOKOGAWA ENGINEERING ASIA

Page 46: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

YIN reserves the right to correct at typographical or clerical errors which may be present in the prices or specifications in this proposal.

* TERMS OF PAYMENT20% DP, 75 before Shipment and 5% against Documentation

* DELIVERY SCHEDULETime of shipment stated herein is approximate and subject to prompt receipt of Purchase Order, and all necessary system design and engineering information by YIN at its factory.The delivey time is 16 to 18 weeks after documents approved.Excluded FAT and all procedures, invitattion, and others

* SUSPENSION OF THE WORKSIn the event that the Purchase requires, after establishment of the contract, to temporarily suspend thework order processing for some time or indefinitely or requires to defer the agreed delivery time, and that YIN accepts such request, YIN RESERVES THE RIGHT TO CLAIM FROM THE Purchaser anequitable compensation for all the expenses directly or indirectly caused by such suspension of the work or postponement.

* WARRANTYYIN warrants that all its manufactured equipment shall be free from defects in material or workmanship under normal or proper usage. YIN’s obligation is limited to replacing, free of charge, any part of an instrument or apparatus which shall be returned, transportation charges prepaid, by the purchaserswithin twelve (12) months after starting-up or otherwise eighteen (18) months from shipment by YINwhichever comes first, and which examination proves not to be within the specified limit of calibrationor to be defective in material or workmanship. In no event shall YIN be liable for consequential damages.

However, consumable item and fragile item, thermo-couples, resistance bulbs are not subject to replacement unless returned unused.

On equipment other than YIN manufactured, supplied by YIN the Warranty of the original manufacturer applies.

* INSPECTIONAll equipment shall be tested before shipment by YIN or its sub-contractors. The inspection or test byPurchaser or purchaser nominated inspector is acceptable, provided that the costs for such inspection such as man-hour rate, travel expenses, etc.,. shall be borne by Purchaser nominated inspector. Timingfor such inspection shall be by prior agreement between YIN and Purchaser.

* DOCUMENTATIONThe document to be submitted by YIN shall be in YIN standard form.

* LANGUAGEAll documents and working language for this contract shall be in English.

* EXPORT PACKAGINGExport Packing, if required will be made in accordance with YIN standard procedure.

* FORCE MAJEUREYIN shall not be liable for loss, damage, detention or delay caused by fire, strike, civil or military authority, insurrection or riot, or for any other course beyond its reasonable control.

* DISPUTESAll disputes and differences in opinions arising our of or in connection with orders based on his proposalshall be settled between Purchaser and YIN in an amicable way. The validity, performance and construction of these terms and conditions and any sale made shall be governed by the laws of Republic Indonesia and subject to the exclusive jurisdiction of the courts of Repulic Indonesia.

* OTHERSAll other item and conditions shall be subject to mutual agreement. The definitions and understanding

Page 47: PT PP (Persero) Tbk. Divisi EPCapps.pp-epc.com/eproc/upload_file/selection_project/31B9B8E7F9B94EFD...project : gresik gas cogeneration plant project doc. number : ggcp-00-i0-te-005-pp

of works used herein and in the contract, resulting from this quotation shall be subject to INCOTERM 1980 (International Rules for the Interpretation or Trade Terms) by the internationalChamber of Commerce.

* TERMS AND DUTIESPrices do not include any foreign or local taxes or duties, new or hereafter enacted, applicable to the Equipment sold where YIN is obliged to pay these taxes or duties in the first instance, the Purchaser shall reimburse YIN the same amount.