Quick Installation Guide IDU 910

Embed Size (px)

Text of Quick Installation Guide IDU 910

OptiX RTN 910 Radio Transmission System V100R002

IDU Quick Installation GuideOptiX RTN 910 V100R002

IDU

Issue: 04 Date: 2010-04-20 04 2010-04-20

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. For any assistance, please contact our local office or company headquarters.

Huawei Technologies Co., Ltd.Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: Email: http://www.huawei.com support@huawei.com

Copyright Huawei Technologies Co., Ltd. 2010. All rights reserved.No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissionsand other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.

NoticeThe information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute the warranty of any kind, express or implied.

Huawei Technologies Proprietary

Contents Precautions Tools for Installation Introduction to the IDU IDU 1 5 6 6 6 7 7 8 8 8 9 10 12 12 12 13 13 14 14

1 2 1 2 1 2 3 4 1 2 3

Introduction to Interfaces Introduction to Installation Holes on Both Sides of the Chassis

Flow Installing Flow Commissioning Flow

Installing the IDU IDUInstalling the Chassis in the 19-Inch Cabinet 19 Installing the Chassis in the ETSI Cabinet ETSI Installing the Chassis on the Wall Installing the Chassis on the Desk

Optional: Installing the E1 Panel E1 PanelFixing the Floating Nuts Fixing the E1 Panel E1 panel Installing the PGND Cable on the E1 Panel E1 panel

Installing the Board Installing the IDU Cables IDU

Contents 1 Installing the PGND Cable 2 Installing the Power Cable 3 Installing the E1 Cable E1 4 Installing the Ethernet Service Network Cable 5 Installing the XPIC cable XPIC 6 Installing the IF Jumper 7 Installing the Fiber Jumper 8 Installing the NM Cable 9 Installing the Orderwire Phone Line 10 Installing the External Clock Cable 11 Installing the Asynchronous and Synchronous Date Cable 12 Installing the External Alarm Cable

14 15 16 17 17 18 19 19 20 21 22 23 24 25 26 26 27 28 29

Powering On the Equipment Configuring the NE Data (by Using the Web LCT) (Web LCT) Aligning the Antennas

1 2

Aligning the Single-Polarized Antennas Aligning the Dual-Polarized Antennas

Checking the Status of a Radio Link Checking the Installation

Precautions

This document aims to provide simple and distinctive guidelines for hardware installation. This document does not describe operations for the pre-delivery installation. Instead, this document describers only the operations for on-site installation.

Electrostatic Discharge Before touching the device, or holding the boards and IC chips, wear the anti-static gloves or anti-static wrist strap to prevent the electrostatic discharge of the human body from damaging the sensitive components. Ensure that the other end of the anti-static wrist strap is well grounded. IC

Bundling Cables The distance between cable ties or fiber binding straps inside the cabinet should be within 250 mm. (For subscriber cable, the distance is 200 mm. ) /250mm 200mm The distance between cable ties for all cables and corrugated pipes outside the cabinet is determined according to the distance between two horizontal beams. For the cabling trough without beams, bundle the cables with the distance not exceeding 250 mm between cable ties. 250mm

Checking Before Installation Before starting installation, you should make the equipment room, power supply, ground wire, optical cables, and other facilities in the equipment ready. When these installation conditions are confirmed, the installation may begin according to the pre-designed layouts.For detailed requirements and related index, refer to Installation Reference.

1

Precautions for Handling the Toggle Lever Switch Location and positions of the toggle lever switch

O : OFF

Before turning the toggle lever switch, you must pull it out slightly. I : ON

Turning on the switch 1 2 3

1 Pull the switch out slightly.

2 Turn the switch.

3 Release the switch.

Turning off the switch 1 2 3

1 Pull the switch out slightly.

2

Turn the switch.

3

Release the switch.

2

Precautions for Handling the IF Jumper Do not remove or insert the IF jumper when the ODU is powered on. ODU

Before removing or inserting the IF jumper, you must power off the ODU. ODU

1

2

Power off the ODU. ODU

Connect or disconnect the IF jumper.

Precautions for Handling the IF Cable

Before removing or inserting the IF cable, you must power off the ODU. ODU

Do not remove or insert the IF cable when the ODU is powered on. ODU

1

2

Power off the ODU. ODU

Connect or disconnect the IF cable.

3

Precautions for Handling the IF Board

Before removing or inserting the IF board, you must power off the ODU. ODU

1

2

3

Remove the IF board.

3

Insert the IF board.

Power off the ODU. ODU

Disconnect the IF Jumper.

Remove or insert the IF board.

Do not remove or insert the IF board when the ODU is powered on. ODU

4

Tools for Installation

Tape Measure

Level Bar

Philips Screwdriver

Flathead Screwdriver

Adjustable Wrench

Socket Wrench

Torque Wrench

Allen Wrench

Ratchet Crimp Tool

Cable Cutter

Wire Stripper

Network Cable Crimping Pliers

Diagonal Pliers

Crimping Tool

Sharp-nose Pliers

Bayonet Wrench

Pliers

File

Multimeter

Heat Gun

Percussion Drill

Marker Pen

Paper Knife

Claw Hammer

Antistatic Gloves

Antistatic Gloves

Antistatic Wrist Strap

Ladder

Electric Iron

Punching Wire Pliers

Cleaner

Binding Strap

Insulation Tape

5

1

Introduction to the IDU IDU Introduction to Interfaces

10

11

12

Input power interface IF interface ODU power switch ODU

Optical interface NM/COM interface /COM NE cascading interface

External clock interface Synchronous/Asynchronous data interface / External alarm interface

101112

Orderwire phone interface Ethernet service interface E1 interface E1

According to different board configurations, the positions of the actual IDU interfaces may be different from the positions shown in the figures. IDU

2

Introduction to Installation Holes on Both Sides of the Chassis

Installation holes in the T63/T66/N66T cabinet T63/T66/N66T

Installation holes in the N63E/19-inch cabinet N63E/19

Before installing the chassis in the ETSI cabinet, adjust the installation holes of the mounting ears according to the type of the cabinet. ETSI

6

1

Flow Installation Flow Start

Page14 14

Installing the PGND Cable

Page 8 to 12 8-12

Installing the IDU IDU

Page 8 8

Installing the Chassis in the 19Inch Cabinet 19

Page 15 15

Installing the Power Cable Page 12 to Optional: Installing the E1 Panel 14 E1 Panel 12-14

Page 9 9

Installing the Chassis in the ETSI Cabinet ETSI

Page 16 16

Installing the E1 Cable E1

Page 10 10

Installing the Chassis on the Wall

Page 17 17

Installing the Ethernet Service Network Cable

Page 14 14

Installing the Board

Page 12 12

Installing the Chassis on the Desk

Page 17 17

Installing the XPIC Cable XPIC

Page 18 18

Installing the IF Jumper Page 14 to 23 14-23 Installing the IDU Cables IDU

Page 19 19

Installing the Fiber Jumper

Page 19 19

Installing the NM Cable Page 29 29 Checking the Installation

Page 210 20

Installing the Orderwire Phone Line

Page 21 21

Installing the External Clock Cable

End

Page 22 22

Installing the Asynchronous and Synchronous Data Cable

Page 23 23

Installing the External Alarm Cable

7

2

Commissioning Flow Start

Page 24 24

Powering On the Equipment

Page 25 25

Configuring the NE Data (by Using the Web LCT) (Web LCT) Aligning the Single-Polarized Antennas

Page 26 to 27 26-27

Page 26 26 Aligning the Antennas Page 27 27

Aligning the Dual-Polarized Antennas

Page 28 28

Checking the Status of a Radio Link

End

1a

Installing the IDU IDUInstalling the Chassis in the 19-Inch Cabinet 19Fixing the floating nuts

b

Removing the screws

Floating nut Installation hole

When tightening the captive nuts, ensure that that a minimum of 25 mm space on the left and right sides of the IDU is reserved for ventilation. IDUIDU 25mm

Keep the removed screws properly for installing the PGND cable in future.

8

c

Installing the chassis in the cabinet