Upload
paco
View
55
Download
0
Embed Size (px)
DESCRIPTION
Sauda Hydro Power Project. Reinsvatnet. Slettedalselva. Istjønna. Holmavatnet. Dalvatnet. Lingvang/Tengesdal. Storlivatnet. Maldal/Tengesdal. Sauda III. Sønnå. Tunnelsystem Sønnå. Dalvatnet. Skarvåna. Liabekken. Raundalen. Sønnåhamn. Raundalsbekken. Breidkvamselva. Kr. stasj. - PowerPoint PPT Presentation
Citation preview
2
Sauda III Sønnå
Storlivatnet
Lingvang/Tengesdal
Reinsvatnet
Istjønna
Slettedalselva
Dalvatnet
Holmavatnet
Maldal/Tengesdal
3
Tunnelsystem Sønnå
Maldal
Sagelva
Risvatnet
Lingvang (Grunnavatnet)
Dalvatnet
Skarvåna
Liabekken
Breidkvamselva
Raundalsbekken
RaundalenSønnåhamn
Kr. stasj.
11
Construction schedule Length of construction period from notice to commence to water on unit 1
Sønnå H is estimated to be 2 years and 9 months. Succeeding this is a period with testing the installation, gates etc.. Unit 2 follows approx. 1 month later.
Sønnå L will be finished approx 1 month after Sønnå H unit 2.
Dalvatn power station is planned to be on line before Sønnå H and L comes on line.
The various transfere / headrace tunnels are planned to be finished as early as possible taking into consideration the limitation on transport etc.