Upload
reuben-george
View
39
Download
3
Embed Size (px)
DESCRIPTION
Design Review Spartan IR Camera E Loh, Physics-Astronomy Department, Michigan State University East Lansing, 22 May 2001. Science Goals (ref: NSF proposal) Optical Design (ref. “Optical Design”) Optical alignment (ref: “Alignment” & “SOBER”) System Design & Electronics (ref. “Electronics”) - PowerPoint PPT Presentation
Citation preview
Design Review Spartan IR CameraE Loh, Physics-Astronomy Department, Michigan State University
East Lansing, 22 May 2001
1 Science Goals (ref: NSF proposal)2 Optical Design (ref. “Optical Design”)
–Optical alignment (ref: “Alignment” & “SOBER”)
3 System Design & Electronics (ref. “Electronics”)4 Mechanical Design (ref. “Mechanical Design”)
5 Budget & Schedule (ref. “Budget & Schedule”)
22 May 2001 DR SOAR Spartan IR Camera 2
The Team
• Jason Biel, technician– Measurements for vacuum design
– Electronics designer & technician
• Mike Davis, graduate student– Optics
• Owen Loh, Okemos High, volunteer– Finite-element analysis
– Drafting
• Tom Palazzolo, head, Phys-Ast shop– Mechanical shop, design advice, contact for mechanical designers &
job shops
• Jack Baldwin, Brooke Gregory, Ron Probst, Dan Edmunds, Phys-Ast EE, advisors
• E Loh
22 May 2001 DR SOAR Spartan IR Camera 3
1. Science Goals
Tip-tilt corrected imaging in the J, H, & K bands
• To cover the wide, corrected field (5’)• To resolve FWHM of median seeing (0.15–-0.23”)• To resolve high-contrast features at the diffraction limit
(0.08” @H & 0.11” @K)
22 May 2001 DR SOAR Spartan IR Camera 4
0 0.05 0.1 0.15 0.2 0.25 0.3q [arcsec]
0
5
10
15
20
ytisnetnI
[cescra
-2]
K-tt
H-tt
J-tt
V-ttK
V
Figure 2 Point-spread functions for median seeing withtip-tilt correction (solid lines) and without correction(dashed line; K and V bands only). Shown in the insert isthe tip-tilt corrected PSF with top quartile seeing.
Point-spread Function with Tip-Tilt Correction
• Point spread function is not a gaussian• Diffraction spike
Bandmedian top 25%
J 0.05 0.15H 0.12 0.30K 0.28 0.50
Strehl Ratio
0 0.1 0.2 0.30
10
20
30
40KHJ
V
Median seeing
Top quartile
22 May 2001 DR SOAR Spartan IR Camera 5
Image Width
• Sub 0.5” images w/o tip-tilt• 0.15-0.23” images w tip-tilt• Telescope optics preserves images
0.5 1 1.5 2 2.5wavelength [m]
0
0.1
0.2
0.3
0.4
0.5
MH
WF
[c
es
cr
a]
Diffraction
TT/top quartileTT/median
Natural/top quartile
Natural/median
Figure 2 Image size (FWHM) for natural seeing, for tip-tiltcorrection, and for diffraction (from top to bottom). For medianseeing with tip-tilt correction, the points show the effect of telescopedegradation with the AOS specification and the Raytheon structurefunction presented at CDR.
Telescope degradation. Goodyear CDR
22 May 2001 DR SOAR Spartan IR Camera 6
2. Optical Design
• Concept• Image Quality• Tolerances
22 May 2001 DR SOAR Spartan IR Camera 7
Optical Concept
• Requirements– Large number of pixels [ 2 x 5’ / 0.08” = 7500 pixels ]
– Large telescope image [ 5’ x 4.2m x 16 = 100mm square]
• Rockwell 2048x2048 HgCdTe detector– 4 detectors & 7500 pixels two plate scales
• Reflective optics large telescope image• Off-axis collimator & camera mirror
– Parent design: two paraboloids
• Perfect image for 1:1 & small field
– Real design for change in plate scale
• Adjust conic constants, distances
• Field flattening lens
22 May 2001 DR SOAR Spartan IR Camera 8
Design
• Four 20482 detectors• Two plate scales: 0.08 & 0.04”/pixel• 20 filters near pupil• Focal plane mask
– coronagraphy
– spectroscopy
22 May 2001 DR SOAR Spartan IR Camera 9
Image Quality: Spot Diagram
• 9 Field points in a grid. Corners are corners of 4 detectors.• H band
f/11
f/21
Airy disk
22 May 2001 DR SOAR Spartan IR Camera 10
Image Quality: Strehl Ratio
• 9 Field points in a grid. Corners are corners of 4 detectors.• Strehl is very high for diffraction sampled cases, f/21 in H and K
bands
Sampled for diffraction limit
22 May 2001 DR SOAR Spartan IR Camera 11
Tolerances
• Error budget– Loss of Strehl of ~0.07mag
• Alignment• Manufacturing
22 May 2001 DR SOAR Spartan IR Camera 12
Alignment Tolerances
Alignment Tolerances of the Optical ElementsElement
x y z x y zmm mm mm mrad mrad mrad
1 Window NA NA NA NA NA NA2 Focal surface 1.00 1.00 0.30 6.38 6.38 NA3 f/21 collimator 0.81 0.28 0.19 0.30 0.52 6.104 f/11 collimator 0.41 0.15 1.01 0.21 0.42 3.145 Fold mirror 1 NA NA 0.69 0.17 0.26 NA6 Filter NA NA NA NA NA NA7 Lyot stop NA NA NA NA NA NA8 f/21 camera mirror 0.67 0.25 0.40 0.26 0.52 4.809 f/11 camera mirror 0.27 0.17 0.49 0.17 0.23 1.86
10 Fold mirror 2 NA NA 0.16 0.31 0.47 NA11 Lens 0.48 0.32 0.33 2.27 11.34 NA12 Detector plane NA NA 0.03 0.64 0.64 NA
Positional Tolerance Angular Tolerance
1mil over 6in
6mil
22 May 2001 DR SOAR Spartan IR Camera 13
Manufacturing Tolerances• Focal lengths are absorbed in
focus
• SORL can manufacture conic constants
• Surface irregularity– Peak-to-valley is /16 to /4.
= 633nm
22 May 2001 DR SOAR Spartan IR Camera 14
Alignment with SOBER• Align at room temperature with
point source, SOBER, & CCD
• SOBER
– f/16 beam
– Move SOBER & shift stop to mimic pupil at 10m
– z stage mimics curved focal surface of telescope
– Tolerances 1mm & 1º
– Image in IR? TBD
Soar Beam Simulator
LED & pinhole
Lenses
R- stage
ISB surface
Sliding stopz stage
22 May 2001 DR SOAR Spartan IR Camera 15
Alignment Indicator
• Intensity of 9 field points indicates error
Y-decenter of collimator 0.34mm X-tilt of fold #1 of 0.2mrad
- 1 - 0.5 0 0.5 1
- 4
- 2
0
2
4
DygrenEcnE@%D
80. 80. 80.
70.7 81.5 70.7
73.5 81.6 73.5
- 1 - 0.5 0 0.5 1
- 4
- 2
0
2
4
DygrenEcnE@%D
80. 80. 80.
70.7 81.5 70.7
73.5 81.6 73.5
22 May 2001 DR SOAR Spartan IR Camera 16
Test of Alignment
-20 -10 0 10 20 30
-20
-15
-10
-5
0
5
10
E-EH
dengilaL@%D 1 2 3
4 5 6
7 8 9x-position of collimator; wrong
y-tilt of lens; right
Defect: I7<I9
Defect: I5<I8
x-tilt of fold #1
22 May 2001 DR SOAR Spartan IR Camera 17
3. System Design & Electronics• System• Electronics• Software• Motors• Vacuum
22 May 2001 DR SOAR Spartan IR Camera 18
System Design
PC
Stages
Detector
Data ArchiveObserver Telescope Control
Pressure Sensor
Umbilical
Camera Controller
Motor Controller
Legend
Camera Controller
Camera Controller
Camera Controller
Detector
Detector
Detector
DeviceNet
NI 6533
RS232
Fiber optic
Ethernet
RS232
RS232
On camera
In vacuum
In control rack
Elsewhere
Camera Controller
Custom
Commercial
22 May 2001 DR SOAR Spartan IR Camera 19
Umbilical Card• Provenance
– CCD system
DRV11 interfaceNI 6533 interface
Laptop-type power supply
Master clock
Test pod
FIFO
NI 6533
Camera card
Serializerdeserializer
Fiber-optic tranceiver
Logic Analyzer
Existing CCD Softwareon Alpha
In FPGA
One of 4 channels shown
For debugging
22 May 2001 DR SOAR Spartan IR Camera 20
Camera Card
• Provenance: CCD camera• 4 analog channels for 4
quadrants
Laptop-typepower supply
Phase-lockedloop
Test pod
Umbilical card
Serializerdeserializer In FPGA
Detector
Fiber-optic tranceiver
Amplifier &16-bit ADC(2 12-bit ADC)
Buffer
Fixed voltages(digital pot)
Timer & clock generator
TemperatureDiodes
Logic AnalyzerInstruction
22 May 2001 DR SOAR Spartan IR Camera 21
Umbilical Card
• 3U 100160 mm• Tested w/ CCD software
160mm
NI 6533Fiber opticto 4 detectors
FPGA
7V in
To logic analyzer
To existing computer
22 May 2001 DR SOAR Spartan IR Camera 22
Camera Card• 3U 100160 mm
• Low crosstalk– 5-mil between signal & ground layers
• Delivery expected in 2 weeks
FPGA
Signal chains
Fiber optic
7V in
Flex cables to detector Neck betweenanalog & digital circuits
• 2.5s/pixel• 4 channels• Power: 1.4W
22 May 2001 DR SOAR Spartan IR Camera 23
Noise
• Detector noise is about 10e–; noise on amplifier glow is 5e–.• Electronics noise is 6e–.• Coupling from a saturated channel is about 2e–.• Coupling from clocks on cable is large.
– Sampling signal must wait 100ns after clock transition.
Source Noise e- SegregatedDetector ~10Glow w 2.5s read 5Electronics 5.7
Opamp 4.5FB resistor 3.5Offset reference 0.6Bias gate 0.06
CouplingSaturated signal on cable 0.2Clock on cable 180 yesADC (difficult to estimate) 2 ? yesSaturated signal on card 1.3 ?
22 May 2001 DR SOAR Spartan IR Camera 24
Detector Card• Card butts on 2 sides• Connects to camera card with 5 flex cables, which are
thermal resistors.• 3 layers with 5-mil G10.
Electrically isolated strapsto nitrogen dewar
Flex cables
Detector
ZIF socket
22 May 2001 DR SOAR Spartan IR Camera 25
Software
• Functions [copied from Optical Imager]– Control detector
– Scripting
– Communicate with motors
– Communicate with telescope control system
– Communicate with user
• ArcView– Used for all SOAR instruments
– CTIO will debug ArcView with Optical Imager, the commissioning instrument
• LabView, “visual programming”– Independent of hardware obsolescence is obsolete
– Self documenting
– Easy to do. ArcView costs < 1 man-year
22 May 2001 DR SOAR Spartan IR Camera 26
Software Tasks
• Design– Use commercial parts with LabView drivers
• Modify ArcView– Computer send commands and receives data from camera
controller through NI 6533 card.
• Replace Leach controller & driver with NI 6533 card.
• Our card has a 4k sample FIFO– 0.6ms margin for 4 detectors reading simultaneously
– Write software for summing pictures
– Change software for formatting picture
– Change motor controls
– Add temperature & vacuum sensing
22 May 2001 DR SOAR Spartan IR Camera 27
Motion
• Phytron stages DT-90 & MT-85– Vacuum compatible
– Stepper motor
– Indexing switch
– Limit switches
– Open loop; controller stores position
• Controller– RS232 to computer
– LabView
– Heat
• Shutoff power? Cooler?
22 May 2001 DR SOAR Spartan IR Camera 28
Vacuum Measurement
• Granville-Phillips ion gauge– Computer readout via DeviceNet
– LabView
– 12W; need to shut off
22 May 2001 DR SOAR Spartan IR Camera 29
4 Mechanical Design• Cryogenic optical box
– A-frame attachment to vacuum enclosure
– Analysis of flexure
• Vacuum enclosure– Analysis of stress
– Transfer of forces from A-frame to instrument mounting box (ISB)
• Mechanisms using warm stages– Layout
– Proof of concept
• Flexure
• Heat load
• Operating temperature of stage & optics
22 May 2001 DR SOAR Spartan IR Camera 30
Cryogenic Optical Box
• Symmetric box having two plates equidistant from optics.– Gravity vector is in plane.
– Optics supported by both plates.
• Torque perpendicular to plates
• Box is attached near focal surface of telescope– Rotation of optical box
causes no boresight error.
22 May 2001 DR SOAR Spartan IR Camera 31
A-frame Attachment• Connect cold optical box to warm vacuum enclosure
• Complies with shrinkage of optical box– Web weak in z
• Hold box w/o sag– Web strong in x & y
• Heat load is 0.7 W for 4 A-frames.
G10 ring
G10 web
Al leg
Section removedfor clarity
Bolt tooptical box
Bolt to warmvacuum enclosure
Weakfor thermal compliance
Strongest; max sag:14 or 0.04”
Safety stop
22 May 2001 DR SOAR Spartan IR Camera 32
Rotation of Optical Box• Gravity parallel to mounting plate.
(Causes boresight error)
• First approximation– Optical box rotates 40rad as a
unit– Sag is 14 at telescope focus.
• More precisely– Error is greater for gravity
perpendicular to mounting plate.– Rotation within box is 2.3rad
peak-to-peak– Boresight shifts 0.007”.
34–46rad0–155rad
22 May 2001 DR SOAR Spartan IR Camera 33
Vacuum Enclosure• Aluminum plate, mostly 1/2”• Max stress is here
– Max is tensile strength / 2.2.– Code for pressure vessels is 3.5.– Is this OK?
22 May 2001 DR SOAR Spartan IR Camera 34
Transfer of Forces to Bolts on ISB• Does the vacuum enclosure transfer forces between the A-frames and the
bolts on the instrument mounting box (ISB) without sag? Yes. Sag is 2.
Bolts toA-frames
Bolts to ISB
Sides of vacuum enclosure
Optical box
22 May 2001 DR SOAR Spartan IR Camera 35
Mechanisms
• Two filter wheels– Loose tolerances
• Focal-plane mask– 300 along optic axis, 18 in transverse direction
• Collimator insertion– Tilt 5rad (1”) as instrument turns for boresight with tip-tilt sensor
• Camera mirror insertion– Tilt 5rad as instrument turns
• Rotate lens-detector by 112.7±0.6mrad– Tilt 0.2mrad (30 over 150mm)
• Move lens-detector assembly for focusing
Difficult
22 May 2001 DR SOAR Spartan IR Camera 36
Layout of Mask & Filter Wheel• Load is balanced Easy to meet tolerances.• Phytron DT-90 rotational stages
– Integrated stepper motor, indexing switch, limit switch– Spring constant 2rad/(N-m). Wobble is ±15rad (Clarification needed.)
100 200 300 400
-200
-100
100
200
DT - 90
100 200 300 400
-200
-100
100
200
DT - 90
Vacuum enclosure
Optical box
Rotation stage
Mask wheel Filter wheel
22 May 2001 DR SOAR Spartan IR Camera 37
Layout of Mirror Insertion
• Mirrors must be balanced to meet 5rad tolerance.
100 200 300 400
-200
-100
100
200
Mirrorout
CWout
CWin
DT - 90
Mirrorin 100 200 300 400
-200
-100
100
200
Mirrorout
CWout CW
inDT- 90
Mirrorin
Vacuum enclosure
Optical box
Rotation stageMirror
Counterweight
Background mirror
f/21 collimator f/11 camera
22 May 2001 DR SOAR Spartan IR Camera 38
Proof of Concept: Insert f/21 Mirror
• Requirements. Cold mirror — warm stage — cold optical box– Support with tilt < 5rad
– Keep mirror cold
– Keep stage warm
– Minimize heat load
– Comply with thermal expansion
• Precepts– Balance load
– Use G10 A-frames to control conduction & comply with thermal expansion
– Shield stage from cold to control radiation
– Allow stage to absorb radiation from warm vacuum enclosure
22 May 2001 DR SOAR Spartan IR Camera 39
Mirror Insertion
f/21 collimator
Counterweight
DT90 rotational stage
Bracket attachesto optical box
4 A-frames
4 A-frames betweenstage & bracket (hidden)
Center mass
22 May 2001 DR SOAR Spartan IR Camera 40
Results for f/21 Insertion
• A-frames have 1x1x5mm legs.• Balance within 1mm.• Wrap stage in 10 layers of aluminized mylar.• Results
– Conduction is 170mW
– Tilt is 2rad; tolerance for boresight alignment is 5rad.
– Sag with mirror vertical is 8; tolerance for internal alignment is 0.8mm.
– Sag with mirror horizontal is 4; tolerance for focus is 15.
– Temperature of mirror is 88K.
– Temperature of stage is 2K below ambient. (Area of radiator is 10% that of the stage.)
22 May 2001 DR SOAR Spartan IR Camera 41
5 Budget & Schedule• Budget• Contingency• Descope• Risk to budget• Schedule
22 May 2001 DR SOAR Spartan IR Camera 42
Budget• Not allocated or charged: Majority of electrical engineer, mechanical engineer,
project management, drafting (done so far), and finite-element analysis.
SUMMARY BY WBSWBS ITEM M&S CONTINGENCY TOTAL
%1 MECHANICAL 218577 27 58818 2773962 OPTICS 188683 34 63729 2524123 DETECTOR 317263 5 16045 3333094 SOFTWARE & COMPUTERS 49456 59 29021 784785 INSTALLATION AND COMISSIONING49653 23 11643 612966 SUPPORT EQUIPMENT & SUPPLIES38822 22 8397 472207 MANAGEMENT, REPORTING, & DOCUMENTING50610 13 6777 57387
TOTAL 913065 21 194431 1107496
Major ItemsWBS Item Total1.3 Optical Bench, dewar, enclosure 122,5181.4 Mechanisms 147,9082.5 Collimator mirror 63,7462.6 Camera mirror 75,0353.1.1 Detector 250,0003.2 Electronics 52,8944.1 Software 48,657
22 May 2001 DR SOAR Spartan IR Camera 43
Contingency vs Remaining Tasks• Tracking of tasks since budget of Aug 2000
– Electronics design is 17% over budget. ($5k of $29k)– Design of telescope simulator is 65% over budget. ($5k of $8k)– Optics design is 31% under budget. ($6k of $19k)– Overall budget dropped $100k because mechanical design firmed up, optics shortened, and mirror quotes dropped.
• Contingency is 36% of remaining tasks.
CONTINGENCY AS FRACTION OF REMAINDERWBS ITEM
% % AMOUNT1 MECHANICAL 27 59322 292 37 591102 OPTICS 10 18257 6753 41 704813 DETECTOR 89 282777 (5129) 32 109164 SOFTWARE & COMPUTERS 2 835 360 60 293815 INSTALLATION AND COMISSIONING0 0 0 23 116436 SUPPORT EQUIPMENT & SUPPLIES49 19028 (3552) 24 48457 MANAGEMENT, REPORTING, & DOCUMENTING0 0 0 13 6777
TOTAL 42 380219 (1276) 36 193155
CONTINGENCYENCUMBERED
22 May 2001 DR SOAR Spartan IR Camera 44
Descope
• Descope 2nd plate scale, J, H, K, Ks filters only, spectroscopy & coronagraphy.
• Descope will be treated as contingency.– Descoped items will be added as contingency allows.
– Possible formula: spend if
Budgeted Contingency > 1.5 Actual Contingency
WBS M&S Contingency TotalTotal 128439 46958 175397Second f/ratio 83239 35658
2.5 Collimator mirror 21249 106242.6 Camera mirror 25012 12506
Mechanisms 36979 12528Spectroscopy & Coronagraphy 13200 3300
2.13 Grisms 13200 3300Spectral filters 32000 8000
2.9 Defer 8 of 12 32000 8000
22 May 2001 DR SOAR Spartan IR Camera 45
Risk to Project• Number of risks covered
– A big item is $100k.
– Labor for optical box, mechanisms, enclosure is $70k with $30k contingency
• Drafting: 3 mo.
• Internal shop: 7 mo.
• External shop: 1 mo.
• Technician: 6 mo.
– Contingency, $193k, covers 2 big risks
– Descope, $175k, covers 2 big risks.
• Descope & contingency remaining tasks of descoped instrument
22 May 2001 DR SOAR Spartan IR Camera 46
Schedule Overview
22 May 2001 DR SOAR Spartan IR Camera 47
Detector
• Multiplexer & engineering-grade device delivered.• Long slack time before science-grade detector is needed.
Task NameDetector
Rockwell multiplexer
Rockwell engineering device
Rockwell science-grade device
or
xer 1/19
Rockwell engineering device 11/
Rockwell science-grade device
Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 41999 2000
22 May 2001 DR SOAR Spartan IR Camera 48
Electronics• 7 mo. slack
Task NameElectronics
Design & fabricate electronics
Computer board
Design
Fabrication
Debug
UmbA (Old cam & DRV)
UmbB (New cam & DRV)
UmbC (Old cam & 6553)
UmbD (New cam & 6553)
Camera board
Design
Fabrication
Debug
CamA (Emulate old cam)
CamB (One quad)
CamC (4 quads)
Dewar cable
Design
Fabrication
Debug
Modify test dewar
Test engineering detector
Fix problems
s
s 72%
d 85%
gn 2/7
Fabrication 3/27
Debug 23%
UmbA (Old cam & DRV) 4/6
UmbB (New cam & DRV) 1/31
UmbC (Old cam & 6553) 1/31
UmbD (New cam & 6553) 2/14
d 45%
gn 4/27
Fabrication 1/3
Debug 0%
CamA (Emulate old cam) 1/17
CamB (One quad) 1/31
CamC (4 quads) 2/14
le 58%
gn 6/7
Fabrication 2/7
Debug 2/14
Modify test dewar 2/14
Test engineering detector 5/9
Fix problems
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22001 2002
22 May 2001 DR SOAR Spartan IR Camera 49
Optical Box, Enclosure, & Mechanisms• Optical box & enclosure will soon be a critical task.• Plans for mechanisms have changed.
– Swales Aerospace’s estimate is 3 times higher than that of 1998.– New plan is to purchase high quality, warm stages & design non-precision parts.– Short slack.
Task NameDesign thermal concept
Design mechanical concept
Optical bench & enclosure
Drafting
Fabrication
Testing
Mechanisms
Write specifications
Choose vendor
Detailed design
Fabrication & Testing
pt 5/29
ept 6/7
Optical bench & enclosure 0%
Drafting 7/5
Fabrication 11/8
Testing 4/25
Mechanisms 4%
te specifications 12/15
Choose vendor 7/26
Detailed design 10/25
Fabrication & Testing 4/25
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22001 2002
22 May 2001 DR SOAR Spartan IR Camera 50
Optics
• Optics & filters are behind schedule.– Estimated time is 2–3 times longer than vendors’ quotes of 26
weeks, because of word-of-mouth tales.
– Schedule could be made up with immediate requisitions and on-time deliveries
Task NameDesign optical details
Choose vendors
Fabricate optics
Fabricate filters
Write RFQ for telescope simulator
Fabricate telescope simulator
etails 2/15
Choose vendors 4/12
Fabricate optics 4/25
Fabricate filters
Write RFQ for telescope simulator 10/25
Fabricate telescope simulator 4/25
Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 32001 2002
22 May 2001 DR SOAR Spartan IR Camera 51
Software
• ArcView will be fully tested by CTIO with the Optical Imager.• Scope of software task is uncertain.
– No experience with LabView.
– Need to see ArcView.
• If task is beyond students’ capability, we will seek vendor such as Imaginetics.
Task NameSoftware
Write operating manual
Design software
Write software
Test software
are 0%
nual 6/21
oftware 8/16
rite software 2/28
Test software 5/23
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22002 2003
22 May 2001 DR SOAR Spartan IR Camera 52
Integration & Installation
• There is a 16 week period for fixing problems.• Delivery is scheduled for 3/28/03.
Task NameIntegration
Integrate electronics & software
Install optics
System integration
Fix problems
Install science-grade detector
Instrument finished
Install on telescope
0%
are 8/15
s 8/15
m integration 10/10
Fix problems 1/30
Install science-grade detector 2/27
Instrument finished 2/28
Install on telescope 5/8
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22003 2004
22 May 2001 DR SOAR Spartan IR Camera 53
Risk to Schedule
• Tasks on the critical path– Optics are delayed.
– Optical box & enclosure have little slack.
– Mechanisms have a short slack.
• Delay of funding is the greatest risk.– Without starting on the critical tasks, we cannot test our estimates.
We cannot set accurate bounds on the task.