Name of Work
Ref :: For Emulsion (Bulk) :- HINCOL Price List With Effect From Dt.16-12-2009
For Bulk Bitumen 80/100, 60/70:- HPCL Price List With Effect From Dt. 16-12-2009
Lead for KM 7/0 to 7/400
Bulk 80/100 Grade Bulk 60/70 Grade
Visakha Visakha
Basic Price 32432.58 33384.55
Lead from
416.00 Kms 1248.00 1248.00
Lead charges for Bulk @
1.50 per KM
33680.58 34632.55
Visakhapatnam
COST OF BITUMEN / MT WITH LEADS
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD
FROM KM. 5/000 TO 7/000 & 7/600 TO 9/700
Emulsion (Bulk)
Visakha
29448.64
30696.64
1248.00
7/29/2019 SNM Road
2/18
KM Descript ion o f Metal Source of SupplyLead in
KmsConveyance
Initial cost
less
stacking
Blasting
charges
Machine
crushing
charges
Seigniorage
charges
Dedu
ch
con
A) FOR ROAD WORKS
140 to 45 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 491.30 70.00 122.83 50.00
225 to 27 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 821.30 70.00 205.33 50.00
319 to 22 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 836.30 70.00 209.08 50.00
412 to 14 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 681.30 70.00 170.33 50.00
59.5 to 11.20 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 551.30 70.00 137.83 50.00
65 to 7 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 421.30 70.00 105.33 50.00
72.36 to 5 mm IRC and MoRTH
HBG M/C metal
Kethanakonda97 632.25 225.30 70.00 56.33 50.00
8 HBG Stone chips 2.36mmand below Kethanakonda 97 632.25 216.30 0.00 0.00 50.00
9 Selected EarthPurushothapatna
m76 470.40 19.50 0.00 0.00 22.00
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD FROM KM. 5/
TO 9/700
ROAD METAL RATES
NAME OF WORK ::-
7/29/2019 SNM Road
3/18
Average Butimen Lead From Visakha
Visakha to M.N.K.Road 345.326
M.N.K.Road Km 59.800 0.800 59.000
Byepass road 0/0 to 3/100 0.000 3.100 3.100
VM Road 64/985 to 63/8 64.985 63.800 1.182
Sultanagaram - Mukkollu road 0.000 5.000 5.000
Avg lead (5/0 to 9/7) 2.350
415.958
Or Say 416.00
Average HBG metal / Chips Lead From Kathanakonda
CT + 10% 0.220
SHV ROAD (266.30 TO 244.60) 21.700
Vijayawada MPL ROAD 0.200
V.V.ROAD (0/0 to 5/9) 5.900V.M.ROAD(KM1.700 to 63.800 62.100
SNM Road 0/0 to 5/0 5.000
Average Lead (5/0 to 9/7) 2.350
97.470
Or Say 97.00
Average Selected Earth Lead From 11/4 of Meerjapuram-
Gopavaram Road quarry
CT 1.000
10% EXTRA 0.100
G M ROAD(12.8 TO 11.40) 1.400
MNK Road (68.148 to 5.800) 62.348
Byepass road 0/0 to 3/100 0.000 3.100 3.100
VM Road 64/985 to 63/8 64.985 63.800 1.182
Sultanagaram - Mukkollu road 0.000 5.000 5.000
Avg lead (5/0 to 9/7) 2.350
76.480
Or Say 76.00
LEAD STATEMENT
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD FROM KM. 5/000 TO 7/000 & 7/600
TO 9/700
7/29/2019 SNM Road
4/18
7/29/2019 SNM Road
5/18
Name of Work ::
DISTRICT :: Krishna
Assembly constituency: Pedana
Parliament constituency: Machilipatnam
ESTIMATE AMOUNT: Lakhs
C I R C L E :: Vijayawada
D I V I S I O N :: Machilipatnam
S U B-D I V I S I O N :: MachilipatnamS E C T I O N :: Pedana
GOVERNMENT OF ANDHRA PRADESHROADS AND BUILDINGS DEPARTMENT
SPECIAL REPAIRS TO SULTANAGARAM TO
MUKKOLLU ROAD FROM KM. 5/000 TO 7/000 & 7/600
TO 9/700
7/29/2019 SNM Road
6/18
1 Scarifying the existing B.T.Surface.
2 Providing Wet Mix Macadam to a width of 4.10Mts.
3 Providing and laying surface dressing in single coat with 60/70 Grade Bitumen.
4 Providing and applying tack coat with bitumen Emulsion
5 Providing and laying SDBC 25mm thick using 60/70 grade Bitumen.
6 Providing Selected earth shoulders 150mm thick for 1.00 mts width on either side
7 Provision for VAT @ 4%
8
9 Proviison for Q.C.Charges
10 L. S PROVISION FOR Price Escalanation
11 L. S PROVISION FOR Unforseen items
Assistant Executive Engineer Deputy Executive Engineer(R&B)
(R&B) Pedana. Machilipatnam
RATES : The estimate is prepared adopting the average rates as per the
upgraded Current Schedule of rates of Andhra Pradesh for the year 2008-2009
and the work will be carried out as per standard specification and circulars
issued from time to time
Provision for Avagahana Sadassu
NECESSITY:-
Specification Report to accompany the Estimate for the work " Special Repairs to
Nadupukru-Vadavalli-Korukollu Road from 7/0 to 14/0
Estimated cost :: Rs: 30.00 Lakhs
The following provisions are made in the estimate
7/29/2019 SNM Road
7/18
Name of Work ::-
Sl.No NO L B D Quantity Rate Amount
1
From Km 5/0 to 7/000 1 2000 3.80 7600.00
From Km 7/6 to 9/600 1 2000 3.80 7600.00
15200.00
15200.00 5.40 82080
Sqm /Sqm
2
From Km 5/0 to 7/000
From Km 7/6 to 9/600 1 2000 3.80 0.150 1140.00
1140.00 2244.00 2558160
cum /Cum
3
From Km 5/0 to 7/000 1 2000 3.80 7600.00
From Km 7/6 to 9/600 1 2000 3.80 7600.00
15200.00 41.30 627760
Sqm /Sqm
4
From Km 5/0 to 7/000 1 2000 3.80 7600.00
From Km 7/6 to 9/700 1 2100 3.80 7980.00
15580.00 8.30 129314
Sqm /Sqm
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD
FROM KM. 5/000 TO 7/000 & 7/600 TO 9/700
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical meansand disposal of scarified material with all leads and lifts upto 1000 Mtrs as per
MoRT&H (4th Revision) Specn. No.305.4.3
Providing and applying tack coat with bitumen Emulsion (Medium settting)
(Bulk) using Emulsion pressure distributor at the rate of 0.20 kgs per sqm on
the prepared bituminous/granular surface cleaned with mechanical broom for
finished item of work as per MoRT&H Specification 503 (4th revision) and as
directed by the Engineer-in-Charge.
DETAILED CUM ABSTRACT ESTIMATE
Providing, Laying, Spreading and compacting graded HBG crushed stone
aggregate to Wet Mix macadem specification including cost,seignorage of all
materials and including premixing the material with water at OMC in
Mechanical mix plant carriage of mixed material by tipper to site , laying in
uniform layers with paver in base courses on well prepared surface andcompacting with Vibratory roller to acheive the desired density etc., as directed
by the Engineer-in-Charge and as per MoRT&H specification.406 (4th revision)
for finished item of work.
Providing and laying surface dressing in single coat using 6 mm nominal size
IRC HBG machine crushed stone aggregates @ 0.004 cum / sqm on a layer of
bitumen binder of 60/70 grade @ 0.75 kg / sqm including cost, seigniorage
and conveyance of all materials to work site and laid on prepared surface androlling with 8-10 T Power Road Roller etc., complete for finished item of work
as per MoRT&H Specification 510 (4th Revision) and as directed by the
Engineer-in-charge.
Description of Item
7/29/2019 SNM Road
8/18
Sl.No NO L B D Quantity Rate AmountDescription of Item
5
From Km 5/0 to 7/000 1 2000 3.80 0.025 190.00
From Km 7/6 to 9/700 1 2100 3.80 0.025 199.50
390.00 7828.00 3052920
cum /Cum
6
For Shoulders
From Km 5/0 to 7/000 2 2000 1.00 0.100 400.00
From Km 7/6 to 9/700 2 2100 1.00 0.100 420.00
820.00 795.00 651900
cum /Cum
7102134
Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot
mix plant using hard blasted granite crushed aggregates of Grading -2 as per
table 500-15 of specification 508 of MoRT&H (4th Revision), premixed with
bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot mix
to work site, laying with mechanical paver finisher to the required grade, level
and alignment, rolling with smooth wheeled,vibratory and tandem rollers to
achieve the desired compaction as per MoRT&H Specification 508 (4th
Revision) complete for finished item of work in all respects as directed by
Engineer-in-charge.
Construction of earthern shoulders with approved material ( Selected soils
having MDD not less than 17.5KN/Cum ) obtained from borrow pits from
outside road boundary by mechanical means upto SDR with all leads and lifts
including pre-watering of soil at borrow area, removal of top soil, excavation of
soils at borrowed area, conveyance of soil, depositing the soil on the
embankment, spreading soil, breaking clods, sectioning, grading and
consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet
requirement of table 300-2 of MoRT&H, including all hire and operationalcharges of T&P and seigniorage charges, complete for finished item of work
as per MoRT&H specification 305 (4th revision)
TOTAL :
7/29/2019 SNM Road
9/18
Name of Work
Rate per Amount
1
Page 68,69 of MoRT&H SDB
(A) Labour
0.04 day Mate 188.00 day7.52
1.00 day Mazdoor unskilled 146.00 day 146.00
153.52
(B) Machinery
100.00 cum 13.00 cum 1300.00
12160.00 t.km Tipper (for 1 Km = 160x76 = 12160) 4.50 t.km 54720.00
5472.00
0.50 hr 2760.00 hr 1380.00
4.00 hr Water tanker 6 KL 345.00 hr 1380.00
1.00 hr Vibratory roller 8T 1550.00 hr 1550.00
65802.00
(C) Seigniorage charges
100.00 Cum Seigniorage charges 22.00 cum 2200.00
(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C) 4089.33
(E) Total of (A) + (B)+( C)+(D) 72244.85
(F) Add Contractors Profit at 10% on (E) 7224.49
Cost per 100 cum (E) + (F) 79469.34
Rate per Cum 794.69
795.00
2
Unit = sqm Page 67,68 of MoRT&H SDB
Taking output = 100 sqm
(A) Labour
0.01 day Mate 188.00 day 1.88
0.25 day Mazdoor 146.00 day 36.50
Total 38.38
(B) Machinery
0.08 hr Tractor with ripper attachment @ 60 cum p 345.00 hr 27.60
0.20 hr Front end loader 1 cum capacity 1320.00 hr 264.00
0.23 hr Tipper 5.50 cum capacity, 4 trips/Hour 575.00 hr 132.25
Total 423.85
(For KM 7/0 to 7/400 )
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material
with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th
Revision) Specn. No.305.4.3
Taking out put = 100 Cum
Rate as per G.O. Ms No 10, Dt 26/7/2005
Dozer 80 HP for spreading @ 200 cum per hour
Unit : Cum
Rate per 1 cum
Add 10% of cost of carriage to cover cost of loading
and unloading
Construction of earthern shoulders with approved material ( Selected soils having MDD not less than 17.5KN/Cum )
obtained from borrow pits from outside road boundary by mechanical means upto SDR with all leads and lifts
including pre-watering of soil at borrow area, removal of top soil, excavation of soils at borrowed area, conveyance
of soil, depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading and consolidation
with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all
hire and operational charges of T&P and seigniorage charges, complete for finished item of work as per MoRT&H
specification 305 (4th
revision)
DATA
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD FROM
KM. 5/000 TO 7/000 & 7/600 TO 9/700
Quantity Description of Item
Page 9
7/29/2019 SNM Road
10/18
Rate per AmountQuantity Description of Item
(C) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B) 27.73
Add Contractors Profit at 10% on (A)+(B)+ 49.00
Cost per 100 sqm 538.96
Rate per 1 sqm 5.39
Rate to be adopted 5.40
1 Sqm
3
Unit = cum Page 110,111 of MoRT&H SDB
Taking output = 225 cum
(A) Labour
0.48 nos. Mate 188.00 day 90.24
2.00 nos. Mazdoor skilled 193.40 day 386.80
10.00 nos. Mazdoor 146.00 day 1460.00
Total 1937.04
(B) Machinery6.60 hr Wet mix plant of 60 tonne hr. capacity 1320.00 hr 8712.00
6.00 hr Electric generating set 125 KVA 1090.00 hr 6540.00
6.00 hr front end loader 1 cum capacity 1320.00 hr 7920.00
6.00 hr Mechanical Paver finisher 100 TPH 1090.00 hr 6540.00
3.90 hr Vibratory roller 8-10 T 1550.00 hr 6045.00
3.00 hr Water tanker 345.00 hr 1035.00
Total 36792.00
(C) Material
89.10 cum 45 to 22.40mm IRC&MoRT&H HBG M/C metal@ 30% 1638.93 cum 146028.66
(Av. Of 40-45, 25-27, 19-22mm )
118.80 cum 22.4 to 2.36mm IRC&MoRT&H HBG M/C metal@40% 1422.43 cum 168984.68
89.10 cum 889.85 cum 79285.64
Total 394298.98
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 25981.68
(E) Total of (A) + (B)+( C)+(D) 459009.70
(F) Add Contractors Profit at 10% on (E) 45900.97
Cost per 225 cum (E) + (F) 504910.67
Rate per 1 cum 2244.05
Rate to be adopted per 1 cum 2244.00
Cum
4
Unit = sqm Page 141,142 of MoRT&H SDB
Taking output = 9000 sqm
(A) Labour
0.44 nos. Mate 188.00 day 82.72
9.00 nos. Mazdoor 146.00 day 1314.00
2.00 nos. Mazdoor skilled 193.40 day 386.80
Total 1783.52
Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macademspecification including cost,seignorage of all materials and including premixing the material with water at OMC in
Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layers with paver in base
courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc., as
directed by the Engineer-in-Charge and as per MoRT&H specif ication.406 (4th
revision) for finished item of work.
(Av. Of 19-22mm, 12-14mm, 9.5-11.2mm, 5-7mm,2.36 - 5mm )
Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine crushed stoneaggregates @ 0.004 cum / sqm on a layer of bitumen binder of 60/70 grade @ 0.75 kg / sqm including cost,
seigniorage and conveyance of all materials to work site and laid on prepared surface and rolling with 8-10 T Power
Road Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4th
Revision) and as directed
by the Engineer-in-charge.
2.36mm to 75 micron @ 30% (2.36mm & below)
Page 10
7/29/2019 SNM Road
11/18
Rate per AmountQuantity Description of Item
(B) Machinery
7.20 hr 290.00 hr 2088.00
7.20 hr Air compressor 250 cfm 370.00 hr 2664.00
6.00 hr 2070.00 hr 12420.00
6.00 hr 575.00 hr 3450.00
6.00 hr 1320.00 hr 7920.00
6.00 hr Bitumen pressure distributor @1750 sqm/hr 940.00 hr 5640.00
6.00 hr smooth wheeled roller 8 Ton 540.00 h 3240.00
Total 37422.00
(C) Material
6.75 MT Bitumen 60/70 @ 0.75 Kg / sqm 34632.55 MT 233769.72
36.00 cum 1270.18 cum 45726.48
Total 279496.20
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 19122.10
(E) Total of (A) + (B)+( C)+(D) 337823.82
(F) Add Contractors Profit at 10% on (E) 33782.38Cost per 9000 sqm (E) + (F) 371606.20
Rate per 1 sqm 41.29
Rate to be adopted. 41.30
1 Sqm
5
unit = sqm Page 124 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos Mate 188.00 day 15.04
2.00 nos Mazdoor 146.00 day 292.00
Total 307.04
(B) Machinery
2.80 hr 290.00 hr 812.00
2.80 hr Air compressor 250 cfm 370.00 hr 1036.00
2.00 hr 690.00 hr 1380.00
Total 3228.00
(C) Material
0.70 MT 30696.64 MT 21487.65
Total 21487.65
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 1501.36
(E) Total of (A) + (B)+( C)+(D) 26524.05
(F) Add Contractors Profit at 10% on (E) 2652.41
Cost per 3500 sqm (E) + (F) 29176.46
Rate per 1 sqm 8.34
Rate to be adopted 8.30
1 Sqm
Front end loader 1 cum bucket capacity
Providing and applying tack coat with bitumen Emulsion (Medium settting) (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical
broom for finished item of work as per MoRT&H Specification 503 (4th
revision) and as directed by the Engineer-in-
Charge.
Mechanical broom Hydraulic @ 1250 sqm/hr.
Emulsion pressure distributor @1750 sqm/hr
Bitumen Emulsion @ 0.20 Kgs/sqm
Tipper 10Tonne capacity for carriage of stone chips
from stock pile on road side to chip spreader
(Rate of Tipper 5 cum
Crushed stone chippings 6 mm nominal size @0.004
cum/sqm
Mechanical broom @ 1250 sqm/hr.
Hydraulic self propelled chip spreader @ 1500 sqm/hr.
Page 11
7/29/2019 SNM Road
12/18
Rate per AmountQuantity Description of Item
6
Unit = cum Page 135,136,137 of MoRT&H SDB
Taking output = 195 cum (450 tonnes.)
(A) Labour
0.84 nos. Mate 188.00 day 157.92
14.00 nos. 146.00 day 2044.00
5.00 nos. 193.40 day 967.00
Total 3168.92
(B) Machinary
11.00 hr Hot mix plant 40 to 60 TPH 15525.00 hr 170775.00
6.00 hr 1090.00 hr 6540.00
6.00 hr Generator 250 KVA 1550.00 hr 9300.00
6.00 hr Front end loader 1 cum capacity 1320.00 hr 7920.00
3.90 hr 540.00 hr 2106.003.90 hr 1550.00 hr 6045.00
3.90 hr 1320.00
hr
5148.00
Total 207834.00
(C) Material
22.50 M.T 34632.55 MT 779232.40
(ii) Aggregate
For Grading II
162.450 cum 1242.68 cum 201873.37
116.850 cum 957.52 cum 111885.63
cum
5.70 cum 889.85 cum 5072.15
Total 1098063.55
(D) Over head charges @ 6% (10%-VAT)
6.00 % Add for Over head charges @ 6% on (A)+(B)+( C) 78543.99
(E) Total of (A) + (B)+( C)+(D) 1387610.46
(F) Add Contractors Profit at 10% on (E) 138761.05
Cost per 195 cum (E) + (F) 1526371.51
Rate per 1 cum 7827.55
Rate to be adopted 7828.00
1 Cum
Average rate of IRC&MoRT&H HBG M/C metal of
sizes 9.5-11.2, 5-7mm,2.36 - 5mm
IRC &MORT&H HBG M/C chips 4.75 mm and below @41%Average rate of IRC&MoRT&H HBG M/C metal of
sizes 2.36 - 5mm and 2.36mm& below
Filler @ 2% of weight of aggregates.
Vibratory roler 8 tonne for intermediate rolling
Finish rolling with 6-8 tonne smooth wheeled tandem
roller.
(I) Bitumen @ 5% by weight of mix
IRC &MORT&H HBG M/C chips 9.5 to 4.75mm @ 57%
Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using hard blasted granite
crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H (4th
Revision), premixed
with bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot mix to work site, laying with
mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled,vibratory and
tandem rollers to achieve the desired compaction as per MoRT&H Specification 508 (4th
Revision) complete for
finished item of work in all res ects as directed b En ineer-in-char e.
Mazdoor working with HMP, Mechanical broom,
paver,roller,asphalt cutter and assistance for setting
outlines,levels and layout of construction.
Skilled Mazdoor for checking line and levels.
Mechanical Paver finisher @ 100 TPH
Power road roller 8 tonne for initial break down rolling
Page 12
7/29/2019 SNM Road
13/18
DISTRICT : KRISHNA
CIRCLE : (R&B), VIJAYAVADA
CVPD PCU's
1 2 3 4 5 6 7 8 9 10 11 12
1 Krishna Pedana 3% B.T SL 220 1250 Maintenance 2003-04 Poor
Machilipatnam road
F
Rig
SPECIAL REPAIRS PROGRAMME PROPOSALS FOR THE YEAR 2009-10
S.NoName of
Division
Name of
ConstituencyName of work
Sub
Grade
CBR
Existing
Crust
Width of
Carriage
way
SL/IL/DL
Traffic Volume Repairs
carried out
during last
two years
SPECIAL REPAIRS TO
SULTANAGARAM TO
MUKKOLLU ROAD
FROM KM. 5/000 TO
7/000 & 7/600 TO 9/700
Year of Last
Renewal
Drainag
e StatusS
7/29/2019 SNM Road
14/18
Name of Work :
1) The quarry distances noted in the quarry map are correct.
2) The quarries noted are correct.
3) The routes shown are correct.
4) The description of the materials available in the quarries noted are correct.
(R&B) North Section, (R&B) Sub-Division, Machilipatnam (R&B)Division, Machilipatnam
(R&B) Circle, Vijayawada
Superintending Engineer
(R&B) North Section, (R&B) Sub-Division, Machilipatnam (R&B)Division, Machilipatnam
Superintending Engineer
SPECIAL REPAIRS TO SULTANAGARAM TO MUKKOLLU ROAD FROM KM. 5/000 TO 7/000 & 7/600
TO 9/700
QUARRY AND LAND CERTIFICATE
Certified that
Asst. Engineer Dy.Executive Engineer Executive Engineer
(R&B) Circle, Vijayawada
Certified that I have inspected the above road personally on date and the
provisions made in the estimate are essential and adequate.
INSPECTION CERTIFICATE
Asst. Engineer Dy.Executive Engineer Executive Engineer
(R&B) Circle, Vijayawada
Superintending Engineer
CARTING EARTH CERTIFICATE
This is to certify that there is no side earth is availabe in the vicinity of the work. Hence,
Selected earth with 65 km Lead for the stretch from KM 7/0 to 7/4 & 71 Kms lead for the stretch from
KM 13/400 to 14/0 is proposed for shoulders.
Asst. Engineer Dy.Executive Engineer Executive Engineer
(R&B) North Section, (R&B) Sub-Division, Machilipatnam (R&B)Division, Machilipatnam
7/29/2019 SNM Road
15/18
*
7/29/2019 SNM Road
16/18
Earth/Gravel/
Sand
Metal
loading 10.00 12.80 Material Rates
unloading 8.50 8.70 60 to 63 mm IRC & MoRTH HBG metal 360.00
stacking 5.50 8.70 50 to 55 mm IRC & MoRTH HBG metal 390.00
0.25 50.00 110.00 40 to 45 mm IRC & MoRTH HBG metal 500.00
0.5 75.00 110.00
1 100.00 120.00 Roughstone 300mm (HBG)for revetment136.00
2 106.00 126.00Roughstone 225mm (HBG)for revetment 117.00
3 112.00 132.00 SS Revetment work 225mm 71.00
4 118.00 138.00 SS Revetment work 300mm 95.00
5 124.00 144.00 SS Revetment work 450mm 114.00
6 130.00 150.00 Laterite for Revetment 225mm 98.00
7 136.00 156.00 Laterite for Revetment 300mm 114.00
8 142.00 162.00 Jeddy stone above 450mm to 600mm 156.00
9 148.00 168.00
Quarry spall(Field picked metal)
Av. Of rate 25mm & 40mm39.75
10 154.00 174.00 150 mm soling stone HBG metal 82.00
11 160.00 180.00 40 to 45 mm IRC & MoRTH HBG M/C metal 500.00
12 166.00 186.00 25 to 27 mm IRC & MoRTH HBG M/C metal 830.00
13 172.00 192.00 19 to 22 mm IRC & MoRTH HBG M/C metal 845.00
14 178.00 198.00 12 to 14 mm IRC & MoRTH HBG M/C metal 690.00
15 184.00 204.00 9.5 to 11.20 mm IRC & MoRTH HBG M/C metal 560.0016 190.00 210.00 5 to 7 mm IRC & MoRTH HBG M/C metal 430.00
17 196.00 216.00 2.36 to 5 mm IRC & MoRTH HBG M/C metal 234.00
18 202.00 222.00 HBG Stone chips 2.36mm and below 225.00
19 208.00 228.00 Quarry Rubbish 25.00
20 214.00 234.00 40 mm SS-5 m/c HBG metal 500.00
21 219.00 239.75 25 mm SS-5 m/c HBG metal 830.00
22 224.00 245.50 20 mm SS-5 m/c HBG metal 845.00
23 229.00 251.25 12 mm SS-5 m/c HBG metal 690.00
24 234.00 257.00 10 mm SS-5 m/c HBG metal 560.00
25 239.00 262.75 6 mm SS-5 m/c HBG metal 430.00
26 244.00 268.50 Sand for Mortar 175.00
27 249.00 274.25 Sand for Filling 60.00
28 254.00 280.00 HYSD Steel 41500.00
29 259.00 285.75 Mild Steel 42900.00
30 264.00 291.50 Cement 4400.0031 268.80 297.00 Mild Steel 6mm 41500.00
32 273.60 302.50 Blasting charges
33 278.40 308.00 Blasting charges 70.0034 283.20 313.50 Blasting charges for rough stone 67.00
35 288.00 319.00 Seigniorage charges
36 292.80 324.50 Metal 45.00
37 297.60 330.00 Gravel/earth 20.00
38 302.40 335.50 Sand 36.00
39 307.20 341.00 Labour Rates
40 312.00 346.50 Mate 188.0041 316.80 352.00 Mazdoor skilled 193.40
42 321.60 357.50 Mazdoor unskilled 146.0043 326.40 363.00
44 331.20 368.50 Dozer 80 HP for spreading @ 200 cum per hour 2760.00
45 336.00 374.00 Motor grader 3.35M Blade @50 cum/Hr 2600.0046 340.80 379.50 Hydralic excavator 2250.00
47 345.60 385.00 Front end loader 1 cum capacity 1320.00
48 350.40 390.50 Tipper 5 cum 575.00
49 355.20 396.00 Vibratory roller 8T 1550.00
50 360.00 401.50 smooth wheeled roller 8 Ton 540.00
Machinery Rates
7/29/2019 SNM Road
17/18
51 364.60 406.50 Water tanker 6 KL 345.00
52 369.20 411.50 Tractor 345.00
53 373.80 416.50 Tractor with Rotavator 345.00
54 378.40 421.50 Tractor with ripper attachment @ 60 cum per hour 345.00
55 383.00 426.50 Air compressor 250 cfm 370.00
56 387.60 431.50 Wet mix plant of 60 tonne hr. capacity 1320.00
57 392.20 436.50 Mechanical broom @ 1250 sqm/hr. 290.00
58 396.80 441.50Bitumen pressure distributor @1750 sqm/hr
940.00
59 401.40 446.50 Emulsion pressure distributor @1750 sqm/hr 690.00
60 406.00 451.50 Hot mix plant 40 to 60 TPH 15525.00
61 410.60 456.50 Mechanical Paver finisher 100 TPH 1090.00
62 415.20 461.50 Hydraulic self propelled chip spreader @ 1500 sqm/hr. 2070.00
63 419.80 466.50 Finish rolling with 6-8 tonne smooth wheeled tandem roller. 1320.00
64 424.40 471.50 Pneumatic road Roller 1035.00
65 429.00 476.50 GSB Plant 50 Cum 920.00
66 433.60 481.50 Generator 250 KVA 1550.00
67 438.20 486.50 Generator set 125 KVA 1090.00
68 442.80 491.50 Generator set 35 KVA 620.00
69 447.40 496.50 Concrete mixer 0.4/0.28 cum 345.00
70 452.00 501.50 Tipper 5.50 cum capacity per Tonne per km 4.50
71 456.60 506.50 Tipper 5.50 cum per km 45.00
72 461.20 511.50 Plate compactor/Power rammer 40.00
73 465.80 516.5074 470.40 521.50
75 475.00 526.50
76 479.60 531.50
77 484.20 536.50
78 488.80 541.50
79 493.40 546.50
80 498.00 551.50
81 502.40 556.25
82 506.80 561.00
83 511.20 565.75
84 515.60 570.50
85 520.00 575.25
86 524.40 580.00
87 528.80 584.75
88 533.20 589.50 Tipper 10Tonne capacity for carriage of stone
89 537.60 594.25 chips from stock pile on road side to chip90 542.00 599.00 spreader
91 546.40 603.75
92 550.80 608.50
93 555.20 613.25
94 559.60 618.00
95 564.00 622.75
96 568.40 627.50
97 572.80 632.25
98 577.20 637.00
99 581.60 641.75
100 586.00 646.50
101 590.20 651.00
102 594.40 655.50
103 598.60 660.00
104 602.80 664.50105 607.00 669.00
106 611.20 673.50
107 615.40 678.00
108 619.60 682.50
109 623.80 687.00
7/29/2019 SNM Road
18/18
110 628.00 691.50
111 632.20 696.00
112 636.40 700.50
113 640.60 705.00
114 644.80 709.50
115 649.00 714.00
116 653.20 718.50
117 657.40 723.00
118 661.60 727.50
119 665.80 732.00
120 670.00 736.50
121 674.20 741.00
122 678.40 745.50
123 682.60 750.00
124 686.80 754.50
125 691.00 759.00
126 695.20 763.50
127 699.40 768.00
128 703.60 772.50
129 707.80 777.00
130 712.00 781.50
131 716.20 786.00
132 720.40 790.50
133 724.60 795.00134 728.80 799.50
135 733.00 804.00
136 737.20 808.50
137 741.40 813.00
138 745.60 817.50
139 749.80 822.00
140 754.00 826.50
141 758.20 831.00
142 762.40 835.50
143 766.60 840.00
144 770.80 844.50
145 775.00 849.00
146 779.20 853.50
147 783.40 858.00
148 787.60 862.50149 791.80 867.00
150 796.00 871.50