28
State of the Power System Quarterly Update ‘Pre-Winter’ Brian Dames Chief Executive 25 February 2014

State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Embed Size (px)

Citation preview

Page 1: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

State of the Power System Quarterly Update ‘Pre-Winter’

Brian Dames

Chief Executive

25 February 2014

Page 2: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Key messages

Summer Overview

Pre-Winter Prognosis

Conclusion

2

Page 3: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Key messages

• The system remains tight

• The lights are being kept on at a high cost

• Three power emergency declarations were raised this summer, the first in November 2013

• Rotational load shedding was avoided due to the reductions in demand achieved by customers

• It will remain tight up to the end of Summer and throughout Winter, until the build programme delivers new capacity.

• As in 2013 maintenance will continue throughout the year and this could potentially increase the level of constraint.

• It remains important for customers to maintain or achieve 10% electricity savings especially in the commercial, industrial and residential sectors.

• Government officials, Eskom and large customers continue to meet weekly to manage the situation and collaborate on solutions.

• The build programme to bring online additional electricity capacity is making progress.

3

Page 4: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Electricity usage in Summer and Winter…

Sept-March – Spring/Summer

‘Live Lightly’

• Table Mountain profile

• Constrained all day incl. from 5 - 9pm

• Air-conditioning, geysers & pool pumps

primarily impact demand

• Commercial, agricultural & residential

customers can make the biggest

difference

April-Aug – Autumn/Winter

‘Beat the Peak’

• Peak profile

• Constrained from 5pm – 9pm

• Electrical heating, geysers, & pool

pumps primarily impact demand

• Residential customers can make the

biggest difference as demand

increases in the evenings

20 000

22 000

24 000

26 000

28 000

30 000

32 000

34 000

36 000

38 000

23:00 02:00 05:00 08:00 11:00 14:00 17:00 20:00 23:00 02:00

MW Summer & Winter load profiles

Typical Winter Day

Winter Peak Profile

Summer flat (Table Mountain profile)

4

Page 5: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Key messages

Summer Overview

Winter Prognosis

Conclusion

5

Page 6: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Summer Overview: leading up to the first system emergency

• This was a difficult Summer. Open cycle gas turbines and reduction

by contracted industrial customers were used to meet demand, at a high cost.

• Koeberg Unit 1 was on a planned re-fuel shutdown over this period. We could

not tolerate changes to the planned outage program of our nuclear unit, despite

the additional increase in the use of emergency reserves.

• A number of events within the national diesel fuel industry in November 2013

and increased usage resulted in reduced diesel availability, adding pressure on

the availability of emergency reserves.

• This resulted in the first System Emergency being declared on 19 November

2013 and lifted on 21 November 2013 - a difficult but necessary decision, to

avoid a total electricity system collapse.

• Increased Emergency Demand Market Participation and an Energy Buy-Back

of up to 1 000MW was requested to supplement depleted emergency reserves.

• Supply levers such as the short-term IPP program expired at the end of

December 2013, creating further pressure for 2014. 6

Page 7: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Summer Overview: 2014 System Emergencies

• In the week leading up to the 20th of February, there was an increase in unplanned

outages and the imports from Cahora Bassa were reduced due to a conductor failure.

• This required the various emergency reserves and the pumped-storage schemes to be

used extensively.

• A system emergency was declared for the evening peak of the 20th of February in line

with the normal regulatory protocols due to possible risks that could have materialized.

• We saw nearly 1 000MW of reductions from all the customers (industrial, commercial and

residential). Eskom also secured up to 280MW from those IPPs on the Short-Term

Power Purchase Programme.

• A system emergency was declared for the evening peak of the 21st of February as the

emergency reserves and dam levels were still at very low levels.

• The situation recovered over the weekend as imports were restored and 6 generation

units returned to service.

Despite the Emergency Declaration no rotational load shedding was done

thanks to immediate demand reduction by customers

7

Page 8: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Summer Overview (continued)

• A significant level of planned maintenance was conducted this Summer compared to previous years

• The tight system in January resulted in short-term delays in the maintenance programme, impacting the longer-term programme leading into Winter

0

2

4

6

8

10

12

14

16

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Maintenance progress (PCLF)

2012 2013 2014 (To-Date)

8

Page 9: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Generation challenges

• The Duvha coal conveyor belt that transports coal from the adjacent mine to the power station was damaged in December – resulting in significant coal supply challenges for the station, requiring output reduction and additional OCGT usage, thus limiting the opportunity for additional maintenance (short-term outages). Coal is temporarily being transported by trucks as a contingency.

• Increased boiler tube leaks were the prime reason behind generator outages. Outage slips and extensions have taken much longer than initially planned due to the state of the plant when opened up for inspection as well as some performance issues in execution.

• Partial output reduction continued to be a challenge. Hot days impacted the ability of some power stations, particularly Matimba, to generate at full output. This design issue had up to 1 000 MW impact at Matimba alone.

9

Page 10: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

January 2014 compared to January 2013

• During the day, load was on average 500 MW higher than last year due to the absence of energy buybacks in 2014 and the end of the short-term IPP programme.

• Despite the increased maintenance, this demand has been supplied though the extensive use of the OCGTs and increased levels of Demand Market Participation.

10

Page 11: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Increased Open Cycle Gas Turbine usage

A Megawatt of power produced by an OCGT plant costs approximately 16 to

18 times more (dependent on oil prices) than the equivalent produced by a

coal-fired power station

Based on 01 till 19 Feb 2014 data

11

Page 12: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Summer Overview continued

- Tight system leading to

emergency being declared on

19 November 2013 as well as

20 and 21 February 2014.

- Response by key industrial

customers and the general

public resulted in emergency

being lifted earlier than

planned on 21 November

2013.

- Improved response by key

industrial customers and the

general public resulted in the

system being managed back

into Orange on 20 and 21

February 2014 and assisted

with meeting the demand.

12

Page 13: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

0%

10%

20%

30%

40%

50%

60%

Jan

20

09

Feb

20

09

Mar

20

09

Ap

r 2

00

9M

ay 2

009

Jun

20

09

Jul 2

00

9A

ug

20

09

Sep

20

09

Oct

20

09

No

v 2

009

Dec

20

09Ja

n 2

01

0Fe

b 2

01

0M

ar 2

01

0A

pr

20

10

May

20

10Ju

n 2

01

0Ju

l 20

10

Au

g 2

01

0Se

p 2

01

0O

ct 2

01

0N

ov

201

0D

ec 2

010

Jan

20

11

Feb

20

11

Mar

20

11

Ap

r 2

01

1M

ay 2

011

Jun

20

11

Jul 2

01

1A

ug

20

11

Sep

20

11

Oct

20

11

No

v 2

01

1D

ec 2

011

Jan

20

12

Feb

20

12

Mar

20

12

Ap

r 2

01

2M

ay 2

012

Jun

20

12

Jul 2

01

2A

ug

20

12

Sep

20

12

Oct

20

12

No

v 2

012

Dec

20

12Ja

n 2

01

3Fe

b 2

01

3M

ar 2

01

3A

pr

20

13

May

20

13Ju

n 2

01

3Ju

l 20

13

Au

g 2

01

3Se

p 2

01

3O

ct 2

01

3N

ov

201

3D

ec 2

013

Jan

20

14

Feb

20

14

Ave

rage

Mo

nth

ly %

Act

ual

Re

serv

es

Monthly Avg at 06:00 Monthly Avg at 15:00 Monthly Avg at Peak Monthly Avg at 22:00

Created by Hendri Bower

Monthly average percentage available reserves

• While there was adequate reserve available throughout the day, there was very

little reserve available at peaks.

• The relative reserve levels available during the day are lower in summer.

Average at 22:00

Average at Peak

Average at 06:00

Average at 15:00

13

Page 14: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Coal stocks at sufficient levels

14

Actual Stock days F2008, F2012, F2013 vs YTD Actual F2014

25 25 22

20 19 18 17 18

15

12 13 13

40 39 39

36 38

41 41 44 43

41 39 39 38

39 40 42

43 44 45

47 47 48

49 47 48

51 50 51 52

54 56 55

48

0

10

20

30

40

50

60

APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

Sto

ck d

ays

Months

2007/8 2011/12 2012/13 2013/14

• Coal stock days are above the expected level of 42 days, with December ending on 48 days

• Stock days at power stations that are highly dependent on road deliveries like Camden,

Grootvlei, Komati and Tutuka have dropped below alarm levels in December mainly due to

mine and road deliveries stoppages over the festive period

• Duvha Power Station stock days have also dropped due to a section of the conveyor that was

damaged in a fire

14

Page 15: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Since inception in 2004, the IDM programme has established capacity (megawatts) equivalent to that of an average power station

0

500

1000

1500

2000

2500

3000

3500

4000

2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12 2012/13

Cumulative Demand Savings (MW)

2012/13

1 Power Station (6 x 600MW units)

2009/10

4 Units

2007/08

~2 units

2004/05

10% unit

15

Page 16: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Cross-border imports and exports

• Trading power with our neighbouring countries provides mutual benefit

• Export power brings in additional revenue and ensures regional stability

• Importing power assists with SA’s national capacity constraints

• During time of constraints these arrangements allow us to import more than we

export, thereby assisting South Africa to manage its security of supply.

• Imports include up to 1 500MW from Cahora Bassa and up to 107MW from

Aggreko in Mozambique.

• Export contracts with utilities are either firm or un-firm and range in total

between 1 000MW and1 800MW dependent on the national system status.

• Regular exports are made to Lesotho (firm), Swaziland (firm), Botswana (firm

and un-firm contracts) and Namibia (un-firm) and three end-use customers.

• Infrequent exports are made to Zimbabwe or Zambia when surplus is available.

16

Page 17: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Cross-border impact during an emergency

• During Eskom system emergencies the following applies to exports:

• All non-firm energy supplies are reduced to zero,

• All firm energy supplies are reduced by 10%,

• Trading Partners are required to enforce the 10% reduction on their customer

base,

• Trading Partners are required to utilize all their own generation capacity to the

maximum,

• Energy which may inadvertently be drawn out of the Eskom system is charged

at emergency generation rates,

• The interruptibility of the specific customer agreements is activated by

National Control as the system requires it.

17

Page 18: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Key messages

Summer Overview

Pre-Winter Prognosis

Conclusion

18

Page 19: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Outlook for pre-winter

• The system remains tight in the next few months leading into Winter. The

demand forecast assumes standard summer and winter temperatures.

• On the supply-side:

• Maintenance will continue at high levels based on the generation

sustainability strategy and to comply with legislation. Planned outages

vary between 5GW and 6GW up to April 2014, thereafter between 4GW

and 5GW and by June will ramp down between 2GW and 1.5GW

• Koeberg Unit 2 (900 MW) will be taken off load for planned refuelling at

the end of March 2014

• Positively, Cahora Bassa is back at full capacity – 1 500MW and is

expected to remain at this level

• Projected unplanned allowance of 6 500MW for the period January to March 2014 and 4 500MW for the period April to June 2014 is expected, resulting in an increased usage of OCGTs

• The utilisation of pre-commercial output from renewable IPPs is being investigated

19

Page 20: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Supply-side: Renewable IPPs gain momentum

• The Department of Energy introduced three bid windows for the Renewable Independent Power Purchase Programme

• Of the 19 Renewable IPPs connected to the grid, 3 projects (99 MW) have achieved their contractual Commercial Operation Date (COD) and 8 projects are generating Early Operating Energy. Expect the last project of Bid Window 1 by no later than the first half of 2015

Bid Date MW Power

Purchase

Agreements

Type of Technology Status

(As at 21 February 2014)

1 5 Nov. 2012 1416 28 Wind, Solar PV,

Solar CSP

- 19 of 28 connected

- 3 projects achieved

COD; 8 projects in

Early Operating

- Last plant commercial

expected by Feb 2015

2 9 May 2013 1044 19 Wind, Solar PV,

Solar CSP, Landfill &

Biomass

- Progressing well

3 - Bid Window

3 still to be

concluded

17 bidders for 1456 MW - Wind, Solar PV, Solar CSP, Landfill and

Biomass technology

20

Page 21: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Outlook for pre-winter continued

Demand-side

• 10% saving across all customer

sectors is critical until an energy

conservation scheme or similar is

introduced as a safety net

• Customers are asked to manage and

cut all electricity wastage. As we

head into winter, please remember

that less is more. The less electricity

you use, the more electricity will be

available to go around

Demand management continues to

work. We have achieved cumulative

savings of 35 TWh since 2005

21

Page 22: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Projected Pre-winter system outlook

• With the maintenance that needs to be done, and the available capacity, the system will remain tight with an increased use of OCGTs

• Supply and demand-side levers are required to improve the picture

• Because this shows the picture including OCGTs, it must be noted that the Red indicates a severely constrained system with no reserves.

• Decision on license agreements on Kriel PS expected in the latter part of March 2014

22

Page 23: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Continued Progress with New Build …

• Eskom is committed to completing the

new build programme and has put the

necessary resources in place to do so

• Work has resumed at Ingula pumped-

storage scheme after the safety incident

• Medupi and Kusile continue to

demonstrate world-class safety

performance (0.1 loss time incident rate).

Medupi’s first unit is still expected to be

synchronised in the second half of 2014

and Kusile’s first unit following a year

thereafter.

• The technical C&I issues at both Kusile

and Medupi are being addressed with the

on-boarding of Siemens.

23

Page 24: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Continued Progress with New Build

• Three of the 50 wind-turbines at Sere PS are complete and the station’s 100MW is expected to be commissioned by 2014/2015

• Transmission power line construction is progressing well, major sections of the power grid (Western Cape, Limpopo and Gauteng), have been strengthened, although challenges still remain in terms of servitude acquisition.

24

Page 25: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

How to Live Lightly and Beat the Peak

• Saving electricity reduces pressure on the grid and cuts your electricity bill and South Africa’s carbon emissions

• The power system remains vulnerable all day during Summer

1. Use air-conditioning efficiently

- Set air-conditioning at 23 degrees

- Close windows and doors to optimize air-conditioning

- Switch off 30 minutes before leaving the office

2. Continue to switch off all geysers and pool pumps from 5pm to 9pm

3. As we approach winter, use alternatives to electrical heating

4. Switch off all non-essential lighting and appliances

5. Respond to the Power Alert and Power Bulletin radio messages by switching off all appliances that are not being used

25

Page 26: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Key messages

Summer Overview

Pre-Winter Prognosis

Conclusion

26

Page 27: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

In support of

Conclusion

• The system remains tight going into Winter, and will remain so for the next few years until the build programme is completed

• With the projected demand and current trends in plant performance, extensive and expensive use of OCGTs is anticipated, resulting in limited operating reserves to deal with volatility in demand or generation performance.

• We call on all customers, particularly the municipalities and the commercial sectors, to manage and cut out all electricity wastage. The industrial and commercial sector can make significant contributions particularly in large office blocks and shopping centres.

• If this is done, it will ensure a stable power system and reduced costs

• We thank all our customers who continue to assist by reducing consumption.

27

Page 28: State of the Power System Quarterly Update - Eskom · PDF fileState of the Power System Quarterly Update ... • The Duvha coal conveyor belt that transports coal from the adjacent

Thank you