Page 1: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

TATACARA PROJEK SECARA TATACARA PROJEK SECARA

“DESIGN AND BUILD” “DESIGN AND BUILD”

DANDAN

“TURNKEY” “TURNKEY”

Page 2: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENGENALANPENGENALAN

KONSEP KONSEP

CIRICIRI--CIRI KONTRAKCIRI KONTRAK

TATACARA PEROLEHANTATACARA PEROLEHAN

PELAKSANAAN PROJEK SECARA RUNDING TERUS PELAKSANAAN PROJEK SECARA RUNDING TERUS

PERLAKSANAAN PROJEK SECARA TENDER TERBUKAPERLAKSANAAN PROJEK SECARA TENDER TERBUKA

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PENUTUPPENUTUP

BAHAGIAN 1

Page 3: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENGENALANPENGENALAN

SALAH SATU STRATEGI UTAMA PELAKSANAAN SALAH SATU STRATEGI UTAMA PELAKSANAAN

PROJEKPROJEK--PROJEK KERAJAANPROJEK KERAJAAN

Page 4: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

KONSEPKONSEP1. TAKRIF1. TAKRIF

REKABENTUK DAN BINAAN TERMASUK PENGAWASAN KERJA DI REKABENTUK DAN BINAAN TERMASUK PENGAWASAN KERJA DI

BAWAH TANGGUNGJAWAB KONTRAKTORBAWAH TANGGUNGJAWAB KONTRAKTOR

“DESIGN & BUILD”“DESIGN & BUILD”

•• MASIH ADA KELENGKAPAN/PERALATAN YANG PERLU MASIH ADA KELENGKAPAN/PERALATAN YANG PERLU

DISEDIAKAN SEBELUM OPERASI SEPENUHNYADISEDIAKAN SEBELUM OPERASI SEPENUHNYA

TURNKEYTURNKEY

•• SKOP KERJA MERANGKUMI PASANGAN SKOP KERJA MERANGKUMI PASANGAN

KELENGKAPAN/PERALATANKELENGKAPAN/PERALATAN

Page 5: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

KONSEPKONSEP

2.2. TANGGUNGJAWAB & LIABILITI KONTRAKTORTANGGUNGJAWAB & LIABILITI KONTRAKTOR

BERTANGGUNGJAWAB SEPENUHNYA TERHADAP:BERTANGGUNGJAWAB SEPENUHNYA TERHADAP:

–– PENYIASATAN TAPAKPENYIASATAN TAPAK

–– REKABENTUKREKABENTUK

–– PEMBINAANPEMBINAAN

–– PENYELIAANPENYELIAAN

–– PENYIAPANPENYIAPAN

–– PENYELENGGARAANPENYELENGGARAAN

–– SEGALA YANG PERLU SEBAGAIMANA KEHENDAK KERAJAAN SEGALA YANG PERLU SEBAGAIMANA KEHENDAK KERAJAAN DAN KONTRAKDAN KONTRAK

Page 6: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAK

ASAS HARGA KONTRAKASAS HARGA KONTRAK

HARGA TETAP JUMLAH WANG PUKALHARGA TETAP JUMLAH WANG PUKAL

BAGI ITEM YANG TIDAK TENTU SKOP ATAU TIDAK WAJAR BAGI ITEM YANG TIDAK TENTU SKOP ATAU TIDAK WAJAR UNTUK MEMBEBANKAN MANAUNTUK MEMBEBANKAN MANA--MANA PIHAK DENGAN RISIKO MANA PIHAK DENGAN RISIKO KUANTITI MAKA WANG PERUNTUKAN SEMENTARA ATAU KUANTITI MAKA WANG PERUNTUKAN SEMENTARA ATAU KUANTITI SEMENTARA BOLEH DI PERUNTUKANKUANTITI SEMENTARA BOLEH DI PERUNTUKAN

SYARATSYARAT--SYARAT KONTRAKSYARAT KONTRAK

SYARATSYARAT--SYARAT KONTRAK STANDARDSYARAT KONTRAK STANDARD

IAITU DESIGN AND BUILD/TURNKEY IAITU BORANG JKR DB/TIAITU DESIGN AND BUILD/TURNKEY IAITU BORANG JKR DB/T

Page 7: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAKBON PELAKSANAANBON PELAKSANAAN

JAMINAN BANK 5% DARIPADA HARGA KONTRAK JAMINAN BANK 5% DARIPADA HARGA KONTRAK BERKUASA SEHINGGA DUA BELAS (12) BULAN SELEPAS BERKUASA SEHINGGA DUA BELAS (12) BULAN SELEPAS TARIKH TAMAT TEMPOH TANGGUNGAN KECACATANTARIKH TAMAT TEMPOH TANGGUNGAN KECACATAN

JAMINAN REKABENTUKJAMINAN REKABENTUK

JAMINAN BANK YANG NILAINYA DITETAPKAN MENGIKUT JAMINAN BANK YANG NILAINYA DITETAPKAN MENGIKUT JADUAL. BERKUATKUASA SELAMA LIMA (5) TAHUN DARI JADUAL. BERKUATKUASA SELAMA LIMA (5) TAHUN DARI TARIKH SIAP KERJA (PRACTICAL COMPLETION) WALAU TARIKH SIAP KERJA (PRACTICAL COMPLETION) WALAU BAGAIMANAPUN KERAJAAN TELAH MEMBATALKAN BAGAIMANAPUN KERAJAAN TELAH MEMBATALKAN SYARATSYARAT--SYARAT INISYARAT INI

Page 8: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAK

WANG TAHANANWANG TAHANANSELARAS DENGAN AP 200.3(A) WANG TAHANAN SELARAS DENGAN AP 200.3(A) WANG TAHANAN DIBATALKANDIBATALKAN

TEMPOH TANGGUNGAN KECACATAN (TTK)TEMPOH TANGGUNGAN KECACATAN (TTK)TTK. TIDAK KURANG DARI DUA (2) TAHUN TTK. TIDAK KURANG DARI DUA (2) TAHUN BERMULA DARI PADA TARIKH SIAP KERJA YANG BERMULA DARI PADA TARIKH SIAP KERJA YANG DINYATAKAN DALAM PERAKUAN SIAP KERJADINYATAKAN DALAM PERAKUAN SIAP KERJA

Page 9: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENYELENGGARAAN SELEPAS PENYIAPANPENYELENGGARAAN SELEPAS PENYIAPAN

MENYELENGGARA DALAM TEMPOH (2) MENYELENGGARA DALAM TEMPOH (2) TAHUN PERTAMA SERENTAK DENGAN TTK.TAHUN PERTAMA SERENTAK DENGAN TTK.

SKOP KERJA PENYELENGGARAAN PERLU SKOP KERJA PENYELENGGARAAN PERLU DIJELASKAN DAN HARGA TERPERINCI DIJELASKAN DAN HARGA TERPERINCI DIMASUKKAN DALAM HARGA KONTRAKDIMASUKKAN DALAM HARGA KONTRAK

CIRICIRI--CIRI KONTRAKCIRI KONTRAK

Page 10: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAK∞∞ PENYELENGGARAAN SELEPAS PENYIAPANPENYELENGGARAAN SELEPAS PENYIAPAN

BAGI TEMPOH TIGA (3) TAHUN BERIKUTNYA BAGI TEMPOH TIGA (3) TAHUN BERIKUTNYA KONTRAKTOR YANG SAMA BOLEH DILANTIK KONTRAKTOR YANG SAMA BOLEH DILANTIK UNTUK MENJALANKAN KERJAUNTUK MENJALANKAN KERJA--KERJA KERJA PENYELENGGARAAN UNTUK MEMASTIKAN PENYELENGGARAAN UNTUK MEMASTIKAN LIABILITI KONTRAKTOR TIDAK TERJEJAS.LIABILITI KONTRAKTOR TIDAK TERJEJAS.

KONTRAK YANG BERASINGAN PERLU KONTRAK YANG BERASINGAN PERLU DIRUNDINGKAN KERANA PEMBIAYAAN INI DIRUNDINGKAN KERANA PEMBIAYAAN INI DARIPADA PERUNTUKAN PENYELENGGARAANDARIPADA PERUNTUKAN PENYELENGGARAAN

Page 11: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAKDASAR KERAJAANDASAR KERAJAAN

BEBERAPA DASAR KERAJAAN PERLU DIMASUKKAN DALAM SYARATBEBERAPA DASAR KERAJAAN PERLU DIMASUKKAN DALAM SYARAT--SYARAT SYARAT KONTRAK ATAU KEHENDAK AM.KONTRAK ATAU KEHENDAK AM.

PENGGUNAAN BARANGPENGGUNAAN BARANG--BARANG TEMPATANBARANG TEMPATANKUMPULAN IKRAM QAS SDN. BHD (KISB)KUMPULAN IKRAM QAS SDN. BHD (KISB)SIRIM QAS SDN. BHDSIRIM QAS SDN. BHD

PERLANTIKAN JURUPERUNDING (JP.)PERLANTIKAN JURUPERUNDING (JP.)

JP. BEBAS (NOT INJP. BEBAS (NOT IN--HOUSE)HOUSE)PERLU KELULUSAN JABATANPERLU KELULUSAN JABATANBAYARAN TERUS KEPADA JP. TEMPATAN YANG BERDAFTAR DENGAN BAYARAN TERUS KEPADA JP. TEMPATAN YANG BERDAFTAR DENGAN KEMENTERIAN KEWANGAN, JP. DAN LEMBAGA PROPESIONALKEMENTERIAN KEWANGAN, JP. DAN LEMBAGA PROPESIONALJP. YANG SAMA MENYELIAKAN PROJEKJP. YANG SAMA MENYELIAKAN PROJEKINSURAN UNTUK JP.INSURAN UNTUK JP.

Page 12: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAKDASAR KERAJAAN DASAR KERAJAAN ((sambsamb.).)

PENYERTAAN KONTRAKTOR BUMIPUTERAPENYERTAAN KONTRAKTOR BUMIPUTERA

MEMASTIKAN PENGLIBATAN 30% SYARIKAT BUMIPUTERA MEMASTIKAN PENGLIBATAN 30% SYARIKAT BUMIPUTERA BAGI MELAKSANAKAN KERJA/BEKALAN/ PERKHIDMATAN BAGI MELAKSANAKAN KERJA/BEKALAN/ PERKHIDMATAN SECARA SUBSECARA SUB--KONTRAKKONTRAK

SYARIKAT PERLU BERDAFTAR DENGAN SYARIKAT PERLU BERDAFTAR DENGAN LPIP/PKK/PERBENDAHARAANLPIP/PKK/PERBENDAHARAAN

MENYENARAIKAN KERJAMENYENARAIKAN KERJA--KERJA YANG AKAN KERJA YANG AKAN DISUBKONTRAKKAN KEPADA SYARIKAT BUMIPUTARADISUBKONTRAKKAN KEPADA SYARIKAT BUMIPUTARA

Page 13: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

CIRICIRI--CIRI KONTRAKCIRI KONTRAKDASAR KERAJAAN DASAR KERAJAAN ((sambsamb.).)

PEROLEHAN, PENGANGKUTAN DAN INSURANS BAGI PEROLEHAN, PENGANGKUTAN DAN INSURANS BAGI BAHANBAHAN--BAHAN, LOGI, PERALATAN DAN KENDERAAN YANG BAHAN, LOGI, PERALATAN DAN KENDERAAN YANG DIIMPORT DIIMPORT

IMPORT TERUS DARIPADA NEGARA ASAL BARANGAN IMPORT TERUS DARIPADA NEGARA ASAL BARANGAN TERSEBUT SECARA F.O.B.TERSEBUT SECARA F.O.B.

MENGGUNAKAN MULTIMODAL TRANSPORT OPERATOR MENGGUNAKAN MULTIMODAL TRANSPORT OPERATOR (MTO) YANG DILULUSKAN OLEH KERAJAAN(MTO) YANG DILULUSKAN OLEH KERAJAAN

KONTRAKTOR PERLU MENGEMUKAKAN BUKTI KEPADA KONTRAKTOR PERLU MENGEMUKAKAN BUKTI KEPADA PENGARAH PROJEK (PROJECT DIRECTOR) BAHAWA PENGARAH PROJEK (PROJECT DIRECTOR) BAHAWA PERATURAN DI ATAS TELAH DIPATUHI JIKA TIDAK PERATURAN DI ATAS TELAH DIPATUHI JIKA TIDAK PENALTI AKAN DKENAKANPENALTI AKAN DKENAKAN

Page 14: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

TATACARA PEROLEHANTATACARA PEROLEHANPEMANGGILAN TENDERPEMANGGILAN TENDER

TERBUKA/TERHAD TERBUKA/TERHAD –– TempohTempoh mentendermentender 22--3 3

bulanbulan

RUNDINGAN TERUSRUNDINGAN TERUS

Page 15: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUS

ASAS HARGA KONTRAKASAS HARGA KONTRAK

BERASASKAN HARGA SILING YANG TERTAKLUK BERASASKAN HARGA SILING YANG TERTAKLUK KEPADA PENILAIAN/PENGUKURAN SEMULAKEPADA PENILAIAN/PENGUKURAN SEMULA

JIKA PENILAIAN SEMULA KURANG DARIPADA SILING MAKA JIKA PENILAIAN SEMULA KURANG DARIPADA SILING MAKA PENJIMATAN AKAN DIBERI KEPADA KERAJAAN DAN PENJIMATAN AKAN DIBERI KEPADA KERAJAAN DAN HARGA KONTRAK AKAN DIKURANGKAN SEWAJARNYAHARGA KONTRAK AKAN DIKURANGKAN SEWAJARNYA

Page 16: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUS

PROSES PELAWAAN/CADANGAN TENDERPROSES PELAWAAN/CADANGAN TENDER

PERMOHONAN DAN KELULUSANPERMOHONAN DAN KELULUSAN

-- PERLU DAPATKAN KELULUSAN KEMENTERIAN KEWANGANPERLU DAPATKAN KELULUSAN KEMENTERIAN KEWANGAN

SURAT NIATSURAT NIAT

-- SURAT NIAT HENDAKLAH DIKELUARKAN KEPADA SURAT NIAT HENDAKLAH DIKELUARKAN KEPADA KONTRAKTOR TERPILIH. SURAT INI MENGANDUNGI:KONTRAKTOR TERPILIH. SURAT INI MENGANDUNGI:

HASRAT KERAJAANHASRAT KERAJAAN

SYARATSYARAT--SYARAT YANG DITETAPKANSYARAT YANG DITETAPKAN

KONTRAKTOR DIMINTA KEMUKAKAN CADANGANKONTRAKTOR DIMINTA KEMUKAKAN CADANGAN

SEBAIKSEBAIK--BAIKNYA DOKUMEN PRABAIKNYA DOKUMEN PRA--TAWARAN DISEDIAKAN DAN TAWARAN DISEDIAKAN DAN DISERTAKAN KEPADA KONTRAKTOR BERSAMA DENGAN SURAT NIATDISERTAKAN KEPADA KONTRAKTOR BERSAMA DENGAN SURAT NIAT

Page 17: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUS

PREPRE--BID BRIEFINGBID BRIEFING

PELAKSANAANPELAKSANAANJIKA PROJEK KOMPLEKSJIKA PROJEK KOMPLEKS

LAWATAN TAPAK PERLU DIATURLAWATAN TAPAK PERLU DIATUR

TEMPOH MENTENDERTEMPOH MENTENDERAMNYA 1 HINGGA 3 BULANAMNYA 1 HINGGA 3 BULAN

Page 18: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUS

PROSES PENILAIAN, PERUNDINGAN DAN PENERIMAANPROSES PENILAIAN, PERUNDINGAN DAN PENERIMAAN

PROSES PENILAIANPROSES PENILAIAN

PENERIMAAN CADANGAN DAN TAKLIMAT OLEH PENERIMAAN CADANGAN DAN TAKLIMAT OLEH KONTRAKTORKONTRAKTOR

PENILAIAN KONTRAKTUAL DAN TEKNIKALPENILAIAN KONTRAKTUAL DAN TEKNIKAL

PENILAIAN HARGAPENILAIAN HARGA

SYARATSYARAT--SYARAT TAMBAHANSYARAT TAMBAHAN

LAPORAN PENILAIAN TENDER UNTUK JAWATANKUASA LAPORAN PENILAIAN TENDER UNTUK JAWATANKUASA RUNDINGAN HARGARUNDINGAN HARGA

Page 19: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUS

RUNDINGAN HARGARUNDINGAN HARGA

JAWATANKUASA RUNDINGAN HARGAJAWATANKUASA RUNDINGAN HARGA

TEMPOH PENYIAPAN PROJEKTEMPOH PENYIAPAN PROJEK

SYARATSYARAT--SYARAT TAMBAHANSYARAT TAMBAHAN

Page 20: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN SECARA RUNDINGAN TERUSPELAKSANAAN SECARA RUNDINGAN TERUSKELULUSAN KEMENTERIAN KEWANGAN DAN PENGELUARAN KELULUSAN KEMENTERIAN KEWANGAN DAN PENGELUARAN SURAT SETUJUTERIMASURAT SETUJUTERIMA

HASIL RUNDINGAN DILAPOR KE KEMENTERIAN KEWANGAN UNTUK HASIL RUNDINGAN DILAPOR KE KEMENTERIAN KEWANGAN UNTUK KELULUSANKELULUSAN

SURAT SETUJUTERIMA DIKELUARKAN SETELAH DILULUSKAN SURAT SETUJUTERIMA DIKELUARKAN SETELAH DILULUSKAN KEMENTERIAN KEWANGANKEMENTERIAN KEWANGAN

JIKA KEPUTUSAN BERBEZA DENGAN PERAKUAN JABATAN MAKA SATU JIKA KEPUTUSAN BERBEZA DENGAN PERAKUAN JABATAN MAKA SATU SURAT NIAT HENDAKLAH DIKELUARKAN UNTUK MENDAPATKAN SURAT NIAT HENDAKLAH DIKELUARKAN UNTUK MENDAPATKAN PERSETUJUANPERSETUJUAN

Page 21: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENYEDIAN DOKUMEN PRAPENYEDIAN DOKUMEN PRA--TAWARAN TAWARAN (PREBID)(PREBID)

VOLUME 1 VOLUME 1 –– CONTRACTUAL & GENERAL REQUIREMENTCONTRACTUAL & GENERAL REQUIREMENTINSTRUCTION TO TENDERER INCLUDING CRITERIA FOR INSTRUCTION TO TENDERER INCLUDING CRITERIA FOR APPOINTMENT OF CONSULTANTAPPOINTMENT OF CONSULTANTCONTRACTUAL & GENERAL REQUIREMENTSCONTRACTUAL & GENERAL REQUIREMENTSFORM OF TENDERFORM OF TENDERCONDITIONS OF CONTRACT INCLUDING ARTICLES OF CONDITIONS OF CONTRACT INCLUDING ARTICLES OF AGREEMENTAGREEMENT

Page 22: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENYEDIAN DOKUMEN PRAPENYEDIAN DOKUMEN PRA--TAWARAN TAWARAN (PREBID)(PREBID)

APPENDICES:APPENDICES:APPENDIX 1 APPENDIX 1 –– APPENDIX TO THE CONDITIONS OF CONTRACTAPPENDIX TO THE CONDITIONS OF CONTRACTAPPENDIX 2 APPENDIX 2 –– SCHEDULE OF PAYMENTSCHEDULE OF PAYMENTAPPENDIX 3 APPENDIX 3 –– GOVERNMENT REQUIREMENTSGOVERNMENT REQUIREMENTSAPPENDIX 4 APPENDIX 4 –– CONTRACTOR’S PROPOSALCONTRACTOR’S PROPOSALAPPENDIX 5 APPENDIX 5 –– TENDER SUM ANALYSISTENDER SUM ANALYSISAPPENDIX 6 APPENDIX 6 -- CONTRACT SCHEDULE OF RATESCONTRACT SCHEDULE OF RATESAPPENDIX 7 APPENDIX 7 –– FORM OF BANK GUARANTEE FORFORM OF BANK GUARANTEE FOR

PERFORMANCE BOND AND ADVANCE PAYMENTPERFORMANCE BOND AND ADVANCE PAYMENTAPPENDIX 8 APPENDIX 8 –– LIST OF LIST OF MULTIMODAL TRANSPORT MULTIMODAL TRANSPORT

OPERATOR (MTO)OPERATOR (MTO)FORM FOR FINANCIAL STANDING AND TECHNICAL BACKGROUNDFORM FOR FINANCIAL STANDING AND TECHNICAL BACKGROUNDSTANDARD FORM OF AGREEMENT FOR CONSULTANCY SERVICESTANDARD FORM OF AGREEMENT FOR CONSULTANCY SERVICE

Page 23: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENYEDIAN DOKUMEN PRAPENYEDIAN DOKUMEN PRA--TAWARAN TAWARAN (PREBID)(PREBID)

VOLUME 2 VOLUME 2 –– TECHNICAL REQUIREMENTS (CIVIL WORK)TECHNICAL REQUIREMENTS (CIVIL WORK)

BRIDGESBRIDGESPAVEMENTSPAVEMENTSPIPEPIPE

Page 24: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PENYEDIAN DOKUMEN PRAPENYEDIAN DOKUMEN PRA--TAWARAN TAWARAN (PREBID)(PREBID)

VOLUME 2 VOLUME 2 –– TECHNICAL REQUIREMENTS (BUILDING)TECHNICAL REQUIREMENTS (BUILDING)

PART 1 PART 1 -- ARCHITECTUAL WORKSARCHITECTUAL WORKSPART 2 PART 2 -- CIVIL AND STRUCTURAL WORKSCIVIL AND STRUCTURAL WORKSPART 3 PART 3 -- MECHANICAL SERVICESMECHANICAL SERVICESPART 4 PART 4 -- ELECTRICAL SERVICESELECTRICAL SERVICES

Page 25: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PERLAKSANAAN TENDER SECARA TENDER PERLAKSANAAN TENDER SECARA TENDER TERBUKA/TERHADTERBUKA/TERHAD

PENILAIAN DAN SETUJUTERIMA TENDERPENILAIAN DAN SETUJUTERIMA TENDER

JAWATANKUASA PENILAIAN TENDERJAWATANKUASA PENILAIAN TENDERJAWATANKUASA PENILAIAN TEKNIKALJAWATANKUASA PENILAIAN TEKNIKAL

MenjalankanMenjalankan analisaanalisa terhadapterhadap cadangancadangan pentenderpentender dan dan memastikanmemastikan pematuhanpematuhan kehendakkehendak--kehendakkehendak teknikal teknikal

JAWATANKUASA PENILAIAN HARGAJAWATANKUASA PENILAIAN HARGA

MenjalankanMenjalankan analisaanalisa terhadapterhadap cadangancadangan pentenderpentender dan dan memastikanmemastikan pematuhanpematuhan kehendakkehendak--kehendakkehendak kontraktualkontraktualdan dan penilaianpenilaian kemunasabahankemunasabahan hargaharga

Page 26: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PERLAKSANAAN TENDER SECARA TENDER PERLAKSANAAN TENDER SECARA TENDER TERBUKA/TERHADTERBUKA/TERHAD

PENILAIAN DAN SETUJUTERIMA TENDERPENILAIAN DAN SETUJUTERIMA TENDER

PROSES PENILAIAN TENDERPROSES PENILAIAN TENDERPENILAIAN PERINGKAT PERTAMA PENILAIAN PERINGKAT PERTAMA –– PENILAIAN AWALPENILAIAN AWALPENILAIAN PERINGKAT KEDUA PENILAIAN PERINGKAT KEDUA –– PENILAIAN DARI SEGI PENILAIAN DARI SEGI KONTRAKTUAL DAN KEUPAYAAN BIAYAYAANKONTRAKTUAL DAN KEUPAYAAN BIAYAYAANPENILAIAN PERINGKAT KETIGA PENILAIAN PERINGKAT KETIGA –– PENILAIAN TEKNIKALPENILAIAN TEKNIKAL

Page 27: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

MESYUARAT PENJELASAN TENDERMESYUARAT PENJELASAN TENDERTEKNIKAL KURANG JELAS DAN SENARAI PERTANYAANTEKNIKAL KURANG JELAS DAN SENARAI PERTANYAANMESYUARAT PENJELASAN DIADAKANMESYUARAT PENJELASAN DIADAKANMINIT MESYUARAT DESEDIAKANMINIT MESYUARAT DESEDIAKANUBAHSUAI/PENINGKATAN DINYATAKAN DALAM UBAHSUAI/PENINGKATAN DINYATAKAN DALAM LAPORAN TENDERLAPORAN TENDER

LAPORAN PENILAIAN TENDER & PERAKUAN TENDERLAPORAN PENILAIAN TENDER & PERAKUAN TENDERLAPORAN TENDERLAPORAN TENDERPENTENDER YANG DIPERAKUPENTENDER YANG DIPERAKULEMBAGA PEROLEHANLEMBAGA PEROLEHAN

PERLAKSANAAN TENDER SECARA TENDER PERLAKSANAAN TENDER SECARA TENDER TERBUKA/TERHADTERBUKA/TERHAD

PENILAIAN DAN SETUJUTERIMA TENDERPENILAIAN DAN SETUJUTERIMA TENDER

Page 28: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PERLAKSANAAN TENDER SECARA TENDER PERLAKSANAAN TENDER SECARA TENDER TERBUKA/TERHADTERBUKA/TERHAD

PENILAIAN DAN SETUJUTERIMA TENDERPENILAIAN DAN SETUJUTERIMA TENDER

SETUJUTERIMA TENDERSETUJUTERIMA TENDERSURAT NIATSURAT NIATMESYUARAT PENJELASAN PRA AWARDMESYUARAT PENJELASAN PRA AWARDMINIT MESYUARAT DESEDIAKAN DAN DISAHKANMINIT MESYUARAT DESEDIAKAN DAN DISAHKANCADANGAN LAIN DENGAN TAMBAHAN KOS PERLU DIPERAKU CADANGAN LAIN DENGAN TAMBAHAN KOS PERLU DIPERAKU SEMULA KEPADA LEMBAGA PEROLEHANSEMULA KEPADA LEMBAGA PEROLEHAN

SURAT SETUJUTERIMA TENDERSURAT SETUJUTERIMA TENDERFORMAT PIAWAIFORMAT PIAWAIMENGANDUNGI RUJUKAN MINIT MESYUARAT PENJELASAN MENGANDUNGI RUJUKAN MINIT MESYUARAT PENJELASAN TENDER DAN PRA AWARD DAN LAINTENDER DAN PRA AWARD DAN LAIN--LAINLAIN

Page 29: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PENYEDIAAN DOKUMEN KONTRAKPENYEDIAAN DOKUMEN KONTRAKDISEDIAKAN OLEH KONTRAKTOR DAN DISEMAK OLEH DISEDIAKAN OLEH KONTRAKTOR DAN DISEMAK OLEH JABATAN SEBELUM DITANDATANGANIJABATAN SEBELUM DITANDATANGANI

PENYEDIAAN LUKISAN TERPERINCIPENYEDIAAN LUKISAN TERPERINCIPENYEDIAAN LUKISAN TERPERINCI BOLEH PENYEDIAAN LUKISAN TERPERINCI BOLEH DITERUSKAN DAN HENDAKLAH DISEDIAKAN OLEH DITERUSKAN DAN HENDAKLAH DISEDIAKAN OLEH JURUTERA/AKITEK PROFESIONALJURUTERA/AKITEK PROFESIONALHENDAKLAH DIKEMUKAKAN KEPADA JABATAN UNTUK HENDAKLAH DIKEMUKAKAN KEPADA JABATAN UNTUK PERSETUJUAN BERSAMA SEBELUM MULA KERJAPERSETUJUAN BERSAMA SEBELUM MULA KERJALUKISANLUKISAN--LUKISAN HENDAKLAH DIJILID DAN DISERAHKAN LUKISAN HENDAKLAH DIJILID DAN DISERAHKAN KEPADA JABATAN UNTUK RUJUKAN DAN SIMPANANKEPADA JABATAN UNTUK RUJUKAN DAN SIMPANAN

Page 30: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PENGAWASAN KERJAPENGAWASAN KERJA

KERJAKERJA--KERJA DIAWASI OLEH JURUPERUNDING YANG SAMA KERJA DIAWASI OLEH JURUPERUNDING YANG SAMA YANG TELAH MENYEDIAKAN REKABENTUKYANG TELAH MENYEDIAKAN REKABENTUK

JABATAN TIDAK MENYEDIAKAN “STANDING SUPERVISION”. JABATAN TIDAK MENYEDIAKAN “STANDING SUPERVISION”. BAGI PROJEK BESAR, P.D. PERLU MELANTIK SEORANG BAGI PROJEK BESAR, P.D. PERLU MELANTIK SEORANG PEMERHATI UNTUK MEREKODKAN SEBARANG KERJAPEMERHATI UNTUK MEREKODKAN SEBARANG KERJA--KERJA KERJA YANG TIDAK MEMATUHI KONTRAK DAN MELAPORKAN YANG TIDAK MEMATUHI KONTRAK DAN MELAPORKAN KEPADA P.D.KEPADA P.D.

Page 31: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

MESYUARATMESYUARAT

MESYUARAT KORDINASI BAGI PROJEK YANG TERDAPAT MESYUARAT KORDINASI BAGI PROJEK YANG TERDAPAT BANYAK LOKASI TAPAK KERJA.BANYAK LOKASI TAPAK KERJA.

MESYUARAT TAPAK DIADAKAN SEBULAN SEKALI DAN MESYUARAT TAPAK DIADAKAN SEBULAN SEKALI DAN PEMERIKSAAN TAPAK AKAN DILAKUKAN OLEH JABATAN PEMERIKSAAN TAPAK AKAN DILAKUKAN OLEH JABATAN SEBELUM MESYUARAT INI. KONTRAKTOR PERLU SEDIAKAN:SEBELUM MESYUARAT INI. KONTRAKTOR PERLU SEDIAKAN:

LAPORAN KEMAJUAN KERJA YANG TERPERINCI I.E. BAR CHART LAPORAN KEMAJUAN KERJA YANG TERPERINCI I.E. BAR CHART ‘S’ CURVE, FOTO, LAPORAN CUACA , ISU‘S’ CURVE, FOTO, LAPORAN CUACA , ISU--ISU BERBANGKIT DAN ISU BERBANGKIT DAN LAINLAIN--LAINLAINLAPORAN JAMINAN KUALITI i.e. NONLAPORAN JAMINAN KUALITI i.e. NON--PERFORMANCE STANDARDPERFORMANCE STANDARDLAPORAN KELULUSAN DARIPADA PIHAK BERKUASA TEMPATANLAPORAN KELULUSAN DARIPADA PIHAK BERKUASA TEMPATAN

Page 32: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

BAYARAN INTERIMBAYARAN INTERIM

BAYARAN BERJADUALBAYARAN BERJADUALSyaratSyarat--syaratsyarat terdahuluterdahulu sebelumsebelum bayaranbayaran pertamapertamaPenilaianPenilaian kemajuankemajuan kerjakerja dan dan pelarasanpelarasan kepada kepada jadualjadualbayaranbayaran

SETIAP ENAM BULANSETIAP ENAM BULANPERBEZAAN NILAI KERJA DAN BAYARAN DIJADUALKAN TIDAK LEBIH PERBEZAAN NILAI KERJA DAN BAYARAN DIJADUALKAN TIDAK LEBIH 25% DARIPADA HARGA KONTRAK25% DARIPADA HARGA KONTRAK

PENILAIAN KERJA DITAPAK BINA SETIAP BULAN PENILAIAN KERJA DITAPAK BINA SETIAP BULAN SyaratSyarat--syaratsyarat terdahuluterdahulu sebelumsebelum bayaranbayaran pertamapertama

Page 33: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

UJIAN DAN UJILARIUJIAN DAN UJILARI

DIJALANKAN SECARA IN DIJALANKAN SECARA IN -- HOUSEHOUSEKEPUTUSAN DISAHKAN OLEH JURUTERA KEPUTUSAN DISAHKAN OLEH JURUTERA PROFESIONALPROFESIONALDIKEMUKAKAN KEPADA PENGARAH PROJEKDIKEMUKAKAN KEPADA PENGARAH PROJEK

Page 34: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PEMERIKSAAN BERSAMAPEMERIKSAAN BERSAMA

UNTUK MEMBOLEHKAN PERAKUAN SIAP KERJA UNTUK MEMBOLEHKAN PERAKUAN SIAP KERJA DIKELUARKANDIKELUARKANDUA SENARAI DIKELUARKANDUA SENARAI DIKELUARKAN

SENARAI KERJA BELUM SIAPSENARAI KERJA BELUM SIAPSENARAI KERJASENARAI KERJA--KERJA KECACATANKERJA KECACATAN

Page 35: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PENYIAPAN PROJEKPENYIAPAN PROJEK

KERJAKERJA--KERJA BELUM SIAP ADALAH KECIL DAN KERJA BELUM SIAP ADALAH KECIL DAN PROJEK BOLEH BEROPERASIPROJEK BOLEH BEROPERASI

SENARAI KERJA BELUM SIAP DAN KECACATAN SENARAI KERJA BELUM SIAP DAN KECACATAN DILAMPIRKAN KEPADA PERAKUAN SIAP KERJADILAMPIRKAN KEPADA PERAKUAN SIAP KERJA

Page 36: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PERLAKSANAAN KONTRAKPERLAKSANAAN KONTRAK

PENYELENGGARAAN DI BAWAH KONTRAK MEMBAIKI PENYELENGGARAAN DI BAWAH KONTRAK MEMBAIKI KECACATANKECACATAN

TEMPOH TANGGUNGAN KECACATAN DAN PENYELENGGARAAN TEMPOH TANGGUNGAN KECACATAN DAN PENYELENGGARAAN BERMULABERMULA

DUA JENIS PENYELENGGARAANDUA JENIS PENYELENGGARAAN

BERJADUALBERJADUAL

KEROSAKANKEROSAKAN

KERJAKERJA--KERJA PENYELENGGARAAN MENGIKUT JADUALKERJA PENYELENGGARAAN MENGIKUT JADUAL

KLIEN PERLU ISI BORANG LAPORAN KEROSAKAN DAN BILA KLIEN PERLU ISI BORANG LAPORAN KEROSAKAN DAN BILA KEROSAKAN DIBAIKI KLIEN PERLU TANDATANGAN BORANG KEROSAKAN DIBAIKI KLIEN PERLU TANDATANGAN BORANG YANG SAMAYANG SAMA

Page 37: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAKPENYELENGGARAAN DI BAWAH KONTRAK PENYELENGGARAAN DI BAWAH KONTRAK ((sambsamb.).)

KONTRAKTOR SEDIA LAPORAN PENYELENGGARAAN SETIAP BULANKONTRAKTOR SEDIA LAPORAN PENYELENGGARAAN SETIAP BULAN

BAYARAN UNTUK KERJABAYARAN UNTUK KERJA--KERJA PENYELENGGARAAN MENGIKUT KERJA PENYELENGGARAAN MENGIKUT JADUAL YANG TELAH DIPERSETUJUIJADUAL YANG TELAH DIPERSETUJUI

PEMERIKSAAN AKHIR PERLU UNTUK MENYEMAK SEMUA KERJAPEMERIKSAAN AKHIR PERLU UNTUK MENYEMAK SEMUA KERJA--KERJA KECACATAN YANG TELAH DIBAIKIKERJA KECACATAN YANG TELAH DIBAIKI

SENARAI PERTAMA KECACATAN DALAM TEMPOH 14 HARI DAN SENARAI PERTAMA KECACATAN DALAM TEMPOH 14 HARI DAN SENARAI AKHIR DALAM TEMPOH 28 HARI SELEPAS TTKSENARAI AKHIR DALAM TEMPOH 28 HARI SELEPAS TTK

TEMPOH BAIKI KECACATAN 3 BULANTEMPOH BAIKI KECACATAN 3 BULAN

PENGELUARAN PERAKUAN SIAP MEMPERBAIKI KECACATAN (PSMK) PENGELUARAN PERAKUAN SIAP MEMPERBAIKI KECACATAN (PSMK) SETELAH SEMUA KECACATAN DIBAIKISETELAH SEMUA KECACATAN DIBAIKI

Page 38: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PERUBAHAN KERJA/PERAKUAN MUKTAMADPERUBAHAN KERJA/PERAKUAN MUKTAMAD

PERUBAHAN KERJA (PK)PERUBAHAN KERJA (PK)KEDUAKEDUA--DUA PIHAK MEMPUNYAI HAK UNTUK DUA PIHAK MEMPUNYAI HAK UNTUK MEMBUAT PINDAANMEMBUAT PINDAAN

PENYEDIAAN DAN KELULUSAN PK. ADALAH MENGIKUT PENYEDIAAN DAN KELULUSAN PK. ADALAH MENGIKUT PERATURAN SEMASAPERATURAN SEMASA

Page 39: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PERUBAHAN KERJA/PERAKUAN MUKTAMAD (PERUBAHAN KERJA/PERAKUAN MUKTAMAD (SambSamb.).)

PERAKUAN MUKTAMAD (PM)PERAKUAN MUKTAMAD (PM)

KONTRAKTOR PERLU KEMUKAKAN PM. DALAM TEMPOH KONTRAKTOR PERLU KEMUKAKAN PM. DALAM TEMPOH 3 BULAN SELEPAS PSMK.3 BULAN SELEPAS PSMK.

PP PERLU KELUAR PM SELEPAS 3 BULAN PP PERLU KELUAR PM SELEPAS 3 BULAN

JIKA KONTRAKTOR LEWAT KEMUKA PM., P.P. PERLU JIKA KONTRAKTOR LEWAT KEMUKA PM., P.P. PERLU KELUAR NOTIS BERTULIS MINTA KONTRAKTOR KEMUKA KELUAR NOTIS BERTULIS MINTA KONTRAKTOR KEMUKA DALAM TEMPOH 2 BULANDALAM TEMPOH 2 BULAN

JIKA GAGAL P.P. SEDIAKAN PMJIKA GAGAL P.P. SEDIAKAN PM

Page 40: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

PELEPASAN JAMINAN REKABENTUKPELEPASAN JAMINAN REKABENTUKTIADA BERKENAANTIADA BERKENAAN

LUKISAN/DOKUMEN ASLUKISAN/DOKUMEN AS--BUILTBUILTDIKEMUKAKAN DALAM TEMPOH 3 BULAN DARI TARIKH DIKEMUKAKAN DALAM TEMPOH 3 BULAN DARI TARIKH SIAP KERJASIAP KERJA

Page 41: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

PELAKSANAAN KONTRAKPELAKSANAAN KONTRAK

JAMINAN KUALITIJAMINAN KUALITIKONTRAKTOR KEMUKAKAN CADANGAN PROGRAM KONTRAKTOR KEMUKAKAN CADANGAN PROGRAM JAMINAN KUALITIJAMINAN KUALITI

SECARA AM BAGAIMANA KONTRAKTOR MENGEKALKAN SECARA AM BAGAIMANA KONTRAKTOR MENGEKALKAN STANDARDSTANDARD

SEBELUM MULA KONTRAKTOR KEMUKAKAN PROGRAM SEBELUM MULA KONTRAKTOR KEMUKAKAN PROGRAM JAMINAN KUALITI TERPERINCI MEMENUHI STANDARD ISOJAMINAN KUALITI TERPERINCI MEMENUHI STANDARD ISO

LAPORAN JAMINAN KUALITI YANG DISAHKAN OLEH LAPORAN JAMINAN KUALITI YANG DISAHKAN OLEH JURUTERA PROFESIONAL PERLU DIKEMUKAKAN SETIAP JURUTERA PROFESIONAL PERLU DIKEMUKAKAN SETIAP BULANBULAN

LAPORAN MENGANDUNGI KEPUTUSAN UJIAN, PERAKUAN LAPORAN MENGANDUNGI KEPUTUSAN UJIAN, PERAKUAN UJIAN, LAPORAN MAKMAL DAN GAMBAR/FOTOUJIAN, LAPORAN MAKMAL DAN GAMBAR/FOTO

Page 42: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

LIST OF SELECTED GOVERNMENT’S MULTIMODAL LIST OF SELECTED GOVERNMENT’S MULTIMODAL TRANSPORT OPERATORTRANSPORT OPERATOR

KONTENA NATIONAL SDN. BHD.KONTENA NATIONAL SDN. BHD.MALAYSIAN SHIPPING AGENCIES SDN. BHD.MALAYSIAN SHIPPING AGENCIES SDN. BHD.MISC AGENCIES SDN. BHD.MISC AGENCIES SDN. BHD.SHAPADU TRANS SYSTEM SDN.BHD.SHAPADU TRANS SYSTEM SDN.BHD.GAPIMA SDN. BHD.GAPIMA SDN. BHD.TANJONGRIA SHIPPING & FORWARDING SDN. BHD.TANJONGRIA SHIPPING & FORWARDING SDN. BHD.PELANGI SHIPPING SDN. BHD.PELANGI SHIPPING SDN. BHD.PRIMA LOGISTICS SDN. BHD.PRIMA LOGISTICS SDN. BHD.MULTIMODAL FREIGHT SDN. BHD.MULTIMODAL FREIGHT SDN. BHD.S. A. KARGO SDN. BHD.S. A. KARGO SDN. BHD.

Page 43: TATACARA PROJEK SECARA “DESIGN AND BUILD” DAN “TURNKEY”

SEKIANSEKIAN