PMLCProjectManagementLifeCycle
TheGeorgeWashingtonUniversityeExpenseSystemImplementationProjectProjectDeploymentPlan
PreparedBy: Adam Donaldson
Version: 1.1
Date: October 12, 2012
ProjectOwner: Deb Dickenson, Comptroller Donna Ginter, Director ‐ Procurement
ProjectManager: Adam Donaldson, BMAG
STATUS: Draft
Routing for Document Approval
Approved
Unapproved
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 2
TableofContentsRevision History ............................................................................................................................................ 2
1 Project Summary ................................................................................................................................... 3
2 Deployment Strategy ............................................................................................................................ 3
2.1 Objectives / Strategy ..................................................................................................................... 3
2.1.1 Objective ............................................................................................................................... 3
2.1.2 Timing .................................................................................................................................... 3
2.1.3 Impacted Systems ................................................................................................................. 3
2.1.4 Stakeholders.......................................................................................................................... 4
2.2 Software Deployment ................................................................................................................... 4
2.2.1 High Level Software Modification Deployment Plan ............................................................ 4
2.2.2 System Modification Validation and Acceptance ................................................................. 4
2.2.3 System Modification Back Out Plan ...................................................................................... 5
2.3 Process Modification Deployment ................................................................................................ 5
2.3.1 High Level New Process Deployment Plan ............................................................................ 5
2.4 Hardware Deployment .................................................................................................................. 5
2.5 Milestones & Schedule ................................................................................................................. 6
2.6 Resources & Roles ......................................................................................................................... 7
2.7 Communications Plan ................................................................................................................... 9
2.8 Deployment Support & Issue Resolution .................................................................................... 10
2.8.1 Support Personnel Availability ............................................................................................ 10
2.8.2 Deployment Issue Resolution Procedure ............................................................................ 10
2.8.3 Escalation Procedure .......................................................................................................... 10
2.8.4 Stabilization / Post Implementation Support Plan (SWAT) ................................................. 10
3 Training ............................................................................................................................................... 11
4 Approval .............................................................................................................................................. 12
5 Appendix A – Related Documents ...................................................................................................... 13
6 Appendix B – Glossary ......................................................................................................................... 14
RevisionHistoryVersion Number
Date Author Notes
1.1 10/12/12 A.Donaldson Updated Section 2.1.3, 2.2.1, 2.2.3 and 2.5 with changed plan for T&E Form retirement.
*Begin revision history after first, non‐draft release.
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 3
1 ProjectSummaryThe objective of the electronic Expense Reporting system is to implement a third‐party software as a service expense management solution which will automate and simplify expense report submissions, P‐Card allocations, approval workflows, and tracking.
2 DeploymentStrategy
2.1 Objectives/Strategy
2.1.1 ObjectiveThe deployment is intended to activate Concur Expense, which is a software‐as‐a‐service (SaaS) application, for the George Washington staff and faculty. The deployment plan provides an overview of steps required to deploy the system, including the timing, impact and resources required, as well as details of the cutover, backout plan, milestones and communication efforts.
2.1.2 TimingThe official go‐live date for users will be Monday October 29, 2012. See Section 2.5 for a more detailed view of the deployment schedule and activities. See Section 2.7 for specific communications related to the deployment.
2.1.3 ImpactedSystemsBanner – Will not need to be taken down for this deployment. A full Employee Feed and Alias Upload will need to occur several times throughout the deployment.
EAS – EAS will not need to be taken down for this deployment. All DIT‐developed programs can be moved to production while the system is live.
EAS T&E Form – UPDATE 10/12/12: The EAS T&E Form will remain available for non‐employee reimbursements only into 2013. To use this form, reimbursement requests must be submitted by a GW employee on behalf of the non‐employee. AP will own a separate project which will plan for the transition of this functionality for non‐employees to a different tool and will provide a retirement date for this form. AP will reject any requests for employee reimbursements submitted through this EAS T&E Form.
iBuy Travel – Will not need to be taken down for this deployment. However, users will see changes as of October 29, 2012 when integration with Expense occurs.
Pathway –Will be disabled for users as part of this deployment. The system will remain for P‐Card management operations
PCMS – Will be decommissioned after this deployment. Servers will remain for approximately 6 months after the deployment. Procurement will own the effort to retire these servers.
Sciquest – Will not need to be taken down for this deployment. Access link redirect from ibuy.gwu.edu will change as this link will now be used for the iBuy+ landing page. Also, because the funds checking web service interface for Concur will reside on the same server as the same functionality for Sciquest, cutover to production will need to occur during a Sciquest maintenance window.
Stipends (SMA) – Also impacted by the funds checking web service migration described under ‘Sciquest’ above.
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 4
2.1.4 StakeholdersAll University Faculty and Staff University P‐Card users, purchasers, travelers and users requiring out‐of‐pocket expense reimbursement. All users of the applications described in Section 2.1.3.
2.2 SoftwareDeployment
2.2.1 HighLevelSoftwareModificationDeploymentPlanSpecific details of the DIT interface software modification migration steps will be included in an Excel file titled “eExpense Cutover Steps.xls” and will be shared via the eRoom (See Appendix A for specific location).
The high‐level plan is as follows:
September 10‐18, 2012 ‐ Concur will first move the Expense system to production but will remain connected to the EAS test environment. The Concur Expense system will not be live for GW users yet as this is controlled by the GW employee feed.
October 10‐17, 2012 – DIT security scan
October 18, 2012 – Testing & Readiness (GO LIVE) Gate Review with Executive Sponsors
October 19‐22, 2012 – DIT interfaces pushed to production
October 22‐26, 2012 – Financial Systems Support (FSS) performs production validation testing
October 26, 2012 – Final ‘Go / No‐Go’ decision made by Project Owners / Leads
October 26, 2012 –UPDATE 10/12/12: Pathway taken offline for users
October 29, 2102 – Concur Expense activated for GW users via updated Employee Feed and updated Single Sign On (SSO) feed.
See Section 2.5 for a complete timeline of the execution for these steps.
2.2.2 SystemModificationValidationandAcceptanceSAIG will lead the system Production Validation efforts beginning on October 22, 2012 and culminating in a Go / No Go decision at close‐of‐business on October 26, 2012. The Production Validation will include but is not limited to:
End‐to‐end testing with real transactions in a controlled production environment with verification through to Oracle EAS – as dictated by the updated Test Plan.
Testing of Travel / Expense Integrated Audit Rules – which includes audit rules that cannot be currently tested because our Travel environment is in production
Testing of SSO directed links (direct to Travel and direct to MyConcur pages)
Testing of system emailing and communications
Testing of eReceipt functionality
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 5
2.2.3 SystemModificationBackOutPlanThis deployment plan contains three GO / NO GO decision points.
1. October 18, 2012 at 12pm there is a Gate Review where the decision is made by Executive Sponsors on whether to proceed.
2. October 21, 2012 at 5pm the decision is made to proceed into Production Validation by the Technical Lead.
3. October 26, 2012 at 1pm the decision is made by the Project Owners to proceed for final cutover.
Should the deployment of system modifications fail at any time before these decision points, the Project Owners will decide, with support from the Project Manager, Technical Lead and Functional Lead, to abandon the planned system implementation and process changes.
If this decision is made, the following must occur:
Executive Sponsors notified of decision to abort the deployment
Pathway access restored to users / links returned / JPM transactions brought into Pathway
Update 10/12/12: T&E Form restored / links returned
New deployment date selected by Project Owners / Project Leads
Communication delivered via INFOMAIL to faculty & staff informing of delay and revised date
Targeted communications to key stakeholders
2.3 ProcessModificationDeployment
2.3.1 HighLevelNewProcessDeploymentPlanAll of the new and modified processes related to this system will go into effect upon the Go Live date of October 29, 2012. These include:
Personal Expense Reimbursement process
P‐Card Allocation process
Cash Advance Request process
Late Allocation Monitoring & Correction process
Expense Report Support Process
2.4 HardwareDeploymentThere are no hardware modifications as a result of this project.
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 6
2.5 Milestones&ScheduleDate / Time Activity Leads
iBuy+ Website Launch
Sep 12, 2012 9:00 AM
iBuy+ Website – iBuy+ website goes live, all redirects in place, ‘Expense Report’ states “Going Live 10/29”
Megan Flood / UWS / T.Nwachukwu
Concur Expense Pushed to Production / EAS Remains in Test
Sep 17, 2012 5:00 PM
Concur Configuration Sign‐Off Completed by GW A.Donaldson / J.Pearson
Sep 17 to Sep 19, 2012
System Cutover Configuration by Concur Concur’s Brandon Campbell
Sep 20, 2012 Release to Production notification sent to GW Concur’s Anthony Patrick
Sep 21 to Sep 24, 2012
DIT Employee Load & Configuration A.de Lapparent
DIT Security Review
Oct 10 to Oct 17, 2012 Concur Expense ‐ DIT Security Scan G.Guzman
Pathway Cutover
Oct 20, 2012 5:00 PM
Pathway final JPM transactions brought into Pathway. G.Bedford
Oct 20, 2012 6:00 PM to Oct 26, 2012 5:00 PM
P‐Card users allocate all remaining card transactions in Pathway.
G.Bedford / P‐Card Users
Oct 26, 2012 5:05 PM
Final JPM transaction sent from Pathway to EAS G.Bedford
EAS Interfaces Moved to Production
Oct 18, 2012 1:00 PM
Testing & Readiness Gate Review / GO LIVE decision made by Executive Sponsors
Executive Sponsors / Project Owners / Project Leads
Oct 18 to Oct 21, 2012
DIT will push EAS interfaces to prod(DIT will maintain spreadsheet of detailed steps) A.de Lapparent
Oct 21, 2012 5:00 PM
Go / No Go Decision from DIT for Production Validation A.de Lapparent
Production Validation
Oct 22, 2012 9:00 AM to Oct 26, 2012 12:00 PM
FSS will lead production validation. Project team will run real transactions J.Pearson / Project team
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 7
Date / Time Activity Leads
October 26, 2012 9:00 AM
P‐Card transactions & assignments verified G.Bedford
October 26, 2012 1:00 PM
FINAL GO / NO GO Decision Project Owners / Project Leads
Cutover for GW Go Live
Oct 26, 2012 5:05 PM
Pathway
- Users deactivated in Pathway
- Link to Pathway removed from web pages G.Bedford / J.Rubin
Oct 26, 2012 6:00 PM
EAS Online T&E
Take down the application at http://eas.gwu.edu/home/alt/travel/travel.cfm and redirect to https://www.gwu.edu/~supchn/iBuyCentral/applogin.asp
A.de Lapparent
Oct 28, 2012 1:00 PM
Concur Expense ‐ Employee Feed Refreshed, all employees loaded and feed validated
A.de Lapparent / J.Pearson
Oct 28, 2012 6:00 PM
Concur Expense ‐ Put in Production
- UWS Single Sign On Put in Production - iBuy+ Expense Reimbursement Link Live - Final Production Test
J.Pearson
Table 1 – Deployment Milestones & Schedule
2.6 Resources&RolesResource Role Contact Info
During Deployment
Project Leaders
Deb Dickenson Project Owner
Adam Donaldson Project Manager
Donna Ginter Project Owner
Ed Martin Project Senior Leader
Deployment Leaders
Anna de Lapparent Technical Lead \ Manage DIT Cutover
Jeff Pearson Functional Lead \ Manage Production Validation
Megan Flood Communication Lead \ Manage Communications
Division of IT Resources
Yelena Buchmuller EAS Interface Cutover Support
Liz Cobb Banner Data Interface Support
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 8
Resource Role Contact InfoDuring Deployment
Michelle Hall EAS Interface Cutover Lead
Anjana Ghosh EAS Interface Cutover Support
Sadam Shailaja EAS Interface Cutover Support
John Sweeney EAS Interface Cutover Support
Neelam Thakur EAS Interface Cutover Support
Financial Systems Support
Jaime Maestrey Production Validation Testing \ Configuration Support
Aileen Miller Production Validation Testing \ Configuration Support
Kevin Perry Production Validation Lead
Jen Whaley Production Validation Testing \ Configuration Support
Procurement
George Bedford P‐Card Lead \ JPM Feed Validation
Josh Rubin Procurement Lead \ Production Validation Testing \ Web Modification Support
Accounts Payable
Lennox Jones Accounts Payable Lead
Rachel Waple Accounts Payable
Business Management & Analysis Group
Megan Flood Communication Lead \ Manage Communications
Concur
Brandon Campbell Concur Technical Lead
Zack Harwell Concur Configuration Lead
Anthony Patrick Concur Project Manager
Kristine Truax Concur Travel Integration Lead
Table 2 – Deployment Resources and Roles
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 9
2.7 CommunicationsPlanThe following table lists the planned communications points for the deployment:
Date Communication Method Audience Deliverer
9/5/12 Deployment e‐mail to managers/executives to engage help in communicating pending change
e‐mail GW Leaders
(Dean / Director & above)
Lou Katz / Steve Lerman
9/5/12 E‐mail Sciquest users to alert change in name, web links
e‐mail iBuy / Sciquest Users
iBuy System / J.Rubin
9/7/12 Update to FOPS meeting participants Meeting FOPS A.Donaldson
9/12/12 Launch iBuy+ web page, with new AP/P‐Card info page
WebsiteGW Faculty &
Staff J.Rubin
9/12/12 Banner Announcement in Pathway.net system
System Pathway Users G.Bedford
9/12/12 Banner message in EAS for users submitting Online T&E
System T&E Form Users A.de Lapparent
10/29/12 Update links to EAS T&E and to P‐Card to iBuy+
WebsiteGW Faculty &
Staff J.Rubin
9/12/12, 10/16/12, 10/29/12
INFOMAIL: Announcement to all GW staff and faculty
e‐mail GW Faculty & Staff
Infomail
9/18/12, 10/16/12
Targeted Discussion with Finance Directors
MeetingsFinance Directors
A.Donaldson / J.Pearson
bi‐weekly starting 9/18/12
Targeted e‐mail to Pcard users for final allocations
e‐mail P‐Card Holders G.Bedford
early Sept Targeted OVPR/Researchers Discussion Meetings OVPR D.MacGregor
early Sept Targeted Faculty Discussion Meetings Faculty D.MacGregor
early Sept Targeted Administrative Assistants Discussion
Meetings Faculty D.MacGregor
Table 3 – Communications Schedule
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 10
2.8 DeploymentSupport&IssueResolutionSee Section 2.6 / Table 2 for roles and responsibilities.
2.8.1 SupportPersonnelAvailabilityThe teams listed in Table 2 above are expected to be available for the duration of their tasks listed within. The Functional Lead and Technical Lead will be responsible for ensuring that their respective teams are available during the planned deployment time frames.
2.8.2 DeploymentIssueResolutionProcedureAny issues raised by the functional or technical teams which require resolution and may impact the deployment schedule will be immediately raised to the Project Manager by either the Technical Lead or Functional Lead.
Additionally, a conference bridge has been established and can be initiated at any time between October 26 at 5pm and October 29 at 12pm in order to convene any necessary ad hoc meetings. The conference bridge is and the passcode is . The leader passcode will be provided to the Technical Lead and Functional Lead and either can use the conference bridge at any time for any discussions related to this deployment.
2.8.3 EscalationProcedureAny issues unable to be resolved by the team will be immediately escalated to the Project Owner by the Project Manager.
Upon initiating the escalation procedure, the Project Manager will notify the Project Owner, Functional Lead and Technical Lead and establish the conference bridge referenced in 2.8.2 and convene a meeting to discuss the escalation.
If necessary, the decision to cease or delay the deployment will be made by the Project Owner, with consultation from the Project Manager, Technical Lead and Functional Lead.
2.8.4 Stabilization/PostImplementationSupportPlan(SWAT)This section describes the plan and procedure for monitoring the system to ensure the changes implemented as a result of this project are successful and don’t negatively impact system usage.
2.8.4.1 StabilizationPeriodThe stabilization period will last from October 29, 2012 through November 30, 2012
2.8.4.2 StabilizationIssueAnalysisProcedureA special issue analysis procedure will be established for the duration of the stabilization period.
1. The project team will create a special group (SWAT) to triage DIT Help Desk and/or iBuy+ support tickets and determine which are issues related to the system changes implemented by this project.
2. The DIT Help Desk and/or iBuy+ support person will initially route all tickets through this group during the Stabilization Period.
3. If an issue is determined to be unrelated to the changes implemented as part of this project, the ticket will be sent back to the DIT Help Desk and/or iBuy+ support person for normal resolution.
4. If an issue is suspected of being related to the changes implemented as part of this project, the SWAT team will manage the issue through resolution.
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 11
3 TrainingTraining Plan is maintained separately and is located in the eRoom at https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_33111.
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 12
4 ApprovalBy signing, the individuals listed below have approved this deployment plan.
Name: DebDickenson Name: DonnaGinterTitle:ComptrollerRole:ProjectOwner
Title:DirectorofProcurementRole:ProjectOwner
Date:September6,2012 Date:September6,2012
Name: AnnadeLapparent Name: JeffPearsonTitle:AsstDirector,EnterpriseIA&SDRole:TechnicalProjectLead
Title:DirectorFinancialSystemsSupportRole:FunctionalProjectLead
Date:September6,2012 Date:September6,2012
<For an approval received via electronic means, such as email, please indicate by placing “Electronic Approval” on the approval line. Please then place a copy of the electronic approval in the same project file folder where the approved version of this document is stored.>
Electronic Approval Received See attached
Electronic Approval Received See attached
Electronic Approval Received See attached
Electronic Approval Received See attached
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 13
5 AppendixA–RelatedDocuments
File Name Document Owner
Document Location or Link
GW Concur Agreement ‐ 25 Sep 11.pdf D.Ginter https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e969
Travel and Expense ‐ Project Proposal 1,82 APPROVED.pdf
A.Donaldson https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
Travel Portal Concur Expense Management Proposal ‐ APPROVED BY KATZ.pdf
D.Lawlor https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
eExpense – Project Workbook.xls A.Donaldson https://eroom.gwu.edu/eRoom/EVPT/eExpense
eExpense ‐ Project Charter v1,0 APPROVED.pdf
A.Donaldson https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
eExpense Implementation ‐ Project Definition Document v1.0
A.Donaldson https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
eExpense Project ‐ Test Plan Approved 081512.pdf
J.Pearson https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_33066
eExpense Training Plan ‐ DRAFT 1.3.pdf M.Flood https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_33111
eExpense Cutover Steps.xls M.Hall https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_37759
PMLCProjectDeploymentPlan eExpenseSystemImplementationProject
Confidential Not for release outside of The George Washington University without written permission
Page 14
6 AppendixB–GlossaryTerm / Acronym Definition
AEBTS American Express Business Travel Services
AP Accounts Payable
AR Accounts Receivable
AX American Express (also American Express Business Travel Services)
BMAG Office of Finance ‐ Business Management & Analysis Group
CO Office of Finance ‐ Comptroller's Office
CSV Comma Separated Values
DIT Division of Information Technology
EAS Enterprise Accounting System
EIS Division of IT – Enterprise Information Services group
ETS Endowment Tracking System
FSS Office of Finance ‐ Financial Systems Support
G/L General Ledger
GM Grants Module
GW The George Washington University
GWU The George Washington University
HR Human Resources
IT Division of Information Technology
JPM JP Morgan Chase
PMLC Project Management Lifecycle
SaaS Software as a Service
SAIG Systems Analytics & Insight Group
SAML Security Assertion Markup Language
SSO Single Sign On
T&E Travel and Expense
UAT User Acceptance Testing
UWS University Web Services
XML Extensible Markup Language