    TUGAS AKHIR

    MANAJEMEN RISIKO DALAM PEMBANGUNAN

    DERMAGA CURAH KERING DI PELABUHAN

    MULTIPURPOSE TELUK LAMONG

    DISUSUN OLEH:

    BAYU PUJI NUGROHO

    NIM. 03117132

    PROGRAM STUDI TEKNIK SIPIL

    FAKULTAS TEKNIK

    UNIVERSITAS NAROTAMA SURABAYA

    2019

  • ii

    TUGAS AKHIR

    MANAJEMEN RISIKO DALAM PEMBANGUNAN DERMAGA CURAH

    KERING DI PELABUHAN MULTIPURPOSE TELUK LAMONG

    Disusun Oleh:

    BAYU PUJI NUGROHO

    NIM. 03117132

    Diajukan guna memenuhi persyaratan

    untuk memperoleh gelar Sarjana Teknik (S.T)

    pada Program Studi Teknik Sipil

    Fakultas Teknik

    Universitas Narotama

    Surabaya.

    Surabaya, Februari 2019

    Mengetahui

    Dosen Pembimbing,

    Dr. M. Ikhsan Setiawan,. S.T.,M.T

    NIDN : 0701097503

  • iii

    TUGAS AKHIR

    MANAJEMEN RISIKO DALAM PEMBANGUNAN DERMAGA CURAH

    KERING DI PELABUHAN MULTIPURPOSE TELUK LAMONG

    Disusun Oleh:

    BAYU PUJI NUGROHO

    NIM. 03117132

    Tugas akhir ini telah memenuhi persyaratan dan disetujui untuk di ujikan.

    Surabaya, Februari 2019

    Mengetahui

    Dosen Pembimbing,

    Dr. M. Ikhsan Setiawan,. S.T.,M.T

    NIDN : 0701097503

  • Scanned by CamScanner

  • v

    SURAT PERNYATAAN

    Yang bertanda tangan dibawah ini, Saya :

    Nama : BAYU PUJI NUGROHO

    NIM : 03117132

    JUDUL TUGAS AKHIR : MANAJEMEN RISIKO DALAM

    PEMBANGUNAN DERMAGA CURAH KERING

    DI PELABUHAN MULTIPURPOSE TELUK

    LAMONG.

    Dengan ini saya menyatakan bahwa dalam Tugas Akhir ini tidak terdapat karya

    yang pernah diajukan untuk memperoleh gelar kesarjanaan disuatu Perguruan

    Tinggi, dan sepanjang pengetahuan saya juga tidak terdapat Karya/Pendapat

    yang pernah ditulis oleh orang lain, kecuali yang secara tertulis diacu dalam

    naskah ini dan disebutkan dalam Daftar Acuan/Daftar Pustaka.

    Apabila ditemukan suatu Jiplakan/Plagiat maka saya bersedia menerima akibat

    berupa sanksi Akademis dan sanksi lain yang diberikan oleh yang berwenang

    sesuai ketentuan peraturan dan perundang-undangan yang berlaku.

    Surabaya, Februari 2019

    Yang membuat pernyataan

    BAYU PUJI NUGROHO

    NIM : 03117132

  • vi

    KATA PENGANTAR

    Puji Syukur saya panjatkan atas kehadirat Allah SWT yang telah

    melimpahkan rahmat dan hidayah-Nya sehingga saya dapat menyelesaikan.

    Tugas Akhir ini. Sebagai manusia saya menyadari akan adanya keterbatasan,

    kekurangan dan kesalahan. Namun saya telah berusaha semaksimal mungkin

    untuk melakukan yang terbaik agar Tugas Akhir ini dapat selesai sesuai dengan

    harapan. Pada kesempatan ini saya mengucapkan terima kasih yang sebesar

    besarnya kepada :

    1. Bapak Dr. Ir. Koespiadi, M.T. selaku Dekan Teknik Universitas Narotama

    Surabaya.

    2. Bapak Ronny Durrotun Nasihien, S.T., M.T. selaku Ketua Program Studi

    Teknik Sipil Universitas Narotama Surabaya.

    3. Bapak Dr. M. Ikhsan Setiawan,. S.T.,M.T selaku Dosen pembimbing yang

    penuh tanggung jawab memberikan pengarahan dalam penyusunan tugas

    akhir ini.

    4. Almarhum ayah saya, terima kasih atas doa dan semangatnya sehingga bisa

    menyelesaikan tugas akhir ini;

    5. Ibu saya atas ketulusan doa dan dorongan moril maupun materil yang tak

    akan pernah penulis mampu membalasnya.

    6. Kepada istri dan anak – anak saya yang selalu menjadi penyemangat untuk

    menyelesaikan tugas akhir ini.

    7. Rekan rekan semua mahasiswa Teknik Sipil Universitas Narotama

    Surabaya dan Semua Pihak yang ikut membantu dalam Penyusunan Tugas

    Akhir ini.

    Harapan saya semoga Tugas Akhir ini bisa memenuhi syarat dan tujuan

    yang dikehendaki, atas perhatiannya kami ucapkan terima kasih.

    Surabaya, Februari 2019

    Penulis

  • vii

    MANAJEMEN RISIKO DALAM PEMBANGUNAN

    DERMAGA CURAH KERING DI PELABUHAN

    MULTIPURPOSE TELUK LAMONG

    Oleh : Bayu Puji Nugroho

    Pembimbing : M. Ikhsan Setiawan

    ABSTRAK

    Risiko adalah suatu keadaan yang tidak pasti dan terdapat unsur bahaya,

    konsekuensi yang bisa terjadi akibat proses yang sedang berlangsung maupun

    kejadian yang akan datang. Salah satunya dalam kegiatan konstruksi, dimana

    dalam kegiatan ini terdapat beberapa risiko yang mungkin terjadi dan memberikan

    dampak yang besar dalam keberhasilan penyelesaian pekerjaan tersebut.

    Pendekatan dilakukan terhadap risiko yang ada yaitu dengan pemahaman /

    identifikasi risiko, pengukuran risiko, pemetaan risiko, respon terhadap risiko.

    Sehingga dengan adanya kegiatan tersebut dapat memberikan rekomendasi

    apakah risiko tersebut dapat diterima, dibagi, dikurangi atau dihindari. Penelitian

    ini dilakukan dengan metode penelitian kuantitatif deskriptif. Hasil penelitian ini

    menyimpulkan bahwa terdapat 7 faktor risiko yang di tingkat sangat tinggi yaitu

    pemahaman dokumen kontrak, different site condition, produktivitas peralatan,

    mutu / kualitas material, kelancaran cash flow, kompetensi sub kontraktor, dan

    pengaruh cuaca. Penanganan terhadap risiko sangat tinggi yaitu dengan cara

    melakukan usaha – usaha semaksimal mungkin sehingga dapat menurunkan

    tingkat risiko yang ada sehingga pekerjaan dapat terselesaikan dengan baik dan

    ketiga sasaran proyek bisa tercapai.

    Kata kunci : Manajemen risiko, pekerjaan konstruksi

  • viii

    RISK MANAGEMENT IN CONSTRUCTION OF DRY BULK

    JETTY AT TELUK LAMONG MULTIPURPOSE TERMINAL

    By : Bayu Puji Nugroho

    Mentor : M. Ikhsan Setiawan

    ABSTRACT

    Risk is a situation that is uncertain and there is an element of danger, the

    consequences that could occur due to a process that is ongoing or upcoming

    events. One of them in construction, where activity in this activity, there is some

    risk that may occur and give a great impact in the success of the completion of the

    work. Approaches were made to the risks involved with

    understanding/identification of risk, risk measurement, risk mapping, the response

    to risk. So with the existence of such activities can provide a recommendation as

    to whether the risks are acceptable, divided, reduced or avoided. This research

    was conducted with descriptive quantitative research methods. The results of this

    study concluded that there were 7 risk factors in very high level understanding of

    contract documents i.e., different site condition, productivity, quality

    equipment/material quality, smooth cash flow, the competence of sub contractors,

    and the influence of the weather. Against the risk of handling very high i.e. by

    way of doing business – business everything possible so that it can reduce the

    level of risk that exists so that the work can be resolved properly and the third

    project targets can be achieved.

    Keywords : risk management, contruction project

  • ix

    DAFTAR ISI

    HALAMAN SAMPUL ........................................................................................... i

    HALAMAN JUDUL ............................................................................................. ii

    LEMBAR PERSETUJUAN PEMBIMBING .................................................... iii

    LEMBAR PENGESAHAN ................................................................................. iv

    HALAMAN KEASLIAN KARYA ILMIAH...................................................... v

    KATA PENGANTAR .......................................................................................... vi

    ABSTRAK ........................................................................................................... vii

    DAFTAR ISI ......................................................................................................... ix

    DAFTAR TABEL................................................................................................. xi

    DAFTAR GAMBAR ........................................................................................... xii

    BAB I PENDAHULUAN ................................................................................... 1

    1.1. Latar Belakang Masalah .................................................................. 1

    1.2. Perumusan Masalah ......................................................................... 4

    1.3. Batasan Masalah .............................................................................. 5

    1.4. Maksud dan Tujuan Penelitian ........................................................ 5

    1.5. Manfaat Penelitian ........................................................................... 5

    1.6. Lokasi Penelitian ............................................................................. 6

    BAB II TINJAUAN PUSATAKA ....................................................................... 8

    2.1. Penelitian Terdahulu ........................................................................ 8

    2.2. Teori-Teori Dasar .......................................................................... 12

    2.2.1. Manajemen ........................................................................ 12

    2.2.2. Risiko ................................................................................. 13

    2.2.3. Manajemen Risiko ............................................................. 14

    2.2.4. Sumber Risiko ................................................................... 21

    2.2.5. Dermaga ............................................................................. 22

    BAB III METODOLOGI PENELITIAN .......................................................... 24

    3.1. Diagram Alir Kegiatan (Flowchart) .............................................. 24

    3.2. Metode Penelitian .......................................................................... 25

  • x

    3.3. Lokasi Dan Waktu ......................................................................... 25

    3.4. Bahan Dan Alat ............................................................................. 27

    3.5. Metode Pelaksanaan ...................................................................... 27

    3.6. Pengolahan Data ............................................................................ 28

    3.6.1. Perencanaan Risiko (Risk Planning) ................................. 28

    3.6.2. Identifikasi Risiko (Risk Identification) ............................ 30

    3.6.3. Metode Penelitian .............................................................. 31

    3.6.4. Peta Skala Likert ................................................................ 32

    3.7. Jadwal Pelaksanaan ....................................................................... 32

    BAB IV ANALISIS DAN PEMBAHASAN....................................................... 33

    4.1. Profil Proyek .................................................................................. 33

    4.2. Analisis Data dan Pembahasan ...................................................... 34

    4.2.1. Identifikasi Risiko .............................................................. 34

    4.2.2. Analisis Risiko ................................................................... 36

    4.2.3. Plan Risk Response ........................................................... 45

    4.2.4. Perbandingan Hasil Penilitian dengan Kondisi Eksisting . 46

    BAB V KESIMPULAN DAN SARAN ............................................................. 48

    5.1. Kesimpulan .................................................................................... 48

    5.2. Saran .............................................................................................. 48

    DAFTAR PUSTAKA .......................................................................................... 50

    LAMPIRAN ......................................................................................................... 53

  • xi

    DAFTAR TABEL

    Tabel 3. 1 Skala Likert .......................................................................................... 32

    Tabel 3. 2 Jadwal Kegiatan ................................................................................... 32

    Tabel 4. 1 Kuesioner ............................................................................................. 34

    Tabel 4. 2 Contoh Jawaban Kuesioner .................................................................. 37

    Tabel 4. 3 Rekap Jawaban Kuesioner ................................................................... 37

    Tabel 4. 4 Pengolahan Kuesioner.......................................................................... 39

    Tabel 4. 5 Klasifikasi Risiko ................................................................................. 42

    Tabel 4. 6 Hasil analisis risiko frekuensi dan dampak .......................................... 43

    Tabel 4. 7 Pengelompokan tingkat risiko .............................................................. 44

  • xii

    DAFTAR GAMBAR

    Gambar 1. 1 Lokasi Penelitian ................................................................................ 6

    Gambar 2. 1 Matriks Tingkat Risiko..................................................................... 18

    Gambar 3. 1 Diagram Alir Penelitian ................................................................... 24

    Gambar 3. 2 Layout Terminal Teluk Lamong ...................................................... 25

  • 48

    BAB V

    PENUTUP

    5.1. Kesimpulan

    Dari hasil Analisis dan pembahasan pada bab sebelumnya dapat

    diambil kesimpulan sebagai berikut :

    1. Terdapat 7 Faktor risiko yang berada pada level sangat tinggi yaitu

    pemahaman dokumen kontrak, different site condition, produktivitas

    peralatan, mutu / kualitas material, kelancaran cash flow, kompetensi

    sub kontraktor, dan pengaruh cuaca;

    2. Cara pengukuran yang dilakukan yaitu menggunakan metode

    deskriptif kuantitatif dengan menyebarkan kuesioner kepada 30

    responden untuk mendapatkan nilai interprestasi dari dampak dan

    tingkat kemungkinan yang muncul dari risiko yang ada;

    3. Penanganan terhadap risiko tinggi dilakukan dengan cara mengurangi

    risiko yaitu proses mitigasi dengan melakukan usaha – usaha

    semaksimal mungkin sehingga dapat menurunkan tingkat risiko yang

    ada sehingga pekerjaan dapat terselesaikan dengan baik dan ketiga

    sasran proyek bisa tercapai;

    5.2. Saran

    Berdasarkan seluruh hasil perhitungan /Analisis yang diperoleh serta

    survey yang dilakukan sebelumnya dalam penelitian ini tentunya masih

    sangat banyak kekurangan, maka kedepan untuk penilitian serupa dapat

  • 49

    menggunakan metode lain dan faktor – faktor risiko yang lebih rinci

    sehingga bisa mendapatkan hasil yang lebih sempurna.

  • 50

    DAFTAR PUSTAKA

    Abidin, Ismeth S. 2010. Bahan Kuliah Manajemen Risiko, Universitas Indonesia

    Dorfman. 1998. Introduction To Risk Management And Insurance. Edisi Keenam.

    Upper Saddle River, N.J. : Prentice Hall.

    Duffield Colin. 2003. International Project Management, Universitas Indonesia

    Flyvbjerg, B. 2007. Megaproject policy and planning: problems, causes, cures.

    Aalborg: Institut for Samfundsudvikling og Planlægning, Aalborg

    Universitet

    Godfrey, P. S. 1996. Control of Risk. A Guide to The Systematic Management of

    Risk from Construction. Westminster London: Connstruction Industry

    Research And Information Association (CIRIA).

    Handoko, T. Hani. 2003. Manajemen Sumber Daya Manusia, Bandung : Salemba

    Empat

    Irham Fahmi. 2013. Manajemen Risiko, cetakan ketiga, alfabeta, Bandung

    Joni, I Gede Putu. 2012. Risiko Manajemen Proyek. Jurnal Fakultas Teknik

    Universitas Udayana, Denpasar.

    Kamus Besar Bahasa Indonesia (KBBI). (2009) pengertian dermaga

    Karunia, Meutia Nadia. 2016. Analisis Risiko Keterlambatan Waktu Pada Proyek

    (Studi Kasus: Pembangunan Jalan Tol Trans Sumatera Bakauheni-

    Terbanggi Besar (Paket II Sidomulyo-Kotabaru Sta. 39+400 - Sta. 80+000)

    dan (Paket III Kotabaru-Metro Sta 80+000 – Sta. 109+000)). Jurnal

    Jurusan Teknik Sipil Universitas Lampung

    Pertiwi, I Gusti Agung Istri Mas,. Kristinayanti, Wayan Sri, Aryawan, I Gede

    Made Oka. 2016. Manajemen Risiko Proyek Pembangunan Underpass

  • 51

    Gatot Subroto Denpasar. Jurnal Jurusan Teknik Sipil, Politeknik Negeri

    Bali

    Pramana, Tony. (2011). Manajemen Risiko Bisnis. Jakarta : Sinar Ilmu.

    Project Management Institute. 2004. A Guide to the Project Management Body of

    Knowledge (PMBOK Guide) 3th Edition. Newton Square, Pennsylvania:

    Four Campus Boulevard.

    Santoso, Nurcahyo Budi. 2017. Analisis Manajemen Risiko Pada Proyek

    Pembangunan Jalan Tol (Studi Kasus Proyek Pembangunan Jalan Tol Solo-

    Ngawi-Kertosono Ruas Ngawi-Kertosono Paket 3). Skripsi Program Studi

    Magister Teknik Sipil Sekolah Pascasarjana Universitas Muhammadiyah

    Surakarta

    Smith, C.W., Jr. 1990.”Corporate Risk Management : Theory and Practice”.

    Journal De-rivatieves, Vol. 2, No. 4, Page 21-30

    Soputan, Gabby E. M.. 2014. Manajemen Risiko Kesehatan Dan Keselamatan

    Kerja (K3) (Study Kasus Pada Pembangunan Gedung SMA Eben Haezar).

    Jurnal Pascasarjana Teknik Sipil Universitas Sam Ratulangi

    Sukaarta, I Wayan. 2012. Analisis Risiko Proyek Pembangunan Dermaga Study

    Kasus Dermaga Pehe Di Kecamatan Siau Barat Kabupaten Kepulauan

    Sitaro. Jurnal Universitas Sam Ratulangi Manado

    Suprapto, Nurlela Heri. 2014. Identifikasi Dan Analisis Manajemen Risiko Pada

    Proyek Pembangunan Infrastruktur Bangunan Gedung Bertingkat. Jurnal

    Fakultas Teknik Sipil dan Perencanaan Universitas Gunadarma

    Tangdiembong, Obert.2013. Risiko Pada Proyek-Proyek Dermaga Di Sulawesi

    Utara. Jurnal Universitas Sam Ratulangi Manado

    Triatmodjo, Bambang, 1996, Pelabuhan, Beta Offset, Yogyakarta

    Uher, Thomas E. 1996. Introduction to Risk Management. New South Wales

    Faculty of The Built Environment: UNSW Press.

  • 52

    Wang, Lina, Li, Yaqib, Wang, Enmao. 2011. Research on Risk Management of

    Railway Engineering Construction. Journal a School of Civil Engineering,

    Lanzhou Jiaotong University, Lanzhou

    Zhi-qiang, Hou,. Ya-mei, Zeng.2016. Research on Risk Assessment Technology of

    the Major Hazard in Harbor Engineering. Journal School of Traffic and

    Transportation,Beijing Jiaotong University,Beijing.