UNIVERSITY KUALA LUMPUR
MALAYSIAN INSTITUTE OF AVIATION TECHNOLOGY
Subject Code:
Subject:
Report: Jet Star Engine Removal, Inspection & Installation.
Prepared For: Sir Roslan B. Basit
Prepared By:
1.2.3.4.5.6.7.8.9.
Date: 16 November 2011
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
2/13
Introduction:
Cerita Jet Star Gas Turbine Engine
Objective:
i. To Remove an Engine From Its Pylon Using a Hoisting For General & VisualInspection .
ii. To Familiarize with Different Type of Gas Turbine Engine Assembly.Tools & Equipment:
i. Dial Torque Wrench F igure 1ii. Flashlight
iii. RatchetF iqure 1iv. Socket ExtensionF igure 1v. Socket SetF igure 1
vi. Spanner Open End Head Set F igure 1vii. Engine StandF igure 2
F igure 1
F igure 2
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
3/13
Removal:
General: The Engine Removal is done when the engine experiences an internal damage
Or When Engine Performance Doesnt Achieve It Desirable Values whereby
Engine Trimming is required.
Procedures Pictures
The Nacelle can be divided into two
areas with the box beam being the
dividing point. The Top forward side
of each nacelle has a door for
providing access to the upper part of
the engine.
The Access Panel is Open to allow
for the hoist to be hooked on
specified location only stated by
Manufacturer Manual .
Once the both side have been
properly and securely hoist .
Remove the following connection:
i. Fluid Linesii. Electrical Connection
iii. Control Cable
Make Sure Before Any Connection
or Mechanical Linkages Is being
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
4/13
removed , Switch Off the Master
Switch and Wait For a Few Minutes.
Once both C-Clamp Fasteners have
been removed , the engine will be
lowered straight and level to prevent
collision with the pylon and any
accessory mounted with the pylon.
2 Personnel were required in this
process to monitored it from the
Front and Rear of the Engine.
Both C Clamp Fasteners will
be removed prior lowering
down the engine .
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
5/13
The Engine Stand need to placed
parallel to the engine .
The Engine has two support strut on
both side . These support strut is
used to hold the engine when it is on
the engine stand .
Upon Reaching the Engine Stand ,
the Support Strut need to be exactly
matched with the Engine Stand
Support Strut.
Engine Support Strut Need to be
Firm and Secured to hold the engine
prevent it from swinging back and
forth .
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
6/13
Once the engine has been totally
lowered , the hoist will be removed
from engine before sending it for
inspection.
Additional Locking Method is
used to prevent Engine Rear
and Front Bottoming .
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
7/13
Inspection
General: Inspection Done in Shop Maintenance involves checking engine component ,
list down any missing component , State the defects and look out for
any components that require replacement or in need for repair .
Observation:
Component Figure
Combustion Chamber:
1) Combustor Type : Can AnnularDefects:
1) Heavily dent on all side ofsurfaces.
2) Combustor Lining is badlydamage.
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
8/13
CClamp
Defects:
1) Sealant or Packing need to bereplace as fluid is seen leaking or
proper lubrication method need
to be followed.
2) Each Bushing and Nuts RequireReplacement as the bushing is
damage and the nut thread has
already worn.
Missing:
1) Upon Removal found that OneBushing is missing from C-
Clamp .
3) Ignition Exchanger insulation
& connection required to be
replace .
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
9/13
Exhaust Assembly
Defects:
1) Tearing of Insulation Material
2) Realignment and RewiringLocking of thermal probe
3) Dent on Edge of Exhaust Cone.
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
10/13
Result:
Parts Defects Action Taken
Combustion Chamber
i. Ignition Exchanger Dent Rust Corrodes
Replaced
CClamp
i. Fastenersii. Packing / Seals
Bushing Missing Leaking Thread Wear
Replaced
Repair
Replace
Exhaust Assembly
i. Thermal Probeii. Insulation
iii. Exhaust Cone
Tearing Rust Corrodes Dent
Replaced
Replaced
Replaced
Repair
Reassembly:
Procedures Pictures
Similar Procedures but with a few
Differences .
The Engine , again hook it into
designated places .
Before hoisting the engine up , the hoist
cables need to be straighten and stress .
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
11/13
This time , the C-Clamp Nuts are
required to be torque as stated in the
manual which is 50 inch pound .
The engine need to be aligned with
the C- Clamp with straight and level
hoisting for both cables.
7/27/2019 TURBINE HANGER UNIVERSITY KUALA LUMPUR.docx
12/13
Conclusion:
The removal of the engine requires a lot of workforce and consumed a lot of
downtime for the aircraft which eventually deal with the aircraft operators budget . So ,
necessary removal engine will only be done on certain cases such as internal damage of
the engine whereby further inspection for internal component , major overhauling &
engine trimming.
Diagram of How Jet Star Engine is being Removed / Reinstall
Reference:
Jet Star Engine Installation & Removal Vol. 1.
Jeppesen Airframe Textbook .