Urban development and Environmental sustainability for 10.000 subsidised houses
Systems for monitoring. Energy Efficiency in Smart Urban Developments
CASE: ECOCITY VALDESPARTERAZARAGOZA
NOELIA OLONA SOLANO
22/10/2013
LOCATION
MADRID
ZARAGOZA BARCELONA
BILBAO
2
ZARAGOZA´S DIGITAL STRATEGY:OPENNESS
MUNICIPAL NETWORK OF WIFI INTERNET ACCESS 462 POINTS.
CITIZEN CARD. 130.000
OPEN DATA & OPEN SOFTWARESERVICE OF DIGITAL PERSONAL FILE BY TWINDOCS
HTTP://WWW.ZARAGOZA.ES/CIUDAD/SECTORES/TECNOLOGIA/LOCAL NORMATIVE: TRANSPARENCY AND FREE ACCESS TO INFORMATION (LAW 37/2007)
3
ZARAGOZA´S DIGITAL PROJECTS
DIGITAL MILE
VALDESPARTERA
4
22/10/2013
SUSTAINABILITY
ENVIRONMENTAL
ECONOMIC
SOCIAL
PUBLIC INITIATIVE &
SUPPORT: GOVERNANCE
STATE
REGIONAL GOVERNMENT
LOCAL GOVERNMENT
U.E.
ACCUMULATION OF KNOWLEDGE & PARTICIPATION
UNIVERSITY
PRIVATE SECTOR
COMPANIES
CITIZENS
ECOCITY VALDESPARTERA: FOUNDATIONS
5
20022010
6
22/10/2013
PROJECT DESCRIPTION
Building area
Public area
Special installations
DENSITY 40 FLATS/HA
Total surface area 243.2 HaGeneral systems 60.5 HaSurface area of sector 182.7 HaEquipment and infrastructure 40.3 HaOpen space 27.6 HaRoad network 63.5 HaBuilding land 51.3 HaNumber of dwellings 9680
7
ECONOMIC INVESTMENTS
Edification Urbanization Remote Control Network
CUS
1000
135
3 3
SUBSIDIZED DWELLINGS: ≈ 1100 €/M2
LAND´S & BUILDING COST FOR SUBSIDIZED DWELLINGS: ≈950 €/M2.
OVER COST BIOCLIMATIC IMPROVEMENTS IN HOUSING: ≈7.200 €/FLAT
OVER COST REMOTE CONTROL NETWORK: ≈270€ /FLAT
PUBLIC SUBSIDY
22 MILL.
8
PROJECT STAGES
• BASIC CONDITIONS . BIOCLIMATIC COMMITMENT
PHASE 1: PLANNING AGREEMENT. ZARAGOZA CITY COUNCIL AND THE MINISTRY OF DEFENCE
• HOUSING PLANNING• DESIGN• MATERIALS• TECHNICAL BUILDING CODE• UNIVERSITY
PHASE 2: URBAN PLANNING
PHASE 3: DEVELOPMENT OF URBANIZATION
9
22/10/2013
SUSTAINABILITY: PROJECT OF URBAN PLANNING
10
DEVELOPMENT COSTS
4%
76%
8%
2%1%
5%
2%
Urban services (electric-ity, gas ...)Urban developmentRNBControl NetworkMaintenanceTechnical support specialistManagement cost
11
•18 €/T (TRAD. ~50 €/T)MAINTENANCE COST :
•26 € (FLAT/YEAR)MAINTENANCE COST (PRIVATE
PIPES):•0.2 KWH (FLAT/DAY).ENERGY
CONSUMPTION :
COST OF THE INSTALLATION (PUBLIC PIPES) 1357,23 €/flat
COST OF THE INSTALLATION (PRIVATE PIPES) 720 €/flat
VACUUM SYSTEM FOR WASTE
12
22/10/2013
REMOTE CONTROL NETWORK:TARGETS
•OPTIMIZING RESOURCES•DETECTING BREAKDOWN•AUTOMATIC BILLING
TECHNICAL MANAGEMENT
•LEARNING ABOUT THE BEHAVIOUR OF VALDESPARTERA•COMPARING WITH OTHER SIMILAR POPULATION AREAS•CHECKING THE EFFECTIVENESS OF THE BIOCLIMATIC
MEASURES TAKENCREATING THE ‘’KNOWLEDGE
DATEBASE”
•SPREADING RESULTS TO TECHNICAL SECTORS •ENCOURAGING CITIZEN TO PROPERLY USE OF RESOURCES /
TRAINING•IMPROVING FUTURE PLANNING AND DESIGNSHARING
KNOWLEDGE WITH CITIZENS
13
22/10/2013
NETWORK
DRINKING WATER.
IRRIGATION
RNB
PUBLIC LIGHTNING
METEO DATA
WATER METERS
ENERGY EFFIC. IN
BUILDINGS
SEWAGE
RAIN WATER
CONTROLLED NETWORKS
(300 KM)
FIELDBUS (30 KM, OPTICAL FIBER)
DATA INTERPRETATION
CENTRE
REMOTE CONTROL NETWORK: STRUCTURE
14
22/10/2013
ILLUSTRATION:DRINKING WATER SUPPLY NETWORK
WATER TANKS
• WATER QUALITY• CHLORINE• WATER LEVELS• WATER CONSUMPTION• VALVES, PUMPS• INTRUSION DETECT, ETC
PUMP PLANT
• AUTOMATION PROCESS• FLOW MEASURES
DISTRIBUTION PIPES
• FLOW METER (15)• VALVES CONTROL(31)• PRESSURE METER (21)
ENDING-PIPE SECTOR
• WATER QUALITY: TURBIDITY, CHLORINE(9)
HOMES
• WATER CONSUMPTION IN HOMES( 9.680)
Drinking Water
15
22/10/2013
TECHNOLOGICAL INFRAESTRUCTURE
¿¿¿ WHERE IS IT ???
16
22/10/2013
Drinking
Water
Flow meter
Water sampling
Motorized valveElectric cabinet
17
22/10/2013
Power Supply
Monitoring System
Drinking
Water
18
22/10/2013
Quality of Water Turbidity Chlorine Presure
Water quality sensors
Drinking
Water
Ending-pipe sector Purge-valve Control Flow meter
TECHNOLOGICAL INFRAESTRUCTURE
19
22/10/2013
REMOTE CONTROL NETWORK
P3
Comunication infrastructure
- 196 CONTROL POINT - 30 KM OPTICA FIBER
USING A UNIQUE COMMUNICATION INFRASTRUCTURE, THE SYSTEM COLLECT
DATA FROM ALL THE DIFFERENT NETWORKS AND STORE IT IN A MAIN-SERVER-
COMPUTER
20
SUSTAINABLE URBAN CENTER
21
22
• MONITORING OF HOUSING• WATER METERS• PNEUMATIC WASTE COLLECTION
23
LIVING LAB: CITIZENS
24
22/10/2013
Very efficie
nt: 5kW
h/m2/yr
Efficie
nt: 13 kW
h/m2/yr
According t
o estimate
s: 27 kW
h/m2/yr
High: 3
9 kWh/m
2/yr
Very High
: 59 kW
h/m2/yr
6%
22% 25%17% 14%
PERCENTAGE OF HOUSING
ENERGY CONSUMPTION IN HEATING
NATIONAL AVERAGE: 70 KWH/M2/YEAR
VALDESPARTERA: 27 KWH/M2/YEAR
SAVING 185€/YEAR1600 HOUSING ANALYSIS
25
22/10/2013
H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11
0.10 0.10
0.04
0.06
0.05
0.04
0.07
0.04
0.05
0.04
0.06
kWh/m2/year
NATIONAL AVERAGE: 0,11
VALDESPARTERA AVERAGE: 0,06
ELECTRICITY CONSUMPTION IN HOMES
SAVING 228€/YEAR
26
CHECK, DISSEMINATE AND PROMOTE SUSTAINABLE HABITS
27
SHOWCASE: SEMINARS, COURSES, PANEL DISCUSSIONS…
28
SMART CITIES NEED SMART CITIZENS
2929
22/10/2013
2004 GOOD2006 GOOD2012 BEST
HARVARD,LA SAPIENZA.
2005 CONCERTO.2007
PARLAM.
THANK YOU FOR YOUR ATTENTION.
30