1 BROOKHAVEN SCIENCE ASSOCIATES
Vacuum Systems
H.C. Hseuh, Vacuum Group Leader8th ASAC Meeting for NSLS-II Project
May 10-11, 2011
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline• Injector Vacuum Systems
• Storage Ring Vacuum Chambers• Cell vacuum chamber layout
• Cell chamber cross sections
• Cell chamber fabrication and assembly
• S4A, S5A and fast corrector chambers
• Production of Absorbers and RF Shielded Bellows
• Procurement of Pumps, Valves and Instruments
• Summary
3 BROOKHAVEN SCIENCE ASSOCIATES
Injector Vacuum Systems (1)• Linac
• Vacuum details agreed upon with Research Instruments (RI)• RI will purchase identical vacuum gauges, pumps and controllers• RI will use different PLC modules and interlock logics
• Linac-Booster Transport Line• Layout finalized, detail component design is underway• B1, B3 & B4 chambers fabricated• B2 design done, being fabricated• All pumps, pump controllers, gauges and valves purchased
B2 chamber model B3 & B4 chambersB1 chamber
4 BROOKHAVEN SCIENCE ASSOCIATES
Injector Vacuum Systems (2)• Booster Ring
• Arc chamber fabrication started at Budker after FDR in Feb• Straight section details & interface to TL are underway• Pumps, valves, gauges and controllers were purchased by BNL• PLC layout and logic were developed
– Same PLC chassis/modules will be used for Booster and Transport Lines– All six PLC wiring will be done by Budker
• Booster-Storage Ring Transport Line• General layout is completed• Detail design of four bending chambers is underway
– B1 and B3 will have Booster arc chamber profile– B2 and B4 will have exit port to dump and SLM
B1/B3 chamber
B2/B4 chamber
5 BROOKHAVEN SCIENCE ASSOCIATES
Cell Vacuum Chamber Layout
BM Beamline
ID Beamline
L.S.
S.S.
S2 S3S4 S5
S6
Short aluminum chambers
S1
S1
• 191 aluminum chambers, 3 – 5.5 m long• > 12 types (length, magnet cutouts, diag. etc.)
• 60 short aluminum chambers (S4A and S5A)• 30 x 1.5 m after BM-A; 30 x 0.6 m for 3PW
• 90 short inconel chambers for fast correctors (FC)• ID chambers: 6 DW, 1 EPU, 4 IVU, ….• Special ones for Inj., RF, Diag…
Dipole
Multipole
BLW BLW BLWBLW
BLW
BLW
S5A
BM-ABM-B
FC
FC
S4A
FC
6 BROOKHAVEN SCIENCE ASSOCIATES
Cell Chamber Cross Sections
RF screenNEGBPM
Stick absorber
Pump port Pump port Crotch absorber
Multipole Dipole
ID / 3PW fans
7 BROOKHAVEN SCIENCE ASSOCIATES
Chamber Extrusion and Bending
Extrusion bending ➾ ➾ machining ➾ cleaning ➾ welding assembly➾V #1,2 BNL V # 3 - 7 APS APS BNL
Inspection
Multipole
Bending at BNL50 ton press w 45 cm throat
3 m, 6o (ρ = 25m) accuracy to < 1.5 mm / 3m
before
after
Shims
Spacer
All extrusion completed in DecAll bending completed in Feb~ 20% extra extrusions available
8 BROOKHAVEN SCIENCE ASSOCIATES
Chamber Fabrication and Assembly
Robotic welding at APS
Vacuum certification
Bi-metal flanges
Machined extrusion
~ 10 chambers per month at APS and at BNL
Adaptor plate
Completed chamber
9 BROOKHAVEN SCIENCE ASSOCIATES
S4A, S5A & FC Chambers
S4A changed from inconel to aluminumRelocated BLW, added two flange ABSThree 1st articles met requirementsProduction of 31 S4A is underway
S4A ~ 500 watts
BM-A BM-B
S5A for 3PWFC
FC
FC
S5AS4A
FC are made by BNL Shop and brazed to flanges
S5A changed from stainless to aluminumOrders for 34 S5A placed with vendors
New design
Old design
10 BROOKHAVEN SCIENCE ASSOCIATES
Cell Chamber Production Status
11 BROOKHAVEN SCIENCE ASSOCIATES
Absorber locations and quantity
SS
S
C,F
C,F FS
> 8 ABS per cell, ~ 300 ABS for storage ring
12 BROOKHAVEN SCIENCE ASSOCIATES
Production of BM Photon Absorbers
Stick ABS w/ Stainless tube (130C/119C)
Crotch ABS w/ Cu tube (180C/127C)
Crotch ABS w/ wide opening (170C/107C)
Flange ABS
SC
C
F
• All ABS are made of GlidCop
• Re-design stick and crotch ABS after Sept review
• To improve cooling, reliability and corrosion resistance
• To make them easier to fabricate
• Added 90 flange ABS to protect d/s BLW from large beam deviations
• Production of 60+ ABS underway by two vendors and at BNL Shop
13 BROOKHAVEN SCIENCE ASSOCIATES
Production of RF shielded bellows
RF bellows requirementsMax mis-alignment: ± 2 mm Max extension: -15/+10 mm Max angle deviation: ±10 mradLow impedance
Outside finger design wide fingers, no brazing, water cooling @ d/s flange RF fingers assembled in-house
• Improved after Sept review and APS beam test• Better thermal contacts with fewer parts
• One sleeve, longer RF fingers, electroplating
• Stronger inconel springs for higher contact force
• Eight(8)1st articles completed by BNL Shop• Order of 240 bellows housings by vendor being placed
• All internal parts by BNL Shop
• Assembly by Vacuum staff
• APS beam test resumes in June
14 BROOKHAVEN SCIENCE ASSOCIATES
Vacuum Pumps and Valves
• Ion pumps (350) - 40% delivered
• Dual ion pump controllers (200) - 80% delivered
• Titanium sublimation pumps (300) - 70% delivered
• TSP power supplies (280) – 1st article received
• Custom NEG strips and supports (1500m)• All strips delivered, 40 % assembled into chambers• All NEG power supplies purchased
• Turbopump stations – compact design, 18 assembled
• RF shielded gate valves (62) – 1st article next week
• All metal gate valves (40) – order being placed
• Right angle valves (270) – 35% ordered and received
15 BROOKHAVEN SCIENCE ASSOCIATES
Gauges, RGA and PLC • Vacuum gauges and controllers (100 sets)
• 1st articles accepted, production has started
• Residual gas analyzers (53 sets) – bids are due in mid May
• Bakeout controllers – 4 needed for each cell bakeout• 4 available now, order placed for 9 more BC• Order for 3 mobile power distribution transformers placed
• All cables identified – low smoke, zero halogen, tray rated…• Cables for pentent 1 ordered and most delivered• Pentent 1 cable run lists provided to EE Group
• Programmable logic controllers (36)• Booster and TL PLC layouts generated and approved
– Six(6) PLC chassis and code to be done by Budker
• Storage ring PLC layout and chassis generated
16 BROOKHAVEN SCIENCE ASSOCIATES
Summary• Fabrication of transport line and Booster chambers has started
• Storage Ring cell chambers - 40% completed• ~ 10 chambers per month• Production of FC and S4A/S5A aluminum chambers started
• Production of RF bellows and absorbers started
• Procurement of pumps and controllers is ahead of schedule
• Procurement of vacuum gauges and RGA is underway
• Detail design of straight sections and exit pipes has started
• RFP for DW chambers is underway
• Girder and chamber integration has started
• Ready to start tunnel/mezzanine installation
S6 & exit pipe
DW chamber layout
FE
Cross section