FICHA TECNICA DE OBRA VALORIZACION DE OBRA N°02 SUPERVISION DE OBRA 1.00 A.D.P. N° : 009-2012-CEP/MDC 2.00 OBRA : 3.00 UBICACIÓN DEPARTAMENTO : JUNIN PROVINCIA : HUANCAYO DISTRITO : PUCARA LOCALIDAD : PUCARA 4.00 ENTIDAD CONTRATANTE : MUNICIPALIDAD DISTRITAL DE PUCARA 5.00 CONTRATISTA : CONSORCIO BOLOGNESI 6.00 SUPERVISOR DE OBRA : ING. JOSE AGUILAR VILCAHUAMAN 7.00 RESIDENTE DE OBRA : ING. ROLANDO PALACIOS CABELLO 8.00 PROYECTISTA : ING. VLADIMIR ARCE RECUAY 9.00 FINANCIA : CONVENIO MUNICIPALIDAD PROVINCIAL DE HUANCAYO 10.00 VALOR REFERENCIAL : S/. 970,000.00 INC. IGV. Mes Base : P.C /S/IGV 11.00 PRESUPUESTO CONTRATADO (PC) : S/. 970,000.00 INC. IGV. S/. 822,033.90 + 12.00 MODALIDAD : SUMA ALZADA 13.00 No. DE CONTRATO : 183-GM/MDC-2012 14.00 FECHA DE FIRMA DE CONTRATO : 12/28/2012 15.00 FECHA DE ENTREGA DE TERRENO : 10/12/2013 16.00 ADELANTO DIRECTO SOLICITADO : S/. 0.00 INC. IGV 17.00 ADELANTO DE MATERIALES SOLICITADO : S/. 0.00 INC. IGV 18.00 FECHA DE INICIO DEL PLAZO CONTRACTUAL : 10/14/2013 19.00 PLAZO DE EJECUCION : 120 DIAS CALENDARIO 20.00 FECHA DE TERMINO DE PLAZO CONTRACTUAL : 2/10/2014 "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. SICAINOS Y AV. CEMENTERIO DISTRITO DE PUCARA

Valorizacion 02 Supervision

Embed Size (px)

DESCRIPTION

Valorizacion 02 Supervision

Citation preview

Page 1: Valorizacion 02 Supervision

FICHA TECNICA DE OBRA

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

1.00 A.D.P. N° : 009-2012-CEP/MDC

2.00 OBRA :

3.00 UBICACIÓNDEPARTAMENTO : JUNINPROVINCIA : HUANCAYODISTRITO : PUCARALOCALIDAD : PUCARA

4.00 ENTIDAD CONTRATANTE : MUNICIPALIDAD DISTRITAL DE PUCARA

5.00 CONTRATISTA : CONSORCIO BOLOGNESI

6.00 SUPERVISOR DE OBRA : ING. JOSE AGUILAR VILCAHUAMAN

7.00 RESIDENTE DE OBRA : ING. ROLANDO PALACIOS CABELLO

8.00 PROYECTISTA : ING. VLADIMIR ARCE RECUAY

9.00 FINANCIA : CONVENIO MUNICIPALIDAD PROVINCIAL DE HUANCAYO

10.00 VALOR REFERENCIAL : S/. 970,000.00 INC. IGV. Mes Base : SETIEMBRE - 2013

P.C /S/IGV IGV11.00 PRESUPUESTO CONTRATADO (PC) : S/. 970,000.00 INC. IGV. S/. 822,033.90 + S/. 147,966.10

12.00 MODALIDAD : SUMA ALZADA

13.00 No. DE CONTRATO : 183-GM/MDC-2012

14.00 FECHA DE FIRMA DE CONTRATO : 12/28/2012

15.00 FECHA DE ENTREGA DE TERRENO : 10/12/2013

16.00 ADELANTO DIRECTO SOLICITADO : S/. 0.00 INC. IGV

17.00 ADELANTO DE MATERIALES SOLICITADO : S/. 0.00 INC. IGV

18.00 FECHA DE INICIO DEL PLAZO CONTRACTUAL : 10/14/2013

19.00 PLAZO DE EJECUCION : 120 DIAS CALENDARIO

20.00 FECHA DE TERMINO DE PLAZO CONTRACTUAL : 2/10/2014

"MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. SAN LORENZO, AV. HEROES SICAINOS Y AV. CEMENTERIO DISTRITO DE PUCARA-HUANCAYO-JUNIN"

Page 2: Valorizacion 02 Supervision

RESUMEN DE VALORIZACION DE OBRA N° 02 Del 01 de Noviembre al 30 de Noviembre del 2013

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESISUPERVISOR : ING. JOSE AGULAR VILCAHUAMANFECHA : 31 DE OCTUBRE DEL 2013PRESUPUESTO OFERTADO SIN IGV S/. 822,033.90PRESUPUESTO OFERTADO CON IGV S/. 970,000.00

ITEM CONCEPTO Presente Mes

I. AVANCE CONTRACTUAL DEL PRESENTE MESTotal I FORMULAS 132,041.32 77,259.09 209,300.41

Avance Fisico de la Obra 16.06% 9.40% 25.46%Avance Programado 0.00% 31.79% 31.79%

II. REAJUSTES Y REINTEGROSReajuste del presente mes 0.00 0.00Reintegro del mes anterior 0.00 0.00Reintegro del penultimo mes 0.00 0.00Total II 0.00 0.00 0.00

III. DEDUCCIONESIII.1 Deduccion del reajuste por adelanto de efectivoDel presente mes 0.00 0.00Mes anterior 0.00 0.00Penultimo mes 0.00 0.00Total III.1 0.00 0.00 0.00

III.2 Deduccion del reajuste por adelanto de materialesDel presente mes 0.00 0.00Mes anterior 0.00 0.00Penultimo mes 0.00 0.00Total III.2 0.00 0.00 0.00

IV. MONTO BRUTO (I + II - III.1 - III.2) 132,041.32 77,259.09 209,300.41

V. AMORTIZACIONESV.1 Amortizacion por adelanto en efectivo 0.00 0.00V.2 Amortizacion por adelanto de materiales 0.00 0.00Total V 0.00 0.00 0.00

VI. MONTO BRUTO A PAGAR (IV - V) 132,041.32 77,259.09 209,300.41

VII. I.G.V. (18% (VI)) 23,767.44 13,906.64 37,674.07

VIII. MONTO A FACTURAR (VI + VII) 155,808.76 91,165.73 246,974.48

IX GARANTIAS (FIEL CUMPLIMIENTO)

10% MONTO TOTAL (DOS PARTES) 0.00 48,500.00 48,500.00

X MONTO LIQUIDO A COBRAR (VIII-IX) 0.00 42,665.73 42,665.73

: “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR SAN LORENZO, AV. HEROES SICAINOS Y AV. CEMENTEREO DISTRITO PUCARA-HUANCAYO-JUNIN”

Acumulado Anterior

Acumulado Actual

Page 3: Valorizacion 02 Supervision

RESUMEN DE VALORIZACION

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA :

: “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA-HUANCAYO-JUNIN”PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARACONTRATISTA : CONSORCIO BOLOGNESISUPERVISION : ING. JOSE AGUILAR VILCAHUAMAN

FECHA : 31/10/2013

Item Descripción Costo DirectoValorización

Anterior Presente Mes Acumulado Saldo

1.00 : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION PUCARA 747,303.54 120,037.56 70,235.53 190,273.09 557,030.45

A TOTAL COSTO DIRECTO S/. 747,303.54 120,037.56 70,235.53 190,273.09 557,030.45

GASTOS GENERALES 7.00% 52,311.25 8,402.63 4,916.49 13,319.12 38,992.13

UTILIDADES 3.00% 22,419.11 3,601.13 2,107.07 5,708.19 16,710.91

B SUB TOTAL S/. 822,033.90 132,041.32 77,259.09 209,300.40 612,733.49

FACTOR DE RELACION 1.00

C TOTAL VALORIZADO SIN IGV 822,033.90 132,041.32 77,259.09 209,300.40 612,733.49

D PORCENTAJE DE AVANCE 100.00% 16.06% 9.40% 25.46% 74.54%

Page 4: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

01.00 OBRAS PROVISIONALES

01.01 CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00

1.00 1.00

02.00 TRABAJOS PRELIMINARES

02.01 LIMPIEZA DE TERRENO MANUAL M2 17,138.10

JR. BOLOGNESI 1.00 446.50 12.00 5,358.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 12.00 10,080.00

AV. HEROES SICAINOS 1.00 283.35 6.00 1,700.10

02.02 DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUCCION M2 180.00

6.00 10.00 3.00 180.00

02.03 TRAZO, NIVELES Y REPLANTEO DE VIAS M2 17,138.10

JR. BOLOGNESI 1.00 446.50 12.00 5,358.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 12.00 10,080.00

AV. HEROES SICAINOS 1.00 283.35 6.00 1,700.10

02.04 MOVILIZACION DE MAQUINARIAS GLB 1.00

1.00 1.00

03.00 MOVIMIENTO DE TIERRAS

03.01 EXCAVACION A NIVEL DE SUB RASANTE M3 5,743.96

JR. BOLOGNESI 1.00 2,199.36 2,199.36

JR. SAN LORENZO

AV. CEMENTERIO 1.00 2,963.40 2,963.40

AV. HEROES SICAINOS 1.00 581.20 581.20

03.02 PERFILADO Y COMPACTADO DE LA SUB RAZANTE M2 9,510.96

JR. BOLOGNESI 1.00 446.50 6.60 2,946.90

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 6.60 5,544.00

AV. HEROES SICAINOS 1.00 283.35 3.60 1,020.06

03.03 SUB BASE GRANULAR H=0.20 M. M2 9,510.96

JR. BOLOGNESI 1.00 446.50 6.60 2,946.90

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 6.60 5,544.00

AV. HEROES SICAINOS 1.00 283.35 3.60 1,020.06

03.04 BASE AFIRMADO E=0.20 M. M2 9,510.96

JR. BOLOGNESI 1.00 446.50 6.60 2,946.90

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 6.60 5,544.00

AV. HEROES SICAINOS 1.00 283.35 3.60 1,020.06

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

Page 5: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

03.05 CARGUIO Y TRANSPORTE BASE Y SUB BASE M3 3,804.38

JR. BOLOGNESI 2.00 446.50 6.60 0.20 1,178.76

JR. SAN LORENZO

AV. CEMENTERIO 2.00 840.00 6.60 0.20 2,217.60

AV. HEROES SICAINOS 2.00 283.35 3.60 0.20 408.02

03.06 ELIMINACION DE MATERIAL EXCEDENTE M3 4,536.74

GENERAL 1.00 4,536.74 4,536.74

04.00 PAVIMENTOS FLEXIBLES

04.01 IMPRIMACION ASFALTICA M2 0.00

JR. BOLOGNESI 1.00 0.00 6.60 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.60 0.00

AV. HEROES SICAINOS 1.00 0.00 3.60 0.00

04.02 CARPETA ASFALTICA EN CALIENTE E=2" M2 0.00

JR. BOLOGNESI 1.00 0.00 6.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.00 0.00

AV. HEROES SICAINOS 1.00 0.00 3.00 0.00

04.03 SELLADO ASFALTICO M2 0.00

JR. BOLOGNESI 1.00 0.00 6.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.00 0.00

AV. HEROES SICAINOS 1.00 0.00 3.00 0.00

05.00 SARDINEL

05.01 SARDINEL ENCOFRADO Y DESENCOFRADO M2 0.00

JR. BOLOGNESI 2.00 0.00 0.40 0.00

JR. SAN LORENZO 0.40

AV. CEMENTERIO 2.00 0.00 0.40 0.00

AV. HEROES SICAINOS 2.00 0.00 0.40 0.00

05.02 SARDINEL CONCRETO F'C=175 KG/CM² M3 0.00

JR. BOLOGNESI 2.00 0.00 0.15 0.50 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.15 0.50 0.00

AV. HEROES SICAINOS 2.00 0.00 0.15 0.50 0.00

06.00 DRENAJE PLUVIAL

06.01 CUNETA ENCOFRADO Y DESENCOFRADO M2 0.00

JR. BOLOGNESI 2.00 0.00 0.15 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.15 0.00

Page 6: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

AV. HEROES SICAINOS 2.00 0.00 0.15 0.00

06.02 CUNETA CONCRETO F'C=175 KG/CM² M3 0.00

JR. BOLOGNESI 2.00 0.00 0.30 0.10 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.30 0.10 0.00

AV. HEROES SICAINOS 2.00 0.00 0.30 0.10 0.00

09.00 SEÑALIZACION HORIZONTAL

09.01 PINTURA ZONAL CRUCE PEATONAL M2 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

09.02 PINTURA INTERM. DISCONT.-CENTRO DE VIA ML 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

09.03 PINTURA DE SIMBOLOS - FLECHAS M2 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

Page 7: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

01.00 OBRAS PROVISIONALES

01.01 CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00

1.00 1.00

02.00 TRABAJOS PRELIMINARES

02.01 LIMPIEZA DE TERRENO MANUAL M2 720.00

JR. BOLOGNESI 1.00 180.00 4.00 720.00

JR. SAN LORENZO

AV. CEMENTERIO 0.00 0.00 0.00 0.00

AV. HEROES SICAINOS 0.00 0.00 0.00 0.00

02.02 DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUCCION M2 30.00

1.00 10.00 3.00 30.00

02.03 TRAZO, NIVELES Y REPLANTEO DE VIAS M2 2,573.00

JR. BOLOGNESI 1.00 446.50 2.00 893.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 840.00 2.00 1,680.00

AV. HEROES SICAINOS 0.00 0.00 0.00 0.00

02.04 MOVILIZACION DE MAQUINARIAS GLB 0.25

0.25 0.25

03.00 MOVIMIENTO DE TIERRAS

03.01 EXCAVACION A NIVEL DE SUB RASANTE M3 776.13

JR. BOLOGNESI 0.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 776.13 776.13

AV. HEROES SICAINOS 0.00 0.00 0.00

03.02 PERFILADO Y COMPACTADO DE LA SUB RASANTE M2 2,208.06

JR. BOLOGNESI 0.00 0.00 6.60 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 180.00 6.60 1,188.00

AV. HEROES SICAINOS 1.00 283.35 3.60 1,020.06

03.03 SUB BASE GRANULAR H=0.20 M. M2 3,306.00

JR. BOLOGNESI 1.00 240.00 6.60 1,584.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 130.00 6.60 858.00

AV. HEROES SICAINOS 1.00 240.00 3.60 864.00

03.04 BASE AFIRMADO E=0.20 M. M2 3,372.00

JR. BOLOGNESI 1.00 120.00 6.60 792.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 260.00 6.60 1,716.00

AV. HEROES SICAINOS 1.00 240.00 3.60 864.00

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

Page 8: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

03.05 CARGUIO Y TRANSPORTE BASE Y SUB BASE M3 2,671.20

JR. BOLOGNESI 2.00 360.00 6.60 0.20 950.40

JR. SAN LORENZO

AV. CEMENTERIO 2.00 390.00 6.60 0.20 1,029.60

AV. HEROES SICAINOS 2.00 480.00 3.60 0.20 691.20

03.06 ELIMINACION DE MATERIAL EXCEDENTE M3 340.26

GENERAL 1.00 340.26 340.26

04.00 PAVIMENTOS FLEXIBLES

04.01 IMPRIMACION ASFALTICA M2 0.00

JR. BOLOGNESI 1.00 0.00 6.60 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.60 0.00

AV. HEROES SICAINOS 1.00 0.00 3.60 0.00

04.02 CARPETA ASFALTICA EN CALIENTE E=2" M2 0.00

JR. BOLOGNESI 1.00 0.00 6.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.00 0.00

AV. HEROES SICAINOS 1.00 0.00 3.00 0.00

04.03 SELLADO ASFALTICO M2 0.00

JR. BOLOGNESI 1.00 0.00 6.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 6.00 0.00

AV. HEROES SICAINOS 1.00 0.00 3.00 0.00

05.00 SARDINEL

05.01 SARDINEL ENCOFRADO Y DESENCOFRADO M2 0.00

JR. BOLOGNESI 2.00 0.00 0.40 0.00

JR. SAN LORENZO 0.40

AV. CEMENTERIO 2.00 0.00 0.40 0.00

AV. HEROES SICAINOS 2.00 0.00 0.40 0.00

05.02 SARDINEL CONCRETO F'C=175 KG/CM² M3 0.00

JR. BOLOGNESI 2.00 0.00 0.15 0.50 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.15 0.50 0.00

AV. HEROES SICAINOS 2.00 0.00 0.15 0.50 0.00

06.00 DRENAJE PLUVIAL

06.01 CUNETA ENCOFRADO Y DESENCOFRADO M2 0.00

JR. BOLOGNESI 2.00 0.00 0.15 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.15 0.00

Page 9: Valorizacion 02 Supervision

METRADOS EJECUTADOS

Del 01 de Noviembre al 30 de Noviembre del 2013

VALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

CONTRATISTA : CONSORCIO BOLOGNESI

MODALIDAD : A Suma Alzada MES : Octubre

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA PERIODO : Del 14 al 31 de Octubre

RESIDENTE : Ing. Rolando Silvio Palacios Cabello DIAS ACUMULADOS : 20 días calendario

SUPERVISOR : Ing. Jose Aguilar Vilcahuaman FECHA DE VALORIZACIÓN : 31 - Octubre - 2013

ITEM DENOMINACION UND VECES LARGO ANCHO ALTO PARCIAL SUB-TOTAL

: "MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA - HUANCAYO - JUNIN"

AV. HEROES SICAINOS 2.00 0.00 0.15 0.00

06.02 CUNETA CONCRETO F'C=175 KG/CM² M3 0.00

JR. BOLOGNESI 2.00 0.00 0.30 0.10 0.00

JR. SAN LORENZO

AV. CEMENTERIO 2.00 0.00 0.30 0.10 0.00

AV. HEROES SICAINOS 2.00 0.00 0.30 0.10 0.00

09.00 SEÑALIZACION HORIZONTAL

09.01 PINTURA ZONAL CRUCE PEATONAL M2 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

09.02 PINTURA INTERM. DISCONT.-CENTRO DE VIA ML 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

09.03 PINTURA DE SIMBOLOS - FLECHAS M2 0.00

JR. BOLOGNESI 1.00 0.00 0.00

JR. SAN LORENZO

AV. CEMENTERIO 1.00 0.00 0.00

AV. HEROES SICAINOS 1.00 0.00 0.00

Page 10: Valorizacion 02 Supervision

VALORIZACION DE OBRA N°02

SUPERVISON DE OBRA

OBRA : “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA-HUANCAYO-JUNIN”

FORMULA : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION PUCARA

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA

CONTRATISTA : CONSORCIO BOLOGNESI

SUPERVISION : ING. JOSE AGUILAR VILCAHUAMAN

FECHA : 30 DE NOVIEMBRE DEL 2013

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO A EJECUTAR

UND. METRADO P.U. PARCIAL METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO % METRADO VALORIZADO %

I : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION PUCARA 747,303.54

01.00. OBRAS PROVISIONALES

01.01. CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00 945.87 945.87 0.00 0.00 0.00% 1.00 945.87 100.00% 1.00 945.87 100.00% 0.00 0.00 0.00%

02.00. TRABAJOS PRELIMINARES

02.01. LIMPIEZA DE TERRENO MANUAL M2 17,138.10 0.46 7,883.53 15,352.10 7,061.97 89.58% 720.00 331.20 4.20% 16,072.10 7,393.17 93.78% 1,066.00 490.36 6.22%

02.02. DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUCCION M2 180.00 5.16 928.80 90.00 464.40 50.00% 30.00 154.80 16.67% 120.00 619.20 66.67% 60.00 309.60 33.33%

02.03. TRAZO, NIVELES Y REPLANTEO DE VIAS M2 17,138.10 0.77 13,196.34 11,992.10 9,233.92 69.97% 2,573.00 1,981.21 15.01% 14,565.10 11,215.13 84.99% 2,573.00 1,981.21 15.01%

02.04. MOVILIZACION DE MAQUINARIAS GLB 1.00 5,000.00 5,000.00 0.50 2,500.00 50.00% 0.25 1,250.00 25.00% 0.75 3,750.00 75.00% 0.25 1,250.00 25.00%

03.00. MOVIMIENTO DE TIERRAS

03.01. EXCAVACION A NIVEL DE SUB RASANTE M3 5,743.96 2.42 13,900.38 4,967.83 12,022.15 86.49% 776.13 1,878.23 13.51% 5,743.96 13,900.38 100.00% 0.00 0.00 0.00%

03.02. PERFILADO Y COMPACTADO DE LA SUB RASANTE M2 9,510.96 1.54 14,646.88 7,038.90 10,839.91 74.01% 2,208.06 3,400.41 23.22% 9,246.96 14,240.32 97.22% 264.00 406.56 2.78%

03.03. SUB BASE GRANULAR H=0.20 M. M2 9,510.96 5.35 50,883.64 4,092.00 21,892.20 43.02% 3,306.00 17,687.10 34.76% 7,398.00 39,579.30 77.78% 2,112.96 11,304.34 22.22%

03.04. BASE AFIRMADO E=0.20 M. M2 9,510.96 6.06 57,636.42 0.00 0.00 0.00% 3,372.00 20,434.32 35.45% 3,372.00 20,434.32 35.45% 6,138.96 37,202.10 64.55%

03.05. CARGIO Y TRANSPORTE BASE Y SUB BASE M3 3,804.38 6.60 25,108.91 0.00 0.00 0.00% 2,671.20 17,629.92 70.21% 2,671.20 17,629.92 70.21% 1,133.18 7,478.99 29.79%

03.06. ELIMINACION DE MATERIAL EXCEDENTE M3 4,536.74 13.35 60,565.54 4,196.48 56,023.01 92.50% 340.26 4,542.47 7.50% 4,536.74 60,565.48 100.00% 0.00 0.06 0.00%

04.00. PAVIMENTOS FLEXIBLES

04.01. IMPRIMACION ASFALTICA M2 9,510.96 5.11 48,601.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9,510.96 48,601.01 100.00%

04.02. CARPETA ASFALTICA EN CALIENTE E=2" M2 8,569.05 31.96 273,866.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8,569.05 273,866.84 100.00%

04.03. SELLADO ASFALTICO M2 8,569.05 6.06 51,928.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8,569.05 51,928.44 100.00%

05.00. SARDINEL

05.01. SARDINEL ENCOFRADO Y DESENCOFRADO M2 1,255.48 20.66 25,938.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,255.48 25,938.22 100.00%

05.02. SARDINEL CONCRETO F'C=175 KG/CM² M3 235.40 246.23 57,962.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 235.40 57,962.54 100.00%

06.00. DRENAJE PLUVIAL

06.01. CUNETA ENCOFRADO Y DESENCOFRADO M2 470.81 20.66 9,726.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 470.81 9,726.93 100.00%

06.02. CUNETA CONCRETO F'C=175 KG/CM² M3 94.16 260.66 24,543.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 94.16 24,543.75 100.00%

09.00. SEÑALIZACION HORIZONTAL

09.01. PINTURA ZONAL CRUCE PEATONAL M2 90.00 21.32 1,918.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 90.00 1,918.80 100.00%

09.02. PINTURA INTERM. DISCONT.-CENTRO DE VIA ML 525.00 2.74 1,438.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 525.00 1,438.50 100.00%

09.03. PINTURA DE SIMBOLOS - FLECHAS M2 45.00 15.16 682.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 45.00 682.20 100.00%

1 COSTO DIRECTO 747,303.54 120,037.56 70,235.53 190,273.09 557,030.45

2 GASTOS GENERALES 7.00% 52,311.25 8,402.63 4,916.49 13,319.12 38,992.13

3 UTILIDADES 3.00% 22,419.11 3,601.13 2,107.07 5,708.19 16,710.91

4 TOTAL PRESUPUESTO 822,033.90 132,041.32 77,259.09 209,300.40 612,733.49

5 FACTOR DE RELACION (1,00) 1.00 1.00 1.00 1.00 1.00 1.00

6 TOTAL VALORIZADO SIN IGV 822,033.90 132,041.32 77,259.09 209,300.40 612,733.49

7 PORCENTAJE DE AVANCE 100% 16.06% 9.40% 25.46% 74.54%

% DE AVANCE MENSUAL A EJECUTADO 9.40%

% DE AVANCE ACUMULADO 25.46%

Page 11: Valorizacion 02 Supervision

CRONOGRAMA VALORIZADO DE OBRA

UBICACIÓN : PUCARA - HUANCAYO - JUNINFECHA : OCTUBRE DEL 2013

Item Descripción Und Metrado P.U Parcial (S/.) Mes 1 Mes 2 Mes 3 Mes 4

01.00 OBRAS PROVISIONALES 945.87 945.87 0.00 0.00 0.00

01.01 CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00 945.87 945.87 945.87

02.00 TRABAJOS PRELIMINARES 27,008.67 13,914.81 3,531.29 3,531.29 6,031.29

02.01 LIMPIEZA DE TERRENO MANUAL M2 17,138.10 0.46 7,883.53 7,883.53

02.02 DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUCC M2 180.00 5.16 928.80 232.20 232.20 232.20 232.20

02.03 TRAZO, NIVELES Y REPLANTEO DE VIAS M2 17,138.10 0.77 13,196.34 3,299.09 3,299.09 3,299.09 3,299.09

02.04 MOVILIZACION DE MAQUINARIAS GLB 1.00 5,000.00 5,000.00 2,500.00 2,500.00

03.00 MOVIMIENTO DE TIERRAS 222,741.77 222,741.77 0.00 0.00 0.00

03.01 EXCAVACION A NIVEL DE SUB RASANTE M3 5,743.96 2.42 13,900.38 13,900.38

03.02 PERFILADO Y COMPACTADO DE LA SUB RAZANTE M2 9,510.96 1.54 14,646.88 14,646.88

03.03 SUB BASE GRANULAR H=0.20 M. M2 9,510.96 5.35 50,883.64 50,883.64

03.04 BASE AFIRMADO E=0.20 M. M2 9,510.96 6.06 57,636.42 57,636.42

03.05 CARGIO Y TRANSPORTE BASE Y SUB BASE M3 3,804.38 6.60 25,108.91 25,108.91

03.06 ELIMINACION DE MATERIAL EXCEDENTE M3 4,536.74 13.35 60,565.54 60,565.54

04.00 PAVIMENTOS FLEXIBLES 374,396.29 0.00 24,300.51 24,300.51 325,795.28

04.01 IMPRIMACION ASFALTICA M2 9,510.96 5.11 48,601.01 24,300.51 24300.51

04.02 CARPETA ASFALTICA EN CALIENTE E=2" M2 8,569.05 31.96 273,866.84 273,866.84

04.03 SELLADO ASFALTICO M2 8,569.05 6.06 51,928.44 51,928.44

05.00 SARDINEL 83,900.76 0.00 83,900.76 0.00 0.00

05.01 SARDINEL ENCOFRADO Y DESENCOFRADO M2 1,255.48 20.66 25,938.22 25,938.22

05.02 SARDINEL CONCRETO F'C=175 KG/CM² M3 235.40 246.23 57,962.54 57,962.54

06.00 DRENAJE PLUVIAL 34,270.68 0.00 0.00 34,270.68 0.00

06.01 CUNETA ENCOFRADO Y DESENCOFRADO M2 470.81 20.66 9,726.93 9,726.93

06.02 CUNETA CONCRETO F'C=175 KG/CM² M3 94.16 260.66 24,543.75 24,543.75

07.00 SEÑALIZACION HORIZONTAL 4,039.50 0.00 0.00 0.00 4,039.50

07.01 PINTURA ZONAL CRUCE PEATONAL M2 90.00 21.32 1,918.80 1,918.80

07.02 PINTURA INTERM. DISCONT.-CENTRO DE VIA ML 525.00 2.74 1,438.50 1,438.50

07.03 PINTURA DE SIMBOLOS - FLECHAS M2 45.00 15.16 682.20 682.20

COSTO DIRECTO 747,303.54 237,602.46 111,732.55 62,102.47 335,866.07

GASTOS GENERALES 7.00% 52,311.25 16,632.17 7,821.28 4,347.17 23,510.62

UTILIDAD 3.00% 22,419.11 7,128.07 3,351.98 1,863.07 10,075.98

SUBTOTAL 822,033.90 261,362.70 122,905.81 68,312.71 369,452.67

IGV (18%) 18.00% 147,966.10 47,045.29 22,123.05 12,296.29 66,501.49

TOTAL PRESUPUESTO 970,000.00 308,407.99 145,028.86 80,609.00 435,954.15

PORCENTAJE MENSUAL % 31.79% 14.95% 8.31% 44.94%PORCENTAJE ACUMULADO % 31.79% 46.75% 55.06% 100.00%

PROYECTO : “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. HEROES SICAINOS, AV. CEMENTERIO Y JR. ALEJANDRO O DEUSTUA, DISTRITO DE PUCARA- HUANCAYO-JUNIN”

Page 12: Valorizacion 02 Supervision

CONTROL DE AVANCE DE OBRAVALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA

CONTRATISTA : CONSORCIO BOLOGNESI

SUPERVISION : ING. JOSE AGUILAR VILCAHUAMAN

FECHA : 31/10/2013

Inicio MES 1 MES 2 MES 3 MES 4PROGRAMADO 0.00% 31.79% 14.95% 8.31% 44.94%ACUMULADO 0.00% 31.79% 46.75% 55.06% 100.00%

EJECUTADO 0.00% 16.06% 9.40%ACUMULADO 0.00% 25.46% 34.86%

: “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA-HUANCAYO-JUNIN”

Inicio MES 1 MES 2 MES 3 MES 40%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

31.79%

46.75%55.06%

100.00%

25.46%

34.86%

LEYENDARow 33

Row 36

% D

E A

VA

NCE

Page 13: Valorizacion 02 Supervision

PRESUPUESTO DE OBRAVALORIZACION DE OBRA N°02

SUPERVISION DE OBRA

OBRA

FORMULA : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION PUCARA

PROPIETARIO : MUNICIPALIDAD DISTRITAL DE PUCARA

CONTRATISTA : CONSORCIO BOLOGNESI

SUPERVISION : ING. JOSE AGUILAR VILCAHUAMAN

FECHA : 31 DE OCTUBRE DEL 2013

ITEM DESCRIPCION PRESUPUESTO CONTRACTUAL

UND. METRADO P.U. PARCIAL

I : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION PUCARA 747,303.54

01.00. OBRAS PROVISIONALES 945.87

01.01. CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00 945.87 945.87

02.00. TRABAJOS PRELIMINARES 27,008.67

02.01. LIMPIEZA DE TERRENO MANUAL M2 17,138.10 0.46 7,883.53

02.02. DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUCCION M2 180.00 5.16 928.80

02.03. TRAZO, NIVELES Y REPLANTEO DE VIAS M2 17,138.10 0.77 13,196.34

02.04. MOVILIZACION DE MAQUINARIAS GLB 1.00 5,000.00 5,000.00

03.00. MOVIMIENTO DE TIERRAS 222,741.77

03.01. EXCAVACION A NIVEL DE SUB RASANTE M3 5,743.96 2.42 13,900.38

03.02. PERFILADO Y COMPACTADO DE LA SUB RAZANTE M2 9,510.96 1.54 14,646.88

03.03. SUB BASE GRANULAR H=0.20 M. M2 9,510.96 5.35 50,883.64

03.04. BASE AFIRMADO E=0.20 M. M2 9,510.96 6.06 57,636.42

03.05. CARGIO Y TRANSPORTE BASE Y SUB BASE M3 3,804.38 6.60 25,108.91

03.06. ELIMINACION DE MATERIAL EXCEDENTE M3 4,536.74 13.35 60,565.54

04.00. PAVIMENTOS FLEXIBLES 374,396.29

04.01. IMPRIMACION ASFALTICA M2 9,510.96 5.11 48,601.01

04.02. CARPETA ASFALTICA EN CALIENTE E=2" M2 8,569.05 31.96 273,866.84

04.03. SELLADO ASFALTICO M2 8,569.05 6.06 51,928.44

05.00. SARDINEL 83,900.76

05.01. SARDINEL ENCOFRADO Y DESENCOFRADO M2 1,255.48 20.66 25,938.22

05.02. SARDINEL CONCRETO F'C=175 KG/CM² M3 235.40 246.23 57,962.54

06.00. DRENAJE PLUVIAL 34,270.68

06.01. CUNETA ENCOFRADO Y DESENCOFRADO M2 470.81 20.66 9,726.93

06.02. CUNETA CONCRETO F'C=175 KG/CM² M3 94.16 260.66 24,543.75

09.00. SEÑALIZACION HORIZONTAL 4,039.50

09.01. PINTURA ZONAL CRUCE PEATONAL M2 90.00 21.32 1,918.80

09.02. PINTURA INTERM. DISCONT.-CENTRO DE VIA ML 525.00 2.74 1,438.50

09.03. PINTURA DE SIMBOLOS - FLECHAS M2 45.00 15.16 682.20

1 COSTO DIRECTO 747,303.54

2 GASTOS GENERALES 7.00% 52,311.25

3 UTILIDADES 3.00% 22,419.11

4 TOTAL PRESUPUESTO SIN IGV 822,033.90

5 IMPUESTO GENERAL A LA VENTA IGV 18.00% 147,966.10

6 TOTAL VALORIZADO CON IGV 970,000.00

: “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. CEMENTEREO Y AV. HEROES SICAINOS DEL DISTRITO DE PUCARA-HUANCAYO-JUNIN”