Upload
veronica-wilkerson
View
217
Download
0
Embed Size (px)
DESCRIPTION
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand Requirements on VD design VELO workshop in Amsterdam (April ‘00): Top/bottom halves should have intermediate steps (not only open/closed), with `relaxed’ overall position accuracy (0.3 mm). Only useful if we can acquire meaningful data in intermediate positions ! trigger algorithm Higher cooling power required (20 W/module 40 W/module) to accommodate for backup solution SCTA/velo. Should be no problem for CO 2 cooling system, but is it realistic at all ? thermal modeling needed
Citation preview
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
LHCb Vertex Detector System:Status Report
J.F.J. van den BrandSubatomic Physics Group, VUA - NIKHEF
• Review of TP design mechanics, vacuum system, cooling system.
• Requirements more cooling power,
intermediate Y positions of two halves
• Milestones
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Mechanics: “TP” design
Side flange
Bending hinges
Detector support and cooling
Bellows (22000signal wires)
Support frame
Si detector
moves by 30 mmonly two positions:open or closed !!
See LHCb 99-042/VELO
top half = bottom half
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Requirements on VD designVELO workshop in Amsterdam (April ‘00):
• Top/bottom halves should have intermediate steps (not only open/closed), with `relaxed’ overall position accuracy (0.3 mm). Only useful if we can acquire meaningful data in intermediate positions ! trigger algorithm
• Higher cooling power required (20 W/module 40 W/module) to accommodate for backup solution SCTA/velo. Should be no problem for CO2 cooling system, but is it realistic at all ?
thermal modeling needed
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Modified design
VELO Design:
• Single flange • XY table•CO2 cooling•WF suppressors•Second. vacuum•Studied
• assembly• alignment
•To do• further design• FEA
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Vacuum tank• new FEA required (probably additional ribs are needed)• flange will be on inside of LHC ring • solves lack of space issue on outside of ring• all feedthroughs on the same big flange • all cables and repeater cards on same side (present choice of feedthrough limits total number of pins to about 25,000 !!)
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Detector Modules
Number of planes: 25
Discuss
Liverpool delivers modules
40 W, 1 m cable, 50 % isolation thickness, 10 - 15 K T, radiative cooling
44 pins,440 / module
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Detector Mounting
Install Modules
3D alignment
Mount References
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Wake field Suppressor
Central cooling line
Temperature sensors (2 per station, 4 wires per measurement
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Wake field Suppressor
Welding tests: 250 m Al
FEA: Beryllium
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Foil design options (continued)
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Foil design options (continued)
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Foil design options (continued)
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
CO2 Cooling Tubes
Cooling tubes
1.1 (0.9) mm S.St.
Welding and brazing
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
CO2 Cooling Tests
Cooling system
-30o C
40 W/module
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Detector Assembly
• External reference marks• Wires fed through 7 bellows• Structure connects to frame
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames• No more problems of bending: stiff, stable structure• XY-table can move down enough to allow insertion of complete detector (tilting mechanism no longer needed)• frames not any longer `in our way’ (more accessibility to critical items of VD)
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames
• FEA studies ongoing• Connect to outside• Allows vacuum tests
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames
• How to mount?• How to align?• Vacuum testing?• Cabling?• Rigidity?
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames
• Wake field screens• 3-point support• Alignment• XY table
• 5 mm, - 25 mm• Reset switches• LVDTs• Step motors
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames
•S.St. vacuum vessel•Exit foil by CERN
• RICH conflict?• Mounting RF shield?• Coating - Au, ..• z = 970 mm
• Acceptance• 300 mrad (hor.)• 250 mrad (vert.)• from IP• zero bunchlength
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Support frames
• Steel frame• Fill with sand• Dimensions
• 1630 mm• 1500 mm• 1200 mm
• Align frame within 1 - 2 mm• Fix frame
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Detector and support frame• both halves on same side• VD easier to mount and position in the tank• install complete VD at once• the two halves are no longer interchangeable
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Vacuum Tests
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Vacuum Tests
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
TP design
center frame
New design
Sideways accessibility (1)
Side wake field suppressors
Ti evaporatorNo room onthe sides !
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Sideways accessibility (2)• More access to critical WF suppressor• Much room left on one side of the tank 2ary vacuum pumps (pumping on the detector boxes is more efficient) if required, a Ti eva- porator with much more favorable design conditions
vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand
Cooling system with mixed-phase CO2
Phase diagram CO2
1
10
100
-80 -70 -60 -50 -40 -30 -20 -10 0 10 20 30 40 50
Temperature [°C]
Pre
ssur
e [b
ar]
vapor
liquidsolidgas
critical point
triple point
*