  • Wi-MAX BTS INSTALLATION-Indoor

  • BTS Rack Positioning

  • Battery Bank

  • Cable routing through tray

  • BSNL DCDB (-48 V DC) & DC power should be extended from DC Breaker to WiMAX BTS Rack DCDB Panel

  • Termination of DC Input for WiMAX Rack from Bsnl

    - 48 V DC+48 v DC

  • Termination of Grounding Cable for WiMAX Rack from BSNL &WiMAX DCDB panel to be grounded with nearest electrical grounding bus-bar

    & WiMAX BTS Rack to be grounded

    GND

  • MCB LINK PLATE

    IDU 1

    IDU 2

    RRHA

    RRHB

    RRHC

    E1

    CO

    NV

    ER

    TE

    R

    Ring Type Lug Pin Type Lug

    INP

    UT

    S - 48V DC+ ve

    GND

    - 48V OUTPUTS

    Need to use Ring Type lugs

    Need to use Pin Type lugs

    +VE OUTPUTs

    1- Dual Pole MCB 6- Single Pole MCBS

    GROUND OUTPUTS

    DCDB CONNECTIVITY DIAGRAM WITH MCB LINK PLATE

    MCB Holding Plate

  • DCDB in Rack & WiMAX MCB(DC Breaker ) should be installed and tapped nearby BSNL DCDB

  • BSNL Input cable connected to DCDB

  • Input looping for all MCBs in DCDB

  • Input cable and Output cable connected to DCDB

  • Cable vent & RRH ground bus bar

  • Checking of Input Source (- 48 V) , Power level voltage to be verified for DCDB Panel and documented

  • Fixing of IDU in the Rack

  • Termination of Input cable for IDU from DCDB

  • Cable routing in tray

  • Cable routed & connected to our BTS

  • DC Connectors connected to WiMAX IDU

    Power 1 - Primary

    Power 2 - Secondary

  • Power 1 Primary Input

    Power 2 Secondary Input

  • BTS Outdoor installation photographs

  • Fixing of Sectorial Antennas

    TOP

    BOTTOM

  • Remove the cover and check the conditons of the connectors

  • RRH Clamp Installations

    Third BracketSecond Bracket

    First Clamp

    Double side Bolts & Nuts

  • Install the RRH Holding clamps as per below

  • RRH before installation

  • Holding clamps for RRH

    Bottom side of RRH

    RF Antenna Ports

    DC Input

    Fiber Input

  • Installation Tower

    Free Space for Installing Antenna Mount

  • Use pulley to pull the RRH & Sectorial antenna

  • Mounting of Antenna Mount along with Antenna

  • Mounting of Antenna Mount along with Antenna

  • Installing the Antenna Mount along with Antenna

  • Fixing of RRH on the Antenna Mount

  • Fixing of RRH on the Antenna Mount

  • Tighten the RRH clamp bolts

  • Rechecking the antenna mounts, Antennas and RRH

  • Position of installed equipments in tower

  • RRH & Antenna position

  • Position of Antenna Mount along with Antennas & RRH for all 3 Sectors

    Sector 3 - Gamma

    Sector 1 - Alpha

    Sector 2 - Beta

  • RRHDCCABLES

    FIBERCABLES

    RRH DC Cable & Fiber Cable

  • Cable Tray from Tower to BTS building/ Shelter Entry

  • Cable vent & RRH ground bus bar

  • Installation of GPS ANTENNA

  • GPS Antenna cable

  • Thread the bottom connector to the GPS Antenna

  • Installtion of the bottom connector of the GPS Antenna

  • Installation of the adjustment clamp of the GPS Antenna

  • Fixing of the adjustment clamp of the GPS Antenna

  • Bolts & Nuts for Installing GPS Antenna

  • Fixing of Bolts & Nuts

  • After fixing of Bolts & Nuts

  • Fixing of Wall Mount Clamp to GPS Antenna

  • Positioning of Wall Mount Clamp to GPS Antenna

  • Fixing of Wall Mount Clamp using bolts & nuts

  • Tighten the bolts & nuts

  • GPS Antenna installed on Tower

  • GPS Antenna fixed using U Clamps on Tower

  • Fixing of GPS Antenna on Wall

    WiMAX GPS

  • Need to purchase the U clamp to fix the GPS Antenna

    Fixing of GPS Antenna in GI Pipe using U Clamp

  • RRH Side Connector

    Fiber Cable

  • IDU Side Connector

    RRH Side Connector

    Fiber Cable

  • Fixing of GPS Antenna in Wall

  • ZTE OCLAN SWITCH

    WiMAX BH terminated in GE port and extended to BTS

  • UTSTAR OCLAN SWITCH

    WiMAX BH terminated in GE port and extended to BTS

  • ASN Reachable check

  • BTS Reflecting in EMS

  • E1 Media converter @ BTS for NON OCLAN

  • ROSETTE or I/O BOX Top View

  • BSNL MDF

  • Backhaul extension to Atrie converter

    E1 Media Converter installed & grounded

  • BETASEC

    TOR

    ALPHA

    SECTO

    R

    GAM

    MA

    SECTO

    R

    GPS

    Antenna FiberCables

    R PERouter

    INTERNET

    RRH

    WiMAXRACK

    DCDB

    16 E1 toEth

    converter

    WiMAXIDU

    Network Schematic Diagram ofBSNL WiMAX BTS

    Power Cables

    OCLAN LOCATION

    16 E1 to EthconverterE1 Lines/STM

    OCLAN

    RF Cables

    CLOUD

    GPS Antenna Cable

    ASN

    MCR

    HA

    EMS

    12 3 4 5

    GWN

    ASN

    CSN Connectivity Services Network

    Mobile Subscriber

    Metro Core RouterAccess Service NetworkHome AgentElement Management System

    MCRASNHAEMS

    802.16e Remote Radio HeadRRHProvider Edge

    CSN

    PE

  • Optimization & DT

  • BTS Optimization:-

    Sectors azimuth and tilt to be done as per RF planning.If needed, azimuth and tilt to be changed as per DT report.

    Drive Test:-

    Ensure DT software loaded in to the laptop.Laptop to be connected to the GPS & USB dongle or CPEs as per coverage then open the Drive test tool.Required parameters to be selected in DT tool.Select the record mode in DT tool and start test and record the session for DT.Move in and around 15km from the BTS sectors wise and record the same.If needed, re-optimization to be done in BTS based on DT report.

  • Sample DT GUI report

  • Sample Excel report

  • Coverage& Mobility

  • Refer file name

    Coverage & Mobility

  • Remove the Outer Sleeve of the cable upto 3 inch

  • Remove the Outer Sleeve of the cable upto 3 inch

  • Colour of the cable should be like this Blue-Green-Red

  • Remove the sleeve of the cable for 1/2 inch

  • Insert the cable into the Lugs

  • Insert the cable into the Lugs properly

  • Crimp the Lugs by crimping tool not with any other tool which is shown below

  • Check Whether the Lugs have crimped properly

  • Check Whether all the Lugs have crimped properly

  • Solder the lugs properly

  • Check wheather the all the lugs Soldered properly

  • Insert the bottom shell of the connector into the cables

  • Check the top shell connectors have numbering

  • 2 1

    3

    BlueRed

    Check the top shell connectors have numbering

    Green

  • Insert the cables as per the numbering

    Blue 1Red 2Green - 3

  • Insert the cables fully into the connectors

  • Check wheather the lugs inserted properly in top

  • Check wheather the lugs came out from the holes

  • Insulate the cables in the bottom of the connectors & use heat sink blower for proper connectivity

  • Insulation tape must be applied firmly

  • Tight packing of connetor

  • Insulate the cables in the bottom of the connectors

  • Thread the Top & Bottom connectors

  • Cable holder need to be screwed properly

  • Cable holder need to be screwed properly

  • Final connetorization