February 2005 Work Management Process Alignment Work Management Process Alignment Engineering

WMPA Lee Presentation

Embed Size (px)

Citation preview

Page 1: WMPA Lee Presentation

February 2005 Work Management Process

Alignment

Work Management Process Alignment Engineering

Page 2: WMPA Lee Presentation

MSS History

•Implemented in 1987•Mechanism to capture and manage information•Links various operations through a common database•Improved efficiency and accuracy of information being used

Page 3: WMPA Lee Presentation

Work Management System The Work Management

System is the focal point of the MSS System which monitors and tracks company wide work flow to insure proper planning and ultimate use of all resources.

Page 4: WMPA Lee Presentation

Work Management System

$140 Million67,000 Work Requests

1,000+ Employees Daily

Page 5: WMPA Lee Presentation

Work Management Work Requests Work Mgt

Construction Street Light Leased Lighting E, G, W

Distribution

Non-Work Mgt Substation Operations Telecom

Page 6: WMPA Lee Presentation

Work ManagementSubsystems

Closing

PlantAcct

ContractMgmt

CU/MU

WorkScheduling

Work Requesting

WMS

Design&

Estimating

Page 7: WMPA Lee Presentation

Major Responsibilities

ContractAnalysis

WRSchedules

SpecialCosts

WMSystemSupport

WMS

Page 8: WMPA Lee Presentation

Where we want to go…

Page 9: WMPA Lee Presentation

Vision

To be the Work Management Process Owner by providing highly accurate estimates, highly accurate schedules, and highly efficient customer support, thus improving the overall integrity of the WMS

Page 10: WMPA Lee Presentation

Mission To provide innovative, process-

driven services for the Work Management System and its’ users that make a positive contribution to the vision of MLGW and the mission of the Analysis, Strategy and Performance Department.

Page 11: WMPA Lee Presentation

Highlights for 2005 Improved confidence level of labor

standards Training Perceived contracts accuracy

(ACT) Work Management Process Team

Page 12: WMPA Lee Presentation

Organizational ChartDirector, ASPDana Jeanes

WM Engr Lvl IIIRuss Counce

BSEE

WM Engr Lvl IIILinda Whittaker

BSME

WM Engr Lvl IIIMartrice Anderson

BSME

Admin AsstStephanieRehnelt

WM Engr Lvl IThai Tran

BSIE

Work Management ProcessAlignment

SupportSusan Carter

SupportGuy Thomason

WM Engr Lvl IV(open)

WorkManagementSupervisor

Tonya Jordan

WM Engr Lvl IIIPhyllis Hunt

BSIE

Page 13: WMPA Lee Presentation

Workload Analysis

Work Management System Support Area Responsibilities Projected

Man Hours Financial Impact

CU/MU/CS - Creation and general maintenance - Field Observations/Time studies

850 2,000

Designer reports Provide Design vs Actual cost comparison reports to Engr. Mgrs/VPs 88

Crew Updates Update crew and labor rates for all WM crews 316

Automated Estimating Monitoring Monitor accuracy of Design and Estimating System in MSS 633

Work Management Training (construction crews and engineering) 400 Monitor/adjust costs of material purchases included in CUs 120 Truck Inventory Attend truck inventory meetings and assist with physical counts 288

WM Process Team Leader Between Depts (Monthly meetings) 192 New WM System Preliminary Design 1,000

Total Man Hours 5,887

$89,600,000

Page 14: WMPA Lee Presentation

Workload AnalysisResource Spreading

Area Responsibilities Projected Man Hours

Financial Impact

Monitor Resource Spreading Allocations (SL/Pavement Replacement) 210 Total Man Hours 210

$5,000,000

Work Request Schedules

Area Responsibilities Projected Man Hours

Financial Impact

Network Changes - MSS - BCIS

500 704

Organization Numbers Updates Maintain accurate organization numbers in Personnel Database (WRs) 100

Total Man Hours 1,304

Page 15: WMPA Lee Presentation

Workload AnalysisSpecial Projects

Area Responsibilities Projected Man Hours

Financial Impact

Develop New Training Manuals/Documents 528 Special Projects (1 month/yr for 4 engineers) 700

Total Man Hours 1,228

Schedule of Charges Area Responsibilities Projected

Man Hours Financial Impact

Schedule of Charges Update the E,G,& W Policy Costs that are charged to customers 485

Fixed Charges Update fixed estimates used by Customer Engr 110

Future Costs of Service Update estimates for OH service and UG meter costs use by Res. Engr. 15

Total Man Hours 610

$5,286,707

Page 16: WMPA Lee Presentation

Workload AnalysisManual Estimates

Area Responsibilities Projected Man Hours

Financial Impact

TDOT State Reimbursable Estimates Prepare documents and provide cost estimates for TDOT WRs 350

Non-Work Management Estimates Provide non-WM estimates for various engineering areas 100

$262,000

Total Man Hours 450

Contract Analysis Area Responsibilities Projected

Man Hours Financial Impact

Utilization Percentages Provide utilization percentages for E,G, W & SL construction contracts 88

Provide MLGW Bid for E,G & W construction contracts (3 contracts) 1188 Provide cost analysis of all construction contracts 440

Total Man Hours 1,716

$21,000,000

Total WMPA Projected Man Hours: 11,405

Page 17: WMPA Lee Presentation

# of people needed

7.3 Engineers

Page 18: WMPA Lee Presentation

“The Howard closing”

Page 19: WMPA Lee Presentation

Work Requesting

Work Request Creation Work Request Schedule Review Work Request Activity Completion

Page 20: WMPA Lee Presentation

Work Scheduling

Crew Data Work Request Network Schedules Work Management Users Database

Page 21: WMPA Lee Presentation

CU/MU Compatible Units Macro Units Construction Standards

Page 22: WMPA Lee Presentation
Page 23: WMPA Lee Presentation
Page 24: WMPA Lee Presentation
Page 25: WMPA Lee Presentation
Page 26: WMPA Lee Presentation
Page 27: WMPA Lee Presentation

Design & Estimating

CU/MU Entered Automated Estimating of Design

Cost

Page 28: WMPA Lee Presentation

Contract Management

Construction Contract Units Pavement Replacement

Page 29: WMPA Lee Presentation

Major Responsibilities WM Systems Support

Process owner 52,700 WM Work Requests $100 - $140 Million Dollars

CU/MU/CS Number of Compatible Units Electric: 6,765 Gas & JT: 3,674 Water: 3,538 Total: 13,977

Page 30: WMPA Lee Presentation

Major Responsibilities WM Systems Support (cont.)

Crew labor rates 266 Crews (Work Management Crews) 914 Individual Workers (Based on

Average Crew Sizes) Average Labor Rate for each crew:

$67.64 Average Equipment Rate for each crew:

$30.03

Page 31: WMPA Lee Presentation

Major Responsibilities WM Systems Support (cont.)

CU/MU trainingOver 550 WMS users

Design vs. Actual cost comparisons 12,729 Work Requests Design: $56.7 Million Actual: $56.2 Million Percent Difference: -0.89%

Page 32: WMPA Lee Presentation

Major Responsibilities Special Costs

Schedule of Charges 135 costs that we charge to any outside

entity TDOT estimates

5 estimates for the state of Tenn in 2004 Special non-work management

estimates 7 manual estimates performed in 2004

Page 33: WMPA Lee Presentation

Major Responsibilities Work Request Schedules

WR Scheduling Process and Networks 67,000 Work Requests 1,392 Work Request Networks 337 Work Request Activities

Page 34: WMPA Lee Presentation

Major Responsibilities Contract Analysis

Electric, gas, and water construction contracts

375 Contract Units $21 Million

Non-construction contractsApprox $10 Million