LAPORAN KEMAJUAN PROJEK NO.23
‘JULAI 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
ADTEC TAIPING
LOKASI PROJEK
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
KEMAJUAN KERJA FIZIKAL
JADUAL : 95.18 %SEBENAR : 95.42 %KESELURUHAN : 0.24 %
TARIKH LAPORAN : 10 JULAI 2009
KEMAJUAN KERJA KEWANGAN
JADUAL : 94.99 %SEBENAR : 94.97 %KESELURUHAN : -0.02 %
TARIKH LAPORAN : 10 JULAI 2009
Graf Kemajuan Kerja Fizikal Sehingga 10/7/2009 (EOT 1)
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Bulan
Per
atu
s %
% Kem. Fizikal J adual Asal
% Kem. Fizikal Sebenar
% Kem. Fizikal J adual EOT NO.1
% Kem. Fizikal J adual Asal 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 70.88 84.22 99.14 100.00
% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03 73.45 80.28 87.59 95.42
% Kem. Fizikal J adual EOT NO.1 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03 73.45 79.69 85.16 95.18 100.00
16-05-
07
25-06-
07
24-07-
07
20-08-
07
13-09-
07
18-10-
07
09-11-
07
05-12-
07
12-01-
08
21-02-
08
27-03-
08
15-04-
08
29-05-
08
08-07-
08
15-07-
08
22-08-
08
19-09-
08
28-10-
0814-11-08
04-12-
08
08-01-
09
12-02-
09
11-03-
09
15-04-
09
16-05-
09
12-06-
09
10-07-
09
13-08-
09
% Kem. Fiz ikal Jadual EO T 95.18%
% Kem. Fiz ikal Sebenar 95.42%
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 94.21% 96.74% 2.53%
JULAI 09’ 98.28% 99.36% 1.08%
MECHANICAL PLANNED
ACTUAL
AIR COND 98.46% 100.00%
FIRE FIGHTING 92.70% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS NA NA
PA 100.00% 93.51%
SMATV 100.00% 99.29%
CCTV NA NA
ICT 100.00% 99.25%
DEWAN BESAR
DEWAN BESAR
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.68% 99.72% 0.04%
JULAI 09’ 99.95% 100.00% 0.05%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 98.80% 100.00%
SUBMAIN CABLE 97.69% 100.00%
DB 75.00% 100.00%
LUMINAIRE 94.22% 100.00%
MAIN S/BOARD NA NA
LPS NA NA
PA NA NA
SMATV NA NA
CCTV 100.00% 98.70%
ICT NA NA
LOBI UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 98.54% 98.19% -0.35%
JULAI 09’ 99.93% 99.94% 0.01%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 90.81% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 75.00% 100.00%
LUMINAIRE 99.82% 100.00%
MAIN S/BOARD 75.00% 100.00%
LPS 98.84% 98.00%
PA 84.88% 93.10%
SMATV NA NA
CCTV NA NA
ICT 90.38% 99.00%
DEWAN KULIAH UTAMA
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 97.50% 98.54% 1.04%
JULAI 09’ 99.42% 99.83% 0.42%
MECHANICAL PLANNED
ACTUAL
AIR COND 98.33% 100.00%
FIRE FIGHTING 84.79% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 98.77% 100.00%
SUBMAIN CABLE 96.40% 100.00%
DB 85.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 85.00% 100.00%
LPS 93.29% 98.29%
PA 91.27% 94.22%
SMATV 100.00% 99.63%
CCTV NA NA
ICT 28.81% 81.00%
PUSAT SUMBER / PERPUSTAKAAN
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 96.42% 96.51% 0.09%
JULAI 09’ 99.37% 99.66% 0.29%
MECHANICAL PLANNED
ACTUAL
AIR COND 95.34% 100.00%
FIRE FIGHTING 92.57% 87.38%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 99.00%
SUBMAIN CABLE 100.00% 100.00%
DB 85.00% 100.00%
LUMINAIRE 96.42% 98.00%
MAIN S/BOARD 75.00% 100.00%
LPS 87.80% 96.95%
PA 21.28% 91.07%
SMATV 100.00% 99.57%
CCTV 100.00% 99.90%
ICT 78.44% 92.00%
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.58% 99.23% -0.35%
JULAI 09’ 100.00% 99.85% -0.15%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 78.00% 100.00%
KITCHEN EQUIP. 83.70% 92.00%
LPG INSTALL. 82.56% 90.00%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD NA NA
LPS 100.00% 93.78%
PA 100.00% 92.30%
SMATV 100.00% 99.43%
CCTV NA NA
ICT 0.00% 100.00%
KAFETERIA
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 98.05% 98.01% -0.05%
JULAI 09’ 99.85% 99.70% -0.15%
MECHANICAL PLANNED
ACTUAL
AIR COND 94.61% 100.00%
FIRE FIGHTING 83.25% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00 % 100.00 %
SUBMAIN CABLE 100.00 % 100.00%
DB 100.00 % 100.00%
LUMINAIRE 100.00 % 100.00%
MAIN S/BOARD 75.00% 100.00%
LPS 100.00% 98.22%
PA 100.00% 95.30%
SMATV 100.00% 99.79%
CCTV 100.00% 99.30%
ICT 89.88% 82.28%
BENGKEL TEKNOLOGI MAKLUMAT
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 98.42% 98.30% -0.12%
JULAI 09’ 99.99% 99.61% -0.38%
MECHANICAL PLANNED
ACTUAL
AIR COND 98.20% 100.00%
FIRE FIGHTING 90.15% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 93.26% 95.00%
DUST CONTROL NA NA
PROCESS COOLING
91.12% 39.45%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 75.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 75.00% 95.00%
LPS 100.00% 98.22%
PA 98.80% 95.87%
SMATV 76.76% 98.87%
CCTV 100.00% 99.32%
ICT 97.03% 81.86%
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 98.46% 98.41% -0.05%
JULAI 09’ 99.87% 99.64% -0.23%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 89.89% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 93.26% 95.00%
DUST CONTROL 87.72% 96.58%
PROCESS COOLING
91.30% 22.05%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 96.25%
PA 100.00% 94.94%
SMATV 79.29% 98.24%
CCTV 100.00% 99.20%
ICT 97.00% 80.81%
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 97.15% 97.14% -0.02%
JULAI 09’ 99.20% 99.60% 0.40%
MECHANICAL PLANNED
ACTUAL
AIR COND 96.66% 100.00%
FIRE FIGHTING 86.34% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 93.26% 95.00%
DUST CONTROL 92.74% 95.59%
PROCESS COOLING
47.25% 39.45%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 99.29% 100.00%
DB 78.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 85.00% 100.00%
LPS 100.00% 98.05%
PA 100.00% 95.15%
SMATV 77.45% 97.54%
CCTV 100.00% 99.34%
ICT 100.00% 82.44%
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 96.50% 96.99% 0.48%
JULAI 09’ 98.70% 99.63% 0.94%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 81.58% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 93.26% 95.00%
DUST CONTROL 58.90% 96.91%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 98.98% 100.00%
SUBMAIN CABLE 97.49% 100.00%
DB 97.48% 100.00%
LUMINAIRE 89.27% 100.00%
MAIN S/BOARD 85.25% 100.00%
LPS 89.22% 97.89%
PA 88.09% 93.93%
SMATV 100.00% 98.97%
CCTV 100.00% 99.00%
ICT 15.65% 81.61%
BENGKEL KEJ. JAMINAN KUALITI
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 95.58% 95.59% 0.01%
JULAI 09’ 98.23% 98.62% 0.39%
MECHANICAL PLANNED
ACTUAL
AIR COND 97.16% 100.00%
FIRE FIGHTING 80.91% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 93.26% 95.00%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 99.00%
SUBMAIN CABLE 99.95% 100.00%
DB 96.10% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 99.48% 98.16%
PA 97.01% 94.88%
SMATV 100.00% 99.30%
CCTV 100.00% 98.91%
ICT 98.34% 92.94%
BENGKEL MIKRO ELEKTRONIK
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 100.00% 100.00% 0.00%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 97.60%
PA NA NA
SMATV 100.00% 98.74%
CCTV 100.00% 99.82%
ICT 100.00% 100.00%
KUARTERS KELAS ‘B’
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 100.00% 100.00% 0.00%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 97.66%
PA NA NA
SMATV 100.00% 98.55%
CCTV NA NA
ICT 100.00% 99.06%
KUARTERS KELAS ‘C’
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 100.00% 100.00% 0.00%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 97.96%
PA NA NA
SMATV 100.00% 98.74%
CCTV NA NA
ICT 100.00% 100.00%
KUARTERS KELAS ‘C’ + ‘D’
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 98.63% 98.85% 0.12%
JULAI 09’ 99.99% 100.00% 0.01%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 99.02% 98.32%
PA NA NA
SMATV 100.00% 99.83%
CCTV NA NA
ICT 99.42% 99.34%
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.57% 99.58% 0.01%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G
(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 98.32%
PA NA NA
SMATV 100.00% 99.83%
CCTV NA NA
ICT 100.00% 98.37%
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.83% 96.63% 0.01%
JULAI 09’ 99.82% 100.00% 0.18%
MECHANICAL PLANNED
ACTUAL
AIR COND 98.79% 100.00%
FIRE FIGHTING 78.92% 100.00%
KITCHEN EQUIP. 83.70% 92.00%
LPG INSTALL. 82.56% 90.00%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 98.51%
PA 96.95% 95.23%
SMATV 100.00% 99.43%
CCTV NA NA
ICT 100.00% 100.00%
DEWAN MAKAN
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.39% 99.55% 0.16%
JULAI 09’ 99.97% 100.00% 0.03%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 40.44% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 98.60%
PA 93.00% 96.06%
SMATV 99.82% 99.31%
CCTV 100.00% 99.78%
ICT 100.00% 99.43%
ASRAMA LELAKI A & B
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.44% 99.50% 0.06%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 92.70% 100.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 97.77% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 98.69%
PA 94.38% 95.64%
SMATV 99.75% 99.31%
CCTV 100.00% 99.75%
ICT 100.00% 99.62%
ASRAMA PEREMPUAN C & D
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 96.94% 96.63% -0.31%
JULAI 09’ 98.50% 99.90% 1.40%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 80.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 85.00% 100.00%
LPS 99.32% 97.61%
PA 86.67% 92.79%
SMATV NA NA
CCTV NA NA
ICT NA NA
SURAU
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 99.99% 99.83% -0.16%
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 80.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 96.60%
PA 98.28% 93.55%
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
ASTAKA
MONTH PLANNED ACTUAL AHEAD / DELAY
JULAI 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 99.53%
FIRE FIGHTING 78.13% 99.22%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 96.52% 100.00%
MAIN S/BOARD 80.52% 100.00%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
DECORATIVE FENCE
BANGUNAN SOKONGAN
GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
RUMAH SAMPAH
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN
GELANGGANG PERMAINAN
PADANG PERMAINAN BOLA SEPAK
BENGKEL MIKRO - CLEANROON
M&E : AHU @ CLEAN ROOM
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) - EPOXY
PERABUT – PUSAT SUMBER
• SEKIAN TERIMA KASIH