Welcome toHICOM Automotive
Manufacturer Malaysia
MODEL INVOLVE
INTRODUCTIONTime Line1st Week• Induction programme.• 4H High Voltage Awereness Programne
(include test).• Department segregation (Production
Engineering Dept./Comercial Vehicle).• Line Visit
2nd Week• Visit Light Duty Line• Make stopper for Oil Drum (task)-CUTI HARI RAYA-3rd Week• Stopper Oil Drum
4th Week• Starting making of ‘Standard Working
Instruction’ (SWI)- start from CH2( axle)• Complete CH3(piping)• Update signage (Pre Leveling)5th Week• Truck engine noise (Vehicle Problem)• Complete SWI on CH4 (wiring)
Signage PPE
5th Week (cont’d)• Product Levelling (Auditor From Japan-
Mr. Kumamoto).• Process Levelling (Auditor From India-
Mrs. Shanti).• Report Recheck, Redo, Redone.
Audit in progress Remind Operator On SOP and AOS
6th Week• Documentation on SWI CH4(wiring)• Completing SWI CH5(Fuel Tank)7th Week- Present• Torque wrench Registration and
Recalibration for new Fuso Model Medium Duty (05TA)
Marking torque wrench
THANK YOU FOR LISTENING