PARTIDA DESCRIPCION
03 .05 .02 .04 .01 ESTRIBOS3.05.02.04.01.01 ACERO FY=4200 Kg / cm2 PARA ESTRIBOS
ACERO EN PANTALLA ALETAS DE ESTRIBOCara ExteriorHorizontales exterior
Cara Interior
Horizontales interior
ACERO EN PANTALLA DE ESTRIBOCara ExteriorHorizontales exterior
Cara Interior
Horizontales interior
ACERO EN ZAPATAS DE ESTRIBOCara Inferior
Cara Superior
ACERO EN ZAPATAS DE ALETASCara Inferior
Cara Superior
PROYECTO : "CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTAUBICACIÓN: LOCALIDAD: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
PROYECTO : "CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA" (KM6-KM9)UBICACIÓN: LOCALIDAD: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
PARTIDA DESCRIPCION
ENCOFRADO Y DESENCOFRADO EN ESTRIBOS DE PUENTEALETAS
ESTRIBOS
03 .05 .02 .04 .02 VIGA PRINCIPAL03.05.02.04.02.01 ENCOFRADO Y DESENCOFRADO VIGAS PRINCIPALES
LadosFondos
03.05.02.04.02.02 ACERO FY=4200 Kg / cm2 P/ VIGASViga Lateral ExteriorV1V2V3V4V5V6V7V8
Viga Central interiorV1V2V3V5V6V7V8
03.05.02.04.02.03 CONCRETO F´C =280 kg / cm2 P/ VIGAS
PARTIDA DESCRIPCION
03.05.02.04.03 VIGA DIAFRAGMA03.05.02.04.03.01 ENCOFRADO Y DESENCOFRADO EN VIGAS DIAFRAGMA
FONDOS
03 .05 .02 .04 .01 .02
PROYECTO : "CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6-KM 9 )"UBICACIÓN: LOCALIDAD: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
03.05.02.04.03.02 ACERO FY=4200 KG/CM2 VIGA DIAFRAGMAD1D2D3D4
03.05.02.04.03.03 CONCRETO F´C= 280 KG/CM2 VIGA DIAFRAGMA
03.05.02.04.04 LOSAS DE CONCRETO ARMADO ( PUENTES)03.05.02.04.04.01 ENCOFRADO Y DESENCOFRADO DE LOSAS
03.05.02.04.04.02 ACERO FY=4200 Kg/cm P / LOSASL1
L2L3L4L5
03.05.02.04.04.03 CONCRETO LOSA F´C = 280 KG/CM2 P/ LOSAS
03.05.02.04.05 VEREDAS
03.05.02.04.05.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS
03.05.02.04.05.02 ACERO FY=4200 KG/CM2 P / VEREDASL6L7
PARTIDA DESCRIPCION
03.05.02.04.05.03 CONCRETO VEREDA F´C = 210KG / CM2 P/ VEREDAS
03.05.02.04.05.04 ACERO DE REFUERZO FY=4200 KG / CM2 (ANCLAJE Y A
PROYECTO : "CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6-KM 9 )"UBICACIÓN: LOCALIDAD: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
03 .05 .02 .04 .06 ASFALTADO03.05.02.04.06.01 RIEGO DE LIGANTE ASFALTICO
03.05.02.04.06.02 CARPETA ASFALTICA
03 .05 .02 .04 .07 OBRA FALSA03.05.02.04.07.01 ENCOFRADO Y DESENCOFRADO DE DADOS DE
FALSO PUENTE
03.05.02.04.07.02 CONCRETO 1:10 + 30% P.M. EN DADOS DE CONCRETO
03.05.02.04.07.03 MADERA EN FALSO PUENTEDURMIENTES (EUCALIPTO ) 16"x16"PIES DERECHO S (EUCALIPTO ) 4"x4"
TABLONES (1 1/ 2"x12")TABLAS . (1"x8")TABLAS (1"x12")SOLERAS 3.00m x 4"x4"
03 .05 .02 .04 .08 APOYO DE NEOPRENE03.05.02.04.08.01 APOYOS FIJOS DE NEOPRENO DE 300x400x30 mm
03.05.02.04.05.02 APOYOS MOVILES DE NEOPRENO DE 300x400x30 mm
03 .05 .02 .04 .09 VARIOS
03.05.02.04.09.01 BARANDA DE TUB. FoGo , MONTAJE, COLOCACIONY SOLDADO .
03.05.02.04.09.02 TUBO DE DRENAJE PVC -SAP 3"
03.05.02.04.09.03 JUNTA DE DILATACION EN PUENTE
PA RTIDA DESC RIPC IO N
PROYECTO : "CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6- KM 9)UBICACIÓN: LOCALIDAD: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
CONCRETODESCRIPCION MEDIDAS
LARGO ANCHOESTRIBOSACERO FY=4200 Kg / cm2 PARA ESTRIBOSACERO EN PANTALLA ALETAS DE ESTRIBO
4444
444444
ACERO EN PANTALLA DE ESTRIBO2222
222222
22222
ACERO EN ZAPATAS DE ESTRIBO2222
ACERO EN ZAPATAS DE ALETAS222
CONCRETO
CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA: HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
NroVECES
CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA" (KM6-KM9): HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
DESCRIPCION MEDIDA SLARGO ANCHO
2
ENCOFRADO Y DESENCOFRADO EN ESTRIBOS DE PUENTEALETAS 8
4
84
VIGA PRINCIPALENCOFRADO Y DESENCOFRADO VIGAS PRINCIPALES
84
ACERO FY=4200 Kg / cm2 P/ VIGAS
22222222
2222222
CONCRETO F´C =280 kg / cm2 P/ VIGAS 4 10.00 0.30
CONCRETODESCRIPCION M EDIDAS
LARGO ANCHO
ENCOFRADO Y DESENCOFRADO EN VIGAS DIAFRAGMA 105
NroVECES
CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6-KM 9 )": HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
NroVECES
ACERO FY=4200 KG/CM2 VIGA DIAFRAGMA
CONCRETO F´C= 280 KG/CM2 VIGA DIAFRAGMA 5 4.20 0.30
LOSAS DE CONCRETO ARMADO ( PUENTES)ENCOFRADO Y DESENCOFRADO DE LOSAS 2
23
ACERO FY=4200 Kg/cm P / LOSAS1
CONCRETO LOSA F´C = 280 KG/CM2 P/ LOSAS 1 10.00 6.60
VEREDAS
ENCOFRADO Y DESENCOFRADO DE VEREDAS 242
ACERO FY=4200 KG/CM2 P / VEREDAS
CONCRETODESCRIPCION M EDIDAS
LARGO ANCHO
CONCRETO VEREDA F´C = 210KG / CM2 P/ VEREDAS 2 10.00 0.95
ACERO DE REFUERZO FY=4200 KG / CM2 (ANCLAJE Y A
CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6-KM 9 )": HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
NroVECES
ASFALTADORIEGO DE LIGANTE ASFALTICO 1 10.00 6.00
CARPETA ASFALTICA 1 10.00 6.00
OBRA FALSAENCOFRADO Y DESENCOFRADO DE DADOS DE
1212
CONCRETO 1:10 + 30% P.M. EN DADOS DE CONCRETO 6 8.00 0.60
MADERA EN FALSO PUENTE p ulgDURMIENTES (EUCALIPTO ) 16"x16" 9 8.30 16PIES DERECHO S (EUCALIPTO ) 4"x4" 176 3.00 4
11 6.00 12165 3.00 122 7.50 1143 3.00 4
APOYO DE NEOPRENEAPOYOS FIJOS DE NEOPRENO DE 300x400x30 mm 4
APOYOS MOVILES DE NEOPRENO DE 300x400x30 mm 4
VARIOS
BARANDA DE TUB. FoGo , MONTAJE, COLOCACION2 10.00
TUBO DE DRENAJE PVC -SAP 3" 10 1.00
JUNTA DE DILATACION EN PUENTE 2 7.70
C O NC RETODESC RIPC IO N M EDIDA S
LA RG O A NC HO
CONSTRUCCION DE LA TROCHA CARROZABLE HUASTA - VILLALTA ( KM 6- KM 9): HUASTA - VILLALTA, DISTRITO : HUASTA, PROVINCIA: BOLOGNESI, DEPARTAMENTO : ANCASH
NroVEC ES
CONCRETO ENCOFRADO ACEROMEDIDAS TOTAL MEDIDAS TOTAL No
ALTO (M3 ) LARGO A LTO (M2 ) DIAM . VARILLAS LONGITUD
3/ 4" 29 6.61/ 2" 31 3.61/ 2" 14 3.61/ 2" 13 3.6
3/ 4" 29 3.23/ 4" 14 4.23/ 4" 14 7.51/ 2" 33 3.51/ 2" 18 3.51/ 2" 22 3.5
3/ 4" 56 6.31/ 2" 31 71/ 2" 14 71/ 2" 5 7
3/ 4" 29 3.23/ 4" 14 4.63/ 4" 14 6.81/ 2" 33 71/ 2" 18 71/ 2" 7 7
5/ 8" 103 1.75/ 8" 65 2.41/ 2" 16 8.53/ 4" 54 3.21/ 2" 13 7.1
5/ 8" 38 6.63/ 4" 42 5.45/ 8" 38 6.63/ 4" 42 5.4
5/ 8" 26 3.63/ 4" 22 45/ 8" 26 3.6
CONCRETO ENCOFRADO ACERO
MEDIDA S TOTAL MEDIDAS TOTA L NoALTO (M 3 ) LARGO ALTO (M2 ) DIAM . VARILLAS LONGITUD
3/ 4" 22 4
920 .844.31 8.35 287.910.80 8.35 26.72
314 .638.60 8.35 574.480.95 8.35 31.73
606 .21
10.00 1.22 97.6010.00 0.45 18.00
115 .60
1" 4 10.901" 4 9.101" 4 5.701" 2 5.70
5/ 8" 4 10.101" 3 11.50
1/ 2" 2 10.101/ 2" 86 3.80
1" 3 10.901" 3 9.101" 3 5.70
5/ 8" 4 10.101" 3 11.50
1/ 2" 2 10.101/ 2" 86 3.80
0.4 4.80
4 .80
CONCRETO ENCOFRADO ACEROM EDIDAS TOTAL MEDIDAS TOTAL No
ALTO (M 3 ) LARGO ALTO (M 2 ) DIAM . VARILLA S LONGITUD
4.20 0.40 16.84.20 0.25 5.3
22.05
5/8" 6 7.353/8" 63 2.601/2" 6 6.453/4" 12 6.75
1 6.30
6.30
10.00 0.76 15.210.00 0.18 3.69.30 1.6 44.64
63.44
5/8" 51 6.80
5/8" 67 7.001/2" 18 10.603/8" 32 10.601/2" 8 10.60
0.2 13.20
13.20
10.00 0.15 30.95 0.15 0.57
10.00 0.7 1417.57
3/8" 20 10.601/2" 134 2.90
CONCRETO ENCOFRADO A C EROM EDIDAS TOTAL MEDIDAS TOTAL No
ALTO (M 3 ) LARGO ALTO (M2 ) DIAM . VARILLA S LONGITUD
0.175 3.33
3 .33
5/ 8" 9 0.70
1/ 2" 9 0.30
60 .00
0.07 4 .20
8.00 1.00 960.60 1.00 72
103 .2 m2
1.00 28 .80 m3
p ulg 20 .00 92 184.0016 5224.92 Pie 24 2308.20 Pie 2
7533 .1115 324.59 Pie 28 1081.97
12 540.984 1875.41 Pie 2
3822 .95
4 .00 und
4 .00 und
20 .00 ml
10 .00 ml
15 .40 ml
C O NC RETO ENC O FRA DO A C EROM EDIDA S TO TA L M EDIDA S TO TA L No
A LTO (M 3 ) LA RG O A LTO (M 2 ) DIA M . VA RILLA S LO NG ITUD
LONGITUD TOTAL
ø 3 / 8 " ø 1 / 2 " ø 5 / 8 " ø 3 / 4 " ø 1 "
766 1730.256446 455.328202 205.632187 190.944
371 838.912258 582.176420 949.2
462 471.24252 257.04308 314.16
706 1594.656434 442.68196 199.9270 71.4
186 419.456129 291.088190 430.304
462 471.24252 257.0498 99.96
350.2 560.32312 499.2
272 277.44346 781.056
185 188.292
501.6 802.56454 1025.136
501.6 802.56454 1025.136
187.2 299.52176 397.76
187.2 299.52
LONGITUD TOTA L
SUB TOTAL(KG )
TOTAL(KG )
ø 3 / 8 " ø 1 / 2 " ø 5 / 8 " ø 3 / 4 " ø 1 "176 397.8 17628 .89
0 00 00 00 0
87 352.28873 294.11246 184.22423 92.112
81 129.2869 278.76
40 41.208654 666.672
65 264.21655 220.58434 138.168
81 129.2869 278.76
40 41.208654 666.672 3777 .54
LONGITUD TOTAL
ø 3 / 8 " ø 1 / 2 " ø 5 / 8 " ø 3 / 4 " ø 1 "
SUB TOTAL(KG )
TOTAL(KG )
SUB TOTAL(KG )
TOTA L(KG )
44.1 70.56163.8 95.00
38.7 39.4781 183.06 388.10
346.8 554.88
469 750.40190.8 194.62
339.2 196.7484.8 86.50 1783.13
212 122.96388.6 396.37 519.33
LONGITUD TOTAL
ø 3 / 8 " ø 1 / 2 " ø 5 / 8 " ø 3 / 4 " ø 1 "
6.3 9.77
2.7 2.67 12 .44
SUB TOTAL
TOTA L(KG )
LO NG ITUD TO TA L
ø 3 / 8 " ø 1 / 2 " ø 5 / 8 " ø 3 / 4 " ø 1 "SUB TO TA
L(KG )
TO TA L(KG )
PA RTIDA DESC RIPC IO N N° VEC ES C O NC RETOM EDIDA S LA RG O A NC HO A LTO
03 .05 .02 .04VIGA DIAFRAGMA03.05.02.04.03.ENCOFRADO Y DESENCOFRADO EN VIGAS DIAFRAGM 10 4.20 0.40 16.8
03.05.02.04.03.ACERO FY=4200 KG / CM2 VIGA DIAFRAGMA
D1 5/ 8" 6 7.35 44.1 70.56
D2 3/ 8" 63 2.60 163.8 95.00
D3 1/ 2" 6 6.45 38.7 39.47
03.05.02.04.03.CONCRETO F´C = 280KG / CM2 VIGA DIAFRAGMA 5 4.20
03 .05 .02 .04LOSAS DE CONCRETO ARMADO (PUENTES)03.05.02.04.04.ENCOFRADO Y DESENCOFRADO DE LOSAS 2
2
3
03.05.02.04.04.ACERO FY= 4200 kg / cm P/ LOSAS
L1 1 5/ 8" 51 6.80 346.8 554.88
L2 5/ 8" 67 7.00 469 750.40
L3 1/ 2" 18 10.60 190.8 194.62
L4 3/ 8" 32 10.60 339.2 196.74
03.05.02.04.04.CONCRETO LOSA F´C = 280KG / CM2 P/ LOSAS 1 10.00
03 .05 .02 .04VEREDAS03.05.02.04.05.ENCOFRADO Y DESENCOFRADO DE VEREDAS 2
4
2
03.05.02.04.05.ACERO FY=4200 KG / C M2 P/ VEREDAS
L6 3/ 8" 20 10.60 212 122.96
PRO YEC TO : "C O NSTRUC C IO N DE LA TRO C HA C ARRO ZABLE HUASTA - VILLALTA
UBIC A C IÓ N: LO C A LIDA D: HUASTA - VILLALTA, DISTRITO : HUASTA, PRO VINC IA: BO LO G NESI, DEPARTAMENTO : ANC AS
5 4.20 0.30 6.30
D4 3/ 4" 12 6.75 81 183.06 388 .10
L5 1/ 2" 8 10.60 84.8 86.50 1783 .13
L7 1/ 2" 134 2.90 388.6 396.37 519 .33
C O NC RETO ENC O FRA DO A C EROM EDIDA S M EDIDA S TO TA L (M2) DIAM . N° VARILLASLA RG O A NC HO A LTO LA RG O A LTO
10 4.20 0.40 16.8
22 .05
D1 5/ 8" 6 7.35 44.1 70.56
D2 3/ 8" 63 2.60 163.8 95.00
D3 1/ 2" 6 6.45 38.7 39.47
0.30 1 6.30
6.30
10.00 0.76 15.2
10.00 0.18 3.6
9.30 1.6 44.64
63.44
L1 1 5/ 8" 51 6.80 346.8 554.88
L2 5/ 8" 67 7.00 469 750.40
L3 1/ 2" 18 10.60 190.8 194.62
L4 3/ 8" 32 10.60 339.2 196.74
6.60 0.20 13.20
13.20
10.00 0.15 3
0.95 0.15 0.57
10.00 0.7 14
17.57
L6 3/ 8" 20 10.60 212 122.96
: HUASTA - VILLALTA, DISTRITO : HUASTA, PRO VINC IA: BO LO G NESI, DEPARTAMENTO : ANC AS
5 4.20 0.30 6.30
3/ 4" 12 6.75 81 183.06 388 .10
1/ 2" 8 10.60 84.8 86.50 1783 .13
1/ 2" 134 2.90 388.6 396.37 519 .33
LO NG ITUD TO TA L SUBTOTAL TOTALLO NG ITU ø 3 / 8 " ø 1 / 2 " ø 5 ø 3 / 4 " ø 1 " (KG) (KG)
D1 5/ 8" 6 7.35 44.1 70.56
D2 3/ 8" 63 2.60 163.8 95.00
D3 1/ 2" 6 6.45 38.7 39.47
L1 1 5/ 8" 51 6.80 346.8 554.88
L2 5/ 8" 67 7.00 469 750.40
L3 1/ 2" 18 10.60 190.8 194.62
L4 3/ 8" 32 10.60 339.2 196.74
L6 3/ 8" 20 10.60 212 122.96
3/ 4" 12 6.75 81 183.06 388 .10
1/ 2" 8 10.60 84.8 86.50 1783 .13
1/ 2" 134 2.90 388.6 396.37 519 .33
D1 5/ 8" 6 7.35 44.1 70.56
D2 3/ 8" 63 2.60 163.8 95.00
D3 1/ 2" 6 6.45 38.7 39.47
L1 1 5/ 8" 51 6.80 346.8 554.88
3/ 4" 12 6.75 81 183.06 388 .10
1/ 2" 8 10.60 84.8 86.50 1783 .13
1/ 2" 134 2.90 388.6 396.37 519 .33