  • TOP BUILDERS INTERNATIONAL CO. LTD.

    Method Statement For

    Waterproofing System (WP2)

    Project: Venetian Macau in Cotal, Macau Re: Work Package 5115 (Top Builders), Prefabricated Bathroom Revision: B Date: 2006/06/19

  • Method Statement for Waterproofing System (WP2)

    Page 2 of 5

    Table of Content

    Content .. 2 Scope of work .. 3 Relevant submission .. 3 Application of waterproofing .. 3 - 5

    Preparation work .. 3

    Concerns .. 3 Installation .. 4

    Field quality control .. 4 Protection ... 5 Cleaning ... 5 Appendix i iii Demarcation Plan i Hazard identification ii Risk assessment iii

  • Method Statement for Waterproofing System (WP2)

    Page 3 of 5

    Scope of work Trade contractor of this project will be responsible for the execution of the work in accordance with the specifications and relevant approved documentations. The scope of work includes supply and installation of waterproofing system (WP2) including PCI gisogrund protective primer, PCI lastogum waterproof coating, and PCI pecitape fabric tape system at the L33 to L37 tower suite bathroom areas. Relevant submission

    Material Submission of the wash and protective primer PCI gisogrund for walls and floors.

    Material Submission of the waterproof, flexible protective coating PCI lastogum under marble panels in toilets, shower and bathrooms with official test certificates.

    Material Submission of the special fabric tape system PCI pecitape for waterproof corner and perimeter joints, pipe culverts and floor drains.

    Application of waterproofing system Preparation work

    1. Site Cleaning 2. Site surveying and setting out 3. Erect working platform if necessary and according site safety

    regulations.

    Concerns

    1. Working at Height Working platform will be provided if higher than 2m and erected by experience competent worker and inspected by the appointed professional person signing and certifying Form 4 & 5 before use and re-inspection on 7-14 days.

    2. Substrate Preparation Substrate must be solid, dry, clean and free from oil. The surface must not have any pockets, gaping cracks or ridges.

    3. Factor affecting Evaporation Time for Lastogum Higher temperatures reduce and lower temperatures increase these times. The airflow will affect the evaporation time as well.

    4. Quality of drywall The surface of the board, the workmanship of the joints between boards and wall to floor joint alignment should be inspected before application.

  • Method Statement for Waterproofing System (WP2)

    Page 4 of 5

    y Installation

    1. Remove all debris on wall and floor surface. 2. Absortive mineral substrates are to be primed with PCI gisogrund

    with 1:1 water. 3. Wait the primer to completely dry for at least 3 hours.

    4. Application of PCI lastogum liquid applied waterproofing membrane.

    5. The first coat should be applied with PCI lastogum red. Evaporation

    time after first coat is minimum 3 hours at 23 degree and 50% relative humidity.

    6. Sealing the corner and wall to floor and wall to wall joints by pressing

    PCI pecitape 120 sealing tape onto the fresh first coat at corner or joints. Cut the tape to fit corners.

    7. Sealing the pipe penetrations by using the fingers, stretch a PCI

    pecitape 10X10 sealing gasket to give tight fit over the pipe. Place it in position, bedding it onto the fresh first coat.

    8. Sealing a floor drain by cutting PCI pecitape 35X35 sealing gasket to suit drain system to be used. Place it in position, bedding it onto the fresh first coat. Insert loose flange of the floor outlet and screw down.

    9. For wall application, apply the second coat of PCI lastogum gery

    which is a one-component system. Or floor application, apply second coat of PCI lastogum grey, which is a two-component system.

    10. Ensure the cured waterproofing membrane is dry and has not been

    damaged before fixing marble.

    11. Water testing as per requested in the specification, please refer to field quality control section.

    12. Waterproofing need to be protected after water test.

    Field quality control 1. Visual inspection

    z Visually inspect waterproofing system installation thoroughly in presence of contractors representative for mock-up trail and bubbles formed in the waterproofing system or any defects will be made good as recommended by manufacturer.

  • Method Statement for Waterproofing System (WP2)

    Page 5 of 5

    2. Testing of horizontal installation

    z After allowing waterproofing system installation to completely cure and set, flood test horizontal installations with a minimum of 50mm of water for 24 hours examine for identify and repair any leaks.

    z Make joint inspection with architects, consultants and main

    contractors representative throughout the test. Record the testing result on inspection forms, taking record photos where necessary.

    3. Water spray test to waterproofing system applied to wall

    z For wall exceeding 300mm high only, joint inspection with architects, consultants and main contractors representative for water spray test will be arranged at least 72 hours (in any case, as per the manufacturers advise) after waterproofing membrane is applied.

    z Apply water using a common domestic telephone type shower head

    fitted to a 13mm diameter supply pipe delivering water pressure of not less than 0.2N/mm2. Locate the pressure gauge at a distance not exceeding 1500mm from the shower head.

    z Carefully make inspection of the other side of the waterproofed wall

    surface to check any water seepage.

    z Record the testing result, taking photo record where necessary. Protection

    1. Ensure that all waterproofing are protected from traffic, weather and damage during construction. Repair or replace all damaged waterproofing before covering with other finish materials.

    2. Protect all insulation from damage from wetting, loading or abuse until

    they are under protective covering material or finish. 3. Protect adjacent surfaces and materials from damage and soiling by

    the work of this section. Cleaning

    1. Remove all debris after completion of the work of this section.

    2. Clean adjacent surfaces and materials soiled by any work of this section.

  • WATERPROOFING LEGEND:UP TO SKIRTING

    UP TO FALSE CEILING HEIGHTUP TO 2050mm A.F.F.L.UP TO 950mm A.F.F.L.

    Stone Types:G-ST1 TURKISH BOTTICINOG-ST2 DARK EMPERADORG-ST3 RED DAMASCUSG-ST4 GIALLO SIENA

    195

    Bathtub Baoquan BT-9509A

    WC Kohler K-3323

    120120

    195

    Bas

    in K

    ohle

    r K-2

    211

    195

    Bas

    in K

    ohle

    r K-2

    211

    100

    882 152

    80

    20

    20

    225

    180

    490

    1290

    121

    1740

    150

    600 150 150

    150

    150 2240 150

    250

    900

    800

    150

    2156

    EQ 1400 EQ

    789

    100

    1500

    150

    100

    100 100

    850

    150

    150

    727

    100150

    150

    850 AA

    J

    D

    A F

    A

    F

    F

    J

    J

    J

    808

    95

    275

    645

    100

    195

    1500

    150

    1400

    400

    150

    850

    465

    180

    225

    300

    300

    38

    38

    600Basin Kohler K-2211

    195 195

    WC

    Koh

    ler

    K-3

    323

    35

    1245 150 1481

    232

    900

    170

    1754

    846

    524

    500

    1279

    1019

    900

    195

    35030

    0

    DESCRIPTIONDATEREV. DRAFT

    THE HEIGHT OF WALL WATERPROOFING2120 - 5115 - C-2(B) - DEMARCATION PLAN FOR

    PDF

    crea

    ted

    with

    pdf

    Fact

    ory

    Pro

    trial

    ver

    sion

    ww

    w.p

    dffa

    ctor

    y.co

    m

  • Stone Types:G-ST1 TURKTSH BOTTICINOG-ST2 DARK EMPERADORG-ST3 RED DAMASCUSG-ST4 GTALLO STENA

    310

    400

    W

    C

    K

    o

    h

    l

    e

    r

    K

    -

    3

    3

    2

    3

    S

    u

    p

    p

    l

    i

    e

    d

    b

    y

    o

    t

    h

    e

    r

    s

    I

    n

    s

    t

    a

    l

    l

    e

    d

    b

    y

    T

    B

    I

    600

    3829

    0

    45

    936 2134

    75

    7517

    00

    990 990

    3046

    550

    2968

    EQEQ

    550

    300 300 300 300

    290

    250

    300

    300

    300

    300

    250

    300

    300 300

    300

    300

    300

    300

    EQ

    1E

    Q1

    Basin Kohler K-2211Supplied by othersInstalled by TBI

    EQ5 EQ5

    10

    3838

    EQ

    EQ

    90

    WATERPROOFING LEGEND:UP TO SKIRTING

    UP TO FALSE CEILING HEIGHTUP TO 2050mm A.F.F.L.UP TO 950mm A.F.F.L.

    DESCRIPTIONDATEREV. DRAFT

    THE HEIGHT OF WALL WATERPROOFING2120 - 5115 - DQ_K_K1 - DEMARCATION PLAN FOR

    2120 - 5115 - DQ_K_K1SUITE - DEMARCATIONPLAN FOR THE HEIGHT OF WALL WATERPROOFING

    DQ SUITE (LEFT) L33-L37K SUITE (LEFT) L33-L37K-1 SUITE (LEFT) L33-L37

    PDF

    crea

    ted

    with

    pdf

    Fact

    ory

    Pro

    trial

    ver

    sion

    ww

    w.p

    dffa

    ctor

    y.co

    m

  • WATERPROOFING LEGEND:UP TO SKIRTING

    UP TO FALSE CEILING HEIGHTUP TO 2050mm A.F.F.L.UP TO 950mm A.F.F.L.

    Stone Types:G-ST1 TURKISH BOTTICINOG-ST2 DARK EMPERADORG-ST3 RED DAMASCUSG-ST4 GIALLO SIENA

    208

    614

    600

    195

    120

    600

    120

    195

    195

    150

    BAOQUAN BT-9509A

    Bas

    in K

    ohle

    r K

    -221

    1

    Bas

    in K

    ohle

    r K

    -221

    1

    300

    300

    300

    300

    300

    300300300 300

    G-S

    T1

    300

    1999 150

    348 1400 378

    869

    1906

    250

    712

    1500

    150

    850

    100

    100

    809 1902 809

    1902

    712

    2097 126615

    0640

    0

    J

    J

    F A

    J

    100

    614

    80

    20 38

    2038

    278

    260

    278

    260

    100

    200555

    590

    590

    EQ EQ

    300300200 300100300EQ EQ200 100

    100

    200

    300

    300

    300

    300

    EQ

    300

    300

    300

    300

    EQ

    200

    100

    7575

    EQEQ

    EQ

    EQ

    75

    75

    120

    195

    600

    614

    Basin Kohler

    K-2211

    300

    300

    300

    300

    300

    300 300

    75

    75

    300

    300

    300

    300

    300

    300

    300

    7575

    G-S

    T4

    G-S

    T1

    G-S

    T3

    G-S

    T1

    18371501740

    1806

    806

    150

    195

    318

    150

    600

    1582

    2450

    200

    900

    472

    A

    J

    F

    300 EQEQ

    EQ

    EQ

    300

    300

    300200

    300

    300

    300

    45

    340

    350

    DESCRIPTIONDATEREV. DRAFT

    THE HEIGHT OF WALL WATERPROOFING2120 - 5115 - C-2(C) - DEMARCATION PLAN FOR

    PDF

    crea

    ted

    with

    pdf

    Fact

    ory

    Pro

    trial

    ver

    sion

    ww

    w.p

    dffa

    ctor

    y.co

    m

  • Review No. B Date: 07-06-2006 HAZARD IDENTICATION SHEET Page 1 of 2

    Project: Venetia Cotai, Macau Prefabricated Bathroom Work Package Code: WP 5115 (Top Builders) Subject: Waterproofing system (WP2) Analysis by: Edward Leung Location: Hotel Tower

    Item Job Task Hazard People Affected Cause of Hazard Worst Harm

    Due to Hazard

    Existing Control Measures Remark

    1 General works Personal injury worker and affected people nearby

    - Lack of site safety knowledge

    - Inappropriate use of PPE

    Severely injured

    - Worker should attend Safety Induction Training provided by GAMMON.

    - Provide appropriate PPE to workers.

    - Keep stock of PPE to be maintained for issuing.

    2 Manual handling and transporting of material

    Twisted , slipping, tripping, hit by objects Muscle strain During manual handling

    workers - Using improper lifting method to handle goods

    - poor housekeeping

    - Worker did not wear and use PPE

    Severely injured

    - Provide pre-work body exercise to minimize the risk of injury.

    - Wear long sleeve safety shoes to protect the ankle and foot..

    - Use the mechanical equipment if possible.

    - Always keep the workplace dry and tidy.

    3 Materials

    storage

    Fire worker and affected people nearby

    - Poor Housekeeping

    - Smoking at the workplace and storage yards.

    - Insufficient Ventilation

    Fatality

    - Flammable materials and goods must be kept away from the workplace.

    - Provide fire extinguishers at the workplace and storage yards.

    - Clean all the rubbish, paper, scraps all the time.

    - Display no smoking signage and no smoking is allowed at the workplace.

    - Adequate ventilation

  • Review No. B Date: 07-06-2006 HAZARD IDENTICATION SHEET Page 2 of 2

    Item Job Task Hazard People Affected Cause of Hazard Worst Harm

    Due to Hazard

    Existing Control Measures Remark

    4 Waterproofing application

    Eye contact and skin contact worker nearby

    - Improper use of PPE during the work.

    Eye or skin irritation

    - Wear safety goggles and gloves when working. .

    - After application, worker must wipe off left-out substance and clean with soap and water.

    5 Water proofing application on wall

    Collapse of working platform worker and affected

    people nearby

    - Platform erected by non-experience competent workers.

    Serious injury - Appointed Registered professional inspect and sign for the workability of working platform of height above 1.8m.

    6 Water proofing application on wall

    Fall of person at height worker - Inadequate platform being used by workers.

    - Workers did not wear and use PPE.

    Fatality - 200mm high toe-board and fence at 450mm and 900mm to be installed. - Prohibit to move the working platform if

    any worker on it.

    7 Water proofing application on wall

    Falling objects from the working platform

    Worker and affected people nearby

    - Worker working under the working platform.

    - No Warning sign

    Severely injured

    - Working platform should be closely planked with 200mm toe-board equipped.

    - No other works shall be carried out under the activities that are working above.

    - Chain block shall be used to the materials that are heavy in weight and large in size.

    - Fence off the working area with barrier and notice / warning sign should be provided.

  • Review No. B Date: 07-06-2006 RISK ASSESSMENT SHEET Page 1 of 2

    Note: Probability or Likelihood Rating: Almost Certain ( 5 ) Probable ( 4 ) Possible ( 3 ) Remote (2 ) Impossible (1)

    Consequence Rating: Very High ( 5 ) High ( 4 ) Medium ( 3 ) Low ( 2 ) Very Low ( 1)

    Risk Level: ( RED ) ( ORANGE ) ( YELLOW ) (GREEN)

    Works Related Projects/Department: Venetia Cotai, Macau Works Related Projects/Department Code: 5115 (Top Builders) Type of Activity Operation: Prefabricated Bathroom Analysis by: Edward Leung Location: Hotel Tower

    Rating of Harm Item Risk Existing Control Measures

    Probability1 Consequences2 Risk

    Level3 Recommended Action Remark

    1 Personal injury - Worker should attend Safety Induction Training provided by GAMMON.

    - Provided appropriate PPE as job required.

    - Keep minimum stock of PPE to be maintained for issuing.

    3

    1

    3 (Green)

    Safety Induction Training, Specific PPE required

    2 Twisted , slipping, tripping, hit by objects Muscle strain During manual handling

    - Provide pre-work body exercise to minimize the risk of injury.

    - Wear long sleeve safety shoes to protect the ankle and foot.

    - Use the mechanical equipment if possible.

    - Always keep the workplace dry and tidy.

    2 2 4 (Green)

    Morning Pre-work exercise

    3 Fire - Flammable materials and goods must be kept away from the workplace. - Provide fire extinguishers at the

    workplace and storage yards. - Clean all the rubbish, paper, scraps all

    the time. - Display no smoking signage and no

    smoking is allowed at the workplace. - Adequate ventilation

    1 5 5 (Green)

    Fire equipments Training, Specific Training

  • Review No. B Date: 07-06-2006 RISK ASSESSMENT SHEET Page 2 of 2

    Note: Probability or Likelihood Rating: Almost Certain ( 5 ) Probable ( 4 ) Possible ( 3 ) Remote (2 ) Impossible (1)

    Consequence Rating: Very High ( 5 ) High ( 4 ) Medium ( 3 ) Low ( 2 ) Very Low ( 1)

    Risk Level: ( RED ) ( ORANGE ) ( YELLOW ) (GREEN)

    Rating of Harm Item Risk Existing Control Measures

    Probability1 Consequences2 Risk

    Level3 Recommended Action Remark

    4 Eye contact and skin contact

    - Worker should attend Safety Induction Training provided by GAMMON.

    - Provided appropriate PPE as job required.

    - Keep minimum stock of PPE to be maintained for issuing.

    - Sanitary facility should be provided for workers.

    3 1 3 (Green)

    Use of PPE s training

    5 Collapse of working platform

    - Appointed Registered professional inspect and sign for the workability of working platform of height above 1.8m.

    3 3 9 (Yellow)

    Specific Training

    6 Fall of person at height - 200mm high toe-board and fence at

    450mm and 900mm to be installed. - Prohibit to move the working platform if

    any worker on it.

    2 4 8 (Yellow)

    Specific Training & Safety Harness required

    7 Falling objects from the working platform

    - Working platform should be closely planked with 200mm toe-board equipped.

    - No other works shall be carried out under the activities that are working above.

    - Chain block shall be used to the materials that are heavy in weight and large in size.

    - Fence off the working area with barrier and notice / warning sign should be provided.

    4 2 8 (Yellow)

    Specific Training & Safety Harness required