Proposal for SHDRC Implementation in Tamil Nadu
GROUP 3, SECTION CLIKHITA MANGULURI 140102069
VENKATA MAHEEDHAR 140102139SAYAN CHAKRABORTY 140103149
ARPIT KUMAR MISRA 140101032AKSHAT KULSHRESHTHA 140101013
SIDDHARTH DIXIT 140201156KAUSHIK THANGUDU 140102060
ROHIT SREEKUMAR 140102110
Need for the Project
Tamil Nadu government unable to use the collected information for policy making and monitoring.
Current system: HMS and HMIS where data is collected and bland reports generated (OLTP).
TN government wants to develop a State health data resource centre.
Entire data available at a single place and to make optimum use of the data in policy making.
Hardware Architecture
Server which contains database. Processing engine comprising of the ETL,
reporting and dashboard tools are installed. Network infrastructure to connect server to
individual computers. Connectivity with HMS and HMIS.
Software Architecture
Data access layer.
Data processing layer.
Data model repository
layer.
Web services layer.
Maintenance Methodology
Maintenance once in 15 days due to UNIX maintenance scripts.
Clock speed of the runs of the maintenance would be around 2.3GHz due to Debian OS.
Regular updates to the current software by the Chennai team.
Setting up of a maintenance hotline to help our clients.
Project Implementation Stages & Timeline
Resource Utilization
Server installation
Computers installation
Server S/W installation
Computer S/W installation
Network Establishment
Data Warehouse Model development
Development of internal jobs and dashboards
Development of Web Application
One time data loading of historic files
Validation of loaded data
1-Sep 30-Nov 28-Feb 28-May26-Aug24-Nov 22-Feb 23-May21-Aug
Project Schedule
Project Organization
Main point of contact would be the project manager with the client.
DBA under the PM and the programmers below the DBA.
Data stage and BO report directly to the PM.
Training Plan
Training to be carried out at three levels: Directorate level. District level. SHDO level.
Employees to be divided into two baskets: Basic Users. Power User.
Training programme would run for 6.25 months. Hotline to help employees segregated into various
categories of issues. Application and maintenance employees to be
provided offsite training for two weeks.
Change in Management Methodology
Proposed new layer to act as a bridge between directorate and SHODC structures.
Floating structures which are closely connected to research report building, ETL and console displays.
Also, we suggest to build a five member cross sectional expertise in:
Software maintenance
Validation
Database management
Network support.
Pricing
Products Required
Pricing
Services
Combining services availed and the products required, the entire costing comes up to 5,50,83,000/- INR