12/17/15, 4:05 PM Agenda Page 1 of 3 http://agenda.shakopeemn.gov/agenda_publish.cfm?id=0&mt=ALL&g…&seq=2440&rev=0&ag=365&ln=9183&nseq=2454&nrev=0&pseq=&prev=# Recommendations for Award of Contract 2A Demolition Ebert Inc. $184,000.00 3A Concrete Systems Gresser Company $1,321,800.00 Print Back to Calendar Return Previous Next AI- 2440 General Business 10) E) 1) City Council - Regular Session Meeting Date: 12/15/2015 FROM: Jamie Polley Department: Parks and Recreation Subject Award of Construction Contracts for the Shakopee Ice Arena and Community Center Improvements, Project No. PR2015-3, Res. No. 7659 (A, B, C) Action Sought Award contracts for the construction of a new ice arena and renovations to the Shakopee Community Center. Background The City Council approved the plans and specification and authorized the advertisement for bids for the new ice arena and Community Center renovations on October 20, 2015. The City Council determined that the project will be funded utilizing tax abatement bonds. The Council authorized the hiring of a Construction Manager, RJM Construction, for this project and to work with 292 Design Group to develop a number of bid packages. Discussion On December 1, 2015 the City received a total of one hundred eight bids for twenty-six bid categories. Two of the bid categories will be rebid at a later date due to cost and/or number of bids received. RJM has completed the review of the bids and have conducted a scope review with the apparent low bidders. RJM is recommending the award of contracts to the following low bidders. A letter from RJM with the recommendations is attached.

12:15:15 cc2.0 agenda item

Embed Size (px)

Citation preview

Page 1: 12:15:15 cc2.0 agenda item

12/17/15, 4:05 PMAgenda

Page 1 of 3http://agenda.shakopeemn.gov/agenda_publish.cfm?id=0&mt=ALL&g…&seq=2440&rev=0&ag=365&ln=9183&nseq=2454&nrev=0&pseq=&prev=#

Recommendations for Award of Contract2A Demolition Ebert Inc. $184,000.003A Concrete Systems Gresser Company $1,321,800.00

Print Back to Calendar Return Previous Next

AI- 2440 General Business 10) E) 1) City Council - Regular SessionMeeting Date: 12/15/2015

FROM: Jamie PolleyDepartment: Parks and Recreation

SubjectAward of Construction Contracts for the Shakopee Ice Arena and Community CenterImprovements, Project No. PR2015-3, Res. No. 7659 (A, B, C)Action SoughtAward contracts for the construction of a new ice arena and renovations to the ShakopeeCommunity Center.

Background The City Council approved the plans and specification and authorized the advertisement for bidsfor the new ice arena and Community Center renovations on October 20, 2015. The CityCouncil determined that the project will be funded utilizing tax abatement bonds. The Councilauthorized the hiring of a Construction Manager, RJM Construction, for this project and to workwith 292 Design Group to develop a number of bid packages.

DiscussionOn December 1, 2015 the City received a total of one hundred eight bids for twenty-six bidcategories. Two of the bid categories will be rebid at a later date due to cost and/or number ofbids received. RJM has completed the review of the bids and have conducted a scope reviewwith the apparent low bidders. RJM is recommending the award of contracts to the followinglow bidders. A letter from RJM with the recommendations is attached.

Page 2: 12:15:15 cc2.0 agenda item

12/17/15, 4:05 PMAgenda

Page 2 of 3http://agenda.shakopeemn.gov/agenda_publish.cfm?id=0&mt=ALL&g…&seq=2440&rev=0&ag=365&ln=9183&nseq=2454&nrev=0&pseq=&prev=#

3B Precast Structural Concrete Fabcon Precast, LLC $3,258,506.004A Masonry Systems Del's Construction $1,160,000.005A Structural & Misc Steel -Material Lejeune Steel Co $946,810.00

5B Structural & Misc Steel-Install High Five Erectors II $398,796.00

6A Carpentry Systems Ebert Inc. $1,212,900.007A Waterproofing REBID $108,453.007B Roofing Systems McPhillips Bros $1,288,000.008A AluminumEntrances/Storefront Capital City Glass $867,000.00

9A GypsumBoard/Drywall/Plaster Quality Drywall Midwest $354,000.00

9B Tiling CD Tile $321,340.009C Acoustical Ceilings Kirk Acoustics $328,000.009D Flooring Sonus Interiors $430,400.009E Painting Systems Superior Painting $490,575.0013A Aquatic Systems Associated Pool Builders $1,816,700.00

13B Ice Rink Systems Commercial RefrigerationSystem $1,973,487.00

14A Passenger Elevator REBID $82,938.0021A Fire Protection Systems Frontier Fire Protection $319,980.0022A Plumbing Systems Modern Piping $1,137,700.0023A HVAC Systems SCR $2,070,000.0026A Electrical Systems E2 Electrical Services $1,257,000.0031A Earthwork & Site Utilities Rachel Contracting $1,023,124.0032A Asphalt Paving Bituminous Roadways, Inc $154,900.0032B ConcreteSidewalk/Curb/Gutter Chard Tiling and Excavating $86,344.00

32C Landscaping Plant Pros, LLC $134,034.00

BudgetImpactThe totalconstruction

cost, including contingency and contractor's fee, of the project is $25,826,178.00. In addition tothe construction costs are the owner costs including SAC/TWC charges and permit fees,furniture, equipment, low voltage, security, contingency, etc. totaling $2,854,501.00. Design feestotal $1,736,100.00. The total project cost is $30,416,779, this amount is listed in the Springsted

Page 3: 12:15:15 cc2.0 agenda item

12/17/15, 4:05 PMAgenda

Page 3 of 3http://agenda.shakopeemn.gov/agenda_publish.cfm?id=0&mt=ALL&g…&seq=2440&rev=0&ag=365&ln=9183&nseq=2454&nrev=0&pseq=&prev=#

report that the City Council received on November 17, 2015 and within the amount of thebonds adopted by Resolution No. 7640.

Relationship to VisionA. Keep Shakopee a safe and healthy community where residents can pursue active and qualitylifestyles.B. Positively manage the challenges and opportunities presented by growth development andchange.C. Maintain the City's strong financial health.

Requested ActionIf the City Council concurs, offer Resolution No. 7659, a resolution awarding contracts for theconstruction of the Shakopee Ice Arena and Community Center Improvements, Project No.PR2015-3.

AttachmentsResolution No. 7659RJM Recommendation Letter

AgendaQuick©2005 - 2015 Destiny Software Inc., All Rights Reserved

Page 4: 12:15:15 cc2.0 agenda item

472530v2 JJT SH155-396

RESOLUTION NO. 7659

A RESOLUTION OF THE CITY OF SHAKOPEE, MINNESOTA AWARDING CONTRACTS FOR CONSTRUCTION OF THE SHAKOPEE ICE ARENA AND COMMUNITY

CENTER IMPROVEMENTS, PROJECT NO. PR2015-3

WHEREAS, pursuant to an advertisement for bids for Construction of the Shakopee Ice Arena and Community Center Improvements, Project No. PR2015-3, bids were received for twenty six bid categories, opened and tabulated according to law; and,

WHEREAS, RJM Construction was hired by the City as the projects construction manager; and,

WHEREAS, RJM Construction is recommending the award of contracts to the apparent lowest responsible bidders of each bid category;

NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SHAKOPEE, MINNESOTA:

2A Demolition Ebert Inc. $184,000.003A Concrete Systems Gresser Company $1,321,800.003B Precast Structural Concrete Fabcon Precast, LLC $3,258,506.004A Masonry Systems Del's Construction $1,160,000.005A Structural & Misc Steel -Material Lejeune Steel Co $946,810.005B Structural & Misc Steel- Install High Five Erectors II $398,796.006A Carpentry Systems Ebert Inc. $1,212,900.007A Waterproofing REBID $108,453.007B Roofing Systems McPhillips Bros $1,288,000.008A Aluminum Entrances/Storefront Capital City Glass $867,000.009A Gypsum Board/Drywall/Plaster Quality Drywall Midwest $354,000.009B Tiling CD Tile $321,340.009C Acoustical Ceilings Kirk Acoustics $328,000.009D Flooring Sonus Interiors $430,400.009E Painting Systems Superior Painting $490,575.0013A Aquatic Systems Associated Pool Builders $1,816,700.0013B Ice Rink Systems Commercial Refrigeration System $1,973,487.0014A Passenger Elevator REBID $82,938.0021A Fire Protection Systems Frontier Fire Protection $319,980.0022A Plumbing Systems Modern Piping $1,137,700.0023A HVAC Systems SCR $2,070,000.0026A Electrical Systems E2 Electrical Services $1,257,000.0031A Earthwork & Site Utilities Rachel Contracting $1,023,124.0032A Asphalt Paving Bituminous Roadways, Inc $154,900.0032B Concrete Sidewalk/Curb/Gutter Chard Tiling and Excavating $86,344.0032C Landscaping Plant Pros, LLC $134,034.00

Page 5: 12:15:15 cc2.0 agenda item

472530v2 JJT SH155-396

1. The prime contracts to the recommended low bidders are awarded.2. The assignment of the prime contracts to RJM Construction is authorized.

Adopted in adjourned regular session of the City Council of the City of Shakopee, Minnesota, held this day of , 2015.

__________________________________________Mayor of the City of Shakopee