40
METRO RAIL IN CHENNAI Submitted by Arun S R Libin Paul Prabu Santana Pravin Ram Kumar Thayumanavan S K

Chennai metro rail

Embed Size (px)

Citation preview

Page 1: Chennai metro rail

METRO RAIL IN CHENNAI

Submitted byArun S RLibin PaulPrabu Santana Pravin Ram Kumar Thayumanavan S K

Page 2: Chennai metro rail

Introduction of Indian Metro Railway.

How it began

India's 1st and Asia's 5th metro rail was introduced in Kolkata.

Over a length of 16.45 km and the work on this project was sanctioned on 1.6.1972

The construction work started in 1973-74.After crossing so many hurdles Calcutta Metro started its journey on October 24, 1984

Page 3: Chennai metro rail

Why is it needed ?

Unprecedented growth of personal vehicles.

Growing traffic congestion.

Air pollution and traffic accidents has become a major concern.

To avoid congestion at peak hours.

Time saving. Reduced fuel consumption.

Page 4: Chennai metro rail

Indian Metro RailwayEXISTING METRO RAILWAY

Kolkata Metro Rail.

Delhi Metro Rail.

Bangalore Metro Rail.

FUTURE & PROPOSED METRO RAILWAY

Mumbai Metro Rail

Hyderabad Metro Rail.

Chennai Metro Rail.

Kochi Metro Rail

Page 5: Chennai metro rail

Introduction On CMRLChennai Metropolis has been growing rapidly and the traffic

volumes on the roads have also been increasing enormously.

Chennai, the fourth-largest city in India, is the capital of the State of Tamil Nadu. The city and its surrounding metropolitan area have a population of nearly 8 million. This generates about 11 million passenger trips a day, with about 6 million vehicular trips. There is a strong need for an efficient transportation system in the city, and the people of Chennai have long felt the need for an efficient, economic, and reliable rail-based mass transit system that would augment and complement the existing modes of public transport.

Hence the need for a new rail based rapid transport system has been felt and towards this objective the Government of Tamil Nadu have decided to implement the Chennai Metro Rail Project

Page 6: Chennai metro rail

Introduction On CMRLThis project aims at providing the people of Chennai with a

fast, reliable, convenient, efficient, modern and economical mode of public transport, which is properly integrated with other forms of public and private transport including buses, sub-urban trains and MRTS.

The Government of Tamil Nadu created a Special Purpose Vehicle (SPV) for implementing the Chennai Metro Rail Project. This SPV named as "Chennai Metro Rail Limited" was incorporated on 03.12.2007 under the Companies Act. It has now been converted into a Joint Venture of Government of India and Government of Tamil Nadu with equal equity holding.

Page 7: Chennai metro rail

A total of 7 lines have been planned by the DMRC for the Chennai Metro network. Two routes are currently under construction as part of the first phase, with several planned for future phases of the metro network.

Line 1 Tiruvottiyur

Line 2 Chennai Central

Line 3 Mogappair

Line 4 Porur

Line 5 Ring Road

Line 6 Radhakrishnan Salai

Line 7 Along NH5 Road

Planning

Page 8: Chennai metro rail

• Construction started on 10 June 2009 with the piling work for the elevated viaduct between Koyambedu and Ashok Nagar stretch.

• The construction work on the project was suspended on 9 August 2012, following an accident that killed a worker and injured six others, a day earlier.

• The project is estimated to cost around  146 billion (US$2.3 billion) for the two corridors totaling 45 km.

• The estimated construction cost of Underground and Elevated Station will be Rs1 billion and Rs3 billion respectively.

Construction History

Page 9: Chennai metro rail

The lines of Chennai Metro are double-tracked ones. The average height of the tracks will be 12 m, which increases at two points, namely, above the Vadapalani flyover where it reaches about 18 m and over the Kathipara grade separator where the height reaches a maximum of about 25 m.

The underground stretch will run at a depth of 17 m below the street level. The Metro corridor accommodates a complex structure over the Kathipara grade separator. Technically called the balanced cantilever, it is a bridge-like structure at a height of about 25 m above the street, connecting the Metro corridor on both sides of the grade separator.

DESIGN OF METRO CORRIDORS

Page 10: Chennai metro rail

Line 1 Washermanpet

Line 1 Extension Wimco Nagar

Line 2 Chennai central

PHASES AND TERMINAL

Page 11: Chennai metro rail

Implementation of Phase 1 The implementation of Phase 1 will be carried out in

three main stages (see Section 5):

Stage 1: Commencement of services for the 11 km section from Koyambedu to St. Thomas Mount (currently scheduled for late 2013).

Stage 1A: Commencement of services for an additional 8 km of sections from Chennai Airport to Little Mount, and Chennai Airport to Koyambedu (currently scheduled for mid 2014)

Stage 2: Commencement of full Phase 1 services (currently scheduled for 2015)

Page 12: Chennai metro rail

The scope of the GC for Phase 1 is project design, procurement, civil engineering, construction, and testing and commissioning of the structures/systems: tracks, signals, telecom facilities, traction arrangements, air conditioning and ventilation, rolling stock, maintenance depots, stations, operation control centre, offices, station integration areas, bridges, flyovers, and elevated, surface, and underground sections .

METRO PROJECT DESIGN &

MANAGEMENT

Page 13: Chennai metro rail

OTHER TECHNICAL FEATURES

Platform screen doors (PSD) in underground Stations

Passenger information systems

CCTV

Operational System-wide safety

Rolling stock (Air-Conditioned)

Life Safety & Security

Environmental sustainability

Provisions for persons with disability:

Page 14: Chennai metro rail

METRO STATIONS

Elevated Stations Underground (UG) Stations

Page 15: Chennai metro rail

ENTRANCESStation entrances will be located with particular

reference to passenger catchment points and physical site constraints within the right of way allocated to the CMRL system. Integrated entrances and ticket offices will also be permitted. All entry points will be assessed and addressed to flood control requirements on a station by station basis. Station entrances will have provisions for closing and securing the station during non-operational hours.

Page 16: Chennai metro rail

POWER SUPPLYThe power supply system and overhead equipment

mainly consists of:

Three 110/33 kV & 110/25 kV AC Receiving Substations (RSS) (Gas Insulated Substations), related Auxiliary Main Substations (3), Traction Main Substations (TSS) (3), and civil works

All civil works and equipment for the 25 kV AC traction supply.

Page 17: Chennai metro rail

SIGNALING CATC- Continuous Automatic Train Control

System

ATP - Automatic Train Protection

ATO - Automatic Train Operation

ATS - Automatic Train Supervision

EI - Electronic Interlocking systems

Page 18: Chennai metro rail

LIFTS AND ESCALATORS

The number of lifts and escalators within the

Chennai Metro system will be approximately:

Lifts: 120

Escalators: 300

Page 19: Chennai metro rail

SCHEDULED FARES

Distance (km) Metro Fare ( )

0 - 2 8.002 - 4 10.004 - 6 11.006 - 9 14.00

9 - 12 15.0012 - 15 17.0015 - 18 18.0018 - 21 19.0021 - 24 20.0024 - 27 22.00

>27 23.00

Page 20: Chennai metro rail

STATIONS

A total of 41 stations have been planned along the two

lines. As many as 19 stations are underground and 12 are

elevated. Of these, the Chennai Central (underground) and 

Alandur (elevated) are common for both the corridors and

serve as interchange stations.

Page 21: Chennai metro rail

Chennai Suburban Railway network: Chennai MRTS Chennai Metropolitan Transport Corporation bus

terminuses Chennai International Airport Southern Railway State Express Transport Corporation (Tamil Nadu) Tamil Nadu State Transport Corporation Chennai Contract Carriage Bus Terminus

PROPOSED CONNECTIONS OF

METRO RAIL

Page 22: Chennai metro rail

As of 2011, four urban parks in the city has been taken over by CMRL for construction-related activities. These have been closed to the public since then. They include Corporation parks at Ashok Nagar, Thiru-Vi-Ka Park in Shenoy Nagar, Nehru Park on Poonamallee High Road, and May Day Park in Chintadripet. At the Ashok Nagar Park, the pillars of the elevated corridor would come up on the edge of the park to provide sufficient turning radius

PARKS TAKEN OVER FOR CONSTRUCTION

Page 23: Chennai metro rail

• In August 2012, a construction worker was killed and six others were seriously injured due to a crane boom failure near Pachaiyappa's College.

• On 10 January 2013, a 22-year-old construction worker was killed and three others were injured at a Metro Rail site on Railway Station Road between Alandur and St. Thomas Mount at around 3:45 am

ACCIDENTS DURING CONSTRUCTION

Page 24: Chennai metro rail
Page 25: Chennai metro rail
Page 26: Chennai metro rail

TUNNEL LINING

Page 27: Chennai metro rail

VIA DUCT CONSTRUCTON

Page 28: Chennai metro rail

VIA DUCT CONSTRUCTON

Page 29: Chennai metro rail

Key Issues In Metro Rail Projects

Lack of funds planning as is known that such projects require huge capital investments

A long gestation period

Complex technology

The lack of integration between various systems of mass transportation

The absence of comprehensive traffic and transportation planning.

Page 30: Chennai metro rail

Key issues cont.A metro model for a county would have to depend on its

logistics, financial resources

Planning, construction, designing and management of metros require :-extensive data, detailed surveys, study of economic structure, profile of settlement topography, travel preference, major traffic corridors.

System needs to be made self-reliant and self-contained to minimize O&M (operations & maintenance) cost.

Technology with low initial cost but with high O & M cost should be avoided.

Page 31: Chennai metro rail

COST FACTORS

Metro projects are meant to cater to cities with more than four million population

Larger the underground and elevated proposal, larger shall be the cost involved. 

Funding process is done through the PPP model (Public-Private Partnership) as in Hyderabad and Mumbai or by DMRC model by the state or the central government as in Bengaluru, Chennai and Kolkata.

Page 32: Chennai metro rail

BENEFITS OF METRO RAIL

Requires 1/5th energy per passenger km compared to road-based transport system.

Causes less noise, no air pollution and eco friendly transport system.

Occupies no road space if underground and only about 2.60 meters width of the road if elevated.

Reduces journey time.

Cost effective mass transport system.

Reducing traffic transport problems.

Page 33: Chennai metro rail

A cheap mode of transport, the MRTS helps in low energy consumption

It is eco-friendly (runs on electricity, thus minimizing air and sound pollution)

Averts the number of accidents

Is efficient in terms of space occupancy and provides comfort with ultra-modern coaches and modern systems like automatic ticketing, advanced signaling systems, automatic train protection system and integrated security systems.

Advantages of CMRL

Page 34: Chennai metro rail

Advantages Cont.… Services like ATMs, food outlets, cafés and

convenience stores at these stations make the journey more fruitful.

Also such stations lead to nearby economic development.

The international standard for MRTS with a maximum speed of 80kmph and average speed of around 34kmph helps in saving of time.

With proper designing, the peak hour capacity could be rated at 3-4 lakhs passengers per hour."

Page 35: Chennai metro rail

Disadvantages: The only disadvantage of metros is the slight congestion on

roads at the time of construction which has to be taken care of.

The cost factor is another disadvantage, the solution for which is to integrate metros with others systems considering the volume, structure, availability of space and resources for traffic and transportation. 

Page 36: Chennai metro rail

The Future MRTS is the best way to decongest traffic. However, a number of

considerations should be kept in mind in order to run a successful

MRTS.

"Viability of metro projects depend upon correct defining of traffic

corridors, technology adapted, availability of land, volume of

traffic carried, capacity utilization and acceptance of the mode by

the commuters,"

Conclusively, transport needs to be made an integral part of urban

design/master plan of the city as it cannot be delineated to a

separate entity. A multi-modal transportation system would

ensure the use of MRTS to its best potential. 

Page 37: Chennai metro rail

Cont..The uncertainty about MRTS, which has plagued

the importance of such systems in India seems to be resolving.

Though the Kolkata metro was designed without a rule book and the Delhi Metro was designed on international norms

Page 38: Chennai metro rail

Chennai Metro is primarily a social project, it is recommended that it should be implemented and operated under a SPV owned by GOI and GOTN.

The transport problems of Chennai can be better addressed if an integrated transport system is put in place in the city. With the introduction of Chennai Metro, the city transport system can be designed in a way that other modes of transport. should become complementary to each other.

This can be achieved in a better A Railway background would be an added advantage. A Metro background would be most desirable. way if the Chennai metro remains under the state control.

Suggestions

Page 39: Chennai metro rail

CONCLUSION

Even though the Metro systems are more reliable, comfortable and safer than road-based systems & it reduces congestion on the roads, the systems planned in India show cost overrunning and under utilization of capacity.

High capacity system does not necessarily generate high demand.

Immense thought & planing is needed for such expensive and expansive projects.

Page 40: Chennai metro rail