Upload
huytraining
View
382
Download
15
Embed Size (px)
Citation preview
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 1
THE SOCIALIST REPUBLIC OF VIET NAMMINISTRY OF TRANSPORT
VIETNAM EXPRESSWAY CORPORATION (VEC)
NORTH – SOUTH EXPRESSWAY CONSTRUCTION PROJECTBEN LUC – LONG THANH SECTION
PACKAGE J2
SUMITOMO MITSUI CONSTRUCTION CO., LTD.
27-Oct-2014
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 2
BEN LUC – LONG THANH SECTION
HO CHI MINHCITY
HA NOICITY
PK J1BINH KHANH BRIDGE
TAN SON NHATAIRPORT
LONG THANHAIRPORT
LONG THANH-DAU DAYEXPRESSWAY PROJECT
LONG THANHBRIDGE
DONG NAIBRIDGE
BIEN HOA-VUNG TAUEXPRESSWAY PROJECTPK J2
CHA RIVER BRIDGE
PK J3PHUOC KHANH BRIDGE
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 3
LOCATION MAP OF PROJECT
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 4
OUTLINE OF PROJECT
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 5
OUTLINE OF PROJECT (1/2)(1) Project Name
North-South Expressway Construction Project (Ben Luc - Long Thanh Section),Contract Package J2: Km24+503 – Km29+264 Cha Bridge and Viaduct
(2) Project LocationBinh Khanh Commune, Can Gio District, Ho Chi Minh City
32 months(3) Construction Period
(4) Project summary
・Project length: Total 4750m
Continuous box girder bridge 312m
Super-T girder bridge 4438m
・Project width: Through way 10m
Express way 3.5m (2lanes)
Shoulder 2.50m
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 6
OUTLINE OF PROJECT (2/2)・Substructure: Continuous box girder bridge
Pier foundation by D1.2m, D1.5m bored pilesD1.2m 12 pilesD1.5m 32 piles
Length of bored pile 66~72m Super-T girder bridge
Pier foundation by D1.2m bored piles, includes 567 pilesLength of bored pile 58~80m
・Superstructure: Continuous box girder bridge: Includes 3 spans
Length 86+140+86=312m Super-T girder bridge: Includes 113 spans
Total number of Super-T girder 1017pcsLength of Super-T girder 38.3m; 34.3m; 33.3m
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 7
STRUCTURE CHARACTERISTIC
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 8
GENERAL VIEW OF PK J2
TO BEN LUC
TO LONG THANH
140m 86m86mWestern approach
Eastern approach
CHA RIVER BRIDGECantilever Box girder
Super-T girder 38m
Super-T girder 38m
4.750km
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 9
GEOLOGYCAL SECTION
EL. of Tip of Bored Pile -81.2
EL. of Tip of Bored Pile -79.1
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 10
TYPICAL SECTION (1/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 11
TYPICAL SECTION (2/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 12
TYPICAL SECTION (3/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 13
TYPICAL SECTION (4/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 14
TYPICAL SECTION (5/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 15
CONSTRUCTION METHOD
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 16
ORGANIZATION CHART
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 17
GENERAL SCHEDULE
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 18
SITE ARRANGEMENT OF UTILIZATION
1 2 3 4 5 6
7
89
1
2 3
4
5
9 Tem porary Ram p 2
6 Tem porary Bridge 6m 5
7 Tem porary Bridge 5m 3
8 Pipe C ulvert 9
4 W harf 5
5 Accom odation 3
2 Fabrication Yard 3
3 C oncrete Btching 2
No, Item Q 'ty
1 Site O ffice 2
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 19
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 20
ACCESS ROAD AND RAIL OF GANTRY CRANE
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 21
TEMPORARY BRIDGE
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 22
PLAN OF WHARF AND JETTY
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 23
JETTY DESIGN
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 24
CONSTRUCTION OF BORED PILE (ON LAND)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 25
STRUCTURE EXCAVATION
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 26
CONSTRUCTION OF PILE CAP
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 27
PRE-INSTALLATION OF COLUMN REBAR
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 28
REBAR INSTALLATION OF COLUMN
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 29
FORM WORK INSTALLATION OF COLUMN
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 30
CASTING CONCRETE OF COLUMN
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 31
REMOVE FORM WORK OF COLUMN
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 32
PRE-INSTALLATION OF HEADSTOCK REBAR
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 33
INSTALLATION OF MAIN SUPPORT FOR HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 34
INSTALLATION OF REBAR FOR HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 35
INSTALLATION OF FORM WORK FOR HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 36
CASTING CONCRETE OF HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 37
REMOVE FORM WORK OF HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 38
INSTALLATION OF MAIN SUPPORT FOR HEADSTOCK (HIGH PIER)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 39
INSTALLATION OF REBAR FOR HEADSTOCK (HIGH PIER)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 40
CASTING CONCRETE OF HEADSTOCK (HIGH PIER)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 41
REMOVE FORM WORK OF HEADSTOCK
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 42
ERECTION OF GIRDER BY GANTRY CRANE 1/2
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 43
ERECTION OF GIRDER BY GANTRY CRANE 2/2
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 44
ERECTION OF GIRDER BY LAUNCHING DEVICE (1/2)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 45
ERECTION OF GIRDER BY LAUNCHING DEVICE (2/2)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 46
CONSTRUCTION OF DIAPHRAGM
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 47
CONSTRUCTION OF DECKSLAB
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 48
CONSTRUCTION OF PARAPET
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 49
CONSTRUCTION OF LIGNTING POLE
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 50
SUPPER-T GIRDER FORM (1/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 51
SUPPER-T GIRDER FORM (2/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 52
SUPPER-T GIRDER FORM (3/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 53
CONSTRUCTION OF BORED PILE (IN RIVER)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 54
COFFERDAM IN RIVER-SPSP (1/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 55
COFFERDAM IN RIVER-SPSP (2/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 56
COFFERDAM IN RIVER-SPSP (3/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 57
PIER TABLE SUPPORT (1/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 58
PIER TABLE SUPPORT (2/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 59
PIER TABLE SUPPORT (3/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 60
CAST-IN SITU SPAN (1/4)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 61
CAST-IN SITU SPAN (2/4)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 62
CAST-IN SITU SPAN (3/4)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 63
CAST-IN SITU SPAN (4/4)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 64
CANTILEVER METHOD (1/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 65
CANTILEVER METHOD (2/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 66
CANTILEVER METHOD (3/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 67
CANTILEVER METHOD (4/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 68
CANTILEVER METHOD (5/5)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 69
PERSPECTIVE PHOTO (1/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 70
PERSPECTIVE PHOTO (2/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 71
PERSPECTIVE PHOTO (3/3)
http://revit.huytraining.com Biện pháp thi công bằng Revit - Expressway Bến Lực – Long Thanh
www.huytraining.com 72