22
1 NASA PM Challenge Feb 2011 Multidimensional RISK RISK INTEGRATED WITH SCHEDULE, COST, PERFORMANCE, AND ANYTHING ELSE YOU CAN THINK OF

Doug brown

  • Upload
    nasapmc

  • View
    14.523

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Doug brown

1

NASA PM ChallengeFeb 2011

Multidimensional RISKRISK INTEGRATED WITH SCHEDULE, COST, PERFORMANCE, AND ANYTHING ELSE YOU CAN THINK OF

Page 2: Doug brown

2

NASA Uses Two Complementary Processes For Risk Management Risk-Informed Decision Making (RIDM)

– Emphasizes the proper use of risk analysis to make risk-informed decisions that impact all risk dimensions including safety, technical, cost, schedule, etc…

– Acknowledges the role that subject matter experts (SMEs) play in decisions. Emphasizes that the cumulative wisdom provided of SMEs is essential for integrating technical and nontechnical factors to produce sound decisions due to the availability of technical data and the complexity of missions

– Source: NASA/SP-2010-576 NASA Risk-Informed Decision Making Handbook

Continuous Risk Management (CRM)– To manage those risks associated with the performance levels that drove selection of a

particular alternative (from RIDM)– A systematic and iterative process that efficiently identifies, analyzes, plans, tracks,

controls, and communicates and documents risks associated with implementation of designs, plans, and processes

– Source: NPR 8000.4A Agency Risk Management Procedural Requirements

Page 3: Doug brown

3

RIDM Selects Alternatives & CRM Addresses The Implementation Of Alternatives

* Source: NASA/SP-2010-576 NASA Risk-Informed Decision Making Handbook

Continuous Risk Management (CRM)

Risk-Informed Alternative Selection

Deliberate and Select an Alternative and Associated Performance Commitments Informed by (not solely based on) Risk Analysis

Risk Analysis of AlternativesRisk Analysis (Integrated Perspective) and Development of the

Technical Basis for Deliberation

Identification of AlternativesIdentify Decision Alternatives (Recognizing Opportunities) in the

Context of Objectives

Risk-Informed Decision Making (RIDM)

Page 4: Doug brown

4

CRM Uses The Identify Step To Document Risks In The Form of Risk StatementsRisk Statements have 3 distinct elements1. Scenario

– A sequence of credible events that specifies the evolution of a system or process from a given state to a future state. In the context of risk management, scenarios are used to identify the ways in which a system or process in its current state can evolve to an undesirable state

2. Likelihood– Probability of occurrence

3. Consequence– The possible negative outcomes of the current conditions that are creating uncertainty

Given SCENARIOthere is a

LIKELIHOOD that,

CONSEQUENCE will occur

Page 5: Doug brown

5

Risk Is Typically Measured As Likelihood Times Consequence

Likelihood

Estimation of the likelihood that the risk

event will occur

Likelihood

Estimation of the likelihood that the risk

event will occur

Definitions DefinitionsRISKS

Consequence

Estimation of the impact to the

program if the risk event

occurs

Consequence

Estimation of the impact to the

program if the risk event

occursLikelihood x Consequence

4.79 10.73 48.9429.30

Quantitative Risk Score

Samples

Page 6: Doug brown

6

The Identify Step of CRM Documents Risk In Multiple Dimensions To Get A Complete Risk Picture

Safety

CostConfiguration Management

People

ScheduleEnvironment

Technical

On-Orbit operations risk

Page 7: Doug brown

7

CONSEQUENCE 1 Very Low 2 Low 3 Moderate 4 High 5 Very HighTechnical Negligible or no impact to

achievement of Subsonic Transport System Level

Metrics, Technical Deliverables, Technology Maturation, or KPP Goals

Minor impact to achievement of Subsonic Transport System

Level Metrics, Technical Deliverables, Technology Maturation, or KPP Goals

Some impact to achievement of Subsonic Transport System

Level Metrics, Technical Deliverables, Technology Maturation, or KPP Goals

Moderate impact to achievement of Subsonic

Transport System Level Metrics, Technical Deliverables,

Technology Maturation, or KPP Goals

Major impact to achievement of Subsonic Transport System

Level Metrics, Technical Deliverables, Technology Maturation, or KPP Goals

ScheduleLevel 2 Milestone(s):

< 1 month impact

Level 3,4 Milestone(s): ≤ 1 month impact

Level 2 Milestone(s): ≥ 1 month impact

Level 3,4 Milestone(s): ≤ 2 month impact

Level 1 Milestone(s):≤1 month impact

Level 2 Milestone(s): ≤ 2 month impact

Level 3,4 Milestone(s):≤ 3 month impact

Level 1 Milestone(s): > 1 month impact

Level 2 Milestone(s):> 2 month impact

Level 3,4 Milestone(s): >3 month impact

Level 1 Milestone(s): > 2 month impact

Level 2 Milestone(s):≥ 3 month impact

Cost Between 0% and 5% increase over allocated

budget (Sub-Project, Element or Task level)

Between 5% and 10% increase over allocated budget (Sub-Project, Element or Task

level)

Between 10% and 15% increase over allocated budget (Sub-Project, Element or Task

level)

Between 15% and 20% increase over allocated budget (Sub-Project, Element or Task

level)

Greater than 20% increase over that allocated budget (Sub-

Project, Element or Task level)

Safety Negligible or no impact Could cause the need for only minor first aid treatment

May cause minor injury or occupational illness or minor

property damage

May cause severe injury or occupational illness or major

property damage

May cause death or permanently disabling injury or destruction of

property

7

5

4

3

2

1

Very Likely

Likely

Possible

Unlikely

HighlyUnlikely

5

4

3

2

1

1 2 3 4 5

Expected to happen

Could happen. Controls have significant limitations or uncertainties.

Could happen. Controls exist, with some limitations or uncertainties.

Not expected to happen. Controls have minor limitations or uncertainties.

Extremely remote possibility that it will happen. Strong controls in place.

Likelihood Rating RISK MATRIX

LIKE

LIHO

OD

CONSEQUENCES

Level Probability

Managers Use Customized Criteria To Bin Risks Into A Risk Matrix

Page 8: Doug brown

8

The Risk Matrix Provides The Framework For CRM Risk Analysis

Effective analysis makes it possible to move total project risk from red to green

But how do you know you are focused on the right project risks?

Focusing on the wrong risks may keep total project risk in the red?

5

4

3

2

1

1 2 3 4 5

RISK MATRIX

LIKE

LIHO

OD

CONSEQUENCES

Page 9: Doug brown

9

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

Current Risk Matrix Development Methods Often Fail To Give A Complete Risk Picture

Notional Representation Of Risks In Three Dimensions

Why are we looking at only one dimension at a time?

Should we call pt3(3,3,3) a Cost Risk, a Schedule Risk, or a Performance Risk?

Is pt2(1,4,1) more risky than the other points just because it has a high schedule severity?

Is pt1(3,2,3) just as risky as pt3(3,3,3)?

What if we have risk across four dimensions? Or five? Or Six?

How do we know we are focusing on the right risks?

Cost Risk Schedule Risk

=pt1=pt2=pt3

Performance Risk

Page 10: Doug brown

10

MRisk Makes Use Of Anchor Points And Multidimensional-Distance Measure To Determine Total Risk

The anchor points (1,1,1) and (5,5,5) come from our definition of the consequence scale

Distance for each point is defined by the distance of that point from the minimum over the sum of the distance from the minimum and the maximum

The distance value explains the precise consequence for each risk regardless of the number of dimensions

The greater the distance the greater the consequence and vice versa

This procedure is scalable to infinite dimensions of consequence, i.e. (1,1,…,1n) (5,5,…,5n)

min (1,1,1) max (5,5,5)

dmin

dmin

dmax d =

+

0102030405060708090

100

L M1 M2 M3 H1 H2 H3 C1 C2 C3

Consequence Scale

Low Medium High Critical

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

Cost Risk Schedule Risk Performance Risk

Page 11: Doug brown

11

Anchor Points & Mahalanobis Distance Make Risk Analysis Objective & Logically Consistent

The anchor points make it possible for us to know relative risk – Anchor points allow us to make the distinction between a (3,3,3) and a (4,2,2)– A cost consequence of 3, schedule consequence of 3, and safety consequence of 3 has a

distinct distance away from no consequence (1,1,1) and disaster (5,5,5)

Mahalanobis Distance keeps decision makers consistent in their thinking. By calculating risk based on the relationship between costs, schedule, safety, etc… MRisk identifies when violations of known relationships occur in the risk ranking process– For example, cost and schedule have a known relationship in the PM world

Schedule Cost

Scope

Page 12: Doug brown

12

MRisk Provides A Complete Risk Picture

MRisk addresses several shortcomings in the current methods

1. MRisk deals with all of the dimensions of Risk simultaneously to provide a complete risk picture

2. MRisk makes risk analysis objective and consistent with SME judgment

3. MRisk provides more advanced statistical algorithms to Risk Management without changing the current processes or products

5

4

3

2

1

1 2 3 4 5

RISK MATRIX

LIKE

LIHO

OD

CONSEQUENCES

Schedule Cost

Scope

Page 13: Doug brown

13

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

Mahalanobis Distance Mapping Tells Us How Far Each Risk Is From All Of The Other Risks, Thus Highlighting Outliers

Point Sched Cost Perf …Dimn

1 4 3 3 0

2 2 1 5 3

… … … … …

m 2 4 1 4

Notional Data Set From Risk Scoring

Using traditional distance measures the outlier point in the above scenario could be masked by its proximity to the other points

Mahalanobis distance highlights the point as an outlier because of its relative distance away from the group

Mahalanobis distance accounts for the relationship of each risk to another and highlights the risks that are uncorrelated, thus detecting extreme risks more efficiently

dmin = (x-xmin)S-1(x-xmin)

dmax = (x-xmax)S-1(x-xmax)

where

S-1 is the Inv(Covariance Matrix)

xmin = [1,1,1] xmax = [5,5,5]

Outlier

Typical Point

Page 14: Doug brown

14

Mahalanobis Distance Is Based On The Interdependencies Of Dimensions Consider two, random variables X and Y that consist of risk observations for some project or

program Those observations will have a variance and covariance Any set of random variables will have a Variance-Covariance matrix

𝑉𝑎𝑟 ( 𝑋 )= 1𝑛−1

∑𝑖=1

𝑛

(𝑥𝑖−𝑥 )2

Obs1

Obs2

Obs3

Obsn

X=

Obs1

Obs2

Obs3

Obsn

Y=

¿2𝑉𝑎𝑟 (𝑌 )= 1

𝑛−1∑𝑖=1

𝑛

(𝑦 𝑖− 𝑦 )2

[ 𝑉 𝑎𝑟 (𝑋 ) 𝐶𝑜𝑣 (𝑋 ,𝑌 )𝐶𝑜𝑣 (𝑋 ,𝑌 ) 𝑉𝑎𝑟 (𝑌 ) ]

𝐶𝑜𝑣 ( 𝑋 ,𝑌 )=∑𝑖=1

𝑛

(𝑥𝑖−𝑥)(𝑦 𝑖− 𝑦¿)

𝑛−1¿

=

¿1 ¿1

Page 15: Doug brown

15

Two Dimensional Mahalanobis Distance Example Consider again our two, random variables X and Y that consist of risk observations for some

project or program with the derived variance-covariance matrix The distance between two points in XY-plane depends on the inverse of the variance-

covariance matrix It’s simple to expand this case to Schedule Risks(X) vs Cost Risks(Y) vs Technical Risks(Z) or

any other type of risk comparison

5

4

3

2

1

1 2 3 4 5

Y

X

X0=(2,1)

Y0=(2,4)

Distance = (X-Y)(X-Y)`= (0,3)(0,3)`=18

X-Y = (2,1)-(2,4)=(0,3) Inv(Var-Cov)= =

Page 16: Doug brown

16

Legacy Methods By Contrast Assume Independence Of The Dimensions Of Risk

Consider again our two, random variables X and Y that consist of risk observations for some project or program with the derived variance-covariance matrix

In Euclidean Measure the distance between two points in XY-plane depends on the inverse of the Identity matrix

5

4

3

2

1

1 2 3 4 5

Y

X

X0=(2,1)

Y0=(2,4)

Distance = (X-Y)(X-Y)`= (0,3)(0,3)`=9

X-Y = (2,1)-(2,4)=(0,3) Inv(Identity)= =

Page 17: Doug brown

17

The MRisk Metric Calculates Distance While Accounting For The Point To Point Relationship

Mahalanobis D2 is a multidimensional version of a z-score. It measures the distance of a case from the centroid (multidimensional mean) of a distribution, given the covariance (multidimensional variance) of the distribution.

A case is a multivariate outlier if the probability associated with its D2 is 0.001 or less. D2 follows a chi-square distribution with degrees of freedom equal to the number of variables included in the calculation.

Mahalanobis' distance identifies observations which lie far away from the center of the data cloud, giving less weight to variables with large variances or to groups of highly correlated variables (Joliffe, 1986).

This distance has advantages to other distance measures like the Euclidean distance which ignores the covariance structure and thus treats all variables equally

Page 18: Doug brown

18

Case In Point: Multiple Risks Consider a risk scoring session involving

5 risks

SMEs vote on the probability and consequence (1,5) for five events across three dimensions: Performance, Cost, & Schedule

The score for each event is recorded in the table below

Event Prob Perf Cost Sched1 2 1 2 12 4 4 4 33 4 3 4 54 3 5 1 35 4 4 2 1

Page 19: Doug brown

19

Using MRisk All The Events Fit Onto One Scale

Event Prob dmin dmax d dscaled

1 2 0.75 14.00 0.05 1.202 4 3.69 1.59 0.70 3.793 4 2.85 4.37 0.39 2.584 3 2.02 9.99 0.17 1.675 4 2.46 7.00 0.26 2.04

min (1,1,1) max (5,5,5)

Event 1 Event 3

Event 5

Event 2

MRisk answers the question regarding highest project risk

A (4,4,3) is more consequential than a (3,4,5) or a (5,1,3)

The current methods would have us focus our attention on the (3,4,5) and the (5,1,3) despite the fact that they are not the most consequential

Event Prob Perf Cost Sched1 2 1 2 12 4 4 4 33 4 3 4 54 3 5 1 35 4 4 2 1

Event 4

Page 20: Doug brown

20

MRisk Provides A Clear Picture Of The Risk Profile Regardless Of The Number Of Dimensions Involved

Thi document contains

Booz Allen Hamilton

Inc. Proprietary

and Confidential

Business Information.

Event Prob Perf Cost Sched dscaled

1 2 1 2 1 1.202 4 4 4 3 3.793 4 3 4 5 2.584 3 5 1 3 1.675 4 4 2 1 2.04

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

Page 21: Doug brown

21

Traditional Multivariate Methods Like Euclidean Distance May Not Be As Clear Because They Don’t Consider Relationships

Thi document contains

Booz Allen Hamilton

Inc. Proprietary

and Confidential

Business Information.

Event Prob Perf Cost Sched Escaled1 2 1 2 1 1.102 4 4 4 3 4.143 4 3 4 5 4.414 3 5 1 3 3.005 4 4 2 1 2.11

5

4

3

2

1

1 2 3 4 5

LIKE

LIHO

OD

CONSEQUENCES

Lumping on severity despite

differences

Possible collusion of extreme risks

Page 22: Doug brown

22

MRisk Deals With Several Shortcomings In Risk Analysis

Just because we cannot visualize risk in multiple dimensions doesn’t mean it’s not there. We all realize that Risk Management is a multi-dimensional problem that requires a multi-dimensional solution.

MRisk does not seek to change Risk Management from its current practices and procedures. It just revolutionizes Risk Analysis.

MRisk does not require any change to current data collection techniques for implementation

MRisk takes the data from the current risk methods and allows for interpretation of risks through a multidimensional lens

The use of Mahalanobis Distance as a measure of consequence takes into account the relationships that risk events have across dimensions, i.e. cost, schedule, etc…– Since we know cost relates to schedule, schedule relates to performance, performance

relates to safety, etc… MRisk is most appropriate for measuring risk as it emphasizes the relationships among risks to calculate distance