Korean Electricity Market#9. Reference - Peak Management for Large Factory
World’s Largest Behind-the-meter LiB ESS project for Peak Management
Actual Image
Project Name LG Chem. ESS for Ik-San Factory
Applications Peak Cut and Shifting with ESS
Capacity PCS 3MW / Battery 23MWh
Period ’14. 1 ~ ‘14. 7 (7 months)
Role of LG CNS
- Project Management
- EPC
- EMS
Overview
2 / 23
Korean Electricity Market#9. Reference - Peak Management for Large Factory
Behind-the-meter ESS for maximum demand reduction and load shifting
Max. demand reduction
• Demand charge management
Maximum reduction: 4.84MW
• Energy charge management
Daily average charging & discharging: 17MWh
Monthly Load
Daily LoadLoad Shifting
3 / 23
Korean Electricity Market#9. Reference - Peak Management for Large Factory
Sharing the potential capabilities of the behind-the-meter ESS for whole frequency and local distribution system
• Fast FR Resource Needs bigger customer benefit than peak management
• Small-size Peaking Plant Deferral of MW-size distributed peaking plant
• Small-size Solar/Wind Storage Deferral of ESS for distributed solar/wind plant
T&DSubstation
Conventional Plant
Renewable Farm
Small-size Renewable
Diesel Generator
Behind-the-meter ESS
as …