Extended Metro in Stockholm Helsinki 2015-11-04
Extended Metro Administration Stockholm County Council
Stockholm – one of the fastest growing regions in Europe
Two buses per day
In 2030 approx
2,4 million
35-40 000 per year
Extended Metro Administration Stockholm County Council
The 2013 Stockholm negotiation The negotiation was led by government negotiatiators
Assignment:
An expansion of the Stockholm Metro system
Increasing housing construction in the Stockholm region.
An agreement was signed after 10 month.
Mr HG Wessberg
Ms Catharina Håkansson
Boman
Extended Metro Administration Stockholm County Council
14 000 appartments
5 400 appartments
13 500 appartments
40 000 appartments
2 100 appartments
3 000 appartments
Extended Metro Administration
Sidan 5
Stockholm Metro system, year 2025
78 000
New homes
The metro extension
6
Globen
Enskede gård
Extended Metro Administration
Total investment SEK 25,7 billion
RAIL INFRASTRUCTURE SEK 19,5 billion Finance Government 13 650 million City of Stockholm 2 950 million Municipality of Nacka 850 million City of Solna 600 million Municipality of Järfälla 800 million Stockholm County Council 650 million
DEPOT OCH TRAINS SEK 6,2 billion Finance Stockholm County Council SEK 6,2 billion
Extended Metro Administration Stockholm County Council
A new adminstration
Stockholm County Council is responsible for the metro expansion
March 2014: The extended metro administration was formed
Task: Planning, Design and Construction of the new Metro
Extended Metro Administration Stockholm County Council
Extended Metro Administration
County Council
Nacka, Gullmarsplan/ Söderort
Advisory board
Project board Project board
Project board
Head of Extended Metro Administration
Board
Depot, Signal, Rolling stock
Odenplan- Arenastaden
Järfälla-Barkarby
Engineering and Environment Permission and Land acquisition
Procurement Communication
Economy and Administration
Extended Metro Administration Stockholm County Council
Main Schedule 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Barkarby
Planning
Legal permits
Design
Procurement & construction
Arenastaden
Planning
Legal permits
Design
Procurement & construction
Nacka/söderort
Planning
Legal permits
Design
Procurement & construction
Depot & trains
Planning
Legal permits
Design
Procurement & construction
Extended Metro Administration Stockholm County Council
Akalla - Barkarby
Facts
Track length 3,3 km
2 new stations
Rock excavation 500.000m3
Construction period 2016 -2021
SEK 3 billion
Extended Metro Administration Stockholm County Council
Odenplan - Arenastaden
Facts
Track length 4,6 km
2 new stations
Rock excavation 580.000m3
Construction period 2016 -2022
SEK 4 billion
Extended Metro Administration Stockholm County Council
Facts
Track length 11 km
5 new stations
Rock excavation 1.500.000m3
Construction period 2018 -2025
SEK 12.5 billion
Extended Metro Administration Stockholm County Council
Kungsträdgården- Nacka/Söderort
Depot, Rolling Stock & Signalling system
Extended Metro Administration
Sidan 14
Facts
• 1 depot Stabling & maintenance
• Tunnel and tracks
• Construction 2018-22
• SEK 3,4 billion
Where are we now?
Extended Metro Administration
Sidan 15
Extended Metro Administration
Sidan 16
Legal documents/processes
Planning process
Railway plan
Detailed development plans
Decisions on Environmental impact
Application to the Land and Environmental Court
Extended Metro Administration
Page 17
Conceptual design- stations
Förvaltning för utbyggd tunnelbana
Sidan 18
Information
Open house with information for the public
Pressreleases
Newsletters
Advertising in papers
And more…
Building techniques
Förvaltning för utbyggd tunnelbana
Sidan 19
Tunneling
All tunnels and stations will be done in hard crystalline rock (+250 MPa).
Traditional methods with drill and blast will be used instead of TBM (Tunneling Boring Machine).
Extended Metro Administration
Page 20
Cut and cower, Odenplan
Extended Metro Administration
Sidan 21
The green line was constructed in
the 1940’s
The new platform will be in the
same level
Odenplan, Arenastaden
Förvaltning för utbyggd tunnelbana
Sidan 22
We are analyzing track bed alternatives; traditional ballasted track or slab track.
Extended Metro Administration
Page 23
Track bed
Extended Metro Administration
Page 24
We are planning for double track tunnel with a parallel evacuation/service tunnel where it´s possible.
Extended Metro Administration Stockholm County Council
Kungsträdgården- Nacka/Söderort
2015-11-03 26
Förvaltningen för utbyggd tunnelbana
Metro to Nacka:
Assessed alternatives
Kungsträdgården (Nacka)
Extended Metro Administration
Sidan 27
Förvaltning för utbyggd tunnelbana
Sidan 28
Profile – Extension to Nacka
Extended Metro Administration
Page 30
Sofia
approx.
100 m
Deep stations
Extended Metro Administration
Page 31
The new stations will be situated deep or very deep, 30 to 90 meters under ground level.
The deepest station, Sofia, will only be served by elevators.
Deep station in Barcelona. Pia Lindberg Nedby
Förvaltning för utbyggd tunnelbana
Sidan 32
Förvaltning för utbyggd tunnelbana
Sidan 33
Förvaltning för utbyggd tunnelbana
Sidan 34
Station Hammarby kanal
Förvaltning för utbyggd tunnelbana
Sidan 35
Station Hammarby Kanal
Förvaltning för utbyggd tunnelbana
Sidan 36
Extended Metro Administration
Sidan 37
Procurement
Extended Metro Administration
Page 38
The Extended Metro Administration have to follow the Act on Procurement in the Water, Energy, Transport and Postal Services Sectors ( in Swedish “LUF”).
Buisness form
The contracts will have different buisness forms consisting of:
Extended Metro Administration
Sidan 39
Contract form
• Design and build
• Traditional contract
• Combinations
Form of payment
• Fixed price
• Unit price
• Other and/or combinations
Level of cooperation
• Cooperation (behavior)
• Cooperation/Partnering
Procurement procedure
• Open procedure
• Negotiated procedure
Contract division, example
Extended Metro Administration
Sidan 40
Civil works (including tunneling) 1-3 contracts
Construction work (stations) 1-3 contracts
BEST works (Rail, Electric, Signal and Telecommunication) 1 contract
Announcement and invitation
Extended Metro Administration
Page 41
Qualification will mostly be done by TransQ (Achilles)
The suppliers that are qualified, according to relevant requirements for a contract, will get an invitation to tender. To be able to get an invitation the suppliers must be registered in TransQ.
Announcements can/will be done to inform the market about procurements.
In general we will not start a procurement before we have the necessary decisions for the current project.
Ongoing procurement- Art in the new Metro The Stockholm Metro is famous for its extensive
focus on art and has an international reputation as "The world's longest art gallery". More than 150 artists have so far helped to give the Stockholm Metro its own unique look.
Each new station will have a unique look which also contributes to increasing safety and navigability for travellers.
Extended Metro Administration
Page 42
Extended Metro Administration
Sidan 43
Preliminary design - procurement in December 2015/January 2016
Upcoming procurement
Procurement will be performed trough ZeroChaos.com
ZeroChaos is a global, vendor-neutral provider of integrated workforce management solutions.
Procurements 2016
Preparatory works, Barkarby - temporary roads
Access tunnels, Barkarby.
Preparatory works, Arenastaden
Civil works (tunneling) Barkarby
Förvaltning för utbyggd tunnelbana
Sidan 44
Procurementplan
A plan where all upcoming procurements are specified for the extension.
The plan will be updated as often as necessary.
The information will be shown at: www.sll.se/nyatunnelbanan
Extended Metro Administration
Sidan 45
Follow the extension
Extended Metro Administration
Sidan 46
www.sll.se/ nyatunnelbanan