    EPRTMreactor: the path to certainty

  • 8/6/2019 EPR

    3/30

    > EPRTM: the path to certainty Andreas Goebel3 3

    1950 1970 1988 2010 2040

    Generation I Generation II

    PWR, BWR, PHWR, RBMK, AGRFirst prototypes

    of reactors

    Chooz,

    Brennilis,

    Kahl, MZFR

    PWR, BWR

    < 1,400 MWe

    N4, KONVOI

    1,300 to 1,500 MWe

    R&D on

    Innovative systems

    EPR, ATMEA1,

    KERENA

    1100 to 1,600 MWe

    Generation III+

    PWR, BWR

    PHWR

    An evolutionary approach to Gen III+ reactors

  • 8/6/2019 EPR

    4/30

    > EPRTM: the path to certainty Andreas Goebel4 4

    A complete range of Gen III+ reactors

    TM

    X High power output (1600+MWe)

    X Evolutionary design(Konvoi/N4)

    X Construction permits inFinland and France, China2009. On-going construction

    in these countriesX Low global powergeneration costs

    X Outstanding safety level

    XMinimal environmentalimpact

    XMaximized benefit from sizeeffect

    XMedium power output(1100+ MWe)

    X Evolutionary design(AREVA/MHI)

    X Design based on EPR andMHI model

    X Outstanding safety level

    XMinimal environmentalimpact

    XMedium power output(1250+ MWe)

    X Evolutionary design(Gundremingen referenceplant) with use of passivefeatures in some safety

    systemsXOutstanding safety level

    XMinimal environmentalimpact

  • 8/6/2019 EPR

    5/30

    > EPRTM: the path to certainty Andreas Goebel5 5

    Competitive

    The EPR reactor: performance with certitude

    Evolutionary

    Safe

    Proven technology based on 87 PWRs builtthroughout the world, integrating numeroustechnological innovations

    Core meltdown prevention with 4 times 100% redundant safeguardsystems, mitigation of severe accidents consequences, radiological

    protection, functional diversity of safety systems, robustness

    against external hazards such as airplane crash

    High power output (1600+ MWe), efficiency and availability, reduced powergeneration costs, extended life service

    Double concrete shell designed to

    withstand the impact of a largeairplane crash

  • 8/6/2019 EPR

    6/30

    > EPRTM: the path to certainty Andreas Goebel6 6

    Projects

    Flamanville 3

    Olkiluoto 3

    Taishan 1&2

    4 EPR under construction

  • 8/6/2019 EPR

    7/30

    > EPRTM: the path to certainty Andreas Goebel7 7

    Where Olkiluoto, Finland

    Contract signed Dec 18, 2003

    Customer Teollisuuden Voima Oy (TVO)

    Supplier Consortium formed by AREVA and Siemens AG

    (73% / 27%) and led by AREVA

    Supply scope 1 EPR unit in turnkey construction

    First Concrete Jul, 2005

    Net electric output 1,600 MWe

    Reactor thermal output 4,300 MWth

    Target delivery date 2012

    Olkiluoto 3 Fast Facts

    For internal use only

    The EPR Olkiluoto 3 Project

  • 8/6/2019 EPR

    8/30

    > EPRTM: the path to certainty Andreas Goebel8 8

    July 2007 FLASHBACK - General view

  • 8/6/2019 EPR

    9/30

    > EPRTM: the path to certainty Andreas Goebel9 9For internal use only

    2009 20102008

    February 08Steam GeneratorBlowdown Tankinstallation

    May 08Reactor

    Compartment PoolFrame-work installed

    July 08EDG tanks installationin Nuclear AuxiliaryBuilding

    June 08Erection started:First pipe installedin Fuel Building

    October 08Start of electro-mechanical activities

    November 08Next-to-last double ring linerinstalled in Reactor Building

    First heat exchanger liftedinto Safeguard Building

    Installation of first

    accumulator in ReactorBuilding

    Olkiluoto 3 Milestones

    January 09RPV and itshead deliveryat OL3

    Temporary

    Control Roomready foroperation

    March 09Start of electro-mechanicalactivities in thespreading area

    The EPR Olkiluoto 3 Project

    May 09Reactor domedelivered on site

    Completion of thecooling elementsinstallation in thecore catcher

  • 8/6/2019 EPR

    10/30

    > EPRTM: the path to certainty Andreas Goebel10 10

    Civil construction status reactor building

    Reinforcement ongoing

    Concreted

    April 2009

    July 2007

  • 8/6/2019 EPR

    11/30

    > EPRTM: the path to certainty Andreas Goebel11 11

    The EPR Olkiluoto 3 Project May 2009

    OL3, the 1stof the EPR worldwide fleet

  • 8/6/2019 EPR

    12/30

    > EPRTM: the path to certainty Andreas Goebel12 12

    The EPR Olkiluoto 3 ProjectNuclear Island - May 2009

  • 8/6/2019 EPR

    13/30

    > EPRTM: the path to certainty Andreas Goebel13 13

    The EPR Olkiluoto 3 ProjectTurbine Island - May 2009

  • 8/6/2019 EPR

    14/30

    > EPRTM: the path to certainty Andreas Goebel14 14

    The EPR Olkiluoto 3 ProjectReactor Dome Delivery on site May 4

  • 8/6/2019 EPR

    15/30

    > EPRTM: the path to certainty Andreas Goebel15 15

    The EPR Olkiluoto 3 ProjectInstallations completed at the Spreading area - May 2009

    3D view of IRWST and Spreading Area

    Incontainment

    RefuelingWater

    Storage Tank(IRWST)

    Spreadingarea

  • 8/6/2019 EPR

    16/30

    > EPRTM: the path to certainty Andreas Goebel16 16

    Transfer of activities from civil constructionto electro-mechanical installation

  • 8/6/2019 EPR

    17/30

    > EPRTM: the path to certainty Andreas Goebel17 17

    The EPRTMFlamanville 3 Project

  • 8/6/2019 EPR

    18/30

    > EPRTM: the path to certainty Andreas Goebel18 18

    Flamanville 3 Fast Facts

    General Presentation Market and OutlookProducts and Projects

    Copyright EDF March 2009

    Where Flamanville, France

    Contract signed Apr 11, 2007

    Customer Electricit de France (EDF)

    Supplier AREVA

    Supply scope 1 EPR unit

    - Nuclear Island Nuclear Steam Supply System (NSSS)- Nuclear Island Engineering & Procurement (NI EP)

    First Concrete Dec 2007

    Net electric output 1,630 MWe

    Reactor thermal output 4,300 MWth

    Target delivery date 2012

    For internal use only

    The EPRTMFlamanville 3 Project

  • 8/6/2019 EPR

    19/30

    > EPRTM: the path to certainty Andreas Goebel19 19

    The EPR Flamanville 3 ProjectView of the site May 2009

  • 8/6/2019 EPR

    20/30

    > EPRTM: the path to certainty Andreas Goebel20 20

    The EPR Flamanville 3 ProjectView of the site May 2009

    COPYRIGHT EDF

  • 8/6/2019 EPR

    21/30

    > EPRTM: the path to certainty Andreas Goebel21 21

    The EPR Flamanville 3 ProjectReactor Building May 2009

  • 8/6/2019 EPR

    22/30

    > EPRTM: the path to certainty Andreas Goebel22 22

    The EPR Flamanville 3 ProjectTurbine Building May 2009

  • 8/6/2019 EPR

    23/30

    > EPRTM: the path to certainty Andreas Goebel23 23

    The EPR Taishan 1&2 Project

  • 8/6/2019 EPR

    24/30

    > EPRTM: the path to certainty Andreas Goebel24 24

    Where Taishan, China

    Contract signed Nov 26, 2007

    Customer Taishan Nuclear Power Company (TSNPC)

    Supplier AREVA in consortium with 2 subsidiaries of CGNPC

    Supply scope 2 EPR units and the materials and services to operate them:

    -Nuclear Island Engineering & Procurement (NI EP)- Nuclear Steam Supply System (NSSS)- Balance of Nuclear Island (BNI)

    -Supply fuel and enriched uranium for 15 years

    First concrete Aug 2009

    Net electric output 1,660 MWe

    Reactor thermal output 4,590 MWth

    Target delivery date 2013-14

    Taishan 1&2 Fast Facts

    The EPR Taishan 1&2 Project

    2008

  • 8/6/2019 EPR

    25/30

    > EPRTM: the path to certainty Andreas Goebel25 25

    Site location

    TAISHAN

    Daya Bay

  • 8/6/2019 EPR

    26/30

    > EPRTM: the path to certainty Andreas Goebel26 26For internal use only

    The EPR Taishan 1&2 ProjectView of the site - May 2009

  • 8/6/2019 EPR

    27/30

    > EPRTM: the path to certainty Andreas Goebel27 27For internal use only

    The EPR Taishan 1&2 ProjectExcavation - May 2009

  • 8/6/2019 EPR

    28/30

    > EPRTM: the path to certainty Andreas Goebel28 28

    Future developments of the EPR reactor

    EMIRATES

    X EPR projectunderpreparation withSuez and Total

    X MoU for 2 EPRreactors

    INDIA

    FRANCE

    X 2nd EPRTM inPenly launchedin March 2009

    USA

    X EPRtechnologyselected by fiveutilities

    X Certificationsubmitted in

    Dec. 2007

    X Detailed Designunderway

    UK

    X EPR design

    pre-certificationunderway

    X EPRtechnologyselected by EDFand E.ON

  • 8/6/2019 EPR

    29/30

    We are building the new generation

    for power generation

    > Plants Business Unit - May 2009