HG7/210AD Air compressor
Operation Manual
Part Manual
版本: A
版本号:20150205
8/17/2019 01.75.ZSH-02EN -
2/141
2
2.1 system specification …………………………………………………………… 10
2.1.1 system technology parameters ……………………………………… 11
2.1.2 instrument the value of setting………………………………………… 12
2.2 principle and structure ………………………………………………………… 14
2.2.1 working principle ………………………………………………………… 14
2.2.2 appearance ……………………………………………………………… 17
2.3 Bump configuration …………………………………………………………… 19
2.3.1 crankshaft-rod kit………………………………………………………… 20
2.3.2 crankshaft-rod lubricating ……………………………………………… 21
2.3.3 cylinder kit …………………………………………………………… 222.3.4 cylinder lubrication……………………………………………………… 23
2.4 driving and transmission ……………………………………………………… 24
2.4.1 driving configuration ………………………………………………… 24
2.4.2 transmission…………………………………………………………… 24
2.4.3 mechanism tensioning ………………………………………………… 24
2.5 safety and control kit ………………………………………………………… 25
2.5.1 safety ………………………………………………………………… 25
2.5.2 emergency stop switch ………………………………………………… 26
2.5.3 oil pressure monitoring ……………………………………………… 26
2.5.4 oil pressure monitoring ………………………………………………… 26
2.5.5 temperature monitoring ………………………………………………… 26
2.5.6 check valve …………………………………………………………… 26
2.5.7 D4 control valve …………………………………………………… 27
2.6 other device ……………………………………………………………… 27
2.6.1 gas and water separator ……………………………………………… 27
2.6.2 air inlet filter …………………………………………………………… 28
2.6.3 automatic sewage system …………………………………………… 28
2.6.4 inter stage cooler ……………………………………………………… 29
2.6.5 cylinder group …………………………………………………………… 29
1
2
PREFACE
Preface………………………………………………………………………………………5
1.1 Warranty………………………………………………………………………………8
1.2 Assistance……………………………………………………………………………9
0
WARRANTY AND ASSISTANCE
SYSTEM INTRODUCTION
8/17/2019 01.75.ZSH-02EN -
3/141
3
M A I N T E N A N C E 4
INSTALLATION AND OPERATIO N 3
3.1 Unpacking……………………………………………………………………………32
3.2 Installation ………………………………………………………………………32
3.3 Ready to use …………………………………………………………………… 33
3.2.1 Check before use ………………………………………………………… 33
3.2.2 Lubricating oil filling ………………………………………………………34
3.2.3 Pipe connection …………………………………………………………35
3.2.4 Electrical connection ……………………………………………………35
3.4 Compressor operation ……………………………………………………………36
3.4.1 Electric system operation …………………………………………………36
3.4.2 The control logic ………………………………………………………… 44
3.4.3 Equipment safety operation regulation ……………………………………46
2.7 Safety signs and danger zone………………………………………………………30
2.7.1 Safety signs …………………………………………………………………30
2.7.2 Safety signs …………………………………………………………………31
T R O U B L E S H O T I N G 5
6 CIRCUIRY
6.1 Circuitry …………………………………………………………………………… 69
4.1 Maintenance schedule…………………………………………………………… 48
4.2 Lubrication system maintenance ………………………………………………49
4.3 Transmission parts maintenance ………………………………………………51
4.4 Filtering device …………………………………………………………………53
4.5 Lubrication and maintenance of Diesel …………………………………………59
4.6 coolers …………………………………………………………………………… 60
4.7 Removal of oil carbon ………………………………………………………………61
5.1 Compressor unit ………………………………………………………………62
5.2 piston compressor ……………………………………………………………… 64
5.3 Valve troubles …………………………………………………………………… 68
8/17/2019 01.75.ZSH-02EN -
4/141
4
S P A R E P A R T S7
7.1 Compressor spare parts ………………………………………………… 77
7.1.1 crankcase assembly …………………………………………………… 79
7.1.2 crank shaft assembly …………………………………………………… 817.1.3 rod assembly …………………………………………………………… 82
7.1.4 oil-bump assembly ……………………………………………………… 83
7.1.5 cylinder assembly8.125“ …………………………………………… 84
7.1.6 cylinder assembly6.125“ …………………………………………… 85
7.1.7 cylinder assembly3.25“ …………………………………………… 86
7.1.8 cylinder assembly1.875“ …………………………………………… 87
7.1.9 cylinder assembly1.25“ …………………………………………… 88
7.1.10 guide-cylinder assembly …………………………………………… 89
7.1.11 NO.1 cylinder-head assembly ……………………………………… 90
7.1.12 NO.3cylinder-head assembly ……………………………………… 92
7.1.13 NO.4cylinder-head assembly ……………………………………… 93
7.1.14 NO.5cylinder-head assembly ……………………………………… 94
7.1.15 piston assembly 8.125“ ………………………………………… 95
7.1.16 balanced piston assembly6.125“ ………………………………… 96
7.1.17 piston assembly 3.25“ …………………………………………… 97
7.1.18 piston assembly 1.875“ …………………………………………… 98
7.1.19 piston assembly 1.25“ …………………………………………… 99
7.1.20 Fan & wheel assembly …………………………………………… 100
7.2 packing spare-parts ……………………………………………………… 101
7.2.1 The separator assembly ……………………………………………… 107
7.2.2 Sewage assembly …………………………………………………… 105
7.2.3 mount assembly …………………………………………………… 107
7.2.4 Drive assembly ………………………………………………………… 109
7.2.5 Diesel assembly …………………………………………………… 115
7.2.6 Transmission tighten assembly ………………………………… 1237.2.7 Diesel fuel pipe assembly ………………………………………… 124
7.2.8 pressure meter assembly …………………………………………… 125
7.2.9 air-Cooler assembly ……………………………………………… 128
7.2.10 lubricating pipe assembly ………………………………………… 130
7.2.11 Exhausting pipe assembly ………………………………………… 132
8/17/2019 01.75.ZSH-02EN -
5/141
5
PREFACE0
1, please read and follow this manual provides all the user operation, operationprocess, preventive measures and manual that appears all danger, warning statement,
otherwise there will be likely to lead to serious safety accidents.
2, please read carefully and correctly understand the contents of the manual and thefollowing
! DANGER
Risk mark used when the misuse or failure may cause personal injury.
WARNING
Warning signs used when misoperation or fault may cause damage to units orcomponents.
1 2 3 4
8 7 6 5
WARNING LABLE
NO. Warning label content NO. Warning label content
1 Hand clamp 5 Prohibit to work in the movement
2 Mechanical movement parts 6 Please wear protective glasses
3 electric shock 7 Please wear a helmet
4 Prohibit to remove the protectivestructure
8 Please wear protective gloves
Table 0-1 Label content
8/17/2019 01.75.ZSH-02EN -
6/141
6
8/17/2019 01.75.ZSH-02EN -
7/141
7
For the protection of personnel and property safety, please strictly observe safetyrules in this manual and safety regulations of local government.
This manual should be kept!
8/17/2019 01.75.ZSH-02EN -
8/141
8
WARRANTY AND ASSISTANCE
High Air Machinery (Shang Hai) Co., Ltd. :The machine warranty finished in
12 months after the delivery。Error is to be reported within 8 days, if the customer
found it.
The warranty regulations apply only to the machine running environment in the
warranty period under normal operation, and after refer to manual for proper
operation, use and maintenance, still engender fault or damage.
The warranty explicitly ruled out the consequences due to error using. The
warranty does not include the consumption of materials and periodic maintenance
costs, the costs will be borne by the customer. Any changes without the High Air
Machinery authorization for the structure and control mode of the machine, the
warranty lapsed automatically.
High Air Machinery promised all fault or damage due to design , production,
and materials etc. ,can be Free repair or replacement .
If the Machine has been delivered, the customer found that damaged parts need
to be replacement , shall declare in advance, otherwise the warranty does not produce
any effect.
High Air Machinery has the right to repair and replacement parts, more than the
warranty period does not give change.
The unidentified warranty regulations, High Air Machinery does not provide
any parts of the compensation.
High Air Machinery don't assume for human injury and property damage directly
or indirectly (stop production, loss of interests etc.).
1
WARRANTY 1.1
8/17/2019 01.75.ZSH-02EN -
9/141
9
High Air Machinery (Shang Hai) Co.,Ltd and our agents are always readyto provide technical support and service for you. !
please contact with High-Air Machinery (Shang Hai) Co.,Ltd and our agents.
High Air Machinery (Shang Hai) Co.,Ltd
NO.155 Tinghua road Jin shan distr ict Shang Hai.
TEL:+86 021 60892089
FAX:+86 021 60892120
http://www.highair.cn sale@highair .cn
Service Phone: +8621 60892116 18017133181 18017133182 400-8581-078
E-mail:[email protected]
A S S I S T A N C E 1.2
8/17/2019 01.75.ZSH-02EN -
10/141
10
High Air Compressor W type, 6 cylinder 5 stage single action piston compression, the maximum discharge
pressure 210Bar. The precise balance of piston, single connecting rod design. Large
displacement, low speed, air - cooled and no foundation design , multiple V belt
drive, splash lubrication with forced lubrication. The complete equipment, open
architecture design, is the ideal choice for industrial users.
*The picture is for reference only, please make the object as the standard
SYSTEM INTRODUCTION2
8/17/2019 01.75.ZSH-02EN -
11/141
11
The system consists of five stage high-pressure compression :diesel engine, high
pressure cylinder group system, pressure control valves and electrical. control system. All theparts are mounted on a cabinet control system. All the parts are mounted on a cabinet.
Table 2-1 The working environment of the unit
Ambient Temp. -10~45℃
Elevation ≤1000m
Power Diesel-driven
Working medium Air
Suction Temp. Ambient Temp.
Suction Pressure. Atm. pressure
T h e s y s t e m p a r a m e t e r s 2.1
Technical Data 2.1.1
stage Cyl.No. Dia(inch) style Operating press.*)
1 2 8.125 ingle action piston 2.9Bar
2 1 6.125 11 Bar
3 1 3.25 Single action piston with
a guide cylinder
33 Bar
4 1 1.875 80 Bar
5 1 1.25 210 Bar
Table 2-3 technical data of the cylinder :
Table 2-2 compressor The main technical parameters
model HG7/210AD
cylinder num. /compression stage
6/5
Working medium Air
air flow 6.5Nm3/min
exhaust Pressure. 21MPaGCooling style Air-cooled
Drive style Diesel-driven
shaft power 122KW
stroke 133.6mm
speed 982RPM
Lubricating style Oil-bump + splash lubrication
lubricating oil pressure 1.5-3Bar(hot)
oil tank volume 22L
Lubricant model SH150
Diesel-driven power 183KW@1800rpm
weight ~8000Kg
Suction Pressure. 0.1 MPaA(abs.)
*)The actual operating pressure in the test report shall prevail, this parameter is for reference only .
8/17/2019 01.75.ZSH-02EN -
12/141
12
序
号代号 阀门类型 监测类型 安装位置 常规数值 备注
1 BV01 ball valve Oil draining ,bump
local normally close
2 BV02 ball valve Oil drain, Diesel local normally close
3 BV03 ball valve Oil out, fuel tank local normally open
4 BV04 ball valve Oil back-flow,
fuel tanklocal normally open
5 BV02 ball valve Oil out, fuel tank local normally close
6 BV03 ball valve Water out, tank local normally close
7 BV04 ball valve PRV02 reliefvalve, suction
port
local normally close
8 ILV01 sluice valve Exhaust, cylinder local normally close
9 ILV02 sluice valve Exhaust, exhaust
portlocal normally close
10 ILV03 sluice valve Air-Exhaust
Truncationlocal normally open
表2-4 阀门状态表
2.1.2 Instrument set points
The normal operation of the following monitoring and protection device used toprotect the compressor. If you run the value is out of range of the set value, thecompressor controller will automatically alarm and shutdown, and show the cause of
the problem. At each compression stage, when there is problem for the automatic control and
monitoring system, the safety valve is to prevent overpressure as the last safety line. Incase of necessity, the safety valve will open, gas emptying out of the compressor.
The safety valve in the factory has been set up based on the release of pressure
at all stages of the required, and playing with the lead sealing. The working pressureshall be at least 5% lower than the safety valve set pressure, the visible under the table.
Operation display instrument can indicate operation status of compressor. Oper-
ation data given in the table below are the loading condition based on normal enviro-
nmental conditions.
During the running process of the compressor, some running parameters have
large deviation from the conventional numerical. Once this happens, it should immed-
iately stop the compressor, and troubleshooting.
8/17/2019 01.75.ZSH-02EN -
13/141
13
NO. code Instrument Monitoring type Installation Figure*) remarks
1 DCA01 Current gauge Generation current; Dash board 0-55A
2 DCV01 Voltage gauge Charge voltage Dash board 28V 20V alarm
3 FG01 Fuel gauge oil level Dash board — 1/4 alarm
4 OLT01 oil level sensor oil level local —5 PI01 Press. gauge 1st suc. press. local 0 bar
6 PI02 Press. gauge 1st Exh. press. Dash board 2.9 Bar
7 PI03 Press. gauge 2st Exh. press. Dash board 11 Bar
8 PI04 Press. gauge 3st Exh. press. Dash board 33 Bar
9 PI05 Press. gauge 4st Exh. press. Dash board 80 Bar
10 PI06 Press. gauge 5st Exh. press. Dash board 210 Bar
11 PI07 Press. gauge Lubricant press. Dash board 1.5-3 Bar
12 PI08 Press. gauge Regulated press. local 8 Bar
13 PI09 Press. gauge Exh. Press. Dash board <210 Bar
14 PI10 Press. gauge Exh. Press. Dash board <210 Bar
15 PI11 Press. gauge Regulated press. local 2-3 bar
16 PRV01 Relief valve Instrument air Dash board 8 Bar adjustable
17 PRV02 Relief valve Instrument air Dash board 3 Bar adjustable
18 PS01 Press. switch Exh. Press. local 215 Bar Adjust ban
19 PS01 Press. switch Bump Press. local 1.5 Bar Adjust ban
21 RV01 safety valve 1st Exh. press. local 4 Bar Adjust ban
22 RV02 safety valve 2st Exh. press. local 12 Bar Adjust ban
23 RV03 safety valve 3st Exh. press. local 45 Bar Adjust ban
24 RV04 safety valve 4st Exh. press. local 132 Bar Adjust ban
25 RV05 safety valve 5st Exh. press. local 220 Bar Adjust ban
26 RV06 safety valve Cylinder press. local 220 Bar Adjust ban
27 TT01 Temp sensor Exh.Temp. local —
28 TT02 Temp sensor Water-tank Temp local —
29 TT03 Temp sensor Crankcase Temp local —
20 PT01 Press. Temp. Exh.Temp. local —
Table 2-5 Instrument set points
*) Actual operating pressure to test report shall prevail, this parameter is for reference only .
8/17/2019 01.75.ZSH-02EN -
14/141
14
HG7/210AD compressor Is the reciprocating compressor 5 stage compression,Specifically for the air pressure below the 210bar applications. The actual air delivery
of 6.5Nm3/min, the compression ratio and intercooler efficiency, reasonable design,
high pressure air supply reliable.
The following basic operation principle:
● In the 1st stage piston suction stroke, atmospheric pressure air enters the 1st
stage cylinder through the air inlet filter and the suction valve. The compressionstroke will compress the air to an intermediate pressure, and the air isdischarged to the intercooler piping through the 1st stage of the discharge valve.in here, the compressed air at high temperature and high pressure have heatexchange with the cold air sucked by the cooling fan, so that the temperature of
the compressed air is reduced to above 15-20℃ than environmental
temperature, ensure the 2nd stage compression without over temperature.
● The discharge stroke of 1st stage is just the suction stroke of 2nd stage. coolingair is sucked to cylinder through 2nd stage of suction valve, the air in the cylinder
is further compressed to a higher pressure. In the 2nd stage of the compression
stroke, high temperature and high pressure air enters the 2nd stage intercoolerthrough 2nd stage of discharge valve, in the cooler, high temperature of thecompressed air get heat exchange with the cold air, the temperature is reducedto above 15-20℃ than environmental temperature, ensure that the third stagecompression without over temperature.
● Such a cycle, until after the five stage compression, air pressure to meet userrequirements, At the same time in the unit operation process, as a result of thecompressed air in the inter stage cooler and cooler air to exchange heat, itstemperature decreases, the saturate vapor in the compressed air condense towater due to decreasing temperature, separate with compressed air in the
separator, Then through the automatic control with the drain valve, timing drainout from separator.
● Compressor configuration has a full start unloading system. This willautomatically release the pressure of the cylinder, inter stage cooler, and drainout water from the separator when the compressor stop working.
CATION:When the compressor shutdown,at least should be unloaded for more
than 5 minutes, to exhaust heat air in compressor ,because after the
compressor stops, the vapor in the compressed air will be precipitated when thetemperature drops, the cylinder internal will be get rust; in cold weatherconditions will make the pipes freeze.
Principle and structure 2.2
W o r k i n g p r i n c i p l e 2.2.1
8/17/2019 01.75.ZSH-02EN -
15/141
15
Process indicator diagram
压 缩 机 进 气
口
柴 油 机
1 8 3 K W @
1 8 0 0 r p m
进 气 介 质 : 空
气
主 机 轴 转 速 : 9
6 0 R P M
排 气 压 力 :
2 1 0 B a r
流
量 :
6 . 5 m ³
/ m i n
P I
0 9
R V
0 6
P I
1 0
I L V
0 1
I L V
0 2
H P C 0
1
2 0 T -
3 .
5
排 气 口
3 / 4 U N F × 1 6
J I S s w
i v e
l
柴 油 机 进 气 口
R T
0 1
R C
0 1
柴 油 机 放 油
口
R c
1 / 2
B V
0 2
油 箱 放 油 口
R c 1
/ 2
B V
0 5
O T
0 1
S P F
0 2
B V
0 3
B V
0 4
2 0 T - 3 . 5
1 6 T - 3
进 气 介 质 : 空
气
柴 油 机 转 速 :
1 8
0 0 R P M
B V
0 6
I C
0 6
O L T
0 1
A I
A I
加 油 口
F G
0 1 D
I
呼 吸 口
I F
0 2
1 4 H -
3 1 4 H - 3
G E D C A
0 1
D I
D C V 0
1
D I
L S
0 1 D
I
D C 2 4 V
2 3 H - 3 .
5
T T
0 2
P T
0 2
O L M
0 1
5 6 H - 3
2 3 H -
3 . 5
P S
0 1 D
I
T T
0 1 A I
加 油 口
S S S
P I
0 1
S P F
0 1
P I
0 8
P R V
0 1
8 8 . 9 P - 5
3 8 T - 1 . 5 3 0 T - 1 . 5
3 0 T - 1 . 5
2 5 T - 2 2 5 T - 2
一 级 缸
一 级 缸
二 级 缸
三 级 缸
四 级 缸
五 级 缸
12T-2.5
12T-2.5
12T-2.5
12T-2.5
1 2 T - 2 . 5
I F
0 1
D P I
0 1
H E A
0 1
1 2 H - 5
2 5 T -
2
V S
0 1 D I
3 0 T - 1 . 5
3 0 T - 1 . 5
3 0 T - 1 . 5
2 5 T - 2
2 0 T - 3 . 5 2 0 T - 3 . 5
R V
0 1 S
R 0 1
12T-2.5
6 0 . 3 P - 5
P I
0 2
A B V
0 2
A B V
0 3
A B V
0 1
D O
D O
D O
R V 0 2 S R 0 2
R V 0 3 S R 0
3
R V 0 4 S
R 0 4
R V
0 5 S
R 0 5
P S
0 2
D I
P I
0 7
8 8 . 9 P -
5
B V
0 1
I C
0 1
C V
0 1
H S
D O
3 8 T - 1 . 5
3 8 T - 1 . 5
3 8 T - 1 . 5
3 8 T - 1 . 5
P T
0 1
A I
D O
D O
S V
0 2
S V
0 1
I C
0 2
I C
0 4
I C
0 3
I C
0 5
6 0 . 3 P - 5
1 2 T - 2 . 5
1 2 T - 2 . 5
1 2 T - 2 . 5
1 2 T - 2 . 5
6 T - 1
P I
0 3
6 T -
1
P I
0 4
6 T - 1
P I
0 5
6 T - 1
P I
0 6
6 T - 1
6 T - 1
2 0 T -
3 . 5
6 T - 1
6 T -
1
6 T - 1
T
T
0
3
A
I
6 T - 1
2 0 T - 3 .
5
主 机 放 油 口
R c
1 / 2
排 污 口
G 2 内
P R V
0 2
放 空 口
1 F N P T
2 0 T - 3 .
5
1 6 T - 3
C O V
0 1
P P
0 1
A I
S R
0 6
I F 0
4
P I
1 1
I L V
0 3
A I
2 5 T -
2
P P
0 2
S V
0 3 D O
B V
0 7
I F
0 3
L S L
0 1
H P C
0 2
H P C
0 3
H P C
0 4
1 6 T - 3
1 6 T - 3
1 6 T - 3
2 5 T - 2
8 T - 1 . 5
1 2 H - 2 8 0
R V
0 7
5 0 H - 3
8/17/2019 01.75.ZSH-02EN -
16/141
16
Legend and instructions
A
L e g e n d / A i r
1 S T
电 机
1 3 2 K W
3 8 0 V , 5 0 H Z
A I
S
P P
0 1
H
G E
M
S P F 0
1 I
F 0
1
O i l f i l t e r I F
I F
0 1
O L S
0 1
V i b r a t i o n s w i t c h V S
V S
0 1
F S
0 1
H G T
0 1
L O P
0 1
H O P
0 1
H E A
0 1
P S
0 1
L S
0 1
S L
0 1
D I D O E O M
C o o l e r I C
I C
0 1
a i r
w a t e r
V e r t i c a l
v e s s e l S R
S R
0 1
T T
0 1
P T
0 1
T I
0 1
P I
0 1
T M
0 1
F S
0 1
D P I
0 1
D C A
0 1
A C A
0 1
D C V
0 1
A C V
0 1
F G
0 1
B F V
0 1
F F
0 1
T C V
0 1
A
B C
P C V
0 1
P R V
0 1
B V
0 1
I L V 0
1 I L V 0
1 V
H 0
1 R
V 0
1 R
V 0
1
L D V
0 1
S o l e n o i d v a l
v e
S V
0 1
C V
0 1
U N V
0 1
A B V
0 1
R T
0 1
R C
0 1
O L T
0 1
O L M
0 1
F I
0 1
S D
0 1
G C T
0 1
L T
0 1
O T
0 1
H P C
0 1
B a c k p r e s s u r e
v a l v e B P V
B P V
0 1
D i f f e r e n t i a l
p r e s s u r e
c o n t r o l v a l v e
S Q V
0 1
l e v e r v a l v e T O V
T O V
0 1
B r e a t h i n g
f i l t e r A
B F A
0 1
B
B r e a t h i n g
f i l t e r B
B F B
0 1
B r e a t h i n g
f i l t e r
B F
0 1
g a s p i p e l i n e
O i l p i p e l i n e
T h e c o n t r o l l i n e
V e n t l i n e
D r a i n l i n e
W a t e r w a y
H o s e
C y l i n d e r
A C m o t o r
G e n e r a t o r
P u m p
A i r i n l e t
f i l t e r
S P F
C o n i c a l f i l t e r
A n a l o g i n p u t
O i l l e v e l s w i t c h
D i g i t a l i n p u t
D i g i t a l o u t p u t
A u t o t e m p e r a t u r e
c o n t r o l
V a r i a b l e s y m b o l
F l o w s w i t c h F S
T e m p e r a t u r e s w i t c h
L o w o i l p r e s s u r e
s w i t c h L O P
H i g h o i l p r e s s u r e
s w i t c h H O P
O i l h e a t e r H E A
P r e s s u r e s w i t c h
L i m i t s w i t c h L S
M a n u a l
E l e c t r i c
S i l e n c e r S L
T e m p e r a t u r e
t r a n s m i t t e r T T
P r e s s u r e
t r a n s m i t t e r P T
T e m p e r a t u r e
i n d i c a t o r T I
P r e s s u r e
i n d i c a t o r P I
T a c h o m e t e r T M
T a c h o m e t e r / t i m e
d i s p l a y T M T
D i f f e r e n t i a l p r e s s u r e
i n d i c a t o r P d R
A m m e t e r
V o l t m e t e r
F u e l
g a u g e F G
E l e c t r i c
b u t t e r f l y v a
l v e
T h r o t t l e v a l
v e
T e m p e r a t u r e
c o n t r o l v a l v
e
C o n t r o l
v a l v e P C V
P r e s s u r e r e l
i e f
v a l v e P R V
B a l l v a l v e B
V
G l o b e v a l v e
N e e d l e v a l v e
M a n u a l d r a i n
v a l v e V H
S a f e t y r e l i e
f
v a l v e R V
S a f e t y r e l i e
f
v a l v e R V
C h e c k v a l v e
C V
P n e u m a t i c v a
l v e
P n e u m a t i c
h i g h - p r e s s u r
e
v a l v e A B V
S p e e d s e n s o r R T
S p e e d c o n t r o l l e r R C
O i l l e v e l
t r a n s m i t t e r O L T
O i l l e v e l m e t e r O L M
F l o w i n d i c a t o r F I
S m o k e d e t e c t o r S D
G a s d e t e c t o r G C T
E x p l o s i o n
p r o o f l a m p L T
O i l t a n k O T
S t e e l
c y l i n d e r H P C
E l e c t r i c
T r a c i n g B a n d
L e v e l m a i n t e n a n c e
m e t e r L M
8/17/2019 01.75.ZSH-02EN -
17/141
17
NO. Description NO. Description
1 Compressor suction filter 7 Diesel suction filter
2 compressor 8 Diesel
3 Air-cooler
4 Drain-nozzle;/G2
5 Diesel water tank
6 Fisher D4 control valve
1 2
3 4 5 6
7 8
Table 2 5 main configuration and nozzles;
A p p e a r a n c e 2.2.2
8/17/2019 01.75.ZSH-02EN -
18/141
18
Due to continuous research and improvement ,graphic may differ, please understand.
8/17/2019 01.75.ZSH-02EN -
19/141
19
NO. Name NO. Name
1 1st stage cylinder 6 Oil filling plug
2 2nd stage cylinder 7 crankcase
3 3rd stage cylinder 8 Fan driven wheel
4 4th stage cylinder 9 Breath filter
5 NO.5 cylinder
1
4
3
2
5
8
6 7 9
Table2-6 Components of the compressor unit
Components of the compressor unit 2.3
8/17/2019 01.75.ZSH-02EN -
20/141
20
Crank rod kit 2.3.1
*The drawing is only used for the reference structure, does not represent the set of
8/17/2019 01.75.ZSH-02EN -
21/141
21
Crankshaft-rod lubricating 2.3.2
4.3.
8/17/2019 01.75.ZSH-02EN -
22/141
22
Cylinder kit 2.3.3
8/17/2019 01.75.ZSH-02EN -
23/141
23
Cylinder lubrication 2.3.4
8/17/2019 01.75.ZSH-02EN -
24/141
24
The system adopts the mechanical clutch (model: WTD SP211) + power transmissionbelt, gear clutch applied by hand. Pls reference it’s maintenance
Transmission 2.4.2
Table 2-7 Diesel parameters
Manufacturer Cummins
Type QSB6.7-C260
discharge capacity 6.7L
Power 183KW@1800RPM
Speed 800~1800rpm
Torque 990Nm@1500RPM
Cool style water
Net weight 629Kg
Discharge class Europe III
The tensioning mechanism 2.4.3
◆ Using a large barrel type tensioner, 4 point
support, good rigidity, convenient adjustment.
Drive and transmission 2.4
Drive 2.4.1
Unit driven by Cuminns Diesel,parameters as below。Special maintenance is
available for Diesel 。
8/17/2019 01.75.ZSH-02EN -
25/141
25
Safety valve's role is to protect the compressor (and the
cylinder) and prevent overpressure. Once the failure ofall other automatic control and automatic system, safetyvalve will release the pressure in all compressor.
safety valve is set according to below
pressure before leave the plant:
-NO.1 safety valve:0.4 MPa
-NO.2safety valve:1.2 MPa
-NO.3safety valve:4.5MPa
-NO.4safety valve:13.2 MPar
-NO.5safety valve:22 MPa
NO.NO.2 NO. NO. NO.
Safety and control kit 2.5
Safety valve 2.5.1
◆ WARNING
◆ Each separator equip with safety valve. If the final safety valve occurred jet and
continuous jet more than a minute, the compressor should immediately stop.This shows that the leakage of cylinder pressure, the next higher stage ofsuction / discharge valve have been cracked or carbonization.
◆ Under no circumstances can change these safety valve set pressure.
◆ If the safety valve action, according to the manual examination of the causes of
overpressure.
◆ Do not remove, replace, or replace safety valve. Safety valve can only use the
original HG parts replacement. Any due to the set pressure of safety valvetamper, and cause serious injury, will be immediately automatically cancelledquality assurance.
E m e r g e n c y s t o p s w i t c h 2.5.2
◆ Abnormal cases occur in the unit
work, emergency stop.
Emergencystop
8/17/2019 01.75.ZSH-02EN -
26/141
26
o i l p r e s s u r e m o n i t o r 2.5.3
◆ Compressor oil pressure can be observed on
the panel, also through the pressure switchesto monitor the pressure , if the oil pressure
below 1.5bar, pressure switch act and stop thesystem .
P r e s s u r e m o n i t o r 2.5.4
◆ The pressure sensor is installed after thecheck valve, used for collecting the finalpressure signal, when the signal reaches thepressure setting, automatic shutdown andautomatic start.
pressure sensor
T e m p . m o n i t o r 2.5.5
◆ Temperature sensor installed at
compressor exhaust , the temperature
transfer into a continuous analogsignal, and displayed through the PLC.
check valve
Temp. sensor
C h e c k v a l v e2.5.6
◆ Check valve installed after the NO.5 separator,
preventing rear gas reflux and cause damage.
Check valve
8/17/2019 01.75.ZSH-02EN -
27/141
27
D 4 c o n t r o l v a l v e 2.5.7
g a s w a t e r s e p a r a t o r 2.6.1
◆ After each stage of compression, compressor are equipped with a separator,used
to separate the oil and water in the compression process.
◆After each stage of compression of gas temperature rise, will be to re
cooling,temperature reaches the dew point of the gas, water condenses out from
compressed gas must be separated.◆In a separator, due to the special design of separator, causing cyclone or object
offset effect, the condensed water will accumulate in the bottom of the separator,
◆ waiting for the sewage system will discharge.
NO.5 NO.3
! DANGER If the condensed water to a certain moment without treatment, will lead to theoccurrence of danger. The condensed water will be sucked into the next stage ofcylinder, compressor will damage. This is called "water shock"!
O t h e r d e v i c e 2.6
◆ Fisher D4 control valve, installed at the exhaust
pipe of the unit, maintain the system pressurethrough venting, avoid the system frequentstart and stop .
◆ D4 control valve, normally closed type ,control
pressure is 2-3bar through instrument air . Formore details ,Pls see the correspondinginstructions.
D4control
NO.4 NO.2 NO.1
8/17/2019 01.75.ZSH-02EN -
28/141
28
◆ Automatic drain system consists of a
normally closed solenoid valve +
pneumatic valve.
◆ Automatic drain time and interval time are
arranged on the PLC
◆ Due to the existence of small sundries in
sewage, easy to plug the solenoid valve,
automatic drain valve please timing
cleaning。
◆ Discharge dirt collected in the drain
collection bucket, please timed sewage
collecting barrel。
◆ Please dispose of sewage。
Solenoid valve
Pneumatic high-pressure ball-valve
A i r i n l e t f i l t e r 2.6.2
◆ 80% dust particles in the air will be
filtered by inlet filter, filter need regularmaintenance, please see the
maintenance section. ◆ Under special condition, the rain hatshould be installed to protect the filterelement.
A u t o m a t i c d r a i n s y s t e m 2.6.3
8/17/2019 01.75.ZSH-02EN -
29/141
29
◆ Compressed gas in each stage, must pass through the inter stage cooler, to
cool the heat by compression。
◆ The cooler is air cooler 。
Cylinder pressure spec. 4×40L
Cylinder pressure 250Bar
Cylinder connection 2+2parallelconnection
T a b l e 2 8 C y l i n d e r g r o u p
NO.1
NO.2
NO.3
NO.4
NO.5
C y l i n d e r g r o u p 2.6.5
I n t e r s t a g e c o o l e r 2.6.4
8/17/2019 01.75.ZSH-02EN -
30/141
30
S a f e t y s i g n s a n d d a n g e r z o n e 2.7
NO. Warning label content NO. Warning label content
1 Hand clamp 5 Prohibit to work in the movement 2 Mechanical movement parts 6 Please wear protective glasses 3 electric shock 7 Please wear a helmet
4Prohibit to remove the protectivestructure
8 Please wear protective gloves
Safety signs 2.7.1
1 2 3 4
8 7 6 5
Table 2-7 Label content
8/17/2019 01.75.ZSH-02EN -
31/141
31
!4
2
5
3 1
5 Danger zone 2.7.2
Position Description
1.Compressor To avoid scalding, compressor work will produce hightemperature, any maintenance work please in the unit shutdown after 30 minutes!
2.Diesel engine Avoid high temperature burn!
3.Belt area Beware of broken belt, involved in debris. No closecontact when the unit works!
4.The last stage ofseparator lines
High pressure working area!
5.Fan area To prevent the impact and abrasion, twisted, No closecontact when the unit works!
Table 2-8 Danger area description
8/17/2019 01.75.ZSH-02EN -
32/141
32
● This unit is a container type, non wooden packing shipping. Accessories are as
follows:
NO. iten quantity
1 Manual(Chinese) 4
5 Compressor oil filter 4个
6 Diesel parts/3 sort filter ,V-belt 2set
7 Valve set/NO.1-5 valve sets 1set
8 Piston ring/1-5级 1set
9 Special tool 1set
10 Compressor bump gasket 2set
16 Certificate 1
2 Manual(English)
4 Compressor suction filter 4个
3 Synthetic lubricating oil/ 4.5L 16barrel
13 PLC,CPU224XP,SIEMENS 1个
12 Solenoid valve,10Bar ,DC24V,NC 1个
11 Solenoid valve,G1/2,16Bar ,DC24V 2个
14 V-Velt,SPC4500 2
15 Portable dry powder fire extinguisher ,MFZ/ABC3 2个
Table 3-1 parts list
Remark: Actual shipping list shall prevail
INSTALLATION AND OPERATION3 U n p a c k i n g
3.1
I n s t a l l a t i o n 3.2
◆ Please put the unit is placed on a horizontal surface
◆ Please ensure that the installation area can ensure the unit in good
ventilation, heat dissipation.
◆ Please ensure that the installation area does not exist dust, explosion, corrosion
and fire risk.
◆ When the unit is in 40 degrees Celsius above ambient
temperature operation, please use the air conditioning for the use
of space cooling.
◆ Please make sure that the unit from the wall over 1.5M.
◆ Please make sure that the unit and the ceiling a distance of more than 1.5M.
◆Please ensure that the regional good lighting installation, various partsand indication label clearly visible.
◆ Units on the ground without special foundation, ground leveling can be ok; if
the units used in the ship, before the use should be set a fixed.
8/17/2019 01.75.ZSH-02EN -
33/141
33
Before start compressor ,Please check as the below:
A. Turn compressor round by hand。
B. Check the tightness of belt。
C. Check the connector leakage, power wiring。D. Check the oil level of bump。
E. Check the antifreeze water in water tank of Diesel。
check before initial use3.3.1
R e a d y t o u s e 3.3
◆ If you are the first time to use this product, so the correct installation the unit is
crucial for reliable to operate the compressor . ◆ A lot of problems appearance relate to the compressor is not properly
installed. Please refer to the installation guide correctly installed .
◆ When you receive the compressor unit, please check whether there are damagedparts, please also check the spare parts. Please according to the packing listchecking whether the goods are lost. If you find any damaged ormissing parts, please contact immediately with the shipping company, and informus.
WARNING
Please handle with care in lifting process!
!
◆ Reciprocating compressor system should be installed in the flat level surface can bear on
the unit weight. When installation, maintenance and repair should ensure that thereis enough space around the unit, in order to facilitate maintenance and repair work.
◆ High Air compressor dynamic balance is very good, does not need the special
foundation. However, based on years of experience, a solid foundation is verynecessary for continuous and reliable operation of compressor.
◆ Sewage pipeline of compressor should be as short as possible, as far as
possible, and use straight pipe, in order to reduce the pollution of the backpressure. Sewage pipe installation should be downward sloping, discharge isconvenient for condensed water, oil mixture.
WARNING
Don't block the drain line, do not install the valve in the drain pipeline.
!
WARNING
Only installation of the unit has been Finished (including inlet and outlet port,water inlet and outlet port , and other pipe), Start the compressor when thecondition has been meet (for gas, water, electricity and other equipment),
Otherwise, forcibly start may result in damage to the equipment!
!
8/17/2019 01.75.ZSH-02EN -
34/141
34
L u b r i c a t i n g o i l f i l l i n g3.3.2
◇ Oil filler is positioned at the upper part of the crankcase, as shown in the figure
unscrew the respirator and injecting lubricating oil。
◇ The oil level mirror mounted on the front end lower part of cankcase。◇ The oil leveler maximum level from the bottom of the crankcase is about 11cm,
the lowest level from the bottom of the crankcase is about 9cm; in any case, the
oil level can not be lower than the minimum level, check oil level. every day .
◇ Note: the high pressure compressor synthetic oil viscosity, please slow filling. Or
filling lubricating oil before heated it with warm water.
filling
Compressor lubricating oil
◇ Diesel factory has been filling lubricating oil, It’s necessary to check the oil
leveler before the start, the oil level should be between the the groove ,as
shown below.。
◇ Lubricating oil brand:CG-4,15W-40,25-28L。For details, refer to Diesel
manual
Diesel lubricating oil
Oil leveler
W RNING
Please check the oil level before the start, please filling after driving, otherwise may cause the compressor scuffing of cylinder bore or other serious accident。
!
8/17/2019 01.75.ZSH-02EN -
35/141
35
WARNING
Electrical must be operated by Professional, otherwise cause serious accidents!!
E l e c t r i c a l c o n n e c t i o n 3.3.4
◇ The unit driven by Diesel,No additional electrical connections。
◇ Check the wiring terminal connection whether firm and Completely covered.
P i p e c o n n e c t i o n 3.3.3
The unit needs material and energy exchange with the external , so the
corresponding connection port is reserved for use, as shown in the following table .
NO. Des. Specification Function Qua.
1 Discharge 3/4-16UNF Customer gun hose 1
2 Drain outlet G2 inner The sewage for system 1
3 Drain outlet 1-11.5NPT inner D4control valve、cylinder group 1
4DieselOil
outlet Rc1/2 Diesel lubricant-draining 1
5
Oil tank
drain Rc1/2 Diesel fuel-draining 1
6 Bump drain Rc1/2 compressor oil-draining 1
Table 3-2 table of pipe
◆ Note: the vent and discharge nozzle shall not be installed other valves, prevent blocking
!
8/17/2019 01.75.ZSH-02EN -
36/141
36
C o m p r e s s o r o p e r a t i o n 3.4
E l e c t r i c s y s t e m o p e r a t i o n 3.4.1
3.4.1.1 Notice
General requirements for safety:
This set of electrical control system specially used for air compressor automaticcontrol, please carefully read all instructions and descriptions of this manual. Systemcan endanger people life due to there have high voltage, moving parts, highpressure fluid. part of the equipment surface injure people as a result of hightemperature, in the installation, wiring, start, run or do any adjustment before, pleaseuse the manual as a guide. Improper operation will likely result in personal injuryor property significant losses, so the operation and repair personnel should bestrictly in accordance with the provisions of the manual to operation and
maintenance.
Warning signs and significance:
A warning triangle, said that if you do not take the corresponding care measures, may
Said if you don't pay attention to the corresponding prompt, may appear undesirable
Said that if the note corresponding prompt, may be relatively easy to master the
The records of the supplemental content reference, relevance and other functions.
Qualified professionals:
Only allow installation and drive attached devices or systems associated with the file.Commissioning and operation of equipment or systems allow only by qualifiedprofessionals. This document security technology of qualified professional personnelrefers to technical safety standards has engaged in equipment, system and the
The device only allows the use of prescribed in the manual, and only allow the useof High Air company recommended or designated other manufacturer of equipmentand components. The normal and safe operation of equipment must be dependent onthe appropriate transportation, proper storage, placement and installation and careful
Said that if you do not take corresponding care measures, will cause death or
Said that if you do not take corresponding care measures, can lead to death
According to the provisions to use:
Danger
Warning
Caution
NOTE
key point
Remarks
8/17/2019 01.75.ZSH-02EN -
37/141
37
After electrical preparation of chapter, 3.3.4, supply equipment power by .turn on batteryswitch by clockwise rotation of
The battery switch
3.4.1.2 device power on
◆ Produced by equipment operation noise can cause hearing damage, please
wear earplugs or earmuffs protection;◆ When the equipment works, please pay attention to ventilation;
◆ Don't run the machine under the condition of no secure isolation, set a
soundproof cover can effectively isolate the noise, and also play a protective
Warning
If the emergency stop button is pressed, please press the button popup to reset, otherwise the system will not startup!
Remarks
8/17/2019 01.75.ZSH-02EN -
38/141
38
A-Electrical control panel
HG7/210AD compressor The operation interface as above:
Button introduction:
S1:power switch。
S2:Automatic / manual selection button (manual selection butto must be
supportec by Diesel Controller by plant service personal。
EP1:Emergency stop for Emergency。
PB3:button for Sewage from stage1 to stage 5。
PB7:The ignition switch.
Each position definition is preheating, stop, run, start as Clockwise
direction
PB6:The Diesel accelerator .This feature has been disabled load Diesel by
button switch!
P1:Fault indicating lamp。
PB4:Running lamp。PB5:stop lamp。
1# S3:Toggle switch
Upward: load from rpm to 1800,
Middle:maintain the idle for Diesel。
2# S4:Toggle switch
when Diesel idle ,move upword ,Increase RPM50 every action.
3.4.1.3 Device Operations
8/17/2019 01.75.ZSH-02EN -
39/141
8/17/2019 01.75.ZSH-02EN -
40/141
40
1. C-Operation steps instruction
1、The battery switch is allocated to "/",power selection switch dial exactly right on the electrical
panel,power is available for System :
2、 Select“ Automatic” function,PLC are shown in the following picture After initialization
:
3、Check the settings of the
parameters。
Parameter setting for reference table 3-3
4、Ensure breaking off Clutch and after each checking ,then start Diesel
by ignition switch ,Diesel idling runs with RPM800。
5、Diesel speed is regulated by Toggle switch 2# 。Increase RPM50 every
action along direction upward ,till to rpm 1200m,then load the clucth,
after stable running, when Diesel idle ,stir switch 1# along direction
upward till max 1800rpm
Ch/En Inquiry setting Maintenance setting
reset
Alarm inquiry
8/17/2019 01.75.ZSH-02EN -
41/141
41
6、complete all parameter record for compressor running,such as:compressor
lubricant pressure,stage pressure,exhausting pressure,exhausting
temperature, water temperature of Diesel,speed。
7、PLC records the compressor fault with compressor running,as follow:
8/17/2019 01.75.ZSH-02EN -
42/141
42
9、Under normal circumstances, the system automatically stop when meet the
stop terms, Before stopping the machine, the system will automatically
drain and unload a few minutes, for exhausting the heat in the pipe.
If meet system fault, unit will stop without draining until disconnect
the clutch
10、Unit maintenance queries on PLC as follows:
8/17/2019 01.75.ZSH-02EN -
43/141
43
3.4.1.4 Parameter setting
Parameter Original value Setting range Remarks
Exhaust pressure 210bar 50-250bar PLC setting
Exhaust pressure
min. value 180bar 20-250bar PLC setting
Exhaust temperature 215bar 100-250bar PLC setting
high exhaust 60℃ 40-65℃ PLC setting
Lubricant heating 5℃ -35℃-40℃ PLC setting
Load delay time 10s 5-30s
Unload delay time 5min 2-300min
Sewage Interval 15min 5-60min
Each stage Sewage 10s 2-30s
Table 3-3 Parameter setting table
→ The parameter setting value recommended numerical select provided by our
company, these values are all our years of experience and, more conducive tothe protection of the compressor and the normal operation of the unit.
→ Tip: automatic operation system, the parameter value must
be accurately set page. Parameter is not set or not set the correct value causesthe system operation instability, even trouble!
→ The PLC control unit, set the system parameters stored
in PLC memory. PLC data in memory in case of power off, the general can onlymaintain 100 hours of data memory, if the configuration of a battery, PLC cankeep 1 months of data memory. Therefore, if the system after a long timeof power off, need to recheck the parameter value. Necessary, need to do reinput.
8/17/2019 01.75.ZSH-02EN -
44/141
44
C o n t r o l l o g i c 3.4.2
Running condition.
①When the system is in the automatic control mode, exhausting-pressure up to
210bar ,exhausting regulating valve open and the system idling.
When the system is in the manual control mode,exhausting-pressure is over ,compressor
unload and unit stop.
②If test by automatic control mode, start the unit by Diesel key switch, once unit run
normally:
If supply pressure≤auto draining pressure,pressure regulator close,exhausting pressure
increase.
If supply pressure≥auto draining pressure,pressure regulator open,exhausting pressure
decrease;
③When the system is in the automatic control mode,supply pressure up to 210 bar, unit
stop with delay mode(delay time rang from5-30min),during delay,pressure regulator
open and system unload ,if supply pressure 215bar 、unusual Vibration,unit will stop immediately,drain valve
and pressure control valve open.
If exhausting tem.>50℃,unit will stop with delay.
⑧the Unit point stop or alarm fault, pls see Appendix 1.
8/17/2019 01.75.ZSH-02EN -
45/141
45
NO.Protection
point
normal value Display Alarm Stop unload
1Exhaust
pressure210barg √ × × √
2Exhaust MAX.
pressure215barg × √ √ √
3
exhaust
temperature
high
ambient
temperature+10~15
℃
√ 60℃ 60℃ √
4
water tank
temperature
high
Online √ 104℃ 111℃ √
5Low battery
voltageDC24V √ √ √ √
6 Power current √ × × ×
7Diesel oil
pressure LowNormal 35~70psig √
23-
32psig16psig √
8 Compressor oilpressure Low
Normal 1.8~2.0bar × 1.5bar 1.5bar √
9 Fuel level low √1/4
Range× ×
11 Emergency stop × √ √ ×
12water level of
the water tanklocal × √ √ √
13Speed
protection
full load /
1800rpm× 1850rpm 1850rpm √
14crankcase oil
temperature
approximate
60℃
√ ≤5℃ × ×
15 Unit Vibration
set back Semi
circle after
working point
× √ √ √
Table 3-4 unit shutdown or alarm fault
8/17/2019 01.75.ZSH-02EN -
46/141
46
E q u i p m e n t s a f e t y o p e r a t i o n r e g u l a t i o n 3.4.3
Warning: compression Air is dangerous, only trained and authorized person may operate
compressor, don't change internal structure and control method of units, except authorized by
Highair company.
1. the items must be Checked before start:◇ Check all fasteners, pipe whether loose or damaged, ensure that no debris around the
compressor ;
◇ Check the compressor oil level, replace oil every 2000 hours or 1 years ;
◇ Check the water tank liquid level, the oil and fuel level of diesel ;
◇ Check the belt tightness , disconnect the clutch;
◇ Check the compressor parameter setting according to the instruction check;
2.Start compressor
◇ turn on the power switch on cylinder bracket, and put the control switch on the panel in
the "automatic" location;
◇ Diesel is not allowed to start with load, it is suggested to disconnect clutch before restart
Diesel
◇ Start Diesel turn the key switch with Clockwise rotation , Diesel is in the idle state
(800rpm), increase speed to 1200rpm by the 2# toggle switch , then push on the clutch,
and then use the 1# toggle switch loading (till to 1800rpm), if emergency parking, press
emergency button;
◇ Under condition with Automatic mode, compressor will load and unload automatically
based on the pressure sensor ;
◇ Compressor unload through the control valve Fisher D4 , once supply electromagnetic
valve power ,D4control valve open by instrument air .excess gas drain away through the
control valve ; once the pressure decreased to a value point, the electromagnetic valve
loss electricity power, Instrument air drain and control valve cut off.
3.stop compressor
◇ When does not need to use compression Air , close valves, then press manual draining-
button on panel, the unit unload, and then close the throttle gradually, and Diesel is idle ,
then disconnect the clutch, the Diesel to continue running 5 minutes with idle mode, then
stop the unit by Diesel Ignition switch along counterclockwise ;
◇ Avoid loading and unloading frequently t, it’s not conducive for Reliability of unit;
◇ It is available to stop the unit by pressing emergency button on the control panel in
emergency situation;
◇ Compressor should at least be unloaded more than 5 minutes before stop running, to
ensure the heat Air drained completely, otherwise cause rust on internal cylinder due
to vapor will precipitate.
◇ if let unit unused for longtime after stop, pls. shutdown the battery switch on cylinder
bracket. Otherwise cause unable to restart the unit due to battery leakage.
8/17/2019 01.75.ZSH-02EN -
47/141
8/17/2019 01.75.ZSH-02EN -
48/141
48
Interval Maintenance work remarks
every day
1, Check the oil level before the start or each class , long-termshutdown, must be manual turning before starting, andcheck whether the oil deterioration.2, you should observe the unit has no leakage, unusual sound3, check whether the normal condensed water discharge.4, check abnormal noise and vibration.5, check the inter stage pressure, water pressure, watertemperature.
The first100 h
1、check screw connections and pipe couplings 2、change crank gear oil and oil filter
User self inspection
every 200h
1、check screw connections and pipe couplings2、check crank gear oil level
User self inspection
every 1000h
1, blow the cooler and the compressor cylinder head2, blow the motor heat sink3, clean the crankcase breathing filter
every 2000h
1、clean air inlet filter cartridge 2、replace oil and oil filter 3、clean and replace internal parts of compressor valvesstages 1-5 4、clean and inspect internal parts condensate drain valvesand replace, if necessary.
5、clean and inspect internal parts of non return valve 6、fill grease in motor
4.2.34.3
every 4000h
1、replace complete compressor valves of stages 1-5 2、replace filter cartridge of air inlet filter 3、clean coolers, separators and pipes 4、check V-belt tension of fan drive, replace it if necessary 5、replacement of complete non return valve
examined by professional
every 6000h
1、replace needle bearings with gudgeon pin examined by professional
yearly
1、change crank gear oil filter 2、clean complete unit
3、
check safety valves by slightly lifting during compressoroperation
4.3
weekly 1、check maintenance indicator of air inlet filter 2、check crank gear oil level
User self inspection
M a i n t e n a n c e s c h e d u l e 4.1
8/17/2019 01.75.ZSH-02EN -
49/141
49
Lubrication system maintenance 4.2
8/17/2019 01.75.ZSH-02EN -
50/141
50
注意:
如果compressor 安装了隔离罩,环境温度必须在罩子内靠近crankcase
测量。不要将润滑油加满,油位保持在标示线之间,除非经厂方同意否则不要使用推
荐以外的油品,因此而导致的一切机组损坏制造商概不负责。
8/17/2019 01.75.ZSH-02EN -
51/141
51
T r a n s m i s s i o n p a r t s m a i n t e n a n c e 4.3
4.3.1 V-belt
8/17/2019 01.75.ZSH-02EN -
52/141
52
◆ Comply with 2# lithium grease based on America Petroleum Association;
◆ Fill grease by gun grease every 100 hours 。
◆ More detailed maintenance requirements ,please refer to the instruction manual
of mechanical clutch。
4.3.2 Mechanical clutch maintenance
8/17/2019 01.75.ZSH-02EN -
53/141
53
Filtering device 4.4
Safety 4.4.1
8/17/2019 01.75.ZSH-02EN -
54/141
54
Air cleaner maintenance
Design 4.4.2
4.4.3
8/17/2019 01.75.ZSH-02EN -
55/141
55
Changing the main element
8/17/2019 01.75.ZSH-02EN -
56/141
56
8/17/2019 01.75.ZSH-02EN -
57/141
8/17/2019 01.75.ZSH-02EN -
58/141
58
8/17/2019 01.75.ZSH-02EN -
59/141
59
L u b r i c a t i o n a n d m a i n t e n a n c e o f D i e s e l 4.5
According to the diesel of the user device, shall comply with the following
instructions.
◆ Check the Diesel lubricant level and clean the oil tank regularly。
◆ use clean diesel。
◆ Please refer to the Diesel manual on Diesel maintenance;。
8/17/2019 01.75.ZSH-02EN -
60/141
60
C o o l e r s 4.6
8/17/2019 01.75.ZSH-02EN -
61/141
61
R e m o v a l o f o i l c a r b o n 4.7
8/17/2019 01.75.ZSH-02EN -
62/141
62
TROUBLE SHOOTING5
C o m p r e s s o r u n i t 5.1
WARNING
Before performing any repair, must cut off the power supply and switch on powersuspension warning signs, release the pressure, but also, for repair personnel mustbe authorized!
!
8/17/2019 01.75.ZSH-02EN -
63/141
63
8/17/2019 01.75.ZSH-02EN -
64/141
64
P i s t o n c o m p r e s s o r 5.2
8/17/2019 01.75.ZSH-02EN -
65/141
65
8/17/2019 01.75.ZSH-02EN -
66/141
66
8/17/2019 01.75.ZSH-02EN -
67/141
67
8/17/2019 01.75.ZSH-02EN -
68/141
68
V a l v e t r o u b l e s 5.3
8/17/2019 01.75.ZSH-02EN -
69/141
69
Total 8 page,NO.1 page -Operation panel layout
CIRCUIRY6
8/17/2019 01.75.ZSH-02EN -
70/141
70
Total 8 page,NO.2 page-Diesel Circuit 1
8/17/2019 01.75.ZSH-02EN -
71/141
71
Total 8 page,NO.3 page-Diesel Circuit 2
8/17/2019 01.75.ZSH-02EN -
72/141
72
Total 8 page,NO.4 page-CPU Wiring
C P U 2 2 4 X P
i
m
n
s
8/17/2019 01.75.ZSH-02EN -
73/141
73
Total 8 page,NO.5 page-pressure The current module wiring1
E M 2 3 1 * 4 R T D
i
m
n
s
1
2
3
4
5
6
7
8
O N
8/17/2019 01.75.ZSH-02EN -
74/141
74
Total 8 page,NO.6 page- The control circuit
8/17/2019 01.75.ZSH-02EN -
75/141
75
Total 8 page,NO.8 page -Controller distribution diagram
8/17/2019 01.75.ZSH-02EN -
76/141
76
Total 8 page,NO.8 page -Terminal diagram
8/17/2019 01.75.ZSH-02EN -
77/141
77
◆ spare parts for bump.
SPARE PARTS7
C o m p r e s s o r s p a r e p a r t s 7.1
8/17/2019 01.75.ZSH-02EN -
78/141
78
8/17/2019 01.75.ZSH-02EN -
79/141
79
crankcase assembly 7.1.1
8/17/2019 01.75.ZSH-02EN -
80/141
80
8/17/2019 01.75.ZSH-02EN -
81/141
81
Crankshaft assembly 7.1.2
8/17/2019 01.75.ZSH-02EN -
82/141
82
Rod assembly 7.1.3
8/17/2019 01.75.ZSH-02EN -
83/141
83
Oil-bump assembly 7.1.4
8/17/2019 01.75.ZSH-02EN -
84/141
84
cylinder assembly 8.125“7.1.5
8/17/2019 01.75.ZSH-02EN -
85/141
85
cylinder assembly 6.125“7.1.6
8/17/2019 01.75.ZSH-02EN -
86/141
8/17/2019 01.75.ZSH-02EN -
87/141
87
cylinder assembly1.875“7.1.8
8/17/2019 01.75.ZSH-02EN -
88/141
88
cylinder assembly1.25“7.1.9
8/17/2019 01.75.ZSH-02EN -
89/141
89
Guide-cylinder assembly 6.125“7.1.10
8/17/2019 01.75.ZSH-02EN -
90/141
90
NO.1 cylinder head assembly 7.1.11
8/17/2019 01.75.ZSH-02EN -
91/141
8/17/2019 01.75.ZSH-02EN -
92/141
92
NO.3 cylinder head assembly 7.1.12
8/17/2019 01.75.ZSH-02EN -
93/141
93
NO.4 cylinder head assembly 7.1.13
8/17/2019 01.75.ZSH-02EN -
94/141
94
NO.5 cylinder head assembly 7.1.14
8/17/2019 01.75.ZSH-02EN -
95/141
95
Piston assembly 8.125“7.1.15
8/17/2019 01.75.ZSH-02EN -
96/141
96
Balanced piston assembly6.125“7.1.16
8/17/2019 01.75.ZSH-02EN -
97/141
97
Piston assembly3.25“7.1.17
8/17/2019 01.75.ZSH-02EN -
98/141
98
Piston assembly 1.875“7.1.18
8/17/2019 01.75.ZSH-02EN -
99/141
99
Piston assembly1.25“7.1.19
8/17/2019 01.75.ZSH-02EN -
100/141
100
Fan & wheel assembly 7.1.20
8/17/2019 01.75.ZSH-02EN -
101/141
101
P a c k i n g s p a r e - p a r t s 7.2
8/17/2019 01.75.ZSH-02EN -
102/141
102
8/17/2019 01.75.ZSH-02EN -
103/141
103
Separator assembly7.2.1
8/17/2019 01.75.ZSH-02EN -
104/141
104
8/17/2019 01.75.ZSH-02EN -
105/141
105
Sewage assembly7.2.2
8/17/2019 01.75.ZSH-02EN -
106/141
106
8/17/2019 01.75.ZSH-02EN -
107/141
107
Mount assembly7.2.3
8/17/2019 01.75.ZSH-02EN -
108/141
108
8/17/2019 01.75.ZSH-02EN -
109/141
109
Drive assembly7.2.4
8/17/2019 01.75.ZSH-02EN -
110/141
110
8/17/2019 01.75.ZSH-02EN -
111/141
111
8/17/2019 01.75.ZSH-02EN -
112/141
112
8/17/2019 01.75.ZSH-02EN -
113/141
113
8/17/2019 01.75.ZSH-02EN -
114/141
114
8/17/2019 01.75.ZSH-02EN -
115/141
115
Diesel assembly7.2.5
8/17/2019 01.75.ZSH-02EN -
116/141
116
8/17/2019 01.75.ZSH-02EN -
117/141
117
8/17/2019 01.75.ZSH-02EN -
118/141
118
8/17/2019 01.75.ZSH-02EN -
119/141
119
8/17/2019 01.75.ZSH-02EN -
120/141
120
8/17/2019 01.75.ZSH-02EN -
121/141
121
8/17/2019 01.75.ZSH-02EN -
122/141
122
8/17/2019 01.75.ZSH-02EN -
123/141
123
Transmission tighten assembly7.2.6
8/17/2019 01.75.ZSH-02EN -
124/141
124
Diesel fuel pipe assembly7.2.7
8/17/2019 01.75.ZSH-02EN -
125/141
8/17/2019 01.75.ZSH-02EN -
126/141
126
Pressure meter assembly7.2.8
8/17/2019 01.75.ZSH-02EN -
127/141
127
8/17/2019 01.75.ZSH-02EN -
128/141
128
Air cooler assembly7.2.9
8/17/2019 01.75.ZSH-02EN -
129/141
129
8/17/2019 01.75.ZSH-02EN -
130/141
130
Lubricating pipe assembly7.2.10
8/17/2019 01.75.ZSH-02EN -
131/141
131
放空管
卡套直通管接头
外牙直通接头
溢流阀
形圈
形圈内六角圆柱头螺钉
卡套直通管接头
油泵转接法兰油泵转接法兰
内外牙直通接头
油位镜折弯管
油位镜折弯管
卡套直通管接头
液位计组件
平垫圈
弹簧垫圈
外六角螺栓
油滤支架
管卡
橡胶软管
外牙直通接头
油滤总成
内外牙直通接头
两端卡套直通管接头
卡套直角管接头
卡套直通管接头
油压表管路
油压表管路
油压表管路
油压表管路
齿轮泵
序号 物料代码 名称 数
量
8/17/2019 01.75.ZSH-02EN -
132/141
132
Exhausting pipe assembly7.2.11
8/17/2019 01.75.ZSH-02EN -
133/141
133
8/17/2019 01.75.ZSH-02EN -
134/141
8/17/2019 01.75.ZSH-02EN -
135/141
135
8/17/2019 01.75.ZSH-02EN -
136/141
136
内外牙直通接头
外牙直通接头
卡套直通管接头
钢制管卡
内牙三通接头
弹簧垫圈螺母平垫圈
外六角螺栓
两位三通电磁阀
调压阀支架
调压阀支架
法兰垫密封垫
管法兰专用螺母
全螺纹螺柱油压表管路
卡套直通管接头
末级放空管
油压表管路球阀
卡套直通管接头
卡套直通管接头
外牙直通接头
内牙三通接头
充油压力表
手动减压阀
法兰
调压阀
序号 物料代码 名称 数
量
8/17/2019 01.75.ZSH-02EN -
137/141
137
8/17/2019 01.75.ZSH-02EN -
138/141
138
阀类标签
阀类标签
气瓶标签
压力标签
阀类标签
高压堵头
卡套接头体
卡套直通管接头
内牙三通接头
内外牙直通接头
外牙直通接头
标牌钢制管卡
五级压力表管
末级放空管末级放空管
末级放空管
末级放空管
压力控制管五级气水分离器排气管五级气水分离器排气管旋转螺帽 形三通卡套接头体卡套压力表管接
头管卡
卡套直通管接头
针阀
充油压力表
面板式截止阀
仪表阀门面板
序号 物料代码 名称 数
量
8/17/2019 01.75.ZSH-02EN -
139/141
139
8/17/2019 01.75.ZSH-02EN -
140/141
140
高压软管
扩口直通接头
内牙直通接头
卡套直角管接头
管卡五级气水分离器排气管紫铜垫
压力传感器
温度传感器
四通基座
卡套直通管接头
五级气水分离器排气管止回阀
序号 物料代码 名称 数
量