22
1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

Embed Size (px)

Citation preview

Page 1: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

1

Luminosity of 1035 cm-2s-1

at KEKB

Preliminary planMachine parameters

RF systemVacuum system

Injector

Y. OhnishiKEKSnowmass2001

Page 2: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

2

Preliminary Plan

• Luminosity of 4.49x1033 cm-2s-1 was achieved at KEKB.• Major target of B physics is CP violation, especially sin21(or sin

2):– Belle/KEKB : 0.58±0.33 (10.5 fb-1), March 2001.– Int. luminosity from KEKB is 30 fb-1 now. Statistical error will be 0.19.– There is a chance to say 3 S.D. significance this summer(?).

• Integrated luminosity of100 fb-1 is needed to achieve the required accuracy of 0.1 for sin21.

• We expect to reach 100 fb-1 within 1.5 year even if the luminosity is still 4x1033 cm-2s-1. (very conservative)

• BTeV and LHC-B will become strong competitors in 5 years.

Page 3: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

3

Preliminary Plan (cont’d)

• KEKB will loose its competitiveness in 2005-2007.– Luminosity of BTeV or LHC-B corresponds to 1035 cm-2s-1 e+e- collider.

• SUSY related B physics at 1035 cm-2s-1 e+e- collider is a very attractive choice.

• We hope to upgrade KEKB to Super KEKB(1035 cm-2s-1 ) during 2004-2005 and begin physics run in 2006.

• We try to improve luminosity to 1034 cm-2s-1 up to 2004.

• KEKB is R&D machine for Super KEKB.• Super KEKB project consists of

theorists/experimentalists/accelerator staffs of universities and KEK. (18/5/30)

• We will submit LoI to HEP community and KEK in winter 2001

Page 4: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

4

Parameters for Super KEKB(1035 cm-2s-1)

• Luminosity formula:

• Beam-beam tune shift parameters:

• Assumed that the “transparency” conditions:

• Alternative expression for luminosity:

L=NeN e f4πσ x

*σ y* RL

L=γe

2ere

Ieξy

y*

⎝ ⎜ ⎞

⎠ ⎟ 1 +

σ y*

σ x*

⎝ ⎜ ⎞

⎠ ⎟ RL

Rξy

ξx,ye =re

2πγe

Ne βx,ye*

σ x,y* σ x

* +σ y*

( )Rξx,y

γeIe =γe Ie , εe =εe , etc.

L∝Ieξyβy

*

Page 5: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

5

Parameters for Super KEKB (cont’d)

Design luminosity of KEKB is 1034 cm-2s-1. To achieve 1035 cm-2s-1:

Squeeze beta at IP. : y* σz 3 mm (coherent radiation?)

Higher beam current : 10 A for LER and 3 A for HER

Page 6: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

6

Coherent Synchrotron Radiation

• Power of coherent synchrotron radiation (Kheifets,Zotter)

N: particles/bunch : bending radius h: height of chamber

Particles: Gaussian distribution

incoherentE √∝ N P ∝N

coherentE ∝N P ∝N2

z

z

coherent condition

z≦

Pcoherent≈πN2remec

2 f0ρ

ρσ z

⎝ ⎜ ⎞

⎠ ⎟

43

Γ 2/3,xth( )

xth=23πρh

⎛ ⎝

⎞ ⎠

3 σz

ρ

⎝ ⎜ ⎞

⎠ ⎟

2

Page 7: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

7

Coherent Synchrotron Radiation(cont’d)

• The ratio of coherent power to incoherent:

PcoherentPincoherent

=3N4γ4

ρσz

⎝ ⎜ ⎞

⎠ ⎟

43

Γ 2/3,xth( ) Pincoherent=4πNremec

2 f0γ4

⎝ ⎜ ⎞

⎠ ⎟

LER: 3.5 GeVBending radius: = 16.3 mChamber height: h=47mm

Coherent radiation can be ignore for 3mm bunch length (?)

Page 8: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

8

Questions• Beam current is 10x3 A.• Beta(y) at I.P = 3 mm• Bunch length = 3mm• Energy(or Particle) exchange:

– 3.5 GeV e+/8 GeV e- to 3.5 GeV e-/8 GeV e+

– Advantage: • Beam blow-up due to photoelectron cloud(?)

If fast ion instability for electron beam is ok. • Injection (injection rate: e- > e+ at KEKB).

• Once machine parameters are fixed, questions are:– RF system ?– Vacuum system ?– IR design ?– Injector ?

Page 9: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

9

Layout of KEKB (not Super KEKB)

Double ring,Asymmetric collider

Circumference:3km

Page 10: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

10

RF System

• Beam current at Super KEKB is 3 times larger than KEKB.

• Number of bunches is 15000 or 5120 ?• If we choose harmonic number of15000, we have to

develop completely new 1.5 GHz RF system. (Current RF frequency is 508 MHz.)

• We consider RF frequency is 508 MHz to minimize the cost, time, and man power.

• Normal conducting cavities (ARES) for LER and normal+superconducting cavities(SCC) for HER.

• The severe requirement on HOM damping.• Rf system for LER depends on whether wiggler exists

or not.

Page 11: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

11

RF System (cont’d)

• RF parameters (RF unit includes klystron, power supply, wave guide, circulator, dummy load, cooling, etc)

Page 12: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

12

RF System (cont’d)

• RF system needs small modifications if we keep 508 MHz RF frequency used at KEKB.

• However, we have to develop new HOM damper for higher beam current.

• We increase NC(ARES) cavities from 32 to 36 and SC cavities from 8 to 12.– We should have 36 NC(ARES) cavities for KEKB, we only add 4 SCC.

• Klystron for Two NC(ARES) cavities is modified to Klystron for one NC(ARES) cavity. Number of RF units becomes twice of KEKB.

• We consider RF system with wiggler for LER at this stage.

Page 13: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

13

Vacuum System

• Parameters of vacuum system

Max. cooling power is 〜 8 MW. New powerful cooling system has to be built.This issue is for institute not for accelerator division.

It is difficult forcopper chamber.

510 A/m130 A/m200 kV/m

These valuesare tested andconfirmed.

Page 14: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

14

Vacuum System (cont’d)

• Ante-chamber for positron ring:

We have no experience even if GlidCop is used.

R&D for material.Make incident angleslant?

practicable

In the case ofenergy exchange

Page 15: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

15

Vacuum System (cont’d)• Movable masks.• Photo shows the early version

of movable mask.• SiC blocks were equipped as a

HOM absorber, since trapped mode was very serious.

• However, beam current was limited by the absorbed power(estimated to be 500W).

• This kind of mask can not be used for huge beam current machine.

• The most serious problem is damage of mask head.

• R&D for the structure and material is needed.

Page 16: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

16

Vacuum System (cont’d)• Latest version of movable mas

k at KEKB(LER).• Movable chamber. The chamb

er works as a mask.• There is no trapped mode.• We have already observed ma

sk damage(looks like previous photo).

• To avoid mask damage, mask should be hybrid structure of Al and copper.(Just make energy loss point at mask)

Page 17: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

17

Positron Beam Blow-up

• Positron beam blow-up caused by photoelectrons is reduced by solenoid field.

Beam size measurement using SR interferometer.

Spec. Luminosity/bunch

All solenoid off

All solenoid on

Partialsolenoid off

Page 18: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

18

Positron Beam Blow-up (cont’d)

• Solenoid coils are also necessary for Super KEKB.• Chambers in positron ring are wrapped by solenoids:

– Straight section as well as bending section.– Bellows, inside of steering magnets, …

Page 19: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

19

Injector

• Short lifetime due to collision: 10A/100 min=1.7 mA/s.• Powerful injector is needed to keep the rings filled up.• Super KEKB will be very inefficient machine.

KEKB(current status:4.3x1033)3mA/s(e-)/1.5mA/s(e+)800mA(HER)/900mA(LER)High efficiency!

Super KEKB3mA/s(e-)/1.5mA/s(e+)3A(HER)/10A(LER)

Top-up

Super KEKB(upgrade injector)15mA/s(e-)/3mA/s(e+)3A(HER)/10A(LER)

Inj.+dead time=6.5min

Inj.+dead time=50min

Inj.+dead time=12.8min

Lum

inosi

ty e

ffici

ency

Page 20: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

20

Injector (cont’d)

• Improvement of Injection rate:– Charge intensity can be increased from 1nC to 5 nC for electron.– Positron charge becomes twice, if two-bunch acceleration is performed.

We have already tested.

• Energy exchange(3.5 GeV e-/8GeV e+) may help beam blow-up due to photoelectron cloud in positron ring.

• To accelerate positron up to 8 GeV, there are two possibilities:① Improvement of accelerating electric field(simple):

• C-band is a candidate instead of S-band.• One of techniques of Japan Linear Collider.

② Recirculation(S-band) with damping ring(similar to SLC):• In order to do recirculation, next RF pulse is used.• Damping ring is needed so that beams wait for next RF pulse.• Beam transport lines are very complicated.

Page 21: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

21

Injector (cont’d)

e+ Targete- 3.7 GeV

ECS

KEKB e+3.5 GeV

J-Arc1.7 GeV

S-Band

Gun C-BandB A

C 1 2 3 4

5

40 MeV/m 1.1x2 + 2.2x3 = Max 8.8 GeV

Layout of injector for super KEKB

Layout of injector for KEKB

Super KEKB e- 3.5 GeV

Super KEKB e+ 8 GeV

ECS

J-Arc1.7 GeV

GunB A

C 1 2 3 4

5

e+ Targete- 3.9 GeV

KEKB e-8 GeV

S-Band

Preliminary plan

10nC e- for e+ production1 nC e- for injection

Page 22: 1 Luminosity of 10 35 cm -2 s -1 at KEKB Preliminary plan Machine parameters RF system Vacuum system Injector Y. Ohnishi KEK Snowmass2001

22

Summary

• Machine parameters of Super KEKB:– Beam current: 10A(3GeV e-)/3A(8GeV e+)– Beta at I.P: y*=3mm– Bunch length: σz=3mm– Number of bunches: 5120– Crossing angle at I.P: 15 mrad(?)

• RF system is not so difficult (practicable).– Development of HOM damper

• Vacuum system is very difficult.– R&D of materials and structure of vacuum chamber

• Injector will be widely modified to exchange energy and improve beam intensity.– C-band or recirculation– Two-bunch acceleration