AGENDA

OVERVIEW CONCEPT FEATURES

PROGRAM

MANAGEMENT

TOOLS

Project Purpose

• Address the nation's infrastructure needs to keep

pace with current and projected requirements for

containerized throughput

• Serve new “mega” container vessels that are too big

to enter inland waterways

• Support markets:

• Mississippi River inland waterway system

• Existing Gulf Coast ports

• International ports and markets

Container Cargo Terminal Concept

Deep water berths

(Up to EEE class)

Container Yard with Automated

Ground Vehicles

Barge & Short Sea Ship

berths with quay cranes

Pile supported or floating

terminal platform

Platform Concepts Being Considered

Pile Platform

• 30’ - 35’ platform height above water surface

• 70’+ of water depth

• Piles would be driven down to a depth between 250’ – 300’ below mud/clay surface

• Breakwater requirement under evaluation

Floating Platform

• Unlikely, but being evaluated

Anticipated LIGTT Features

1. Container import/export terminal (phase 1)

2. Tenants’ quarters for on-site employees (phase 1)

a. Port Operator

b. Customs and Border Protection

c. Coast Guard

3. Bulk export terminal (future)

4. Refined petroleum products export terminal (future)

https://www.port.venice.it

Concept for Deep Water Container Transfer Facility

Venice, Italy

Deep Water Container Transfer Terminal

Djakarta, Indonesia

Nov 2013

Nov 2013

Deep Water Container Transfer Terminal

Djakarta, Indonesia

Oct 2014

Deep Water Container Transfer Terminal

Djakarta, Indonesia

Oct 2014

Deep Water Container Transfer Terminal

Djakarta, Indonesia

The LIGTT is strategically located near

Mile 0 of the Mississippi River, 20 miles

downstream of Venice, in Plaquemines

Parish.

The terminal is located east of SW Pass

within state waters.

Owner – LIGTT Midstream, LLC

Land lease (~2300 acres) from State of

Louisiana P3 Project

LIGTT Phase 1 : Programmatic Schedule

Evans-Graves Responsibilities

• Preliminary Planning and Feasibility

• Define Project

• Develop Alternatives

• Site Recon and Record Search

• Geotech Investigations

• Market Studies

• Liaison with Federal, State, and Local Agencies

Program and Project Management – Phase 1

• Permitting Management

• Program Control Process (Dashboard)

• Program Management Plan

• Strategic Communications Plan

• Manage Operating Budget

• Document Archiving

• Develop geotechnical soil model

• Pile Capacity Analysis

• Metocean Survey

• Anchoring Concept

• Economic and Market Study

• Concept Design

• Storm Modeling

• Permitting Documentation

• Master Plan

• General Engineering

• Architectural Design Services

• Life Safety

Project Management Tools

Change Control

• The change control process provides the mechanism to document and

incorporate changes in contract scope, costs, schedule and program

acquisition as established in the program management plan.

• A change control request (CCR) is initiated by the project manager with

senior PM concurrence, and submitted to Program Management / Program

Review Board for review and approval. Approval Authorities are described

in the PMP.

Private Program

Control

Dashboard

Budgets/

Financials

Scheduling

Primavera-P6

Document

Control Change Control

Database

Mapping/GIS

Calendars

Admin

Module

Public Domain

Website

Fire

wall

LIGTT Dashboard (Cloud based Servers)

• Project Fact Sheet

• Team Members

• Budget

• Weekly Reports Archive pdfs

• Milestone Reports

• Any Custom Report

• Photo Archive

• Excel Exports

• Project Fact Sheet

• Project Progress

• Project Photos

• Useful Links

• Public Documents

Program Control Dashboard

One central data location: cloud-based

Maintained for each features: • Current working budget (CWB) by work feature

• Historical cost and schedule changes

• Program schedule data and milestones reports from Primavera (P6).

• Construction status

• Provides access to cost control process database.

Provides program management analysis tools, data reports and

forms

Program Control Dashboard

Cost Features

• Current cost data

• Data exportable for detailed analysis

• Ability to capture project modifications

• Data integrity enforced with drop down data menu selections

• Expenditures monitored

• Fully documented cost control change process

• Data security maintained via user login

Program Control Dashboard Management Features

• Schedule and milestone data

• Single source data for management and staff access

• GIS location mapping capabilities

• Enhanced public relations via public websites

• Data security maintained via user login

• Interactive management reporting

• Enhanced staff communications and projects status

• Ease in monitoring staff progress

Program Control Dashboard Analysis Tools

• Construction earned value reports

• Risk analysis

• Cost comparisons against awarded projects

• Charts and graphs

• Status reports

• Program cost growth projections

• Budget and expenditures reports

• 30, 60 & 90 day forecasting

Project Scheduling

• Primavera P6 software

• Trained team of schedulers

• Interconnected to the dashboard

Discussion