Annexure IB (EMP)

Embed Size (px)

Citation preview

  • 8/7/2019 Annexure IB (EMP)

    1/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    CONTENTS

    1.0 Introduction ..........................................................................................................51.1 The Project .......................................................................................................................5

    1.2 Project Components .........................................................................................................5

    1.3 Objective ..........................................................................................................................51.4 Environmental Management Components ....................................................................... 6

    1.5 Structure of Report ...........................................................................................................6

    2.0 Environmental Mitigation Plan (EMP) ..............................................................7Table 2.1: Environmental Issues, Reason / Source of Pollution and MitigationMeasures .....................................................................................................................7Table 2.2: ACTION SHEET 1 ................................................................................... 28Table 2.4: ACTION SHEET 3 ................................................................................... 30Table 2.5: ACTION SHEET 4 ................................................................................... 31Table 2.6: ACTION SHEET 5 ................................................................................... 313.0 Monitoring & Reporting ................................................................................... 33

    3.1 Monitoring ..................................................................................................................... 333.2 Performance Indicators ..................................................................................................33

    3.3 Responsibilities for Monitoring .....................................................................................333.4 Routine Monitoring ........................................................................................................34

    Site Selection ...................................................................................................................34

    Methodology ....................................................................................................................34

    Table 3.1: Testing of Environmental Parameters and Standard Protocol.......343.4.1 Ambient air Quality Monitoring (AAQM) .............................................................34

    Table 3.2: National Ambient Air Quality Standards (NAAQS) ........................... 35Table 3.3: Primary Water Quality Standards ........................................................ 36Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991 ......38

    Table 3.5: National Ambient Noise Quality Standards ....................................... 413.5 Monitoring Plan .............................................................................................................41

    Table No. 3.6: Components for Monitoring ........................................................413.6 Mitigation Measures ...................................................................................................... 42

    Table 3.7 Implementation Schedule with Responsible/SupervisingOrganization/Authority ............................................................................................43

    3.7 Reporting ........................................................................................................................51

    3.7.1 Reporting Arrangement ..........................................................................................51

    3.7.2 Recording of Data ...................................................................................................513.7.3 Record keeping ....................................................................................................... 51

    4.0 Arboriculture & Landscaping ......................................................................... 53

    4.1 General ...........................................................................................................................534.2 Objective ........................................................................................................................53

    Selection of Plant Species ....................................................................................................54

    Types of Trees / Species ...................................................................................................... 55Table - 4.1: Species Proposed for Plantation ...................................................... 55

    Methodology ........................................................................................................................56

    Landscaping .........................................................................................................................56

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 1 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    2/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    4.6.1 Design for plantation of Trees ............................................................................... 56

    Table 4.2: List of shrubs proposed for plantation .............................................. 585.0 Environmental Enhancement Plan .................................................................. 61

    General .................................................................................................................................61

    Criteria for Selection ............................................................................................................61

    Design Concepts Overview ...............................................................................................62Elements for Enhancement ................................................................................................. 62

    Landscaping .....................................................................................................................62

    Water Bodies ...................................................................................................................63Noise Barriers .................................................................................................................. 63

    Cultural Properties ...........................................................................................................65

    Community Resources .....................................................................................................66

    6.0 Budgets for EMP ................................................................................................ 67Institutional Arrangement .......................................................................................70

    General .................................................................................................................................70

    Environmental Management System (EMS) ....................................................................... 70

    Duties of various Organizations in the EMS ....................................................................... 70Awareness & Training .........................................................................................................72

    7.4.1 Awareness ...............................................................................................................727.4.2 Training ...................................................................................................................72

    Table 7.1: Proposed Training Modules .................................................................73

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 2 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    3/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    List of Tables

    1.0 Introduction ..........................................................................................................51.1 The Project .......................................................................................................................5

    1.2 Project Components .........................................................................................................5

    1.3 Objective ..........................................................................................................................51.4 Environmental Management Components ....................................................................... 6

    1.5 Structure of Report ...........................................................................................................6

    2.0 Environmental Mitigation Plan (EMP) ..............................................................7Table 2.1: Environmental Issues, Reason / Source of Pollution and MitigationMeasures .....................................................................................................................7Table 2.2: ACTION SHEET 1 ................................................................................... 28Table 2.4: ACTION SHEET 3 ................................................................................... 30Table 2.5: ACTION SHEET 4 ................................................................................... 31Table 2.6: ACTION SHEET 5 ................................................................................... 313.0 Monitoring & Reporting ................................................................................... 33

    3.1 Monitoring ..................................................................................................................... 333.2 Performance Indicators ..................................................................................................33

    3.3 Responsibilities for Monitoring .....................................................................................333.4 Routine Monitoring ........................................................................................................34

    Site Selection ...................................................................................................................34

    Methodology ....................................................................................................................34

    Table 3.1: Testing of Environmental Parameters and Standard Protocol.......343.4.1 Ambient air Quality Monitoring (AAQM) .............................................................34

    Table 3.2: National Ambient Air Quality Standards (NAAQS) ........................... 35Table 3.3: Primary Water Quality Standards ........................................................ 36Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991 ......38

    Table 3.5: National Ambient Noise Quality Standards ....................................... 413.5 Monitoring Plan .............................................................................................................41Table No. 3.6: Components for Monitoring ........................................................41

    3.6 Mitigation Measures ...................................................................................................... 42

    Table 3.7 Implementation Schedule with Responsible/SupervisingOrganization/Authority ............................................................................................43

    3.7 Reporting ........................................................................................................................51

    3.7.1 Reporting Arrangement ..........................................................................................51

    3.7.2 Recording of Data ...................................................................................................513.7.3 Record keeping ....................................................................................................... 51

    4.0 Arboriculture & Landscaping ......................................................................... 534.1 General ...........................................................................................................................534.2 Objective ........................................................................................................................53

    Selection of Plant Species ....................................................................................................54

    Types of Trees / Species ...................................................................................................... 55

    Table - 4.1: Species Proposed for Plantation ...................................................... 55Methodology ........................................................................................................................56

    Landscaping .........................................................................................................................56

    4.6.1 Design for plantation of Trees ............................................................................... 56

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 3 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    4/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    Table 4.2: List of shrubs proposed for plantation .............................................. 585.0 Environmental Enhancement Plan .................................................................. 61

    General .................................................................................................................................61Criteria for Selection ............................................................................................................61

    Design Concepts Overview ...............................................................................................62

    Elements for Enhancement ................................................................................................. 62Landscaping .....................................................................................................................62

    Water Bodies ...................................................................................................................63

    Noise Barriers .................................................................................................................. 63Cultural Properties ...........................................................................................................65

    Community Resources .....................................................................................................66

    6.0 Budgets for EMP ................................................................................................ 67Institutional Arrangement .......................................................................................70

    General .................................................................................................................................70

    Environmental Management System (EMS) ....................................................................... 70

    Duties of various Organizations in the EMS ....................................................................... 70

    Awareness & Training .........................................................................................................727.4.1 Awareness ...............................................................................................................72

    7.4.2 Training ...................................................................................................................72

    Table 7.1: Proposed Training Modules .................................................................73

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 4 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    5/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    1.0 Introduction

    1.1 The Project

    Ministry of Shipping Road Transport and Highways (MoSRT&H), Government of India hasdecided to take up the development of various National Highways where the intensity of

    traffic has increased or likely to increase significantly. There is a requirement of

    augmentation of capacity for safe and efficient movement of traffic. One of such corridors of

    significance is North-East corridor connecting Pune to Solapur. National Highways Authority

    of India (NHAI) has been entrusted to implement the development of this corridor.

    Environmental Management Plan sets out the environmental management procedures

    during design, construction and operation phase, including mitigation & enhancement

    measures, institutional and monitoring requirements. This EMP also provides the guidelinesand instructions to be followed by the PIU (PWD) for effective implementation of the project.

    The proposed project involves rehabilitation, strengthening and widening to 4-lane dual

    carriageway of North - East corridor of the National Highway in the States of Maharashtra

    which includes NH-9 from Pune (PWD km 40/000) to PWD km 144/400. The project consists

    of a Feasibility Study and Detailed Design for preparation of a Detailed Project Report

    (DPR). The major towns along the project road include Tembhurni & Indapur.

    1.2 Project ComponentsThe various activities / components involved in the project include design process and

    construction activities. Some of the major activities likely to take place to implement the

    proposed up-gradation / improvement project are: Site clearing & grubbing, Earthwork,

    Pavement removal, Granular sub-base, Water bound macadam sub-base / base,

    Bituminous pavement layers, pavement widening, Drainage, Safety measures, Bridge &

    Culvert improvement, Waste material management, Equipment staging & materials,

    Aggregate and sand quarries etc. These major activities have been taken into account while

    finalizing the methodology for the impact assessment of the project.

    1.3 ObjectiveEnvironmental management plan (EMP) has been recommended by considering broad

    aspects, which includes

    Suitable measures to be taken in light of specific project issues,

    Implementation & supervision through competent agencies for EMP,

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 5 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    6/75

    Package-I Detailed Project Report Vol-IV B EMP Report

    Schedule for implementing these actions,

    Reference to contract documents and specifications,

    Project level environmental monitoring,

    Environmental status reporting frequency, and

    Institutional arrangement, strengthening of their capability, and role.

    1.4 Environmental Management Components

    The various components which are considered for the environmental management aspects

    and to be included in the environmental management plan, broadly consists of

    environmental mitigation aspects, environmental performance indicators to be monitored

    and reporting system, environmental enhancement measures, arboriculture and landscaping

    aspects, financial aspects required for the effective implementation of the environmental

    management Plan and Institutional Strengthening and training of the project implementationunit. These are discussed in the report herein.

    1.5 Structure of ReportThe structure of the report for Environmental Management Plan is as organised as

    follows:

    Chapter 1 - Introduction

    Chapter 2 - Environmental Management Plan

    Chapter 3 - Monitoring & Reporting Plan

    Chapter 4 - Arboriculture & Landscaping

    Chapter 5 - Environmental Enhancement Plan

    Chapter 6 - Environmental Budget

    Chapter 7 - Institutional Arrangement

    This Environmental Management Plan (EMP) is a part of the environmental impact

    assessment report, as per corrigendum issued with the TOR.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 6 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    7/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    2.0 Environmental Mitigation Plan (EMP)

    Table 2.1 below shows the typical environmental mitigation matrix prepared for the proposed project. This includes the project specific

    environmental issues, corresponding remedial measures, its reference to contract document / MoRTH specification, location of the

    measures to be applied, cost of the mitigation measures and responsibility for implementing the typical mitigation measures.

    Table 2.1: Environmental Issues, Reason / Source of Pollution and Mitigation Measures

    Environmental

    IssueRemedial Measures

    Reference to

    Contract

    Documents

    LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Design / Pre-Construction Stage

    1. Alignment

    Critical

    sections /

    settlements

    Provision of large / deep roadside

    drains

    Road widening

    Improvement of Intersections /

    Junctions

    Providing bypasses at Indapur,

    Tembhurni & Mohol where settlement is

    high.

    RAP

    requirements

    Road sections

    with service

    roads,

    Locations of

    thick

    settlements

    Project

    preparation

    cost

    Design

    Consultant

    PIU

    2. Land

    Landacquisition

    Acquisition of land is minimized to

    the maximum extent

    Land shall be acquires as per the

    Government Land Acquisition Policy,

    applicable

    To avoid impact of land outside

    Land AcquisitionPolicy of NHAI,

    Land Acquisition

    Act

    MoRTH 201.2

    All along theroad where

    alignment has

    been modified.

    Projectpreparation

    cost

    DesignConsultant

    PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 7 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    8/75

  • 8/7/2019 Annexure IB (EMP)

    9/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Control Board shall be obtained.

    Adequacy of measures shall be checked

    to control air pollution.

    MoRTH 111

    plant and

    construction

    machinery

    preparation

    cost

    Consultant, PIU,

    (PWD)

    Noise Level NOC from concerned State Pollution

    Control Board shall be obtained

    Improved traffic speeds and riding

    conditions shall reduce noise levels

    Noise screening by trees plantation

    scheme proposed as noise barriers

    Provided noise attenuation at critical

    locations like Hospital, school etc.

    MoRTH 111

    For hot mix

    plant and

    construction

    machinery

    At sensitive

    receptors.

    Project

    preparation

    cost

    Design

    Consultant,

    PIU,

    PWD,

    Departm

    ent of

    Environ

    ment &

    Forests

    6. Utilities

    Relocation of

    utility lines /

    community

    utilities.

    Affected utilities like electric poles, water

    pipe lines, hand pumps, etc. shall be

    relocated with prior approval of the

    concerned agencies

    All the R&R activities shall be reasonably

    completed as per RAP

    All the cultural properties that have been

    identified as affected shall be relocated

    as per resettlement plan

    MoRTH 110

    As per R&R

    plan prepared

    separately

    Project

    preparation

    cost

    All concerned

    state

    Government

    Departments,

    PIU

    PIU

    7. Environmental Safety

    Accidents Design improvements to road geometry

    Provision of adequate sight distance at

    MoRTH 112 All along the

    project road

    Project

    preparation

    Design

    Consultant

    PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 9 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    10/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    curves and road junctions

    Provision of adequate set back distance.

    Provision of proper signage at sensitive

    receptor locations such as schools,

    hospitals and at known accident spots

    especially at

    settlements,

    and locations of

    bad geometry

    cost

    Traffic

    Control

    System

    Temporary traffic arrangement during

    construction shall be planned in DPR.

    The contractor shall take all necessary

    measures for the traffic during demolition

    and site clearing activities.

    MoRTH 112

    All along the

    project road

    and locations of

    settlements

    Project

    preparation

    cost

    Pedestrian

    Safety

    Special considerations shall be given

    in the local traffic management to the

    pedestrian safety Especially at

    congested locations bed

    MoRTH 112.2

    At congested

    locations

    Construction Stage

    1. Soil

    Soil Erosion Soil Stabilization measures by

    immediate grassing and vegetation of

    embankments to control soil erosion,

    sedimentation and water pollution.

    Stone / PVC pitching, gabions near

    banks of water bodies as well as at high

    cut areas

    Provision of berms at high

    MoRTH 306 At identified

    locations,

    embankment

    along water

    courses, high

    cut locations

    Engineering Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 10 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    11/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    embankments.

    Soil

    contaminatio

    n by

    construction

    waste, fuel

    etc.

    Oil & fuel spills from construction

    equipments shall be controlled by good

    O&M practices

    Contaminated soil shall be disposed

    of as per MoEF guidelines

    Project

    requirements

    At construction

    camps and at

    waste disposal

    sites

    Borrow pits Borrow areas shall be levelled

    properly after use.

    MoRTH 111.3,

    Guidelines

    given in

    EMP

    At identified

    locations

    Engineering Contractor PIU

    Uses of

    Excavated

    Material other

    than borrow

    pits

    Excavated material shall be used for

    as a fill material in the embankments

    wherever possibleProject

    requirement

    At identified

    locations

    Engineering Contractor PIU

    Disposal of

    Excavated

    Material

    Surplus material still remaining from

    the above shall be deposited at the

    selected locations and as approved by

    PWD, or if possible it shall be used in

    rehabilitation of quarries

    MoRTH 301.3

    At identified

    locations

    Engineering Contractor PIU

    Transport of

    Excavated

    Earth / debris

    The village roads used for the haulage of

    excavated earth shall be maintained to

    their original condition upon completion

    MoRTH 111.9

    MoRTH 301.3

    Throughout

    project corridor

    Engineering Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 11 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    12/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    of work. PIU may use the services of SC

    to monitor and report.

    Precautionary measures like covering of

    vehicles shall be taken to avoid spillage

    and to reduce dust nuisance duringtransport of materials.

    Quarries The Quarry material shall be procured

    only from licensed quarries operating

    under environmental clearances,

    including transportation of quarry

    material clearances under the Air Act

    Safety precautions shall be ensured

    during transportation of quarry material

    from quarries to the construction sites

    Stockpiling of material shall be properly

    planned so as to ensure smooth traffic

    flow on the highway

    MoRTH 111.3

    Known quarry

    locations listed

    Throughout

    project corridor

    Engineering

    cost

    Contractor PIU

    Sand & Clay During transportation trucks shall be

    covered to prevent dust nuisanceMoRTH 111.3

    Throughout

    project corridor

    Environment

    al cost

    Contractor PIU

    Contaminatio

    n of soil from

    fuel and

    lubricants

    Soak pits along with oil and grease

    traps shall be provided around fuel

    storage areasMoRTH 111

    Construction

    camps

    Environment

    al cost

    Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 12 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    13/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    2. Water

    Water Bodies Impact on surface watercourses

    (rivers and ponds) would be minimized

    throughout by control over construction

    works as per guidelines

    MoRTH 305

    Bridge

    locations along

    the project road

    Engineering

    cost

    Contractor

    Other Water

    Sources

    Community water sources shall not

    be used during construction period. Projectrequirements

    Locations

    identified along

    project corridor

    Engineering

    cost

    Contractor PIU

    Drainage and

    run-off

    At cross drainage structures, the

    earth, stone or any other obstructing

    construction material shall be removed

    and properly disposed of so as not to

    block the flow of water at any time

    Construction material shall not be

    stored so as to block the drainage

    system, if happens, contractor should

    ensure that they are cleaned especially

    during monsoon period.

    Roadside drains have been

    proposed all along the project road to

    improve drainage. Contractor shall clear

    off the drains before opening the road to

    traffic.

    MoRTH 306

    MoRTH 309

    Throughout

    project corridor

    Engineering

    cost

    Contractor PIU

    Contaminatio Construction and sitting of plant & MoRTH 305 At construction Engineering Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 13 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    14/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    n of water

    from

    construction

    waste

    machinery close to the streams and

    water bodies shall be avoided, especially

    during monsoon period.

    Soak pits shall be provided at

    construction site to prevent wastewater

    from entering into rivers and streamsespecially during pile driving across

    major rivers

    All waste arising from the project shall be

    disposed off as per SPCB norms, so as

    not to block the flow of and contaminate

    water

    Waste must be collected, stored and

    transported to approve disposal sites.

    Projectrequirement

    Guidelines given

    in EMP

    camps,

    locations of

    water bodies,

    cost

    Environment

    al cost

    Contaminatio

    n of water

    from fuel and

    lubricants

    To avoid contamination from fuel and

    lubricants, the vehicle and equipments

    shall be properly maintained and

    refuelled

    Vehicle maintenance and refuelling in

    construction camps should be confined

    to areas with traps oil / grease to prevent

    wastewater from entering into rivers and

    streams

    Project

    requirement

    At construction

    camp locations,

    wherever

    located along

    the Project

    corridor.

    Engineering

    cost

    Environment

    al cost

    Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 14 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    15/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Sanitation

    and waste

    disposal in

    construction

    camps

    The construction camps shall be located

    away from habitations (at least 500 m),

    at identified sites.

    The sewerage system for such camps

    shall be properly designed and built sothat no water pollution of any stream or

    watercourses takes place.

    The workplace should have proper

    medical approval by local medical,

    health or municipal authorities.

    MoRTH

    105.2

    Guidelines given

    in EMP

    At construction

    camp locations,

    wherever

    located along

    the Project

    Corridor.

    Engineering

    cost

    Environment

    al cost

    Contractor PIU

    Use of water

    for

    construction

    The contractor shall make independent

    arrangements for water required for

    construction in such a way that the water

    availability and supply to nearby

    communities remain unaffected.

    Wastage of water during construction

    shall be minimized and properly

    controlled.

    Project

    requirement

    Throughout the

    project corridor

    Engineering

    cost

    Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 15 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    16/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    3. Air

    Emission

    from

    construction

    vehicles and

    machinery

    All vehicles, equipments and machinery

    used for construction shall be regularly

    maintained to ensure that the pollution

    emission levels conform to the SPCB

    norms.

    The asphalt plants, crushers and the

    batching plants shall be sited at least

    500 m in the downwind direction from the

    nearest settlement.

    Regular monitoring of Air shall be

    conducted as described in

    Environmental Monitoring Plan.

    Action sheet no. 2 given in Table 2.3

    shall be followed.

    Legal

    requirement

    MoRTH

    111.5

    Throughout the

    project corridor

    Engineering

    cost

    Environment

    al cost

    Contractor PIU

    Dust and

    Nuisance

    Existing hot mix / concrete / asphalt

    plants shall be used to the extent

    possible,

    In case of new hot-mix plants, crushers

    and batching plants, these shall be sited

    at least 500 m downwind from the

    nearest habitation and covered with dust

    MoRTH

    111.5

    Throughout the

    project corridor

    Engineering

    cost

    Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 16 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    17/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    trapping hoods.

    Water shall be sprayed at mixing sites,

    earth mixing sites and asphalt mixing

    sites and on temporary access roads

    and diversions.Action sheet 1 given in Table 2.2 shall be

    followed.

    Vehicle delivering material shall be

    covered. End boards in loaders shall be

    provided to prevent spillage.

    In case of unpaved roads used by

    contractor, it shall be watered regularly

    at least once in day to control fugitive

    dust nuisance.

    MoRTH

    111.8

    MoRTH

    111.9

    MoRTH

    111.10

    Environment

    al cost

    Environment

    al cost

    Environment

    al cost

    4. Noise Levels

    Noise from

    vehicle,

    asphalt

    plants and

    equipments

    The plants and equipment used for

    construction shall be strictly conforming

    to CPCB noise standard.

    Properly sizing and maintaining mufflers,

    engine intake silencers, engine

    enclosures, turning of idle equipment,

    shall be filtered with silencers.

    Legal

    requirement

    Throughout the

    project corridor

    Engineering

    cost

    Contractor PIU

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 17 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    18/75

  • 8/7/2019 Annexure IB (EMP)

    19/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Noise

    barrier /

    buffer

    plantations

    Construction of noise barrier in the

    form of buffer plantation and vegetation

    at sensitive receptors.

    Along sensitive

    locations in the

    road corridor

    Environment

    al cost

    Contractor PIU

    5. Flora

    Loss or

    damage to

    vegetation

    Trees lost shall be replaced just

    before the beginning of the construction

    according to Compensatory A forestation

    Policy of State Forestry Department at

    the rate of two new trees for each tree

    lost.

    The local tree authority shall do

    transplantation of the tree according to

    the site conditions as applicable. The

    contractor shall contact the tree authority

    to carry out compensatory a forestation

    as well as transplantation of trees.

    Legal

    requirement

    As per

    technical

    specification

    s supplied

    with EMP

    Throughout

    project

    Corridor

    Environm

    ental cost

    Department

    of

    Environment

    and Forest,

    PIU (PWD)

    SC, PIU,

    PWD

    Compaction

    of Vegetation

    All construction vehicle movement

    and parking locations shall be such as to

    prevent damage to roadside vegetation

    Project

    requirement

    Throughout

    Project

    Corridor

    Engineeri

    ng cost

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 19 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    20/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Damage to

    trees /

    vegetation by

    workers

    Contractor to ensure prevention of

    damage to vegetation and trees and

    their use by workers. Contractor shall

    supply kerosene for all needs during

    construct ion, to prevent use of

    vegetation and trees for fuel

    Adequate landscaping of median,

    embankment slopes and other open

    space available within ROW shall be

    carried out as suggested in Arboriculture

    and Landscaping Plan and as per

    specification given.

    Project

    requirement

    As per

    specification

    provided

    Throughout

    Project

    Corridor

    Environm

    ental cost

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD

    Departm

    ent of

    Environ

    mentand

    Forest

    6. Fauna

    Loss, injury

    or disruption

    to fauna

    Construction workers shall be

    directed not to poach upon fauna.

    Hunting shall be strictly prohibited.

    Contractor shall take all necessary

    measures to protect wildlife during

    construction in forest areas.

    Necessary signage, controlled /

    timely construction activities shall reduce

    disturbance to wildlife.

    Project

    requirement

    Throughout

    Project

    Corridor

    and

    especially

    at

    settlement

    and at

    forest area

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant

    PIU,

    PWD,

    Departm

    ent of

    Environ

    ment

    and

    Forest

    7. Safety and Accidents

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 20 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    21/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Accident

    risks from

    construction

    activities.

    To ensure safety of the temporary

    accesses during construction, safety

    devices shall be installed.

    Traffic rules and regulation shall be

    strictly adhered to local laws.

    Workers undertaking various operations

    during construction shall be protected by

    providing helmets, masks, safety

    goggles, hand gloves and rubber boots

    etc.

    First aid kits shall be provided at

    construction site for workers to meet

    minor accidents during construction

    MoRTH

    105.2

    Throughout

    Project

    Corridor

    Engineeri

    ng cost

    Environmental cost

    Contractor,

    Supervision

    Consultant

    PIU,

    PWD,

    Departm

    ent of

    Health

    andFamily

    Welfare

    Health Issue At every workplace, good and sufficient

    water supply shall be maintained to

    avoid waterborne / water-related / water-

    based diseases to ensure the health and

    hygiene of workers.

    Adequate drainage, septic tanks, soak

    pits and wastewater disposal shall be

    provided at workplace.

    Preventive Medical care shall be

    provided to workers.

    MoRTH

    105.2

    Project

    requirement

    Throughout

    Project

    Corridor

    and

    particularly

    at workers

    camps

    Engineeri

    ng cost

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD,

    Departm

    ent of

    Health

    and

    Family

    Welfare

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 21 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    22/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Action sheet no 4 given in Table 2.5 shall

    be followed.

    Movement of

    Existing

    Traffic

    Traffic management shall be effected

    through

    Gate system

    Diversion along existing alternative

    routes

    Proper signage

    Project

    requirement

    Near

    temporary

    work sites

    Engineeri

    ng costs

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD

    8. Roadside Trees

    Road Side

    Trees

    Compensatory planting at the rate of

    two trees for every tree to be cut shall be

    carried out,

    As per

    specification

    s provided

    Along

    roadside

    vacant

    lands and

    Forest

    Departmen

    ts land

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant,

    Village

    Councils,

    PIU (PWD),

    Department

    of

    Environment

    & Forests.

    SC, PIU,

    PWD,

    Departm

    ent of

    Environ

    ment &

    Forest

    9. Environmental Enhancement

    Roadside

    landscape

    development

    Roadside plantation and grassing

    measures shall be done to improve

    aesthetics as per the arboriculture and

    landscaping plan developed

    As per

    specification

    s provided

    Throughout

    Project

    Corridor

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant,

    Department

    PIU,

    PWD,

    Departm

    ent of

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 22 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    23/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Action sheet no. 5 given in Table 2.6 shall

    be followed.

    of

    Environment

    & Forest

    Environ

    ment &

    Forest

    Roadside

    amenities

    Enhancement of road side temples, trees

    and market places very near to road

    shall be done as per the instructions of

    the supervision consultant.

    Provision of bus shelters, bus bays and

    rest places as per standard design shall

    be carried out.

    Road furniture including marker posts,

    crash barriers, traffic signs, speed zone

    signs, rumbling strips etc. shall be

    constructed and erected as per design.

    Ponds and water bodies along the road

    & near to communality places shall be

    enhanced.

    Project

    requirement

    Throughout

    Project

    Corridor

    and at

    selected

    sites

    Environm

    ental cost

    Engineeri

    ng cost

    Environm

    ental cost

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD

    Community

    Properties

    Community properties, located away

    from the project road should not be

    disturbed by construction activity;

    workers camp and contractors work

    area.

    Project

    requirement

    Throughout

    Project

    Corridor

    Engineeri

    ng cost

    Contractor,

    Supervision

    Consultant

    SC, PIU,

    PWD

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 23 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    24/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Environment

    al Awareness

    Environmental Awareness Campaigns

    shall be conducted in the project area

    during construction period to ensure the

    applicability of the various environmental

    laws

    Project

    requirement

    At

    settlements

    in project

    area

    Environm

    ental cost

    PIU( PWD) PWD

    Operation Stage

    Contaminatio

    n from

    accidental

    spills

    The spills at the accident sites shall be

    cleared immediately

    The left over spills shall be scraped and

    carried to small lined confined pits at

    identified sites.

    Project R

    Requirement

    Throughout

    Project

    Corridor

    PWD to

    ensure

    this

    (reoccurri

    ng cost)

    Local Govt.

    Bodies State

    PWD and

    State

    Pollution

    Control

    Board.

    PIU,

    SPCB

    Dust

    Generation

    Roadside tree plantations shall be

    maintained.

    Dust generated and deposited shall

    be cleaned regularly.

    Project

    requirement

    Throughout

    Project

    Corridor

    Environm

    ental

    cost

    (reoccurri

    ng cost)

    Department

    of

    Environment

    & Forest,

    PWD

    PIU,

    Departm

    ent

    of

    Environ

    ment &Forest

    Air Pollution Vehicle emission of critical pollutant

    parameters (SPM, CO, SO2 and NO2)

    shall be monitored as per monitoring

    plan

    Legal

    requirement

    At selected

    locations

    Throughout

    Environm

    ental cost

    (reoccurri

    ng cost)

    Motor

    vehicle

    department,

    and SPCB,

    PIU,

    SPCB

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 24 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    25/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Environmental

    IssueRemedial Measures

    Reference to

    Contract LocationMitigation

    Cost

    Institutional

    Responsibility

    Implementation Supervision

    Vehicle emission norms shall be

    enforced

    Roadside tree plantation shall be

    protected and maintained

    Project

    requirement

    Project

    corridor

    PWD

    Noise

    Pollution

    Noise pollution shall be monitored

    Adequate no-horn sign boards shallbe installed at sensitive / critical

    locations

    Legal

    requirement,

    Projectrequirement

    At selected

    locations

    Environm

    ental cost

    (reoccurri

    ng cost)

    Motor

    vehicle

    department,

    and SPCB,

    PWD

    PIU,

    SPCB

    Water The roadside drainage system shall be

    periodically cleared of blockage

    Water quality shall be monitored as per

    plan

    Charecteristics of water used for

    construction should satisfy the standards

    given by CPCB.

    Project

    requirement

    Throughout

    project

    road

    At selected

    locations

    By PWD

    (Reoccur

    ring cost)

    PWD and

    SPCB

    PIU,

    SPCB

    Flora and

    Fauna

    Adequate care of the compensatory

    plantation should be taken up to comply

    success of the replantation scheme shall

    be monitored

    If survival rate is below 70 %,

    replantation shall be done as required

    Project

    requirement

    Throughout

    Project

    corridor

    Included

    in

    compens

    atory

    plantatio

    n cost

    Department

    of

    Environment

    & Forest,

    PWD

    PIU,

    Departm

    ent

    of

    Environ

    ment &

    Forest

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 25 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    26/75

  • 8/7/2019 Annexure IB (EMP)

    27/75

  • 8/7/2019 Annexure IB (EMP)

    28/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 2.2: ACTION SHEET 1

    Environmental

    Attribute

    Air Emissions (Dust/particulate)/Disposal of Construction

    Debris.

    Issue Increased dust levels adjacent to haul roads and construction

    yards. Uncollected construction debris.

    Mitigation

    measure

    Sprinkling of water once a day along the haul routes to project

    road, passing through residential area and at the construction

    yard.

    Methodology

    for

    implementation

    Water tankers should be deployed by the contractor through

    out the winter and summer months and during dry spells in

    monsoon months to water at construction yard and those

    sections of road which shall carry the construction materialthrough the residential areas. Water sprinkling should be

    carried out in the morning hours every day.

    Water from the pond in villages will not be used without the

    consent of the village community.

    The uncollected construction debris can also contribute to

    fugitive dust and insanitary conditions. Daily inspection at haulroutes and construction sites should be conducted to ensure

    speedy disposal of construction debris to landfill sites. Nearby

    borrow pits may be used for disposal of debris or areas which

    may need a noise barrier may utilise the debris to create a

    hump.

    Implementing

    Agency

    Contractor / sub-contractor

    Monitoring

    Agency

    The Engineer

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 28 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    29/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 2.3: ACTION SHEET 2

    Environmental

    Attribute

    Air Pollution from Construction Yard Activities (NO2 Levels

    During Construction)

    Issue Increased exposure to air pollutants near main construction

    yards in downwind directions during winter.Mitigation

    measures

    Construction yard should not be located within 500m of the

    major villages.

    Methodology

    for

    implementation

    Contract conditions on placement of major construction yards.

    Implementing

    Agency

    Contractor

    Monitoring

    Agency

    The Engineer

    Legal

    Instrument

    The above restrictions on placement of construction yards

    should be intimated to the bidder while inviting the bids.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 29 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    30/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 2.4: ACTION SHEET 3

    Environmental

    Attribute

    Noise Pollution

    Issue Increased Noise levels during day and night time in the

    residential areas adjacent to the construction yard.Mitigation

    measures

    Siting of construction yards more than 100 m away from any

    residential areas;

    Methodology

    for

    implementation

    Select construction yards sites leaving adequate distance to

    allow noise to attenuate.

    For the protection of construction workers, ear plugs should be

    provided to those working near the noisy machinery.

    Implementing

    Agency

    Contractor

    Monitoring

    Agency

    The Engineer

    Legal

    Instrument

    The above activity (provision of enclosures) should form a part

    of the contract agreement. This will facilitate the contractor to

    take into account the cost of above measures while bidding for

    the contract.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 30 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    31/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 2.5: ACTION SHEET 4

    Environmental

    Attribute

    Sanitation at Construction Workers Colony

    Issue Adequate sanitation facilities and Hygiene at constructionworkers colony.

    Mitigation

    measures

    Provision of water supply and toilet facilities at construction

    workers colony as per the stipulated guidelines in Indian Labour

    Act along with provisions of septic tanks and refuse composting

    facility.

    Methodology

    for

    implementation

    The camp must not be located within one km of the major

    villages.

    The contractor should ensure adequate water supply and toilet

    facility with septic tanks and mechanisms for composting of

    domestic refuse at construction workers colony.

    Implementing

    Agency

    Contractor

    Monitoring

    Agency

    The Engineer

    Legal

    Instrument

    The above activity should form a part of the contract

    agreement. This will facilitate the contractor to take into account

    the cost of above measures while bidding for the contract.

    Table 2.6: ACTION SHEET 5

    Environmental Landscaping along the highway

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 31 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    32/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Attribute

    Issue To improve the deficient arboriculture along the corridor.

    Mitigation

    measures

    Development and Maintenance of landscape along the

    proposed highway, which acts as air pollution and noise barrier

    and improves aesthetics.Methodology

    for

    implementation

    The concerned forest department will prepare a plan for

    landscaping concurrent with the road construction schedule

    (with a lag of 3-4 months for preparing the ground).

    Phase-wise plantation should be taken up by the forest

    department. Required water should be taken from the bore-

    wells or nearby surface water bodies (except village ponds,

    unless consented by the community) along the highway.

    Implementing

    Agency

    PIU

    Monitoring

    Agency

    The Engineer

    Legal

    Instrument

    The above activity should form a part of the overall project cost.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 32 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    33/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    3.0 Monitoring & Reporting

    3.1 Monitoring

    The adverse environmental impacts identified during the Environmental impact

    Assessment process of the proposed project may increase further during the construction

    as well as during post-construction as well as during post-construction phase. Monitoring

    of environmental factors and constraints will enable agencies to identify the changes in the

    environmental impacts at particular locations, application of mitigative measures and

    utilisation of standard design guidelines for finalisation of alignment design. Monitoring will

    also ensure that actions taken are in accordance with the construction contract and

    specifications. It provides a basis for evaluating the efficiency of mitigation and

    enhancement measures, and suggests further actions needed to be taken to achieve the

    desired effect.

    3.2 Performance Indicators

    In order to evaluate the effectiveness of EMP at project level, certain physical, biological

    and social components identified. These component needs to be analyzed based on

    project specific conditions and data generated. The key quality components include Air

    quality, Water quality, Noise Levels around sensitive locations, Plantation / re-plantation

    success / survival rate, Erosion indices, Restoration of quarries and borrow areas, Quality

    of human health, Accident frequency.

    3.3 Responsibilities for Monitoring

    The responsibility for monitoring of implementation of EMP will rest with the Environmental

    management Unit (EMU). Mitigation and enhancement measures adopted in final design

    will be explicitly identified under the Bill of Quantity (BOQ) so that performance and

    completion is readily documented.

    The PWD will visually assess the progress of Environmental management unit and the

    work of Contractors. If the level of impact is determined to be high, further monitoring will

    be done by a recognised A category laboratory of the concerned State pollution control

    Board (SPCB) and assessed for verification of the increased or decreased emission level

    and pollutants along the project road. And if found more appropriate control measures

    would exercised.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 33 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    34/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    3.4 Routine Monitoring

    During the construction and post construction phase, ambient air quality, water quality

    (surface and Ground water), effluent if any released from construction site / camp) and

    noise levels will be monitored as and when required depending upon the type, nature andduration of the project using standardised monitoring methodologies and laboratories

    testing facilities / techniques.

    Site Selection

    Monitoring stations have been identified based on observation / site conditions such as

    nature of construction, diversions, congestion, parking places, bus / taxi stands, number

    and frequency of vehicles, sources of pollutants (industrial / commercial / residential),

    environmental features and existence of sensitive / critical areas i.e. educationalinstitutions, hospitals, archaeological / cultural sites. The frequency and duration of

    testing / sampling of air, water, noise levels and effluent quality within the ROW is to be

    fixed as per allotted time frame of the project and requirements of SPCB / CPCB and

    MoEF.

    Methodology

    Standard methodology as described in manuals, guidelines, etc. is to be followed as outlinedin Table below

    Table 3.1: Testing of Environmental Parameters and Standard Protocol

    Sr.

    No.Parameters to be Monitored References

    1 Ambient Air Quality

    i. Suspended Particulate Matter

    (SPM) ( g/m3)

    IS: 5182 (pt-4)

    ii. NOx ( g/m3) IS: 5182 (pt-6)

    iii. SO2 ( g/m3) IS: 5182 (pt-2)

    iv. CO (mg/m3) IS: 5182 (pt-10)

    2 Water and Effluent (all parameters as per CPCB (1998)

    i. Surface Water APHA 20th Edition and CPCB (1997)ii. Ground Water

    iii. Effluent (if any released from

    construction work site/camp)

    3 Noise level IS: 3028,IS: 4758, IS: 9779, IS: 10399

    3.4.1 Ambient air Quality Monitoring (AAQM)

    The air quality parameters i.e. Suspended Particulate Matter (SPM), Respirable Particulate

    Matter (RPM), Sulphur Dioxide (SO2), Nitrous Oxides (NOx), Carbon Monoxide (CO) and

    Hydrocarbons (HC) will be regularly monitored at designated locations and analyzed in

    accordance with the National Ambient Air Quality Standards given in Table 3.2. The location,

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 34 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    35/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    duration and pollution parameters to be monitored and the responsible institutional

    arrangements are detailed out in Environmental Monitoring Plan

    Table 3.2: National Ambient Air Quality Standards (NAAQS)

    Pollutants TimeWeighted

    SensitiveArea

    IndustrialArea

    Residential

    Rural &

    Other

    Method ofMeasurement

    Sulphur

    Dioxide

    (SO2)

    Annual* 15 g/m3 80 g/m3 60 g/m3

    Improved West

    and Gaeke

    method

    24 hours** 30 g/m3 120 g/m3 90 g/m3Ultraviolet

    fluorescence

    Oxides of

    Nitrogen

    (NOx)

    Annual 15 g/m3 80 g/m3 65 g/m3

    Jacob and

    Hochheiser

    modified (Na-Arsenite)

    24 hours** 30 g/m3 120 g/m3 91 g/m3

    Gas Phase

    Chemiluminesc

    enceCarbon

    Monoxide

    (CO)

    8 hours** 1000 g/m35000

    g/m32000 g/m3 Non Dispersive

    infrared

    spectroscopy1 hour 2000 g/m3

    1000

    g/m34000 g/m3

    Lead (Pb)

    Annual* 0.50 g/m3 1.0 g/m3 0.75 g/m3 AAS Method 24

    hours after

    sampling using

    EPM 20000 or

    equivalent filter

    paper

    24 hours** 0.75 g/m3 1.5 g/m3 1.00 g/m3

    Respirable

    particulate

    (RPM)-Size

    less than

    10 m

    Annual* 50 g/m3 120 g/m3 60 g/m3

    24 hours** 75 g/m3 150 g/m3 100 g/m3

    Suspended

    Particulate

    Matter

    (SPM)

    Annual* 70 g/m3 360 g/m3 140 g/m3Average flow

    rate not less

    than 1.1 cu.m /

    minute

    24 hours** 100 g/m3 500 g/m3 200 g/m3

    Source: Anon 1996-97, National Ambient Air Quality Monitoring Series NAQMS/a/1996-97, Central

    Pollution Control Board, Delhi.

    * Average Arithmetic mean of minimum 104 measurements in a year taken for a week 24 hourly at uniform interval.

    ** 24 hourly / 8 hourly values should meet 98 percent of the time in a year

    3.4.2 Water Quality MonitoringWater quality parameters such as pH, DO, Total Dissolved Solids, Phosphate,

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 35 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    36/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Calcium, Sulphate, Chlorides, Iron etc. will be monitored at all identified locations

    during construction stage as per standards prescribed by Central Pollution Control

    Board and Indian Standard water specifications presented in Table 3.3 and 3.4

    respectively. The location, duration and pollution parameters to be monitored and

    the responsible institutional arrangements are detailed out in Environmental

    Monitoring Plan (Table 3.6).

    Table 3.3: Primary Water Quality Standards

    Sr. No.Designated Best

    Use

    Class of

    Water

    Criteria

    1 Drinking Water

    source (with

    conventional

    treatment)

    A Total Coliforms MPN/100 ml

    shall be 50 or less

    pH between 6.5 to 8.5

    Dissolved Oxygen 6 mg / 1 or

    more

    Biological Oxygen demand

    (BOD) 5 days 200C, 2 mg/1 or less

    2 Outdoor bathing

    (organized)

    B Total Coliforms MPN/100 ml

    shall be 500 or less

    pH between 6.5 to 8.5

    Dissolved Oxygen 5 mg / 1 or

    more

    Biological Oxygen demand

    (BOD) 5 days 200C 3 mg/1 or less

    3. Drinking Water

    source (without

    conventional

    treatment)

    C Total Coliforms MPN/100 ml

    shall be 5000 or less

    pH between 6 to 9

    Dissolved Oxygen 4 mg / 1 or

    more

    Biological Oxygen demand

    (BOD) 5 days 200C 3 mg/1 or less

    4. Propagation of

    Wildlife

    D pH between 6.5 to 8.5 for

    fisheries

    Dissolved Oxygen 4 mg / 1 or

    more

    Free Ammonia (as N) 1.2 mg/1

    or less

    5. Irrigation,Industrial Cooling,

    E

    pH between 6.0 to 8.5 Electrical Conductivity at 250C

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 36 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    37/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Controlled Waste mhos/cm Max. 2250

    Sodium absorption ratio Max. 26

    Boron, Max.2 mg/1(Source: CPCB (1999). Bio mapping of rivers. Parivesh New Letter, 5 (iv), Central Pollution Control Board,

    Delhi, PP.20)

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 37 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    38/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991

    Sr.

    No.

    Substance or

    Characteristics

    Requirement

    (Desirable limit)

    Undesirable Effect Outside the

    Desirable limit

    Permissible Limit in the

    Absence of Alternate

    Source

    Remarks

    Essential Characteristics

    1 Colour, Hazen Units,

    Max.

    5 Above 5, consumer acceptance

    decreases

    25 Extended to 25 only if toxic

    substances, in absence of

    alternate sources.

    2 Odour Unobjectionable - - a) A test cold and

    when heated

    b) Test at several

    dilution

    3 Taste Agreeable - - Test to be conducted only

    after safety has been

    established

    4 Turbidity NTU, Max. 5 Above 5, consumer acceptance

    decreases

    10

    5 pH value 6.5 to 8.5 Beyond this range the water will not effect

    the mucous membrane and /or water

    supply system

    No relaxation

    6 Total hardness (as

    CaCO3) mg/1, Max.

    300 Encrustation in water supply structures an

    adverse effect on domestic use

    600

    7 Iron (as Fe) mg /l Max. 0.3 Beyond this limit taste / appearance are

    affected has adverse effect on domestic

    uses and water supply structures and

    promotes iron bacteria

    1

    8 Chlorides (as Cl) mg/1

    Max.

    250 Beyond this limit, taste corrosion and

    palatability are affected

    1000

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 38 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    39/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Sr.

    No.

    Substance or

    Characteristics

    Requirement

    (Desirable limit)

    Undesirable Effect Outside the

    Desirable limit

    Permissible Limit in the

    Absence of Alternate

    Source

    Remarks

    9 Residual, free

    chloride, mg/1 Min.

    0.2 To be applicable only when

    water is chlorinated.

    Tested at consumer end.

    When protection against

    viral infection is required, it

    should be Min. 0.5 mg/1Desirable characteristics

    1 Dissolved solids mg/1

    Max.

    500 Beyond the palatability decreases and

    may cause gastro intestinal irritation

    2000

    2 Calcium (as Ca) mg/1

    Max.

    75 Encrustation in water supply structure and

    adverse effects on domestic use

    200

    3 Magnesium (as Mg)

    mg/1, Max.

    30 Encrustation in water supply structure and

    adverse effects on domestic use

    1.5

    4 Copper (as Cu) mg/1

    Max.

    0.05 Beyond taste, discoloration of pipes, f it ting

    and utensils will be caused beyond this

    0.3

    5 Sulphate (as 200

    SO2), mg/1, Max.

    200 Beyond this causes gastro intestinal

    irritation when magnesium or sodium are

    present

    400 May b extended up to 400

    provided ( as Mg) does not

    exceed 30

    6 Nitrate (as NO2) mg/l,

    Max.

    45 Beyond this methamoglobunemia take

    place

    100 To be tested when pollution

    is suspected7 Fluoride (as F) mg/1,

    Max.

    1 Fluoride may be kept as low as possible.

    High fluoride may cause fluorosis

    1.5 To be tested when pollution

    is suspected

    8 Phenolic compounds

    (as C6H5OH) mg/1,

    Max.

    0.001 Beyond this it may cause object ionable

    taste and odour

    0.002 To be tested when pollution

    is suspected

    9 Mercury (as Hg) mg/1, 0.001 Beyond this the water becomes toxic No relaxation To be tested when pollution

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 39 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    40/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Sr.

    No.

    Substance or

    Characteristics

    Requirement

    (Desirable limit)

    Undesirable Effect Outside the

    Desirable limit

    Permissible Limit in the

    Absence of Alternate

    Source

    Remarks

    Max. is suspected

    10 Arsenic (As) mg/1,

    Max.

    0.05 Beyond this the water becomes toxic No relaxation To be tested when pollution

    is suspected

    11 Lead (as Pb), mg/1,

    Max.

    0.05 Beyond this the water becomes toxic No relaxation To be tested when pollution

    is suspected

    12 Zinc (as Zn) mg/1,

    Max.

    5 Beyond this limit it can cause astringent

    taste and an opalescence taste and an

    opalescence in water

    15 To be tested when pollution

    is suspected

    13 Poly nuclear aromatic

    hydrocarbons (as

    PAH) mg/1, Max.

    - May be carcinogenic above this limit - -

    14 Pesticides mg/1, Max. Absent Toxic 0.001 -

    15 Alpha emit

    ters bq/1, Max.

    - - 0.1 -

    (Source: Indian Standard Drinking Water Specification IS 10500, 1994)

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 40 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    41/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    3.4.3 Noise Quality Monitoring

    Ambient noise levels will be monitored at already designated locations in accordance with

    ambient noise quality standards given in Table 3.5. The location, duration and noise

    pollution parameters to be monitored and the responsible institutional arrangements are

    detailed out in Environmental Monitoring Plan

    Table 3.5: National Ambient Noise Quality Standards

    Sr.

    No.Area Code Category of Zone

    Leq*** in dB (A)

    *Day **Night

    1 A Industrial 75 70

    2 B Commercial 65 55

    3 C Residential 55 45

    4 D Silence Zone 50 40* Day Time 6.00 am 9.00 pm (15 hours)

    ** Night Time 9.00 pm 6.00 am (9 hours)

    *** Leq Equivalent noise level

    3.5 Monitoring Plan

    All the actions envisaged during the construction and operation phase will be monitored to

    produce most satisfactory results. The regular components of monitoring and its frequency

    have been identified in the following table: The air and noise quality monitoring will be

    performed at some of the locations where baseline study will be carried out. Water quality

    of the ground and surface water sources will be monitored.

    Environmental Management cell (EMC) constituted by the contractor will be the prime

    agency for monitoring all activities during both phases. PWD will supervise all activities

    and accordingly advise the BOT contractor to control the environment of the areas where

    the shortcomings are observed. The EMC will provide all monitoring results to PWD. PWD

    will keep a record of all information and will suggest suitable measures to be adopted by

    the contractor if any aspect found to be diverting from the anticipated values/standards.

    Table No. 3.6: Components for Monitoring

    Parameter Locations Duration Frequency

    Air Quality: for SPM, CO,

    NOx, SO2.

    Yawat, Kurkumbh

    (MIDC area), Indapur.

    Mohol, Solapur (MIDC

    area)

    24 hours sampling Once in a year

    Noise Level Yawat, Kurkumbh

    (MIDC area), Indapur.

    Mohol, Solapur (MIDC

    area)

    24 hours Continuous

    sampling

    Once in a year

    Water Quality: for differentphysical chemical and

    Khadak wasala maincanal, Pond, Reservoir

    Grab Sampling Once in a year

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 41 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    42/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Parameter Locations Duration Frequency

    biological parameters of Earthen Dam (Malad

    tank), Tube well,

    Reservoir (Ujani dam

    Bhimnagar), Bhimariver, Sina river

    Roadside Plantation

    Maintenance

    All along the highway

    stretch

    Regular Regularly

    throughout the year

    3.6 Mitigation Measures

    Environmental mitigation measures have been incorporated within the design process

    including the avoidance of the potential impacts through alignment sheets and other

    means. The appropriate measures have also been identified for action in construction and

    operational phases. The measures identified for all three phases, are tabulated in table

    ------which identifies the nature of potential environmental impact, which have or will be

    taken, the time frame in which they are taken, the implementing agency and responsible

    organisation and where appropriate, the contractual clause for enforcement of the

    measure.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 42 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    43/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    Table 3.7 Implementation Schedule with Responsible/Supervising Organization/Authority

    CONSTRUCTION PHASE

    SL.

    NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN

    RESPONSIBLE/

    SUPERVISING ORGANISATION/

    AUTHORITY

    1. Preparation of feasible landacquisition plan

    Initiate and complete the process for land acquisition.Prepare & administer land use control measures.

    Contractor in consultation with thestate revenue department.

    2. Utilities Initiate and complete the process of shifting the utilities. Contractor in consultation with the State

    Electricity Department and TelecomDepartment.

    3. Reduction of Forest Cover Initiate & complete the process for compensatory a forestation. Contractor in consultation with StateForest Department.

    4. Road Side Tree Plantation Select species and prepare location plan for roadside tree plantation. TheDetailed Methodology for implementation are as follows:

    Contractor in consultation with ForestDepartment.

    Permission from Forest Department & District Collector for felling ofscheduled trees

    Prepare action plan for fresh plantation with Forest Department

    Budget allocation

    Implement action plan

    5. Borrow pits and quarry sitesdevelopment

    Firm up contract with the Mining department for obtaining the quarrymaterials & identification of borrow pits along the whole stretch with the

    help of PWD and discussion with the concerned landowners.

    Contractor.

    Restoring of the borrow pits to its initial form by LandscapingTechniques.

    6. Site for storage andconstruction camp

    Finalize the detailed road design & select sites for construction camp. Contractor.

    7. Sewerage disposal and solidwaste at worker colonies

    Install lavatory at Construction Workers Colonies

    Collection of domestic refuse and its suitable disposalContractor.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 43 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    44/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    SL.

    NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN

    RESPONSIBLE/

    SUPERVISING ORGANISATION/

    AUTHORITY

    8. Traffic management Secure assistance from local police for traffic control during construction phase.Safety measures will also be undertaken by installing road sign and markingsfor safe and smooth movement of traffic

    9. Noise Level Stationary equipments will be placed as far as possible frominhabited areas to minimize objectionable noise impacts

    Provision of mufflers for stone crushing plants Proper maintenance of machinery and vehicles

    Construction activities strictly prohibit ting between 10 pm and 6 pmnear habitations

    Provision of using ear plugs by workers exposing high noise level

    Contractor in consultation withMaharashtra state Pollution Control

    Board (MPCB)

    10. Air Quality Vehicles and machineries will be regularly maintained so thatemission conform to National and State Standards

    Vehicles carrying construction material will be covered by traps toavoid spilling.

    Asphalt mixing site will be over 500 m away from any communities indown wind direction. Mixing equipment will be seated and beequipped with dust removal device (e.g. wet separators)

    Contractor in consultation with

    MPCB

    Water sprinkling will be carried out in morning and evening hours ofday at construction yard and unpaved sections of the road

    Operators will use masks and ear plugs Speedy disposal of construction debris disposal sites.

    11. Soil Erosion In slopes and other suitable places along the roadside trees and grassshould be planted

    Contractor. /EMC

    12. Loss of Top soil 15 cm of topsoil should be conserved and refilled after excavation isover to minimize the impact on productive land.

    Contractor/EMC

    13. Compaction of Soil Vehicles should operate within the COI on other side of centre line or on the side of widening) to avoid damage to vegetation.

    Contractor/EMC

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 44 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    45/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    SL.

    NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN

    RESPONSIBLE/

    SUPERVISING ORGANISATION/

    AUTHORITY

    14. Floods Bridges and culverts have been designed for the purpose of flooddischarge (100 years flood frequency for big bridges and 50 year floodfrequency for medium bridges and culvert)

    Consultant/EMC/PWD, Maharashtra

    15. Alteration of drainage In all sections where water courses cross the road, earth and stone willbe properly disposed of so as not to block river streams and naturaldrainage

    Contractor/PWD, Maharashtra /EMC

    16. Siltation Construction materials containing fine particles should be stored inclosed enclosures such that sediment laden water does not drain intonearby water courses

    Contractor

    17 Water logging and stagnation ofwater in borrow pits

    Uncontrolled digging of borrow pits will be avoided to prevent wateraccumulation which induces breeding of insects like mosquitoes whichin turn can become a health hazard.

    Control breeding of mosquito larvas by spraying of insecticides onstagnant pool of water.

    Contractor as a partOf the supervision works inConsultation with the StateHealth and Family WelfareDepartment.

    18. Occupational Health and Safety Laborers and Workers will be equipped with proper safety gearslike helmets, gloves and visors etc.

    Contractor.

    19. Basic amenities and sanitaryfacilities for constructionlaborers

    Proper and adequate camp sites will be constructed and sanitaryfacilities will be provided to the workers for avoiding any health relatedproblems.

    Contractor in

    Consultation with Public Health

    Department and Public Works

    Department (PWD).

    Regular inspection about the adequacy of facilities and periodic heathcheckups will be done.

    20 Fuel for Construction labourers Adequate supply of fuel in the form of Kerosene stove and coal will be providedto the construction labourers to avoid felling of trees for cooking and otherhousehold activities.

    Contractor.

    Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 45 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects

  • 8/7/2019 Annexure IB (EMP)

    46/75

    Package-I Draft Detailed Project Report Vol-IV B EMP Report

    SL.

    NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN

    RESPONSIBLE/

    SUPERVISING ORGANISATION/

    AUTHORITY

    21. Maintenance of embankment toprevent erosion scouring andinstability due to adverseweather conditions

    Stabilizing the embankment with ripraps, pitching and other appropriatetechnologies to prevent scouring.

    Contractor in

    Consultation with Public

    Works Department.

    22. Drainage System Development of existing drainage