Upload
sabul1276
View
216
Download
0
Embed Size (px)
Citation preview
8/7/2019 Annexure IB (EMP)
1/75
Package-I Detailed Project Report Vol-IV B EMP Report
CONTENTS
1.0 Introduction ..........................................................................................................51.1 The Project .......................................................................................................................5
1.2 Project Components .........................................................................................................5
1.3 Objective ..........................................................................................................................51.4 Environmental Management Components ....................................................................... 6
1.5 Structure of Report ...........................................................................................................6
2.0 Environmental Mitigation Plan (EMP) ..............................................................7Table 2.1: Environmental Issues, Reason / Source of Pollution and MitigationMeasures .....................................................................................................................7Table 2.2: ACTION SHEET 1 ................................................................................... 28Table 2.4: ACTION SHEET 3 ................................................................................... 30Table 2.5: ACTION SHEET 4 ................................................................................... 31Table 2.6: ACTION SHEET 5 ................................................................................... 313.0 Monitoring & Reporting ................................................................................... 33
3.1 Monitoring ..................................................................................................................... 333.2 Performance Indicators ..................................................................................................33
3.3 Responsibilities for Monitoring .....................................................................................333.4 Routine Monitoring ........................................................................................................34
Site Selection ...................................................................................................................34
Methodology ....................................................................................................................34
Table 3.1: Testing of Environmental Parameters and Standard Protocol.......343.4.1 Ambient air Quality Monitoring (AAQM) .............................................................34
Table 3.2: National Ambient Air Quality Standards (NAAQS) ........................... 35Table 3.3: Primary Water Quality Standards ........................................................ 36Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991 ......38
Table 3.5: National Ambient Noise Quality Standards ....................................... 413.5 Monitoring Plan .............................................................................................................41
Table No. 3.6: Components for Monitoring ........................................................413.6 Mitigation Measures ...................................................................................................... 42
Table 3.7 Implementation Schedule with Responsible/SupervisingOrganization/Authority ............................................................................................43
3.7 Reporting ........................................................................................................................51
3.7.1 Reporting Arrangement ..........................................................................................51
3.7.2 Recording of Data ...................................................................................................513.7.3 Record keeping ....................................................................................................... 51
4.0 Arboriculture & Landscaping ......................................................................... 53
4.1 General ...........................................................................................................................534.2 Objective ........................................................................................................................53
Selection of Plant Species ....................................................................................................54
Types of Trees / Species ...................................................................................................... 55Table - 4.1: Species Proposed for Plantation ...................................................... 55
Methodology ........................................................................................................................56
Landscaping .........................................................................................................................56
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 1 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
2/75
Package-I Detailed Project Report Vol-IV B EMP Report
4.6.1 Design for plantation of Trees ............................................................................... 56
Table 4.2: List of shrubs proposed for plantation .............................................. 585.0 Environmental Enhancement Plan .................................................................. 61
General .................................................................................................................................61
Criteria for Selection ............................................................................................................61
Design Concepts Overview ...............................................................................................62Elements for Enhancement ................................................................................................. 62
Landscaping .....................................................................................................................62
Water Bodies ...................................................................................................................63Noise Barriers .................................................................................................................. 63
Cultural Properties ...........................................................................................................65
Community Resources .....................................................................................................66
6.0 Budgets for EMP ................................................................................................ 67Institutional Arrangement .......................................................................................70
General .................................................................................................................................70
Environmental Management System (EMS) ....................................................................... 70
Duties of various Organizations in the EMS ....................................................................... 70Awareness & Training .........................................................................................................72
7.4.1 Awareness ...............................................................................................................727.4.2 Training ...................................................................................................................72
Table 7.1: Proposed Training Modules .................................................................73
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 2 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
3/75
Package-I Detailed Project Report Vol-IV B EMP Report
List of Tables
1.0 Introduction ..........................................................................................................51.1 The Project .......................................................................................................................5
1.2 Project Components .........................................................................................................5
1.3 Objective ..........................................................................................................................51.4 Environmental Management Components ....................................................................... 6
1.5 Structure of Report ...........................................................................................................6
2.0 Environmental Mitigation Plan (EMP) ..............................................................7Table 2.1: Environmental Issues, Reason / Source of Pollution and MitigationMeasures .....................................................................................................................7Table 2.2: ACTION SHEET 1 ................................................................................... 28Table 2.4: ACTION SHEET 3 ................................................................................... 30Table 2.5: ACTION SHEET 4 ................................................................................... 31Table 2.6: ACTION SHEET 5 ................................................................................... 313.0 Monitoring & Reporting ................................................................................... 33
3.1 Monitoring ..................................................................................................................... 333.2 Performance Indicators ..................................................................................................33
3.3 Responsibilities for Monitoring .....................................................................................333.4 Routine Monitoring ........................................................................................................34
Site Selection ...................................................................................................................34
Methodology ....................................................................................................................34
Table 3.1: Testing of Environmental Parameters and Standard Protocol.......343.4.1 Ambient air Quality Monitoring (AAQM) .............................................................34
Table 3.2: National Ambient Air Quality Standards (NAAQS) ........................... 35Table 3.3: Primary Water Quality Standards ........................................................ 36Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991 ......38
Table 3.5: National Ambient Noise Quality Standards ....................................... 413.5 Monitoring Plan .............................................................................................................41Table No. 3.6: Components for Monitoring ........................................................41
3.6 Mitigation Measures ...................................................................................................... 42
Table 3.7 Implementation Schedule with Responsible/SupervisingOrganization/Authority ............................................................................................43
3.7 Reporting ........................................................................................................................51
3.7.1 Reporting Arrangement ..........................................................................................51
3.7.2 Recording of Data ...................................................................................................513.7.3 Record keeping ....................................................................................................... 51
4.0 Arboriculture & Landscaping ......................................................................... 534.1 General ...........................................................................................................................534.2 Objective ........................................................................................................................53
Selection of Plant Species ....................................................................................................54
Types of Trees / Species ...................................................................................................... 55
Table - 4.1: Species Proposed for Plantation ...................................................... 55Methodology ........................................................................................................................56
Landscaping .........................................................................................................................56
4.6.1 Design for plantation of Trees ............................................................................... 56
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 3 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
4/75
Package-I Detailed Project Report Vol-IV B EMP Report
Table 4.2: List of shrubs proposed for plantation .............................................. 585.0 Environmental Enhancement Plan .................................................................. 61
General .................................................................................................................................61Criteria for Selection ............................................................................................................61
Design Concepts Overview ...............................................................................................62
Elements for Enhancement ................................................................................................. 62Landscaping .....................................................................................................................62
Water Bodies ...................................................................................................................63
Noise Barriers .................................................................................................................. 63Cultural Properties ...........................................................................................................65
Community Resources .....................................................................................................66
6.0 Budgets for EMP ................................................................................................ 67Institutional Arrangement .......................................................................................70
General .................................................................................................................................70
Environmental Management System (EMS) ....................................................................... 70
Duties of various Organizations in the EMS ....................................................................... 70
Awareness & Training .........................................................................................................727.4.1 Awareness ...............................................................................................................72
7.4.2 Training ...................................................................................................................72
Table 7.1: Proposed Training Modules .................................................................73
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 4 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
5/75
Package-I Detailed Project Report Vol-IV B EMP Report
1.0 Introduction
1.1 The Project
Ministry of Shipping Road Transport and Highways (MoSRT&H), Government of India hasdecided to take up the development of various National Highways where the intensity of
traffic has increased or likely to increase significantly. There is a requirement of
augmentation of capacity for safe and efficient movement of traffic. One of such corridors of
significance is North-East corridor connecting Pune to Solapur. National Highways Authority
of India (NHAI) has been entrusted to implement the development of this corridor.
Environmental Management Plan sets out the environmental management procedures
during design, construction and operation phase, including mitigation & enhancement
measures, institutional and monitoring requirements. This EMP also provides the guidelinesand instructions to be followed by the PIU (PWD) for effective implementation of the project.
The proposed project involves rehabilitation, strengthening and widening to 4-lane dual
carriageway of North - East corridor of the National Highway in the States of Maharashtra
which includes NH-9 from Pune (PWD km 40/000) to PWD km 144/400. The project consists
of a Feasibility Study and Detailed Design for preparation of a Detailed Project Report
(DPR). The major towns along the project road include Tembhurni & Indapur.
1.2 Project ComponentsThe various activities / components involved in the project include design process and
construction activities. Some of the major activities likely to take place to implement the
proposed up-gradation / improvement project are: Site clearing & grubbing, Earthwork,
Pavement removal, Granular sub-base, Water bound macadam sub-base / base,
Bituminous pavement layers, pavement widening, Drainage, Safety measures, Bridge &
Culvert improvement, Waste material management, Equipment staging & materials,
Aggregate and sand quarries etc. These major activities have been taken into account while
finalizing the methodology for the impact assessment of the project.
1.3 ObjectiveEnvironmental management plan (EMP) has been recommended by considering broad
aspects, which includes
Suitable measures to be taken in light of specific project issues,
Implementation & supervision through competent agencies for EMP,
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 5 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
6/75
Package-I Detailed Project Report Vol-IV B EMP Report
Schedule for implementing these actions,
Reference to contract documents and specifications,
Project level environmental monitoring,
Environmental status reporting frequency, and
Institutional arrangement, strengthening of their capability, and role.
1.4 Environmental Management Components
The various components which are considered for the environmental management aspects
and to be included in the environmental management plan, broadly consists of
environmental mitigation aspects, environmental performance indicators to be monitored
and reporting system, environmental enhancement measures, arboriculture and landscaping
aspects, financial aspects required for the effective implementation of the environmental
management Plan and Institutional Strengthening and training of the project implementationunit. These are discussed in the report herein.
1.5 Structure of ReportThe structure of the report for Environmental Management Plan is as organised as
follows:
Chapter 1 - Introduction
Chapter 2 - Environmental Management Plan
Chapter 3 - Monitoring & Reporting Plan
Chapter 4 - Arboriculture & Landscaping
Chapter 5 - Environmental Enhancement Plan
Chapter 6 - Environmental Budget
Chapter 7 - Institutional Arrangement
This Environmental Management Plan (EMP) is a part of the environmental impact
assessment report, as per corrigendum issued with the TOR.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 6 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
7/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
2.0 Environmental Mitigation Plan (EMP)
Table 2.1 below shows the typical environmental mitigation matrix prepared for the proposed project. This includes the project specific
environmental issues, corresponding remedial measures, its reference to contract document / MoRTH specification, location of the
measures to be applied, cost of the mitigation measures and responsibility for implementing the typical mitigation measures.
Table 2.1: Environmental Issues, Reason / Source of Pollution and Mitigation Measures
Environmental
IssueRemedial Measures
Reference to
Contract
Documents
LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Design / Pre-Construction Stage
1. Alignment
Critical
sections /
settlements
Provision of large / deep roadside
drains
Road widening
Improvement of Intersections /
Junctions
Providing bypasses at Indapur,
Tembhurni & Mohol where settlement is
high.
RAP
requirements
Road sections
with service
roads,
Locations of
thick
settlements
Project
preparation
cost
Design
Consultant
PIU
2. Land
Landacquisition
Acquisition of land is minimized to
the maximum extent
Land shall be acquires as per the
Government Land Acquisition Policy,
applicable
To avoid impact of land outside
Land AcquisitionPolicy of NHAI,
Land Acquisition
Act
MoRTH 201.2
All along theroad where
alignment has
been modified.
Projectpreparation
cost
DesignConsultant
PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 7 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
8/75
8/7/2019 Annexure IB (EMP)
9/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Control Board shall be obtained.
Adequacy of measures shall be checked
to control air pollution.
MoRTH 111
plant and
construction
machinery
preparation
cost
Consultant, PIU,
(PWD)
Noise Level NOC from concerned State Pollution
Control Board shall be obtained
Improved traffic speeds and riding
conditions shall reduce noise levels
Noise screening by trees plantation
scheme proposed as noise barriers
Provided noise attenuation at critical
locations like Hospital, school etc.
MoRTH 111
For hot mix
plant and
construction
machinery
At sensitive
receptors.
Project
preparation
cost
Design
Consultant,
PIU,
PWD,
Departm
ent of
Environ
ment &
Forests
6. Utilities
Relocation of
utility lines /
community
utilities.
Affected utilities like electric poles, water
pipe lines, hand pumps, etc. shall be
relocated with prior approval of the
concerned agencies
All the R&R activities shall be reasonably
completed as per RAP
All the cultural properties that have been
identified as affected shall be relocated
as per resettlement plan
MoRTH 110
As per R&R
plan prepared
separately
Project
preparation
cost
All concerned
state
Government
Departments,
PIU
PIU
7. Environmental Safety
Accidents Design improvements to road geometry
Provision of adequate sight distance at
MoRTH 112 All along the
project road
Project
preparation
Design
Consultant
PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 9 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
10/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
curves and road junctions
Provision of adequate set back distance.
Provision of proper signage at sensitive
receptor locations such as schools,
hospitals and at known accident spots
especially at
settlements,
and locations of
bad geometry
cost
Traffic
Control
System
Temporary traffic arrangement during
construction shall be planned in DPR.
The contractor shall take all necessary
measures for the traffic during demolition
and site clearing activities.
MoRTH 112
All along the
project road
and locations of
settlements
Project
preparation
cost
Pedestrian
Safety
Special considerations shall be given
in the local traffic management to the
pedestrian safety Especially at
congested locations bed
MoRTH 112.2
At congested
locations
Construction Stage
1. Soil
Soil Erosion Soil Stabilization measures by
immediate grassing and vegetation of
embankments to control soil erosion,
sedimentation and water pollution.
Stone / PVC pitching, gabions near
banks of water bodies as well as at high
cut areas
Provision of berms at high
MoRTH 306 At identified
locations,
embankment
along water
courses, high
cut locations
Engineering Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 10 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
11/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
embankments.
Soil
contaminatio
n by
construction
waste, fuel
etc.
Oil & fuel spills from construction
equipments shall be controlled by good
O&M practices
Contaminated soil shall be disposed
of as per MoEF guidelines
Project
requirements
At construction
camps and at
waste disposal
sites
Borrow pits Borrow areas shall be levelled
properly after use.
MoRTH 111.3,
Guidelines
given in
EMP
At identified
locations
Engineering Contractor PIU
Uses of
Excavated
Material other
than borrow
pits
Excavated material shall be used for
as a fill material in the embankments
wherever possibleProject
requirement
At identified
locations
Engineering Contractor PIU
Disposal of
Excavated
Material
Surplus material still remaining from
the above shall be deposited at the
selected locations and as approved by
PWD, or if possible it shall be used in
rehabilitation of quarries
MoRTH 301.3
At identified
locations
Engineering Contractor PIU
Transport of
Excavated
Earth / debris
The village roads used for the haulage of
excavated earth shall be maintained to
their original condition upon completion
MoRTH 111.9
MoRTH 301.3
Throughout
project corridor
Engineering Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 11 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
12/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
of work. PIU may use the services of SC
to monitor and report.
Precautionary measures like covering of
vehicles shall be taken to avoid spillage
and to reduce dust nuisance duringtransport of materials.
Quarries The Quarry material shall be procured
only from licensed quarries operating
under environmental clearances,
including transportation of quarry
material clearances under the Air Act
Safety precautions shall be ensured
during transportation of quarry material
from quarries to the construction sites
Stockpiling of material shall be properly
planned so as to ensure smooth traffic
flow on the highway
MoRTH 111.3
Known quarry
locations listed
Throughout
project corridor
Engineering
cost
Contractor PIU
Sand & Clay During transportation trucks shall be
covered to prevent dust nuisanceMoRTH 111.3
Throughout
project corridor
Environment
al cost
Contractor PIU
Contaminatio
n of soil from
fuel and
lubricants
Soak pits along with oil and grease
traps shall be provided around fuel
storage areasMoRTH 111
Construction
camps
Environment
al cost
Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 12 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
13/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
2. Water
Water Bodies Impact on surface watercourses
(rivers and ponds) would be minimized
throughout by control over construction
works as per guidelines
MoRTH 305
Bridge
locations along
the project road
Engineering
cost
Contractor
Other Water
Sources
Community water sources shall not
be used during construction period. Projectrequirements
Locations
identified along
project corridor
Engineering
cost
Contractor PIU
Drainage and
run-off
At cross drainage structures, the
earth, stone or any other obstructing
construction material shall be removed
and properly disposed of so as not to
block the flow of water at any time
Construction material shall not be
stored so as to block the drainage
system, if happens, contractor should
ensure that they are cleaned especially
during monsoon period.
Roadside drains have been
proposed all along the project road to
improve drainage. Contractor shall clear
off the drains before opening the road to
traffic.
MoRTH 306
MoRTH 309
Throughout
project corridor
Engineering
cost
Contractor PIU
Contaminatio Construction and sitting of plant & MoRTH 305 At construction Engineering Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 13 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
14/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
n of water
from
construction
waste
machinery close to the streams and
water bodies shall be avoided, especially
during monsoon period.
Soak pits shall be provided at
construction site to prevent wastewater
from entering into rivers and streamsespecially during pile driving across
major rivers
All waste arising from the project shall be
disposed off as per SPCB norms, so as
not to block the flow of and contaminate
water
Waste must be collected, stored and
transported to approve disposal sites.
Projectrequirement
Guidelines given
in EMP
camps,
locations of
water bodies,
cost
Environment
al cost
Contaminatio
n of water
from fuel and
lubricants
To avoid contamination from fuel and
lubricants, the vehicle and equipments
shall be properly maintained and
refuelled
Vehicle maintenance and refuelling in
construction camps should be confined
to areas with traps oil / grease to prevent
wastewater from entering into rivers and
streams
Project
requirement
At construction
camp locations,
wherever
located along
the Project
corridor.
Engineering
cost
Environment
al cost
Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 14 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
15/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Sanitation
and waste
disposal in
construction
camps
The construction camps shall be located
away from habitations (at least 500 m),
at identified sites.
The sewerage system for such camps
shall be properly designed and built sothat no water pollution of any stream or
watercourses takes place.
The workplace should have proper
medical approval by local medical,
health or municipal authorities.
MoRTH
105.2
Guidelines given
in EMP
At construction
camp locations,
wherever
located along
the Project
Corridor.
Engineering
cost
Environment
al cost
Contractor PIU
Use of water
for
construction
The contractor shall make independent
arrangements for water required for
construction in such a way that the water
availability and supply to nearby
communities remain unaffected.
Wastage of water during construction
shall be minimized and properly
controlled.
Project
requirement
Throughout the
project corridor
Engineering
cost
Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 15 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
16/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
3. Air
Emission
from
construction
vehicles and
machinery
All vehicles, equipments and machinery
used for construction shall be regularly
maintained to ensure that the pollution
emission levels conform to the SPCB
norms.
The asphalt plants, crushers and the
batching plants shall be sited at least
500 m in the downwind direction from the
nearest settlement.
Regular monitoring of Air shall be
conducted as described in
Environmental Monitoring Plan.
Action sheet no. 2 given in Table 2.3
shall be followed.
Legal
requirement
MoRTH
111.5
Throughout the
project corridor
Engineering
cost
Environment
al cost
Contractor PIU
Dust and
Nuisance
Existing hot mix / concrete / asphalt
plants shall be used to the extent
possible,
In case of new hot-mix plants, crushers
and batching plants, these shall be sited
at least 500 m downwind from the
nearest habitation and covered with dust
MoRTH
111.5
Throughout the
project corridor
Engineering
cost
Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 16 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
17/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
trapping hoods.
Water shall be sprayed at mixing sites,
earth mixing sites and asphalt mixing
sites and on temporary access roads
and diversions.Action sheet 1 given in Table 2.2 shall be
followed.
Vehicle delivering material shall be
covered. End boards in loaders shall be
provided to prevent spillage.
In case of unpaved roads used by
contractor, it shall be watered regularly
at least once in day to control fugitive
dust nuisance.
MoRTH
111.8
MoRTH
111.9
MoRTH
111.10
Environment
al cost
Environment
al cost
Environment
al cost
4. Noise Levels
Noise from
vehicle,
asphalt
plants and
equipments
The plants and equipment used for
construction shall be strictly conforming
to CPCB noise standard.
Properly sizing and maintaining mufflers,
engine intake silencers, engine
enclosures, turning of idle equipment,
shall be filtered with silencers.
Legal
requirement
Throughout the
project corridor
Engineering
cost
Contractor PIU
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 17 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
18/75
8/7/2019 Annexure IB (EMP)
19/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Noise
barrier /
buffer
plantations
Construction of noise barrier in the
form of buffer plantation and vegetation
at sensitive receptors.
Along sensitive
locations in the
road corridor
Environment
al cost
Contractor PIU
5. Flora
Loss or
damage to
vegetation
Trees lost shall be replaced just
before the beginning of the construction
according to Compensatory A forestation
Policy of State Forestry Department at
the rate of two new trees for each tree
lost.
The local tree authority shall do
transplantation of the tree according to
the site conditions as applicable. The
contractor shall contact the tree authority
to carry out compensatory a forestation
as well as transplantation of trees.
Legal
requirement
As per
technical
specification
s supplied
with EMP
Throughout
project
Corridor
Environm
ental cost
Department
of
Environment
and Forest,
PIU (PWD)
SC, PIU,
PWD
Compaction
of Vegetation
All construction vehicle movement
and parking locations shall be such as to
prevent damage to roadside vegetation
Project
requirement
Throughout
Project
Corridor
Engineeri
ng cost
Contractor,
Supervision
Consultant
SC, PIU,
PWD
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 19 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
20/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Damage to
trees /
vegetation by
workers
Contractor to ensure prevention of
damage to vegetation and trees and
their use by workers. Contractor shall
supply kerosene for all needs during
construct ion, to prevent use of
vegetation and trees for fuel
Adequate landscaping of median,
embankment slopes and other open
space available within ROW shall be
carried out as suggested in Arboriculture
and Landscaping Plan and as per
specification given.
Project
requirement
As per
specification
provided
Throughout
Project
Corridor
Environm
ental cost
Environm
ental cost
Contractor,
Supervision
Consultant
SC, PIU,
PWD
Departm
ent of
Environ
mentand
Forest
6. Fauna
Loss, injury
or disruption
to fauna
Construction workers shall be
directed not to poach upon fauna.
Hunting shall be strictly prohibited.
Contractor shall take all necessary
measures to protect wildlife during
construction in forest areas.
Necessary signage, controlled /
timely construction activities shall reduce
disturbance to wildlife.
Project
requirement
Throughout
Project
Corridor
and
especially
at
settlement
and at
forest area
Environm
ental cost
Contractor,
Supervision
Consultant
PIU,
PWD,
Departm
ent of
Environ
ment
and
Forest
7. Safety and Accidents
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 20 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
21/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Accident
risks from
construction
activities.
To ensure safety of the temporary
accesses during construction, safety
devices shall be installed.
Traffic rules and regulation shall be
strictly adhered to local laws.
Workers undertaking various operations
during construction shall be protected by
providing helmets, masks, safety
goggles, hand gloves and rubber boots
etc.
First aid kits shall be provided at
construction site for workers to meet
minor accidents during construction
MoRTH
105.2
Throughout
Project
Corridor
Engineeri
ng cost
Environmental cost
Contractor,
Supervision
Consultant
PIU,
PWD,
Departm
ent of
Health
andFamily
Welfare
Health Issue At every workplace, good and sufficient
water supply shall be maintained to
avoid waterborne / water-related / water-
based diseases to ensure the health and
hygiene of workers.
Adequate drainage, septic tanks, soak
pits and wastewater disposal shall be
provided at workplace.
Preventive Medical care shall be
provided to workers.
MoRTH
105.2
Project
requirement
Throughout
Project
Corridor
and
particularly
at workers
camps
Engineeri
ng cost
Environm
ental cost
Contractor,
Supervision
Consultant
SC, PIU,
PWD,
Departm
ent of
Health
and
Family
Welfare
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 21 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
22/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Action sheet no 4 given in Table 2.5 shall
be followed.
Movement of
Existing
Traffic
Traffic management shall be effected
through
Gate system
Diversion along existing alternative
routes
Proper signage
Project
requirement
Near
temporary
work sites
Engineeri
ng costs
Contractor,
Supervision
Consultant
SC, PIU,
PWD
8. Roadside Trees
Road Side
Trees
Compensatory planting at the rate of
two trees for every tree to be cut shall be
carried out,
As per
specification
s provided
Along
roadside
vacant
lands and
Forest
Departmen
ts land
Environm
ental cost
Contractor,
Supervision
Consultant,
Village
Councils,
PIU (PWD),
Department
of
Environment
& Forests.
SC, PIU,
PWD,
Departm
ent of
Environ
ment &
Forest
9. Environmental Enhancement
Roadside
landscape
development
Roadside plantation and grassing
measures shall be done to improve
aesthetics as per the arboriculture and
landscaping plan developed
As per
specification
s provided
Throughout
Project
Corridor
Environm
ental cost
Contractor,
Supervision
Consultant,
Department
PIU,
PWD,
Departm
ent of
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 22 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
23/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Action sheet no. 5 given in Table 2.6 shall
be followed.
of
Environment
& Forest
Environ
ment &
Forest
Roadside
amenities
Enhancement of road side temples, trees
and market places very near to road
shall be done as per the instructions of
the supervision consultant.
Provision of bus shelters, bus bays and
rest places as per standard design shall
be carried out.
Road furniture including marker posts,
crash barriers, traffic signs, speed zone
signs, rumbling strips etc. shall be
constructed and erected as per design.
Ponds and water bodies along the road
& near to communality places shall be
enhanced.
Project
requirement
Throughout
Project
Corridor
and at
selected
sites
Environm
ental cost
Engineeri
ng cost
Environm
ental cost
Contractor,
Supervision
Consultant
SC, PIU,
PWD
Community
Properties
Community properties, located away
from the project road should not be
disturbed by construction activity;
workers camp and contractors work
area.
Project
requirement
Throughout
Project
Corridor
Engineeri
ng cost
Contractor,
Supervision
Consultant
SC, PIU,
PWD
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 23 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
24/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Environment
al Awareness
Environmental Awareness Campaigns
shall be conducted in the project area
during construction period to ensure the
applicability of the various environmental
laws
Project
requirement
At
settlements
in project
area
Environm
ental cost
PIU( PWD) PWD
Operation Stage
Contaminatio
n from
accidental
spills
The spills at the accident sites shall be
cleared immediately
The left over spills shall be scraped and
carried to small lined confined pits at
identified sites.
Project R
Requirement
Throughout
Project
Corridor
PWD to
ensure
this
(reoccurri
ng cost)
Local Govt.
Bodies State
PWD and
State
Pollution
Control
Board.
PIU,
SPCB
Dust
Generation
Roadside tree plantations shall be
maintained.
Dust generated and deposited shall
be cleaned regularly.
Project
requirement
Throughout
Project
Corridor
Environm
ental
cost
(reoccurri
ng cost)
Department
of
Environment
& Forest,
PWD
PIU,
Departm
ent
of
Environ
ment &Forest
Air Pollution Vehicle emission of critical pollutant
parameters (SPM, CO, SO2 and NO2)
shall be monitored as per monitoring
plan
Legal
requirement
At selected
locations
Throughout
Environm
ental cost
(reoccurri
ng cost)
Motor
vehicle
department,
and SPCB,
PIU,
SPCB
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 24 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
25/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Environmental
IssueRemedial Measures
Reference to
Contract LocationMitigation
Cost
Institutional
Responsibility
Implementation Supervision
Vehicle emission norms shall be
enforced
Roadside tree plantation shall be
protected and maintained
Project
requirement
Project
corridor
PWD
Noise
Pollution
Noise pollution shall be monitored
Adequate no-horn sign boards shallbe installed at sensitive / critical
locations
Legal
requirement,
Projectrequirement
At selected
locations
Environm
ental cost
(reoccurri
ng cost)
Motor
vehicle
department,
and SPCB,
PWD
PIU,
SPCB
Water The roadside drainage system shall be
periodically cleared of blockage
Water quality shall be monitored as per
plan
Charecteristics of water used for
construction should satisfy the standards
given by CPCB.
Project
requirement
Throughout
project
road
At selected
locations
By PWD
(Reoccur
ring cost)
PWD and
SPCB
PIU,
SPCB
Flora and
Fauna
Adequate care of the compensatory
plantation should be taken up to comply
success of the replantation scheme shall
be monitored
If survival rate is below 70 %,
replantation shall be done as required
Project
requirement
Throughout
Project
corridor
Included
in
compens
atory
plantatio
n cost
Department
of
Environment
& Forest,
PWD
PIU,
Departm
ent
of
Environ
ment &
Forest
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 25 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
26/75
8/7/2019 Annexure IB (EMP)
27/75
8/7/2019 Annexure IB (EMP)
28/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 2.2: ACTION SHEET 1
Environmental
Attribute
Air Emissions (Dust/particulate)/Disposal of Construction
Debris.
Issue Increased dust levels adjacent to haul roads and construction
yards. Uncollected construction debris.
Mitigation
measure
Sprinkling of water once a day along the haul routes to project
road, passing through residential area and at the construction
yard.
Methodology
for
implementation
Water tankers should be deployed by the contractor through
out the winter and summer months and during dry spells in
monsoon months to water at construction yard and those
sections of road which shall carry the construction materialthrough the residential areas. Water sprinkling should be
carried out in the morning hours every day.
Water from the pond in villages will not be used without the
consent of the village community.
The uncollected construction debris can also contribute to
fugitive dust and insanitary conditions. Daily inspection at haulroutes and construction sites should be conducted to ensure
speedy disposal of construction debris to landfill sites. Nearby
borrow pits may be used for disposal of debris or areas which
may need a noise barrier may utilise the debris to create a
hump.
Implementing
Agency
Contractor / sub-contractor
Monitoring
Agency
The Engineer
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 28 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
29/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 2.3: ACTION SHEET 2
Environmental
Attribute
Air Pollution from Construction Yard Activities (NO2 Levels
During Construction)
Issue Increased exposure to air pollutants near main construction
yards in downwind directions during winter.Mitigation
measures
Construction yard should not be located within 500m of the
major villages.
Methodology
for
implementation
Contract conditions on placement of major construction yards.
Implementing
Agency
Contractor
Monitoring
Agency
The Engineer
Legal
Instrument
The above restrictions on placement of construction yards
should be intimated to the bidder while inviting the bids.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 29 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
30/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 2.4: ACTION SHEET 3
Environmental
Attribute
Noise Pollution
Issue Increased Noise levels during day and night time in the
residential areas adjacent to the construction yard.Mitigation
measures
Siting of construction yards more than 100 m away from any
residential areas;
Methodology
for
implementation
Select construction yards sites leaving adequate distance to
allow noise to attenuate.
For the protection of construction workers, ear plugs should be
provided to those working near the noisy machinery.
Implementing
Agency
Contractor
Monitoring
Agency
The Engineer
Legal
Instrument
The above activity (provision of enclosures) should form a part
of the contract agreement. This will facilitate the contractor to
take into account the cost of above measures while bidding for
the contract.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 30 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
31/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 2.5: ACTION SHEET 4
Environmental
Attribute
Sanitation at Construction Workers Colony
Issue Adequate sanitation facilities and Hygiene at constructionworkers colony.
Mitigation
measures
Provision of water supply and toilet facilities at construction
workers colony as per the stipulated guidelines in Indian Labour
Act along with provisions of septic tanks and refuse composting
facility.
Methodology
for
implementation
The camp must not be located within one km of the major
villages.
The contractor should ensure adequate water supply and toilet
facility with septic tanks and mechanisms for composting of
domestic refuse at construction workers colony.
Implementing
Agency
Contractor
Monitoring
Agency
The Engineer
Legal
Instrument
The above activity should form a part of the contract
agreement. This will facilitate the contractor to take into account
the cost of above measures while bidding for the contract.
Table 2.6: ACTION SHEET 5
Environmental Landscaping along the highway
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 31 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
32/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Attribute
Issue To improve the deficient arboriculture along the corridor.
Mitigation
measures
Development and Maintenance of landscape along the
proposed highway, which acts as air pollution and noise barrier
and improves aesthetics.Methodology
for
implementation
The concerned forest department will prepare a plan for
landscaping concurrent with the road construction schedule
(with a lag of 3-4 months for preparing the ground).
Phase-wise plantation should be taken up by the forest
department. Required water should be taken from the bore-
wells or nearby surface water bodies (except village ponds,
unless consented by the community) along the highway.
Implementing
Agency
PIU
Monitoring
Agency
The Engineer
Legal
Instrument
The above activity should form a part of the overall project cost.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 32 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
33/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
3.0 Monitoring & Reporting
3.1 Monitoring
The adverse environmental impacts identified during the Environmental impact
Assessment process of the proposed project may increase further during the construction
as well as during post-construction as well as during post-construction phase. Monitoring
of environmental factors and constraints will enable agencies to identify the changes in the
environmental impacts at particular locations, application of mitigative measures and
utilisation of standard design guidelines for finalisation of alignment design. Monitoring will
also ensure that actions taken are in accordance with the construction contract and
specifications. It provides a basis for evaluating the efficiency of mitigation and
enhancement measures, and suggests further actions needed to be taken to achieve the
desired effect.
3.2 Performance Indicators
In order to evaluate the effectiveness of EMP at project level, certain physical, biological
and social components identified. These component needs to be analyzed based on
project specific conditions and data generated. The key quality components include Air
quality, Water quality, Noise Levels around sensitive locations, Plantation / re-plantation
success / survival rate, Erosion indices, Restoration of quarries and borrow areas, Quality
of human health, Accident frequency.
3.3 Responsibilities for Monitoring
The responsibility for monitoring of implementation of EMP will rest with the Environmental
management Unit (EMU). Mitigation and enhancement measures adopted in final design
will be explicitly identified under the Bill of Quantity (BOQ) so that performance and
completion is readily documented.
The PWD will visually assess the progress of Environmental management unit and the
work of Contractors. If the level of impact is determined to be high, further monitoring will
be done by a recognised A category laboratory of the concerned State pollution control
Board (SPCB) and assessed for verification of the increased or decreased emission level
and pollutants along the project road. And if found more appropriate control measures
would exercised.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 33 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
34/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
3.4 Routine Monitoring
During the construction and post construction phase, ambient air quality, water quality
(surface and Ground water), effluent if any released from construction site / camp) and
noise levels will be monitored as and when required depending upon the type, nature andduration of the project using standardised monitoring methodologies and laboratories
testing facilities / techniques.
Site Selection
Monitoring stations have been identified based on observation / site conditions such as
nature of construction, diversions, congestion, parking places, bus / taxi stands, number
and frequency of vehicles, sources of pollutants (industrial / commercial / residential),
environmental features and existence of sensitive / critical areas i.e. educationalinstitutions, hospitals, archaeological / cultural sites. The frequency and duration of
testing / sampling of air, water, noise levels and effluent quality within the ROW is to be
fixed as per allotted time frame of the project and requirements of SPCB / CPCB and
MoEF.
Methodology
Standard methodology as described in manuals, guidelines, etc. is to be followed as outlinedin Table below
Table 3.1: Testing of Environmental Parameters and Standard Protocol
Sr.
No.Parameters to be Monitored References
1 Ambient Air Quality
i. Suspended Particulate Matter
(SPM) ( g/m3)
IS: 5182 (pt-4)
ii. NOx ( g/m3) IS: 5182 (pt-6)
iii. SO2 ( g/m3) IS: 5182 (pt-2)
iv. CO (mg/m3) IS: 5182 (pt-10)
2 Water and Effluent (all parameters as per CPCB (1998)
i. Surface Water APHA 20th Edition and CPCB (1997)ii. Ground Water
iii. Effluent (if any released from
construction work site/camp)
3 Noise level IS: 3028,IS: 4758, IS: 9779, IS: 10399
3.4.1 Ambient air Quality Monitoring (AAQM)
The air quality parameters i.e. Suspended Particulate Matter (SPM), Respirable Particulate
Matter (RPM), Sulphur Dioxide (SO2), Nitrous Oxides (NOx), Carbon Monoxide (CO) and
Hydrocarbons (HC) will be regularly monitored at designated locations and analyzed in
accordance with the National Ambient Air Quality Standards given in Table 3.2. The location,
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 34 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
35/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
duration and pollution parameters to be monitored and the responsible institutional
arrangements are detailed out in Environmental Monitoring Plan
Table 3.2: National Ambient Air Quality Standards (NAAQS)
Pollutants TimeWeighted
SensitiveArea
IndustrialArea
Residential
Rural &
Other
Method ofMeasurement
Sulphur
Dioxide
(SO2)
Annual* 15 g/m3 80 g/m3 60 g/m3
Improved West
and Gaeke
method
24 hours** 30 g/m3 120 g/m3 90 g/m3Ultraviolet
fluorescence
Oxides of
Nitrogen
(NOx)
Annual 15 g/m3 80 g/m3 65 g/m3
Jacob and
Hochheiser
modified (Na-Arsenite)
24 hours** 30 g/m3 120 g/m3 91 g/m3
Gas Phase
Chemiluminesc
enceCarbon
Monoxide
(CO)
8 hours** 1000 g/m35000
g/m32000 g/m3 Non Dispersive
infrared
spectroscopy1 hour 2000 g/m3
1000
g/m34000 g/m3
Lead (Pb)
Annual* 0.50 g/m3 1.0 g/m3 0.75 g/m3 AAS Method 24
hours after
sampling using
EPM 20000 or
equivalent filter
paper
24 hours** 0.75 g/m3 1.5 g/m3 1.00 g/m3
Respirable
particulate
(RPM)-Size
less than
10 m
Annual* 50 g/m3 120 g/m3 60 g/m3
24 hours** 75 g/m3 150 g/m3 100 g/m3
Suspended
Particulate
Matter
(SPM)
Annual* 70 g/m3 360 g/m3 140 g/m3Average flow
rate not less
than 1.1 cu.m /
minute
24 hours** 100 g/m3 500 g/m3 200 g/m3
Source: Anon 1996-97, National Ambient Air Quality Monitoring Series NAQMS/a/1996-97, Central
Pollution Control Board, Delhi.
* Average Arithmetic mean of minimum 104 measurements in a year taken for a week 24 hourly at uniform interval.
** 24 hourly / 8 hourly values should meet 98 percent of the time in a year
3.4.2 Water Quality MonitoringWater quality parameters such as pH, DO, Total Dissolved Solids, Phosphate,
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 35 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
36/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Calcium, Sulphate, Chlorides, Iron etc. will be monitored at all identified locations
during construction stage as per standards prescribed by Central Pollution Control
Board and Indian Standard water specifications presented in Table 3.3 and 3.4
respectively. The location, duration and pollution parameters to be monitored and
the responsible institutional arrangements are detailed out in Environmental
Monitoring Plan (Table 3.6).
Table 3.3: Primary Water Quality Standards
Sr. No.Designated Best
Use
Class of
Water
Criteria
1 Drinking Water
source (with
conventional
treatment)
A Total Coliforms MPN/100 ml
shall be 50 or less
pH between 6.5 to 8.5
Dissolved Oxygen 6 mg / 1 or
more
Biological Oxygen demand
(BOD) 5 days 200C, 2 mg/1 or less
2 Outdoor bathing
(organized)
B Total Coliforms MPN/100 ml
shall be 500 or less
pH between 6.5 to 8.5
Dissolved Oxygen 5 mg / 1 or
more
Biological Oxygen demand
(BOD) 5 days 200C 3 mg/1 or less
3. Drinking Water
source (without
conventional
treatment)
C Total Coliforms MPN/100 ml
shall be 5000 or less
pH between 6 to 9
Dissolved Oxygen 4 mg / 1 or
more
Biological Oxygen demand
(BOD) 5 days 200C 3 mg/1 or less
4. Propagation of
Wildlife
D pH between 6.5 to 8.5 for
fisheries
Dissolved Oxygen 4 mg / 1 or
more
Free Ammonia (as N) 1.2 mg/1
or less
5. Irrigation,Industrial Cooling,
E
pH between 6.0 to 8.5 Electrical Conductivity at 250C
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 36 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
37/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Controlled Waste mhos/cm Max. 2250
Sodium absorption ratio Max. 26
Boron, Max.2 mg/1(Source: CPCB (1999). Bio mapping of rivers. Parivesh New Letter, 5 (iv), Central Pollution Control Board,
Delhi, PP.20)
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 37 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
38/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 3.4: Indian Standard Drinking Water Specifications: IS 10500:1991
Sr.
No.
Substance or
Characteristics
Requirement
(Desirable limit)
Undesirable Effect Outside the
Desirable limit
Permissible Limit in the
Absence of Alternate
Source
Remarks
Essential Characteristics
1 Colour, Hazen Units,
Max.
5 Above 5, consumer acceptance
decreases
25 Extended to 25 only if toxic
substances, in absence of
alternate sources.
2 Odour Unobjectionable - - a) A test cold and
when heated
b) Test at several
dilution
3 Taste Agreeable - - Test to be conducted only
after safety has been
established
4 Turbidity NTU, Max. 5 Above 5, consumer acceptance
decreases
10
5 pH value 6.5 to 8.5 Beyond this range the water will not effect
the mucous membrane and /or water
supply system
No relaxation
6 Total hardness (as
CaCO3) mg/1, Max.
300 Encrustation in water supply structures an
adverse effect on domestic use
600
7 Iron (as Fe) mg /l Max. 0.3 Beyond this limit taste / appearance are
affected has adverse effect on domestic
uses and water supply structures and
promotes iron bacteria
1
8 Chlorides (as Cl) mg/1
Max.
250 Beyond this limit, taste corrosion and
palatability are affected
1000
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 38 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
39/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Sr.
No.
Substance or
Characteristics
Requirement
(Desirable limit)
Undesirable Effect Outside the
Desirable limit
Permissible Limit in the
Absence of Alternate
Source
Remarks
9 Residual, free
chloride, mg/1 Min.
0.2 To be applicable only when
water is chlorinated.
Tested at consumer end.
When protection against
viral infection is required, it
should be Min. 0.5 mg/1Desirable characteristics
1 Dissolved solids mg/1
Max.
500 Beyond the palatability decreases and
may cause gastro intestinal irritation
2000
2 Calcium (as Ca) mg/1
Max.
75 Encrustation in water supply structure and
adverse effects on domestic use
200
3 Magnesium (as Mg)
mg/1, Max.
30 Encrustation in water supply structure and
adverse effects on domestic use
1.5
4 Copper (as Cu) mg/1
Max.
0.05 Beyond taste, discoloration of pipes, f it ting
and utensils will be caused beyond this
0.3
5 Sulphate (as 200
SO2), mg/1, Max.
200 Beyond this causes gastro intestinal
irritation when magnesium or sodium are
present
400 May b extended up to 400
provided ( as Mg) does not
exceed 30
6 Nitrate (as NO2) mg/l,
Max.
45 Beyond this methamoglobunemia take
place
100 To be tested when pollution
is suspected7 Fluoride (as F) mg/1,
Max.
1 Fluoride may be kept as low as possible.
High fluoride may cause fluorosis
1.5 To be tested when pollution
is suspected
8 Phenolic compounds
(as C6H5OH) mg/1,
Max.
0.001 Beyond this it may cause object ionable
taste and odour
0.002 To be tested when pollution
is suspected
9 Mercury (as Hg) mg/1, 0.001 Beyond this the water becomes toxic No relaxation To be tested when pollution
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 39 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
40/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Sr.
No.
Substance or
Characteristics
Requirement
(Desirable limit)
Undesirable Effect Outside the
Desirable limit
Permissible Limit in the
Absence of Alternate
Source
Remarks
Max. is suspected
10 Arsenic (As) mg/1,
Max.
0.05 Beyond this the water becomes toxic No relaxation To be tested when pollution
is suspected
11 Lead (as Pb), mg/1,
Max.
0.05 Beyond this the water becomes toxic No relaxation To be tested when pollution
is suspected
12 Zinc (as Zn) mg/1,
Max.
5 Beyond this limit it can cause astringent
taste and an opalescence taste and an
opalescence in water
15 To be tested when pollution
is suspected
13 Poly nuclear aromatic
hydrocarbons (as
PAH) mg/1, Max.
- May be carcinogenic above this limit - -
14 Pesticides mg/1, Max. Absent Toxic 0.001 -
15 Alpha emit
ters bq/1, Max.
- - 0.1 -
(Source: Indian Standard Drinking Water Specification IS 10500, 1994)
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 40 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
41/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
3.4.3 Noise Quality Monitoring
Ambient noise levels will be monitored at already designated locations in accordance with
ambient noise quality standards given in Table 3.5. The location, duration and noise
pollution parameters to be monitored and the responsible institutional arrangements are
detailed out in Environmental Monitoring Plan
Table 3.5: National Ambient Noise Quality Standards
Sr.
No.Area Code Category of Zone
Leq*** in dB (A)
*Day **Night
1 A Industrial 75 70
2 B Commercial 65 55
3 C Residential 55 45
4 D Silence Zone 50 40* Day Time 6.00 am 9.00 pm (15 hours)
** Night Time 9.00 pm 6.00 am (9 hours)
*** Leq Equivalent noise level
3.5 Monitoring Plan
All the actions envisaged during the construction and operation phase will be monitored to
produce most satisfactory results. The regular components of monitoring and its frequency
have been identified in the following table: The air and noise quality monitoring will be
performed at some of the locations where baseline study will be carried out. Water quality
of the ground and surface water sources will be monitored.
Environmental Management cell (EMC) constituted by the contractor will be the prime
agency for monitoring all activities during both phases. PWD will supervise all activities
and accordingly advise the BOT contractor to control the environment of the areas where
the shortcomings are observed. The EMC will provide all monitoring results to PWD. PWD
will keep a record of all information and will suggest suitable measures to be adopted by
the contractor if any aspect found to be diverting from the anticipated values/standards.
Table No. 3.6: Components for Monitoring
Parameter Locations Duration Frequency
Air Quality: for SPM, CO,
NOx, SO2.
Yawat, Kurkumbh
(MIDC area), Indapur.
Mohol, Solapur (MIDC
area)
24 hours sampling Once in a year
Noise Level Yawat, Kurkumbh
(MIDC area), Indapur.
Mohol, Solapur (MIDC
area)
24 hours Continuous
sampling
Once in a year
Water Quality: for differentphysical chemical and
Khadak wasala maincanal, Pond, Reservoir
Grab Sampling Once in a year
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 41 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
42/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Parameter Locations Duration Frequency
biological parameters of Earthen Dam (Malad
tank), Tube well,
Reservoir (Ujani dam
Bhimnagar), Bhimariver, Sina river
Roadside Plantation
Maintenance
All along the highway
stretch
Regular Regularly
throughout the year
3.6 Mitigation Measures
Environmental mitigation measures have been incorporated within the design process
including the avoidance of the potential impacts through alignment sheets and other
means. The appropriate measures have also been identified for action in construction and
operational phases. The measures identified for all three phases, are tabulated in table
------which identifies the nature of potential environmental impact, which have or will be
taken, the time frame in which they are taken, the implementing agency and responsible
organisation and where appropriate, the contractual clause for enforcement of the
measure.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 42 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
43/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
Table 3.7 Implementation Schedule with Responsible/Supervising Organization/Authority
CONSTRUCTION PHASE
SL.
NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN
RESPONSIBLE/
SUPERVISING ORGANISATION/
AUTHORITY
1. Preparation of feasible landacquisition plan
Initiate and complete the process for land acquisition.Prepare & administer land use control measures.
Contractor in consultation with thestate revenue department.
2. Utilities Initiate and complete the process of shifting the utilities. Contractor in consultation with the State
Electricity Department and TelecomDepartment.
3. Reduction of Forest Cover Initiate & complete the process for compensatory a forestation. Contractor in consultation with StateForest Department.
4. Road Side Tree Plantation Select species and prepare location plan for roadside tree plantation. TheDetailed Methodology for implementation are as follows:
Contractor in consultation with ForestDepartment.
Permission from Forest Department & District Collector for felling ofscheduled trees
Prepare action plan for fresh plantation with Forest Department
Budget allocation
Implement action plan
5. Borrow pits and quarry sitesdevelopment
Firm up contract with the Mining department for obtaining the quarrymaterials & identification of borrow pits along the whole stretch with the
help of PWD and discussion with the concerned landowners.
Contractor.
Restoring of the borrow pits to its initial form by LandscapingTechniques.
6. Site for storage andconstruction camp
Finalize the detailed road design & select sites for construction camp. Contractor.
7. Sewerage disposal and solidwaste at worker colonies
Install lavatory at Construction Workers Colonies
Collection of domestic refuse and its suitable disposalContractor.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 43 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
44/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
SL.
NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN
RESPONSIBLE/
SUPERVISING ORGANISATION/
AUTHORITY
8. Traffic management Secure assistance from local police for traffic control during construction phase.Safety measures will also be undertaken by installing road sign and markingsfor safe and smooth movement of traffic
9. Noise Level Stationary equipments will be placed as far as possible frominhabited areas to minimize objectionable noise impacts
Provision of mufflers for stone crushing plants Proper maintenance of machinery and vehicles
Construction activities strictly prohibit ting between 10 pm and 6 pmnear habitations
Provision of using ear plugs by workers exposing high noise level
Contractor in consultation withMaharashtra state Pollution Control
Board (MPCB)
10. Air Quality Vehicles and machineries will be regularly maintained so thatemission conform to National and State Standards
Vehicles carrying construction material will be covered by traps toavoid spilling.
Asphalt mixing site will be over 500 m away from any communities indown wind direction. Mixing equipment will be seated and beequipped with dust removal device (e.g. wet separators)
Contractor in consultation with
MPCB
Water sprinkling will be carried out in morning and evening hours ofday at construction yard and unpaved sections of the road
Operators will use masks and ear plugs Speedy disposal of construction debris disposal sites.
11. Soil Erosion In slopes and other suitable places along the roadside trees and grassshould be planted
Contractor. /EMC
12. Loss of Top soil 15 cm of topsoil should be conserved and refilled after excavation isover to minimize the impact on productive land.
Contractor/EMC
13. Compaction of Soil Vehicles should operate within the COI on other side of centre line or on the side of widening) to avoid damage to vegetation.
Contractor/EMC
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 44 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
45/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
SL.
NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN
RESPONSIBLE/
SUPERVISING ORGANISATION/
AUTHORITY
14. Floods Bridges and culverts have been designed for the purpose of flooddischarge (100 years flood frequency for big bridges and 50 year floodfrequency for medium bridges and culvert)
Consultant/EMC/PWD, Maharashtra
15. Alteration of drainage In all sections where water courses cross the road, earth and stone willbe properly disposed of so as not to block river streams and naturaldrainage
Contractor/PWD, Maharashtra /EMC
16. Siltation Construction materials containing fine particles should be stored inclosed enclosures such that sediment laden water does not drain intonearby water courses
Contractor
17 Water logging and stagnation ofwater in borrow pits
Uncontrolled digging of borrow pits will be avoided to prevent wateraccumulation which induces breeding of insects like mosquitoes whichin turn can become a health hazard.
Control breeding of mosquito larvas by spraying of insecticides onstagnant pool of water.
Contractor as a partOf the supervision works inConsultation with the StateHealth and Family WelfareDepartment.
18. Occupational Health and Safety Laborers and Workers will be equipped with proper safety gearslike helmets, gloves and visors etc.
Contractor.
19. Basic amenities and sanitaryfacilities for constructionlaborers
Proper and adequate camp sites will be constructed and sanitaryfacilities will be provided to the workers for avoiding any health relatedproblems.
Contractor in
Consultation with Public Health
Department and Public Works
Department (PWD).
Regular inspection about the adequacy of facilities and periodic heathcheckups will be done.
20 Fuel for Construction labourers Adequate supply of fuel in the form of Kerosene stove and coal will be providedto the construction labourers to avoid felling of trees for cooking and otherhousehold activities.
Contractor.
Consultancy Service for 4/6 Laning From Zaidun Leeng Sdn. Bhd. Page 45 of 75Pune-Solapur of NH-9 in the State of Maharashtra &Package No. NHDP-III/DL4/04 Artefact Projects
8/7/2019 Annexure IB (EMP)
46/75
Package-I Draft Detailed Project Report Vol-IV B EMP Report
SL.
NO.PROJECT RELATED ISSUES ACTIONS TO BE TAKEN
RESPONSIBLE/
SUPERVISING ORGANISATION/
AUTHORITY
21. Maintenance of embankment toprevent erosion scouring andinstability due to adverseweather conditions
Stabilizing the embankment with ripraps, pitching and other appropriatetechnologies to prevent scouring.
Contractor in
Consultation with Public
Works Department.
22. Drainage System Development of existing drainage