36
Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal  held on 24.10.2011 at  12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   ___________________________________________________________________ Name of the members who were present in the meeting are as follows: - 1. Prof. Shymal Kanti Sanyal Chairman, State Level Expert Appraisal Committee (SEAC) 2.  Prof. (Dr.) Siddhartha Dutta Member, SEAC 3.  Prof. (Dr.) Jayashree Roy Member, SEAC 4. Shri  Manoj Kumar Nandi Member, SEAC 5. Prof. Subhash Chandra Santra Member, SEAC 6. Dr. Kalyan Rudra Member, SEAC 7. Shri Somnath Bhattacharyya Member, SEAC 8. Shri Arijit Banerjee Member, SEAC 9. Dr. S. P. Sinha Ray Member, SEAC 10. Shri Sandipan Mukherjee, I.F.S. Secretary, SEAC & Member Secretary, WBPCB In the beginning of the 60 th  meeting of SEAC, which was held on 24.10.2011 at 12:00 hrs at the Conference Room, Paribesh Bhawan, Bidhan Nagar, the Secretary, SEAC welcome all the members. After introductory session, eighteen cases were placed for reconsideration. One additional issue was discussed under 'Miscellaneous' section. Three applicants were requested to make their presentation before the committee. All the three applicants appeared before the SEAC for technical presentation on their respective project proposal. Session I A. Reconsideration proposals: - Eighteen reconsideration proposals were placed in the meeting. 1. Proposed Cement Grinding Unit of M/s. Salasar Cements at Plot No. – G10, Mangalpur Industrial Estate, PS - Raniganj, PO – Baktarnagar, Dist. - Burdwan, Pin - 713321, West Bengal. Name of the Consultant – NIL. Activity: This is a proposal for installation of Cement Grinding unit (1x20 TPD and 1x30 TPD). It is noted that clinker will not be manufactured at the site. The manufacturing process will involve grinding of Cement Clinker with Flyash and Gypsum. Chronology of the event: The proponent delivered a powerpoint presentation in the 58 th  meeting held on 19.08.2011During the presentation in the 58 th  meeting held on 19.08.2011, the committee has noted that- 1. The proponent obtained Consent to Establish from West Bengal Pollution Control Board in 2002. However, the proponent has not obtained any extension of this Consent to Establish nor applied for Consent to Operate. Subsequently the ownership of the unit has changed. 2. The proponent earlier applied for environmental clearance for Portland Slag Cement grinding unit on 19.02.2010. Considering the siting policy of WBPCB, the SEAC recommended that the proposal for Portland Slag Cement grinding unit with coal fired slag drier cannot be considered for Environmental Clearance at the proposed site. Page 1  of 36

Avidipta CESE Power Water Inlands

Embed Size (px)

DESCRIPTION

Avidipta Calcutta Bengal Pearless housing and finance buliding project

Citation preview

Page 1: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Name of the members who were present in the meeting are as follows: ­

1. Prof. Shymal Kanti Sanyal Chairman, State Level Expert Appraisal Committee (SEAC)2.  Prof. (Dr.) Siddhartha Dutta Member, SEAC3.  Prof. (Dr.) Jayashree Roy Member, SEAC4. Shri  Manoj Kumar Nandi Member, SEAC5. Prof. Subhash Chandra Santra Member, SEAC6. Dr. Kalyan Rudra Member, SEAC7. Shri Somnath Bhattacharyya Member, SEAC8. Shri Arijit Banerjee Member, SEAC9. Dr. S. P. Sinha Ray Member, SEAC10. Shri Sandipan Mukherjee, I.F.S. Secretary, SEAC & Member Secretary, WBPCB

In   the   beginning   of   the  60th  meeting   of   SEAC,   which  was   held   on   24.10.2011   at   12:00  hrs   at   the Conference Room, Paribesh Bhawan, Bidhan Nagar, the Secretary, SEAC welcome all the members. After introductory session, eighteen cases were placed for reconsideration. One additional issue was discussed under   'Miscellaneous'   section.  Three   applicants  were   requested   to  make   their  presentation  before   the committee.   All   the   three   applicants   appeared   before   the   SEAC   for   technical   presentation   on   their respective project proposal.

Session I

A. Reconsideration proposals: ­Eighteen reconsideration proposals were placed in the meeting.

1. Proposed   Cement   Grinding   Unit   of   M/s.   Salasar   Cements   at   Plot   No.   –   G10,   Mangalpur Industrial Estate, PS ­ Raniganj, PO – Baktarnagar, Dist. ­ Burdwan, Pin ­ 713321, West Bengal. Name of the Consultant – NIL.

Activity:

This is a proposal for installation of Cement Grinding unit (1x20 TPD and 1x30 TPD). It is noted that clinker will  not  be manufactured at   the  site.  The manufacturing process  will   involve  grinding of Cement Clinker with Flyash and Gypsum. 

Chronology of the event:

The proponent delivered a powerpoint presentation in the 58th meeting held on 19.08.2011. 

During the presentation in the 58th meeting held on 19.08.2011, the committee has noted that­

1. The proponent obtained Consent to Establish from West Bengal Pollution Control Board in 2002. However, the proponent has not obtained any extension of this Consent to Establish nor applied for Consent to Operate. Subsequently the ownership of the unit has changed.

2. The proponent earlier applied for environmental clearance for Portland Slag Cement grinding unit on 19.02.2010. Considering the siting policy of WBPCB, the SEAC recommended that the proposal for  Portland Slag Cement grinding  unit with coal fired slag drier  cannot be considered for Environmental Clearance at the proposed site.

Page 1 of 36

Page 2: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________3. The proponent has now applied for Environmental  Clearance on  23.05.2011 for Portland 

Pozzolona Cement grinding unit instead of the earlier proposal for Portland Slag Cement grinding unit. :­

The committee also recommended the following :­

Recommendations / Directions of the Committee, issued on 26.08.2011

Response of the Proponent submitted on 22.09.2011

1. Scaled   plant   layout   showing   proposed facilities,   Greenbelt   area,   Rainwater Harvesting   storage   area,   internal   roads, storage sheds etc. along with a detailed area statement   on   a   suitable   grid   should   be submitted.

1. The proponent has submitted gridded plant layout   without   any   area   statement.   The greenbelt shown in plan seems to be less than 33% (approx. 26% of land area).

2. Detailed   list   of   plantation   should   be submitted.

2. The   proponent   has   submitted   the   list   of plantation for 200 trees.

3. Revised  Rainwater  Harvesting  plan   should be submitted. 

3. The   proponent   has   submitted   Rainwater Harvesting   calculation   assuming   annual rainfall   as   150   mm   and   has   provided storage area of 713.55 sqm.

The case was placed for reconsideration in the  60th  meeting held on 24.10.2011. The name of the Consultant is not mentioned. However, as the presentation was delivered in the  58th SEAC meeting held on 19.08.2011, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and  the  30th  September deadline as  well  as   the decisions   taken   in   this  meeting scrutinized the documents submitted by the unit, The SEAC has recommended that – 

1. the  scaled  and  gridded   layout  submitted  does  not  consist  of  any area   statement.  Further,   the greenbelt shown in the plan appears to be approx. 26% of total land area instead of 33% of total land area. Revised layout plan should be submitted along with the area statement.

2. the calculation for Rainwater Harvesting submitted is based on annual rainfall of 150 mm only. Supporting document may be provided for annual rainfall in the locality.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

2. Proposed   expansion   of   the   existing   Cement   Grinding   Unit   and   installation   of   CBM   based Captive Power Plant by M/s. Birla Corporation Ltd., Unit : Durgapur Cement Works at Jl. No. – 62 & 63, Vill.  – Sujara, Near DSP Slag Bank, Durgapur ­ 713203, Dist.  ­  Burdwan, West Bengal. Name of the Consultant – M/s. SGS India Pvt. Ltd.

 Activity:

This is a proposal for expansion of the existing Cement Grinding unit for increasing the manufacturing capacity of Portland Slag Cement from 0.6 to 1.3 Million TPA and installation of CBM based Captive 

Page 2 of 36

Page 3: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Power  Plant   (2x6.93  MW  i.e.   13.86  MW).  The   existing  plant   also  produces  Portland  Pozzolana Cement   (1.0   Million   TPA).   It   is   noted   that   clinker   will   not   be   manufactured   at   the   site.   The manufacturing process will involve grinding of Cement Clinker with Slag / Flyash and Gypsum. 

The  existing  coal   fired   slag  drier   shall  be   removed and Roller  Press  unit   shall  be   installed.  The proposed Roller Press shall have dual function – drying and grinding of slag and shall be dual fuel operated – CBM and Coal. However, Coal shall be used only in case of non­availability of CBM. 

Chronology of the event :

The proponent delivered a powerpoint presentation in the 58th SEAC meeting held on 19.08.2011.

The State Level Expert Appraisal Committee (SEAC) also made the following recommendations in the 58th SEAC meeting held on 19.08.2011. During the presentation the committee has noted that the proponent presented the EIA­EMP study in response to the Terms of Reference (ToR) prescribed by Expert Appraisal Committee at Ministry of Environment & Forest (MoEF), Government of India. 

The observations of SEAC in the 58th SEAC meeting held on 19.08.2011 and consequent responses of the project proponent on 23.09.2011 and 12.10.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee  Response of the Proponent  1. Compliance report  of  the existing unit as per 

the Office Memorandum dated 01.07.2011 of MoEF,   Government   of   India,   should   be submitted. 

1. The proponent has submitted compliance report for the existing unit.

2. Details   of   CBM   based   Captive   Power   Plant (CPP)  along with capacity  of  CPP should be submitted.

2. The  proponent  has   submitted  details   of CBM based CPP.

3. The   estimated   emission   load   after   expansion vis­a­vis the current emission load as well as present   permissible   emission   should   be mentioned in a unit wise manner. 

3. The   proponent   has   submitted   emission load estimate.

4. Detailed plantation plan with the list of planta­tion species should be mentioned.

4. The   proponent   has   submitted   detailed plantation plan.

5. Revised Rain Water Harvesting proposal as per SEAC   guidelines   should   be   submitted.   Only storage and reuse is allowed for industrial pro­jects. Recharging is not permitted.

5. The proponent has submitted RWH plan.

6. Scaled   plant   layout   showing   existing   and proposed facilities,  Greenbelt  area,  Rainwater Harvesting storage area, internal roads, storage sheds   etc.   on   a   suitable   grid   should   be submitted. 

6. The   proponent   has   submitted   gridded plant layout.

The name of the Consultant is M/s. SGS India Pvt. Ltd. 

Page 3 of 36

Page 4: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The   case   was   placed   for   reconsideration  in   the  60th  meeting   held   on   24.10.2011.  The   SEAC considered the submission by the proponent with proposal for achieving the standard of 30 mg/Nm3 

and thereby restricting the emission load within initially approved level. The SEAC, also, considering Ambient Air Quality of Durgapur imposed the condition to comply with 30 mg/Nm3  standard for all sections  recommended Environmental Clearance.

3. Proposed Waste paper based plant and Cogeneration Captive Power Plant of M/s. Balaji Paper & Newsprint Private Limited at Jl. No. – 561, 562, 649, 650, Vill. ­ Manikpara, PS – Jhargram, Dist. – Pashim Medinipur, Pin – 721513, West Bengal.

Activity:

This is a proposed Waste Paper Based Paper Plant with additional paper manufacturing capacity of 100 TPD and 6 MW Co­Generation Captive Power Plant. 

Chronology of the event :

The proponent delivered a powerpoint presentation in the 46th SEAC meeting held on 06.09.2010.

The State Level Expert Appraisal Committee (SEAC) also made the following recommendations in the  46th  SEAC meeting held on 06.09.2010.  The recommendations  /  directions  of the Committee dated 11.10.2010 and consequent responses of the project proponent dated 24.02.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee dated 11.10.2010

Response of the Proponent  dated 24.02.2011

1. The   performance   report   of   the   existing   unit should be submitted. 

1.

2. Prior permission should be obtained from DLA for   ground   water   abstraction   and   the   copy should be submitted.

2. The   proponent   has   informed   that   they have obtained permission from DLA for 8nos.   borewell   each   10m3/hr,   copies enclosed.

3. Water   balance   statement   and   water consumption  per   tonne  of  product   should  be mentioned. 

3. The   proponent   has   submitted   revised water   balance   statement.   As   per   the information   provided   the   water consumption per tonne of product is 4.8 m3.

4. Details of Rainwater Harvesting proposal and Corporate Social Responsibility plan should be submitted.

4. The proponent has submitted  Rainwater Harvesting   proposal   and   Corporate Social Responsibility plan.

5. Solid   waste   management   and   Flyash management plans should be submitted.

5.

Page 4 of 36

Page 5: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The response dated 24.02.2011 was placed before SEAC in the  52nd  meeting held on 04.03.2011. Further the SEAC has considered the reply submitted on 16.06.2011 in the  58th  meeting held on 19.08.2011 and the committee has recommended the following :­

Recommendations / Directions of the Committee dated 30.08.2011

Response of the Proponent  dated 30.09.2011

1. The influent BOD value has been assumed to   be   very   low   in   comparison   to   waste water usually generated from such a waste paper based mill. 

1. The proponent has mentioned that they have assumed influent of BOD 600 mg/l  on the basis   of   their   raw   material   input   and production process.

2. The influent BOD is likely to magnify due to   recycling   of   the   treated   /   partially treated waste water.

2. The proponent has mentioned that they will provide   adequate   treatment   so   that magnification   of  BOD due   to   recycling   is less.

3. The   mass   vs   water   ratio   is   also   not realistic. The project proponent should try to   explain   those   ratios  or   should   submit corrected   water   and   mass   balance diagram. 

3. The   proponent   has   stated   that   they   have prepared   water   balance   and   mass   balance statement   based   on   their   past   experience. The proponent has also mentioned that  the proposed water balance and mass balance is achievable.

The case was placed for reconsideration in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned in this application. However, as the presentation was delivered in the 46th 

SEAC meeting held on 06.09.2010, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting scrutinized the documents submitted by the unit. The SEAC has noted that ­

1. The performance report of the existing unit has not been submitted.

2. The BOD influent has been assumed on lower side and there is no specific proposal available, which ensure adequate treatment to prevent magnification of BOD concentration in the re­cycled water.

3. No plausible explanation has been provided to substantiate the claim that the water balance and mass balance, which were submitted to the SEAC earlier and was duly questioned by SEAC through earlier communications, are correct and validated.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

Page 5 of 36

Page 6: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

4. Proposed expansion of the Cement Grinding Unit of M/s. Maa Gouri Cement Industries at Plot No. – 391 (P), 392, Jl. No. – 53, Vill. & PO – Kuldiha, SD ­ Durgapur, PS – Kanksa, Dist. ­  Burdwan,   Pin   –   713212,   West   Bengal.   Name   of   the   Consultant   –   M/s.   Pacific   Scientific Consultancy Pvt. Ltd. 

Activity:

This is a proposal for expansion of the existing Cement Grinding unit for production of Portland Slag Cement & Portland Pozzolana Cement (150000 TPA). It is noted that clinker will not be manufactured at the site. The manufacturing process will involve grinding of Cement Clinker with Slag / Flyash and Gypsum. The existing and the proposed facilities are as follows :

Installations Existing Capacity

Ball Mill (50 TPD)

Proposed Capacity

Ball Mill (2x200 TPD, 1x100 TPD)

Portland Slag Cement (PSC)  50 TPD, 15000 TPA 300 TPD, 90000 TPA

Portland Pozzolana Cement (PPC) 200 TPD, 60000 TPA

Chronology of the event :

The proponent delivered a powerpoint presentation in the 56th meeting held on 15.07.2011.

The observations of SEAC in the 56th meeting held on 15.07.2011 and consequent responses of the project proponent on 13.10.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee issued on 22.07.2011

Response of the Proponent  dated 13.10.2011

1. It   has   been   noted   that   at   present   sun drying of slag is practiced. As slag drying capacity   is   to   be   enhanced   after   the proposed   expansion,   the   SEAC   has recommended CBM as fuel for  the slag drying. Revised proposal for CBM based slag drier should be submitted.

1. The proponent has mentioned that there is no CBM   distribution   centre   nearby.   The proponent has proposed coal fired slag drier and   has   mentioned   that   the   same   shall   be converted to CBM whenever available.

2. The   Rainwater   Harvesting   proposal should be revised as  advised during the presentation and submitted to the SEAC.

2. The proponent has submitted RWH proposal considering annual rainfall of 1300 mm. The proponent  has  proposed  storage  capacity  of 90m3.

3. Prior   permission   is   to   be   obtained   for groundwater  abstraction   for   the  existing project.

3. The proponent has mentioned that they have approached   the   concerned   authority   for groundwater permission for existing project. However,   the   permission   has   not   yet   been obtained since the concerned officer has been 

Page 6 of 36

Page 7: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Recommendations / Directions of the 

Committee issued on 22.07.2011Response of the Proponent  dated 13.10.2011

replaced   and   the   new   person   has   not   yet joined.

4. Design   specification   of   air   pollution control systems should be submitted.

4. The proponent has submitted specification of air pollution control systems.

5. Species   wise   plantation   list   should   be submitted.

5. The proponent has submitted list of existing trees (120 nos.) and proposed plantation. 

6. Specific  Corporate  Social  Responsibility (CSR)   plan   with   adequate   financial commitment   for   improvement   of neighbourhood area  of  proposed  project site  should be submitted.  Atleast  5% of the   project   cost   should   be   utilised   for Corporate   Social   Responsibility programmes.

6. The  proponent  has   submitted   the  details   of CSR proposal alongwith financial planning.

The name of the Consultant is M/s. Pacific Scientific Consultancy Pvt. Ltd. 

The case was placed for reconsideration in the 60th meeting held on 24.10.2011. After scrutinizing the documents submitted by the unit, the SEAC has recommended that ­

a) the prior permission for groundwater abstraction for the existing project must be submitted to SEAC. 

b) considering the typical location of your unit and air quality in surrounding environment, the SEAC once again advices you to modify the scope of converting the coal fired slag drier to CBM based system. For such measure, the proponent should explore the options available in current CBM supply and distribution network exhaustively, as CBM is now available in that region.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

5. Proposed   expansion   project   for   installation   of   Induction   Furnace   and   Continuous   Casting Machine by M/s. Shivam Meltech Pvt. Ltd. at Jl. No. – 58, Vill. – Gopalpur, Mouza ­ Bamunara, PS – Kanksa, SD – Durgapur, Dist. ­ Burdwan, West Bengal. Name of the Consultant – M/s. Pacific Scientific Consultancy Pvt. Ltd.

Activity:

This  is a proposal for expansion for  installation of  Induction Furnaces (2x15T) followed by ladle refining furnace (1x15T) and Continuous Casting Machine for manufacturing MS billets (87300 TPA) at the existing plant. The existing and the proposed facilities are as follows :

Page 7 of 36

Page 8: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Installations Existing Capacity Proposed Capacity

Induction Furnace 2x6T  2x15T (87300 TPA)

Ladle Refining Furnace (Oil fired) 1x15T

Chronology:

The proponent delivered a powerpoint presentation in the 56th meeting held on 15.07.2011.

The observations of SEAC in the 56th meeting held on 15.07.2011 and consequent responses of the project proponent on 13.10.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee issued on 22.07.2011

Response of the Proponent  dated 13.10.2011

1. The   Rainwater   Harvesting   proposal   should be revised as advised during the presentation and submitted to the SEAC.

1. The   proponent   has   submitted   RWH proposal   considering   annual   rainfall   of 1330   mm.   The   proponent   has   proposed storage capacity of 1107 m3.

2. Prior   permission   is   to   be   obtained   for groundwater   abstraction   for   the   existing project.

2. The   proponent   has   mentioned   that   they have approached the concerned authority for   groundwater   permission   for   existing project. However, the permission has not yet   been   obtained   since   the   concerned officer   has   been   replaced   and   the   new person has not yet joined.

3. Species   wise   plantation   list   should   be submitted.

3. The  proponent  has   submitted   the   list   of existing   trees   (36)   and   proposed plantation.

4. Design specification of air pollution control systems should be submitted

4. The proponent has submitted specification of air pollution control systems.

5. Specific   Corporate   Social   Responsibility (CSR)   plan   with   adequate   financial commitment   for   improvement   of neighbourhood area of proposed project site should   be   submitted.   Atleast   5%   of   the project cost should be utilised for Corporate Social Responsibility programmes.

5. The proponent has submitted the details of CSR   proposal   alongwith   financial planning.

The name of the Consultant is M/s. Pacific Scientific Consultancy Pvt. Ltd. The case was placed for reconsideration in the 60th meeting held on 24.10.2011. After scrutinizing the documents   submitted  by   the  unit,  The  SEAC has  noted   that   the  prior   approval   for  groundwater abstraction for the existing project must be submitted to SEAC. 

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

Page 8 of 36

Page 9: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

6. Proposed expansion project for installation of Induction Furnace by M/s. VSP Udyog Pvt. Ltd. at Jl. No. – 58, 65, Banskopa More, Vill. & Mouza – Gopalpur, PO – Bamunara, PS – Kanksa, SD – Durgapur, Dist. ­ Burdwan, Pin – 713212, West Bengal. Name of the Consultant – NIL.

Activity:

This is a proposal for expansion for installation of Induction Furnace (1x15T) for manufacturing MS billets (45000 TPA) at the existing plant. The existing and the proposed facilities are as follows :

Installations Existing Capacity Proposed Capacity

Induction Furnace 2x8T (45600 TPA) 1x15T (45000 TPA)

Rolling Mill 80000 TPA

Chronology of the event :

The proponent  delivered  a  powerpoint  presentation  in   the  56th  meeting held on 15.07.2011.  The observations of SEAC in the 56th meeting held on 15.07.2011 and consequent responses of the project proponent on 18.10.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee issued on 22.07.2011

Response of the Proponent  dated 18.10.2011

1. The   Rainwater   Harvesting   proposal should  be  revised  as  advised  during   the presentation and submitted to the SEAC.

1. The proponent has submitted RWH proposal considering annual rainfall of 1330 mm. The proponent  has  proposed   to  provide   storage capacity of 1107 m3 approx.

2. Prior   permission   is   to   be   obtained   for groundwater   abstraction   for   the   existing project.

2. The proponent has mentioned that they have approached   the   concerned   authority   for groundwater permission for existing project. However,   the  permission  has  not  yet  been obtained   since   the   concerned   officer   has been  replaced  and   the  new person  has  not yet joined.

3. Species   wise   plantation   list   should   be submitted.

3. The   proponent   has   submitted   the   list   of existing trees (75) and proposed plantation.

4. Specific  Corporate  Social  Responsibility (CSR)   plan   with   adequate   financial commitment   for   improvement   of neighbourhood  area  of  proposed   project site  should  be  submitted.  Atleast  5% of the   project   cost   should   be   utilised   for Corporate   Social   Responsibility programmes.

4. The proponent has submitted the details of CSR proposal alongwith financial planning.

Page 9 of 36

Page 10: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

The case was placed for reconsideration in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned. However, as the presentation was delivered in the 56th meeting held on 15.07.2011, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting scrutinized the documents submitted by the unit,  The SEAC has noted that the prior approval for groundwater abstraction for the existing project must be submitted to SEAC.

It has been decided that the case shall be further considered only  after  submission of  the  necessary clarification.

7. Proposed expansion project for enhancement of production of Unsaturated Polyester Resins by M/s. Strongbonds Polyseal Pvt. Ltd. at Plot No. – 26/C, 26/D/1 & 26/D/2, Kalyani Industrial Estate Phase I, Block – D, Dist. – Nadia, Pin – 741235, West Bengal. Name of the Consultant – NIL.

Activity:

This is an expansion proposal for enhancement of production capacity of Unsaturated Polyester Resins (UPR) by 690 TPA. The proposed plant  will  be located adjacent  to   the existing plant at Kalyani Industrial Estate.

Chronology of the event :

The proponent delivered a powerpoint presentation in the 52nd meeting held on 04.03.2011. During presentation it was understood by the SEAC that the proposed expansion work has been started before obtaining   Environmental   Clearance.  The  observations   of   SEAC  in   the  52nd  meeting   held   on 04.03.2011 and consequent responses of the project proponent dated 16.06.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee issued on 15.03.2011

Response of the Proponent  dated 16.06.2011

1. The unit should not continue any work for the   proposed   expansion   project   before obtaining prior necessary clearances.

1. The proponent has stated that they will  not continue   any   work   for   the   proposed expansion   project   before   obtaining   prior necessary clearances.

2. The Hazardous Waste Authorization must be   obtained   from   the   West   Bengal Pollution   Control   Board     before   further consideration   of   this   case   for Environmental Clearance.

2. The proponent has mentioned that they have applied for  Hazardous Waste Authorization to West Bengal Pollution Control Board.

3. The   effluent   characteristics   for   the existing   plant   should   be   submitted. Incremental   load   of   the   proposed 

3. The proponent has submitted analysis report of the effluent. The proponent has mentioned that   the   incremental  wastewater  generation 

Page 10 of 36

Page 11: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Recommendations / Directions of the 

Committee issued on 15.03.2011Response of the Proponent  dated 16.06.2011

enhancement should be mentioned along with the effluent treatment method to be adopted.

will   be   0.2   KLD.   The   proponent   has proposed neutralization and evaporation for treatment of effluent.

4. Adequate no. of trees should be provided. 4. The proponent has mentioned that   total  47 nos. of trees will be provided.

5. Adequate   storage   volume   for   rainwater harvesting should be provided.

5. The proponent has mentioned that  100 KL storage volume will be provided.

6. Modified Corporate Social Responsibility (CSR) Plan with specific programmes and financial commitment to be submitted.

6. The   proponent   has   submitted   revised Corporate Social Responsibility (CSR) Plan with financial commitment.

The   reply   dated   16.06.2011   was   placed   in   the  56th  SEAC   meeting   held   on   15.07.2011.  The observations of SEAC in the 56th SEAC meeting held on 15.07.2011 and consequent responses of the project proponent dated 14.10.2011 are prescribed in the following table : :­

Recommendations / Directions of the Committee issued on 22.07.2011

Response of the Proponent  dated 14.10.2011

1. The Hazardous Waste Authorization must be   obtained   from   the   West   Bengal Pollution   Control   Board   before   further consideration   of   this   case   for Environmental Clearance.

1. The   proponent   has  submitted   copy   of   the Hazardous   waste   Authorisation   valid   upto 30.04.2012.

2. The unit should not continue any work for the   proposed   expansion   project   before obtaining prior necessary clearances.

2. The  proponent  has  stated   that   they will  not continue   any   work   for   expansion   project before obtaining all statutory clearances.

The case was placed for reconsideration  in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned. However, as the presentation was delivered in the 52nd meeting held on 04.03.2011,  the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting considered the submission by the proponent and recommended Environmental Clearance.

Page 11 of 36

Page 12: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

8. Proposed Residential Complex & Hospital by M/s. Oriental Sales Agencies (India) Pvt. Ltd. at 2, Jessore Road, Holding No. – 380 (N), 1108 (O), Cal­Jessore Road, Jl. No. – 19, Mouza – Dum Dum House, South Dum Dum Municipality Ward No. ­ 07, PO & PS – Dum Dum, Kolkata – 700028, Dist. – 24 Parganas (North). Name of the Consultant – M/s. JB Enviro Consultants Pvt. Ltd.

Activity:

This is a proposal for construction of a Residential Complex having 1196 flats (13 blocks of B+G+13 storied buildings, 13 blocks of G+13 storied buildings), Hospital (70 beds, 1 block of G+9 storied building), Club (2 blocks of G+1 storied buildings) and 2 nos. podium.

Chronology of the event :

The proponent delivered a powerpoint presentation in the 56th meeting held on 15.07.2011. 

The   observations   of   SEAC   in   the  56th  SEAC   meeting   held   on   15.07.2011  and   the   consequent responses of the project proponent on 18.08.2011 are prescribed in the following table :

Recommendations / Directions of the Committee, issued on 25.07.2011

Response of the Proponent submitted on 18.08.2011

1. The   project   proponent   should   submit   the copy   of   MSW   authorisation   of   the designated site where the solid waste will be dumped.

1. The   proponent   has   submitted   the   MSW Authorisation   of   SDDM   valid   upto 31.05.2006   to   set   up   waste   disposal facility at Goroi Mathkal.

2. Revised   Rainwater   Harvesting   proposal should   be   submitted.   The   ground   water recharge in hospital area is not permitted.

2. The   proponent   has   submitted  revised Rainwater  Harvesting  proposal  excluding hospital area.

3. Prior   permission   should   be   obtained   from the concerned authority for felling of trees. The   SEAC   also   requested   the   project proponent for submission of detailed census of existing trees. 

3. The proponent has submitted certificate of clearance   dated   10.08.2011   of   DFO,   24 Parganas   (N)   which   refers   to   the concurrence obtained from WBPCB vide letter 25.07.2011. But no such concurrence was conferred by WBPCB.

The reply submitted by the project proponent on 18.08.2011 was placed before the SEAC in the 58th 

meeting held on 19.08.2011. The observations of SEAC in the 58th meeting held on 19.08.2011 and the consequent responses of the project proponent on 22.09.2011 are prescribed in the following table:

Recommendations / Directions of the Committee, issued on 26.08.2011

Response of the Proponent submitted on 22.09.2011

1. The   authorisation   dated   21.06.2005   was valid upto 31.05.2006. The committee has requested the proponent to submit copy of 

1. The proponent has mentioned that as South Dum Dum Municipality is not in a position to   provide   copy   of   valid   MSW 

Page 12 of 36

Page 13: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Recommendations / Directions of the 

Committee, issued on 26.08.2011Response of the Proponent submitted on 

22.09.2011valid Municipal Solid Waste authorisation for  disposal  of   solid  waste   to  designated site.

authorisation,   onsite   treatment   of   solid waste   has   been   proposed.   The   details   of onsite  organic  waste  composting has been submitted.

2. The   Certificate   of   Clearance   dated 10.08.2011 refers to the concurrence of the West   Bengal   Pollution   Control   Board obtained   vide   letter   No. 430­2N­70/2010(E)   dated   25.07.2011. However,   no   such   concurrence   was conferred   to   the   proponent.   Instead,   the SEAC requested   the  proponent   to  obtain necessary  permission  from the  concerned authority   for   felling   trees   and   to   submit necessary details.

2. The  proponent  has   submitted  copy of   the letter   dated   03.08.2011   to   the   DFO,   24 Parganas (North) Division.

     The   letter   dated  14.09.2011  has   also  been received from DFO in response to SEAC's letter dated 26.08.2011.

The case was placed for reconsideration in the  60th  meeting held on 24.10.2011. The name of the Consultant for this application is M/s. JB Enviro Consultants Pvt. Ltd.  However, as the presentation was delivered in the 56th  SEAC meeting held on  15.07.2011,  the  SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th  September deadline as well   as   the  decisions   taken   in   this  meeting  scrutinized   the  documents   submitted  by  the  unit  and considering   this   new   technical   proposal,   the   SEAC   further   desired   that   a   detailed   technical presentation ought to be delivered by the competent agencies about the feasibility and viability of the proposed   solid   waste   treatment   and   disposal   system.   The   performance   report   of   the   proposed composter equipment operating in any residential complex, needed be presented through powerpoint presentation. The final utilisation of the compost and disposal of inorganic wastes needed also be illustrated, before taking any decision in this issue. 

9. Proposed Residential Complex “UJAAS” by M/s. Designer Real Estate India Pvt. Ltd. at Plot No. 69, Holding No. – 152 (new), 97 (old), S.K. Deb Road, Jl. No. ­ 25, Mouza – Dakshindari, PS – Lake Town, South Dum Dum Municipality Ward No. 31, Dist – 24 Parganas (North) West Bengal. Name of the Consultant – NIL.

Activity:

This is a proposal for construction of Residential Complex having 174 flats (20 blocks of G+4 storied buildings and 3 blocks of G+2 bungalows). However, the proposed PHASE I shall comprise of 134 flats (20 blocks of G+3 storied buildings and 3 blocks of G+2 bungalows). This clearance is applicable for the proposed PHASE I only. However, the proposal for subsequent phase should abide by the necessary stipulations of the Provisional Environmental Clearance for the entire project. 

Page 13 of 36

Page 14: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Chronology of the event :

The proponent obtained Environmental  Clearance from the State  Environment Impact Assessment Authority, West Bengal on 14.10.2009 for PHASE – I and NOC from the WBPCB on 08.12.2009.

The proponent has now applied for Environmental Clearance for PHADE – II. The proponent has mentioned that there is no change in sanctioned plan and construction of PHASE – I is completed and PHASE – II has not been started.

Salient features of the proposed PHASE – II is given below: ­

Salient Features As per SCEC dated 21.07.2009

Phase I (As per EC dated 27.08.2009)

Phase II (EC Applied for)

Land Area  4.7828 acres 

(19362.34 sqm.)

 4.7828 acres 

(19362.34 sqm.) 

4.7828 acres (19362.34 sqm.)

Expected Population 810 610 200

Total Water requirement  

191 KLD 167 KLD 24 KLD

Fresh Water requirement  

136 KLD 106 KLD 30 KLD

Wastewater generated 109 KLD 84.8 KLD 24.2 KLD

Wastewater recycled 61 KLD 61 KLD 0

Wastewater discharged 26 KLD 6.8 KLD 19.2 KLD

Solid waste disposal 0.55 tonne per day 0.43 tonne per day 0.12 tonne per day

Total Built­up Area 34920.08 sqm. 28297.5 sqm.  6622.58 sqm.

Page 14 of 36

Page 15: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Salient Features As per SCEC dated 

21.07.2009Phase I (As per EC dated 27.08.2009)

Phase II (EC Applied for)

Ground Coverage 7470.81 sqm. 

(38.58% of land area)

7470.81 sqm. 

(38.58% of land area)

Services 313.67 sqm. 

(1.62% of land area)

313.67 sqm. 

(1.62% of land area)

Landscaped Green Area

5661.54 sqm. 

(29.24% of land area)

5661.54 sqm. 

(29.24% of land area)

Paved Area 3695.21 sqm. 

(19.08% of land area)

3695.21 sqm.

(19.08% of land area)

Semi Paved Area 583.05 sqm. 

(3.01% of land area)

583.05 sqm. 

(3.01% of land area)

Water Body 1568.14 sqm. 

(8.09% of land area) 

1568.14 sqm. 

(8.09% of land area) 

Swimming Pool 73. sqm.

74. (0.38% of land area)

73. sqm.

74. (0.38%   of   land area)

No. of Parking Spaces proposed

230 230

Power requirement 980 KW 980 KW, CESC

Number of DG Set 1 no. x 275 KVA 1 no. x 275 KVA

Number of Trees  486 486

Number of Trees felling

18 18

Shall   remain unchanged

The case was placed for reconsideration  in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned. The SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section)  in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting considered the submission by the proponent and recommended Environmental Clearance.

10. Proposed   project   including   expansion   of   the   Commercial   Complex   “AVANI   RIVERSIDE MALL” by M/s. Avani Projects and Infrastructure Limited at 32, Jagat Banerjee Ghat Road, Howrah . Name of the Consultant – NIL.

Activity:

This is a proposal for expansion of a Commercial Complex from 1 block of 2B+G+2 storied building to 1 block of 2B+G+3 storied building.

Page 15 of 36

Page 16: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Chronology of the event :

The proponent obtained Environmental Clearance from SEIAA, West Bengal on 10.09.2009.

The proponent was requested to apply for Consent­to­Establish on 24.09.2009. The proponent has not yet applied for NOC.

The proponent has applied for the following amendment in Environmental Clearance on 29.09.2011. 

As per EC dated 10.09.2009) Amendment applied on 29.09.2011Total Power Requirement  

4500 KVA, CESC 5625 KVA, CESC

Back up Power DG Sets ( 3x1500 KVA) DG Sets (4x2000 KVA)

It has been noted that Back up power provision is much higher than total power requirement.  

The  case  was  placed   for   reconsideration   in   the  60th  meeting  held  on 24.10.2011.  The  name  of Consultant is not mentioned.  However, as the presentation was delivered in the  7th  SEAC meeting held on 26.07.2007, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th  September deadline as  well  as   the decisions  taken in   this  meeting scrutinized the documents submitted by the unit.

The SEAC has  noted that in case of the proposed amendment, the back up power requirement  is 4x2000 KVA, which exceeds the CESC power requirement i.e. 5625 KVA to a considerable extent. But no clarification has been provided for demand of such additional back up power. Further, the SEAC also desired to obtain the current compliance status of this particular project with respect to the environmental norms prevailing in the country. 

It has been decided that the case shall be further considered only  after  submission of  the necessary clarification.

11. Proposed   Residential   Complex   “SANKALPA   II”   by   M/s.   West   Bengal   Infrastructure Development Finance Corporation Ltd. at Prem. No. – 36, MAR (Plot No. – BF/1, BF/2, BF/3), Action Area I, New Town, Rajarhat, Kolkata, Dist. – 24 Parganas (North), West Bengal. Name of the Consultant – M/s. Centre for Sustainable Development.

Activity:

This is a proposal for construction of a Residential Complex having 228 flats (2 blocks of B+G+15/19 storied buildings and 2 blocks of B+G+11/13 storied buildings) alongwith Club (1 block of B+G+2 storied building).

Page 16 of 36

Page 17: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Chronology of the event :

The proponent delivered a powerpoint presentation in the 56th meeting held on 15.07.2011.  During presentation in the 56th SEAC meeting held on 15.07.2011, the committee noted that ­

1. the construction is almost complete. The unit has requested for post facto clearance. 2. there   was   anomaly   between   the   statement   made   by   the   unit   regarding   the   status   of 

wastewater   treatment   and   the   status   shown   in   presentation   slide.   The   SEAC   has recommended that this kind of anomalies should not occur in future.  

Further   the  observations  of  SEAC  in   the  56th  meeting  held  on 15.07.2011  and  the  consequent responses of the project proponent on 29.09.2011 are prescribed in the following table :

Recommendations / Directions of the Committee, issued on 25.07.2011

Response of the Proponent submitted on 29.09.2011

a) Revised plantation plan should be submitted as   discussed   in   the   meeting   excluding Chattim, Kadam etc.

a) The   proponent   has   submitted   revised plantation plan excluding  Chattim, Kadam etc.

b) Specific   Corporate   Social   Responsibility (CSR)   plan   with   adequate   financial commitment   for   improvement   of neighbourhood area of proposed project site should be submitted.

b) The   proponent   has  mentioned   that   the Corporate Social Responsibility (CSR) plan will   be   submitted   after   approval   from Board of Directors of the company.

The name of the Consultant is M/s. Centre for Sustainable Development. 

The case was placed for reconsideration in the 60th meeting held on 24.10.2011. After scrutinizing the documents submitted by the unit, The SEAC has noted that the Corporate Social Responsibility (CSR) plan requires prior approval from the Board of Directors of the company. The SEAC requested the proponent to submit the CSR plan approved by the competent authority.  

It has been decided that the case shall be further considered only  after  submission of  the necessary documents in relation to CSR.

12. Proposed  renovation  and  reconstruction  project  "DIAMOND  HERITAGE" by  M/s.  Strand Properties Ltd. at  16, Strand Road, KMC Ward No. 45, PS – Hare Street, Kolkata – 700 001, West Bengal. Name of the Consultant – NIL.

Activity:

This is a proposal for restoration cum reconstruction of a Heritage Building. The proposed project shall consist of 1 block of B+G+14 storied building having Office Complex and Multi Level Car Parking.  The State Level Expert Appraisal Committee, West Bengal,  recommended  environmental clearance for the proposed project in the 44th SEAC meeting held on 12.07.2010. 

Page 17 of 36

Page 18: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Chronology of the event :

The proposed project was considered in the SEIAA meeting dated 22.09.2010. The SEIAA observed that the proposal for renovation and reconstruction of the building does not have concurrence of the Heritage Commission of West Bengal. The SEIAA has referred back the case to the SEAC with a request to get the views of Heritage Commission and to reexamine the proposal in light of the same.

The proponent submitted the following documents earlier –

1. The copy of the building plan sanctioned by KMC on 08.01.2010. 2. The copy of the letter dated 20.07.2006 from the Director General (Building) to M/s. Alcove 

Industries Ltd.3. The copy of the minutes of the extended meeting of the Heritage Conservation Committee 

held on 23.06.2006.

The proponent submitted a  letter dated 25.10.2010 regarding final  environmental clearance of  the proposed project. The SEAC considered the same in the 48th SEAC meeting held on 09.11.2010. The SEAC requested  the proponent   to  submit   the  copy of   the  permission obtained  from  the Heritage Commission, West Bengal, for the proposed renovation and reconstruction project.

The proponent has submitted letter dated 22.03.2011 alongwith the copy of the letter dated 20.07.2006 of the Building Department, KMC, which was submitted earlier. The letter states that the project has been   approved   by   the   Heritage   Conservation   Committee.   However,   the   proponent   has   not   yet submitted approval of the Heritage Commission, West Bengal.

The proponent has also mentioned that the initial developer was M/s.  Alcove Industries Ltd. which was subsequently taken over by M/s. Strand Properties Ltd. This was considered in the  53rd SEAC meeting held on 13.04.2011.  The SEAC requested the proponent vide  letter  dated  21.04.2011 to submit necessary approval from the Heritage Commission, West Bengal instead of resubmission of the approval from the Heritage Conservation Committee.

The proponent has submitted their reply on 10.10.2011. The proponent has mentioned that they have obtained permission from the Heritage Conservation Committee and KMC. The proponent has also stated   that   they   don't   have   any   access   to   internal   correspondences   exchanged   between   Heritage Commission, West Bengal and Heritage Conservation Committee. 

The case was placed for reconsideration in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned.   However, as the presentation was delivered in the 24th SEAC meeting held on 30.09.2008, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and  the  30th  September deadline as  well  as   the decisions   taken   in   this  meeting forwarded the communications received from the project proponent to SEIAA, West Bengal.

Page 18 of 36

Page 19: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________13. Proposed  Residential  Complex  "AVIDIPTA” by M/s.  Bengal  Peerless  Housing  Development 

Company Limited at R.S. Dag Nos. 125 (Part) and 126 (Part), J.L. No. 21, Premises No. – 401, Mouza – Barakhola, PS ­ Purba Jadavpur, KMC Ward No. 109, Dist.  24 Parganas (S). Name of the Consultant –  M/s. Centre for Sustainable Development.

Activity:

This is a proposal for construction of Residential Complex having 1068 flats (3 blocks of G+18 storied buildings, 5 blocks of G+17 storied buildings, 4 blocks of G+16 storied buildings, 1 block of G+15 storied building and 2 blocks of G+3 storied buildings) alongwith Community building (2 blocks of G+1 storied buildings). 

Chronology of the event :

The proponent delivered a powerpoint presentation in the  51st meeting held on 03.02.2011.

The SEAC proposed conditions for Environmental Clearance in the 51st meeting held on 03.02.2011.

The proponent mentioned vide letter dated 02.05.2011 that there are certain changes in the layout plan. The modified features were considered in the 54th meeting held on 12.05.2011.

The proponent has now applied for Environmental Clearance alongwith the building plan sanctioned by KMC on 29.09.2011. The modified features of the proposed project is given below :­

Salient Features As per the SCEC issued on 23.02.2011

As per the Revised proposal

Land Area : 12.67 acres (51273 sq m.) : 12.67 acres (51273 sq m.)

Expected Population : 5212 (fixed), 721 (floating) : 5212 (fixed), 721 (floating)

Total Water requirement : 993 KLD (Operation stage) : 993 KLD (Operation stage)

Fresh Water requirement : 894 KLD (KMC supply) : 894 KLD (KMC supply)

Domestic Water requirement

: 800 KLD  : 800 KLD 

Wastewater generated : 640 KLD (to be treated in STP)

: 640 KLD (to be treated in STP)

Treated Effluent : 512 KLD  : 512 KLD 

Wastewater recycled : 93 KLD (to be reused after treatment in STP)

: 93 KLD (to be reused after treatment in STP)

Wastewater discharged : 419 KLD (to be discharged to KMC Sewer line after treatment in STP)

: 419 KLD (to be discharged to KMC Sewer line after treatment in STP)

Solid waste disposal : 3.0 tonnes per day (to be disposed off through local authority) 

: 3.0 tonnes per day (to be disposed off through local authority) 

Total Built­up Area : 103925.47 sqm.  : 112616.22 sqm. 

Page 19 of 36

Page 20: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Salient Features As per the SCEC issued on 

23.02.2011As per the Revised proposal

Ground Coverage : 9086.90 sqm. (17.72% of land area) 

: 9736.79 sqm. (18.99% of land area) 

Total Paved Area : 12192.15 sqm. (24.17% of land area) 

: 12562.96 sqm. (24.50% of land area)

Landscaped Green Area : 21727.01 sqm. (42.37% of land area)

: 19832.49 sqm. (38.675% of land area)

Area for future development : 7500.38 sqm. (14.75% of land area)

: 7500.38 sqm. (14.63% of land area)

Area gifted to local authority

: 566.56 sqm. (1% of land area)

: 1643.318 sqm. (3.205% of land area)

Total No. of plantation : 720 (Existing – 40, Proposed – 680)

: 720 (Existing – 40, Proposed – 680)

No. of Parking spaces proposed 

: 712 (Covered ­ 212, Open ­ 500)

: 755 (Covered ­ 220, Open ­ 535)

Total Power requirement : 6000 KW, CESC  : 6000 KW, CESC 

Backup Power  :  DG Sets   (1  x  40  KVA, 6  x 250 KVA)

:   DG   Sets   (1   x   40   KVA,   6   x   250 KVA)

The proponent has also mentioned that only boundary wall has been constructed at site.

Name of the Consultant is M/s. Centre for Sustainable Development. 

The   case   was   placed   for   reconsideration  in   the  60th  meeting   held   on   24.10.2011.  The   SEAC considered the submission by the proponent and recommended Environmental Clearance.

14. Proposed Medical College & PGI by ESIC Hospital & ODC (EZ) at JL No. 21, Mouza – Joka, Diamond Harbour Road, PS – Thakurpukur, Kolkata – 700104, West Bengal. 

Activity:

This is a proposal for development of Medical College & PGI. The proposed project shall consist of 500 bedded Teaching Hospital,  Medical College, Nursing College, Hostel,  Quarters, Guest House, Auditorium, Community Centre, Laundry, Canteen etc. This is an expansion proposal of the existing 300 bedded Hospital. 

Chronology of the event :

The presentation for   the  proposed  project  was made by School  of  Water  Resources  Engineering, Jadavpur University, in the 47th SEAC meeting held on 05.10.2010. 

The SEAC proposed conditions for  Environmental  Clearance for   the proposed project   in   the  48th 

meeting  held  on 09.11.2010  and  the  unit  was   informed  for   submission  of   sanctioned  plan  after 

Page 20 of 36

Page 21: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________necessary   incorporation   of   environmental   conditions   stipulated   by   SEAC   through   letter   dated 03.12.2010.

The proponent vide letter dated 22.06.2011 enquired whether final Environmental Clearance has been issued by the competent authority. The proponent was informed vide letter dated 11.07.2011 that final Environmental   Clearance   will   be   issued   by   the   SEIAA,   West   Bengal   only   after   submission   of sanctioned plan as per SCEC issued on 03.12.2010.

The proponent has once again informed vide letter dated 24.09.2011 that they have not yet received final Environmental Clearance. The case was placed for reconsideration in the 60th meeting held on 24.10.2011.  However,   the   proponent   has   not   submitted   requisite   documents   for   processing   final Environmental Clearance since 24.10.2011.

The SEAC agreed to inform the proponent that in continuation to the communications from the SEAC, West Bengal dated 03.12.2010 and 11.07.2011, the case would be considered only after submission of sanctioned  building  plan  alongwith   the  comparative  statement  and  current   status  of   the  proposed project. 

The  SEAC  also  decided   to   caution   the   project   proponent   that   no   activity   related   to   the   project including civil construction, can be undertaken at site except fencing of the site and construction of temporary sheds for guards before obtaining Environmental Clearance from the State Environment Impact Assessment Authority, West Bengal and Consent to Establish from the West Bengal Pollution Control Board. 

It has been decided that the case shall be further considered only  after  submission of  the  necessary submission.

15. Proposed Software Park by M/s. DELTA PV Pvt. Ltd. at Plot No. A1­3, Block ­ GP, Sector – V, Salt Lake, Kolkata – 700 091, Dist. – 24 Parganas (North). Name of the Consultant – M/s. Centre for Sustainable Development.

Activity:

This is a proposal for construction of a Software Park (1 block of B+G+20 storied building). 

Chronology of the event :

The proponent  delivered  a  powerpoint  presentation  in   the  55th  meeting held on 10.06.2011.  The presentation   before   the   SEAC  required   further  detailing   as   mentioned  during   the   meeting.  The proponent delivered a revised powerpoint presentation in the 58th SEAC meeting held on 19.08.2011. The SEAC proposed conditions for Environmental  Clearance  in   the  58th  SEAC meeting held on 19.08.2011.  The proponent has now submitted vide letter dated 12.10.2011 copy of building plan sanctioned   by   NDITA   on   24.06.2011.   The   salient   features   of   the   proposed   project   alongwith comparative statement remains unchanged. The proponent has mentioned that construction activity has not been started yet.

The name of the Consultant is M/s. Centre for Sustainable Development. 

Page 21 of 36

Page 22: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________The   case   was   placed   for   reconsideration  in   the  60th  meeting   held   on   24.10.2011.  The   SEAC considered the submission by the proponent and recommended Environmental Clearance.

16. Proposed  construction   project   of   "National   Institute   of   Biomedical  Genomics"   by  National Institute of Biomedical Genomics at Holding No. 34/1, Dag No. 7 & 29, Khatian No. 5, JL No. 75, Gayeshpur Municipality Ward No. 19, Mouza – Gopalpur, PS – Kalyani, Dist – Nadia, West Bengal. 

Activity:

This is a proposal for construction of the Campus of National Institute of Biomedical Genomics, An Autonomous Institution of Government of India, Department of Biotechnology. The complex includes the Main Building (G+4), Faculty Housing (G+4), Director’s Bungalow (G+1), VIP Hostel (G+3), Hostel (G+3), Dinning, Recreation (G+1), Collection Store, Creche, Auditorium (B+G), Substation, Water Tower, Bank, Staff Facilities, Security Rooms, Pump Room etc. 

Chronology of the event :

The proponent delivered a powerpoint presentation in the  59th  SEAC meeting held on 20.09.2011. During presentation in the 59th SEAC meeting held on 20.09.2011, the committee noted that ­

1. The project proponent has stated that existing trees will be retained.

2. Low flow appurtenances shall be used in the buildings. Water meter will be installed in the buildings. 

3. The area development will be done in the project site considering HFL of the area.

The observations of the committee in the 59th SEAC meeting held on 20.09.2011 and the consequent responses of the project proponent on 14.10.2011 are prescribed in the following table :

Recommendations / Directions of the Committee, issued on 30.09.2011

Response of the Proponent submitted on 14.10.2011

1. the list and number of existing trees as well as the number of existing trees to be retained should be provided in detail. Revised list of plantation should be submitted as discussed in the meeting.

1. The proponent has mentioned that a total of 103 no. of trees existing at the site will be retained. The proponent has also submitted the revised list of plantation.

2. The   SEAC   has   noted   that   the   project proponent   has   proposed   illumination   of common area by using of solar light but the location   of   solar   panels   have   not   been specified. 25% external illumination by solar lighting   should   be   substantiated   with adequate details on the lighting arrangement. The   solar   water   heating   should   also   be introduced in the buildings.

2. The proponent has mentioned that 25% of street   lighting   i.e.   42  nos.  of   street   lights will be solar powered. Further, solar water heating   will   be   introduced   in   buildings requiring hot water .

Page 22 of 36

Page 23: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Recommendations / Directions of the 

Committee, issued on 30.09.2011Response of the Proponent submitted on 

14.10.20113. Utilisation   of   fly   ash   building   materials 

should be submitted as per the MoEF latest Notification.

3. The proponent  has mentioned  that   fly  ash building materials will be utilised as per the MoEF notifications.

4. The  proponent  should  clearly  state  whether the paved area is fully paved or semi­paved.

4. The   proponent   has   mentioned   that   paved area shown in the layout is semi paved with 50% hardscape and 50% softspace.

5. A larger copy of gridded Master Plan to be submitted.

5. The proponent has submitted a larger print of gridded Master Plan.

6. Considering   the   typical   nature   of   Research and Development activity to be conducted in this institute, the SEAC requested to comply with the following conditions :­

a) Groundwater   recharge   is   not   desired rather the project proponent should ex­plore the scope of creation of small wa­terbody   for   enhancing   the   surface   re­charging.

b) The   laboratory   waste   as  well   as   solid waste,   even   if   the   quantity   is   small, should   never   be   mixed   with   other sources rather these should be treated in a   separate   system,   preferably   through incineration at CHWTSDF.

c) The rules  and provisions as  applicable in this case for the radio active wastes and biomedical wastes should be strictly followed.

d) Copy of MoU for disposal of Bio­haz­ardous waste to be submitted.

a) The   proponent   has   mentioned   that   no groundwater   recharge   would   be   done. Instead, 10 surface /  storage tanks will  be provided to enable surface recharge.

b) The   proponent   has   mentioned   that laboratory waste and solid waste will never be   mixed   with   other   sources.   The biomedical   waste   would   be   segregated, treated   and   disposed   of   through incineration.

c) The  proponent  has  mentioned   that   use  of radioactive   materials   is   not   envisaged   at present.   However,   if   used   in   future radioactive  wastes  will  be  handled  as  per the   Government   of   India   Rules,   as applicable.

d) The proponent has submitted copy of MoU with   M/s.   Semb   Ramky   Environment Management   Pvt.   Ltd.   for   disposal   of biomedical waste.

7. Name of consultant should be mentioned 7. The   proponent   has   mentioned   that   M/s. Ghosh, Bose & Associates, Kolkata, have been   appointed   to   render   comprehensive design consultancy services for the project.

The case was placed for reconsideration in the 60th meeting held on 24.10.2011. 

The SEAC considered  the submission by  the proponent and  finalised  Stipulated Conditions  for Environmental Clearance. The set of environmental conditions are annexed as Annexure 1.

Page 23 of 36

Page 24: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________17. Proposed Commercial cum Residential project by M/s. Bengal Ambuja Housing Development 

Limited at City Centre, Haldia, West Bengal. Name of the Cosultant – NIL.

Activity:

This  is  a  proposal   for  construction of  Commercial  cum Residential  Complex   in   two phases.  The Commercial Complex is proposed to be developed in Phase I and the Residential Complex in Phase II. The   Commercial   Complex   will   comprise   of   shopping   mall,   multiplex,   food   court,   family entertainment centre etc. The Residential Complex will have 112 dwelling units. 

Chronology of the event :

The proponent delivered a powerpoint presentation in the 3rd meeting held on 29.05.2007.

The State Level Expert Appraisal Committee (SEAC) granted Provisional Environmental Clearance vide letter dated 13.07.2007. The unit mentioned in the letter dated 02.09.2010 that building plan has been sanctioned by Haldia Municipality for PHASE I. However, the plan submitted does not bear any authorization of Haldia Municipality and the total paved area is exceeding 25% of land area. 

The reply dated 02.09.2010 from the project proponent was placed before the SEAC in the 46th SEAC meeting   held   on   06.09.2010  and   the   SEAC   appreciated   the   effort   to   comply   with   the   recent environmental   norms   and   stipulation.   However,   considering   the   fact   that   adequate   area   is   still available in Phase­II, the SEAC requested the project proponent to modify the proposal to limit the paved area within 25% of land area for the total project. Further it was noted that the copy of plan submitted has not been endorsed by HDA.

The   proponent   has   submitted   on   15.09.2011   the   Site   Plan   approved   by   Vice   Chairman,   Haldia Municipality, on 30.08.2011 along with the comparative statement for the proposed PHASE – I. The modified salient features are given below :­

Salient Features As per Provisional EC As per execution plan sanctioned drawing for PHASE – I

Land area 5.37 acres 5.37 acres

Building Description The   Commercial   Complex is proposed to be developed in   Phase   I   and   the Residential   Complex   in Phase II.

The   Commercial   Complex   will comprise   of   shopping   mall, multiplex,   food   court,   family entertainment centre etc.

Estimated Population Residential   560,   total ­11643.

Total Water Requirement  440   KLD   (Haldia Municipality supply)

240 KLD for Phase I

Wastewater Generated 350 KLD  50 KLD for Phase I

Wastewater Recycled 30 KLD for Phase I

Wastewater Discharged 20 KLD for Phase I

Page 24 of 36

Page 25: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Salient Features As per Provisional EC As per execution plan sanctioned 

drawing for PHASE – ISolid waste disposal 1.9 tonne per day

Total Built­up Area 57883 sqm. 28130.49 sqm. for Phase IGround coverage 39.19% 7770.0 sqm. (35.75%)

Water Body 1.97% Nil

Total Number of trees 130 for Phase I

Greenery 15.23% Phase I – 9.78%

Phase II 15.56%

Total 25.33% (Phase I & Phase II)

Parking Surface   Car   Parking   –   99 nos., Basement Car Parking – 334 nos., Total – 433nos. 

For Phase I

Surface Parking – 50 nos., Basement Parking – 134 nos.

Total Power Requirement 3750 KW, WBSEB 3750 KW, WBSEB

Internal Road 11.71% for Phase I

Paved Area 2.86%

Grass Pavers Block Phase I – 14.64%

Phase II – 5.41%

Total (Phase I & Phase II) = 20.09%

Back up Power  DG Sets  (1x 150 KVA, 1x 1000 KVA, 3x 1750 KVA)

DG   Sets   (1x   150   KVA,   1x   1000 KVA, 3x 1750 KVA)

The proponent has also mentioned that boundary wall and site office has been constructed. 

The comparative statement for the proposed PHASE – I is placed before the SEAC in the 59th meeting held on 20.09.2011. The proponent has submitted vide letter dated 20.10.2011 two copies of site plan.

The proponent earlier submitted Rapid EIA report prepared by Environmental Engineers Consortium. The   case   was   placed   for   reconsideration  in   the  60th  meeting   held   on   24.10.2011.  The   SEAC considered the submission by the proponent and recommended Environmental Clearance.

18. Proposed  Residential  Complex  by  M/s.  Lingraj  Properties  Pvt.  Ltd.  at  JL No.  48,  Mouza – Kumrakhali, PO – Narendrapur, PS – Sonarpur, Rajpur­Sonarpur Municipality, Kolkata – 700 103, Dist – South 24 Parganas. Name of the Consultant – M/s. JB Enviro Consultants Pvt. Ltd.

Activity:

This is a proposal for construction of a Residential Complex having 479 flats (7 blocks of B+G+18 storied buildings).

Page 25 of 36

Page 26: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Chronology of the event :

The proponent delivered a powerpoint presentation in the 59th meeting held on 20.09.2011. 

During  presentation in the  59th SEAC meeting, the committee recommended the following  and the proponent submitted their reply on 20.10.2011 ­

The observations of SEAC in the 59th meeting held on 20.09.2011 and consequent responses of the project proponent on 20.10.2011 are prescribed in the following table : 

Recommendations / Directions of the Committee, issued on 30.09.2011

Response of the Proponent submitted on 20.10.2011

1. The   project   proponent   should   obtain assurance   from   Municipality   that   they   will ensure   supply   of   arsenic­free   water   to   the proposed project.

1. The proponent has submitted copy of the letter   dated   19.10.2011   from   Chairman Rajpur   Sonarpur   Municipality  ensuring supply   of   arsenic­free   water   to   the proposed project.

2. The recharge in this arsenic prone zone should be designed as per the MoEF Manual for large construction projects and provisions of State Ground   Water   Act.   Revised   Rainwater Harvesting   Plan   should   be   submitted   as discussed in the meeting.

2. The   proponent   has   submitted  Revised Rainwater Harvesting Plan.

3. 20% tree plantation area and other green area should   be   clearly   shown   in   a   scaled   and gridded plan. Revised plantation list should be submitted.

3. The   proponent   has   submitted  scaled   and gridded plan and revised plantation list.

4. The   SEAC   has   noted   that   the   project proponent   has   proposed   illumination   of common area by using of solar light, but the location   of   solar   panels   have   not   been specified.   Details   of   the   solar   lighting proposal should be submitted.

4. The  proponent  has   submitted   solar   street lighting plan.

5. The  total   impervious  area of   the  site  within permissible Ground Coverage and Paved Area stipulations.

5. The   proponent   has   mentioned   that  total impervious area of the site will be within permissible   Ground   Coverage   and   Paved Area stipulations.

6. Detailed car parking calculation as per West Bengal   Municipal   (Building)   Rules,   2007 should be submitted.

6. The proponent  has submitted  car  parking calculation.

The case was placed for reconsideration  in the  60th meeting held on 24.10.2011.  The name of the Consultant is M/s. JB Enviro Consultants Pvt. Ltd. However, as the presentation was delivered in the 

Page 26 of 36

Page 27: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________59th SEAC meeting held on 20.09.2011, the SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section) in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting considered the submission by the proponent and finalised Stipulated Conditions for Environmental Clearance. The set of environmental conditions are annexed as Annexure 2.

B.  Miscellaneous :­

1. Relevant Circulars  /  Notification of  the Ministry of Environment  & Forests,  Government of India. 

The following circulars and /  or  notifications has been issued by the Ministry of  Environment & Forests –

i. O.M. [30/09/2011] ­  Accreditation of  the EIA Consultants  with Quality  Council  of India (QCI) National Accreditation Board of Education and Training (NABET). [Updated: October 11th, 2011]

ii. O.M. [05/10/2011] ­ Integrated Steel Plants and Sponge Iron Plants, which are linked to iron ore   as   raw   material   from   mining   operations   in   the   Districts   of   Bellary,   Tumkur   and Chitradurga in Karnataka. [Updated: October 5th, 2011]

iii. O.M. [05/10/2011] ­ Ownership of EIA report and other documents by the project proponent. [Updated: October 5th, 2011]

iv. Adherence   to   the   procedure   for   conduct   of   Public   Hearing   as   prescribed   in   the   EIA Notification, 2006 ­ Regarding. Dated September 28, 2011. 

v. Consideration   of   projects   for   environmental   clearance   based   on   Comprehensive Environmental   Pollution   Index   (CEPI)   ­   Extension   of   Moratorium   up   to   31.03.2012   ­ Regarding. Dated September 27, 2011.

vi. Mining Projects from the Districts of Bellary, Tumkur and Chitradurga in Karnataka ­ reg. Dated: September 20, 2011. 

vii. Consideration of projects for grant of environment clearance under EIA Notification, 2006, which involve forestland ­  Procedure  to  be followed ­  further  clarifications ­  reg. Dated: September 9, 2011.

The matter was placed for information in the 60th meeting held on 24.10.2011.

The SEAC noted all the above mentioned Relevant Circulars / Notification in general and  considered the Office Memorandum dated 30.09.2011 in particular. It was decided that as mentioned in the Office Memorandum, the submission endorsed by Category – C consultants shall not be considered for the presentation   cases   any   further.   However,   for   the   reconsideration   cases   the   status   of   relevant environmental data and information provided before 30.09.2011 shall be considered with due regard to the status of eligibility of the concerned consultant prevailing during that period of time.

Page 27 of 36

Page 28: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

Session II

C. Technical Presentations: ­

1. Proposed modernization of the existing 5th unit of Bandel Thermal Power Station by M/s. West Bengal Power Development Corporation Ltd. at Bandel, Dist – Hooghly, West Bengal. Name of the Consultant – M/s. M.N Dastur & Co. Pvt. Ltd.

Activity:

1. This is a proposal for renovation and  modernisation of the existing 5th  unit of Bandel Thermal Power Station resulting in capacity augmentation of 5th unit from 210 MW to 215 MW. Presently BTPS has 4x60 MW (derated capacity) and 1x210 MW units. The proposed capacity enhancement will be achieved by improving the efficiency of the 5th Unit. 

2. Salient features of the proposed modernisation project are :i. Location of the Site ­ Plot Nos. – Bandel, Dist. ­ Hooghly, West Bengal.ii. Land Area – existing plant. iii. Proposed installation – Efficiency of the 5th unit and other auxiliaries will be enhanced. iv. Raw Materials ­ Coal (1.2 MTPA), Start­up Fuel (2391 KL/annum).v. Emission Control System ­ ESP efficiency will be enhanced, stack of adequate height from 

GL.vi. Additional Water Requirement ­ nil.vii. Effluent   ­  DM Plant  effluent will  be  treated   in  a  neutralisation   tank,  all  effluent will  be 

collected in a guard pond. Treated effluent will be used for dust suppression, gardening etc. and excess treated water will be discharged to River Hooghly through existing drain of the plant. 

viii. Ash Handling System ­ Fly Ash will be disposed of in dry condition. Provision will be kept for ash pond for Bottom Ash and unused dry flyash.

The proponent has proposed ToR for EIA­EMP study. The name of the consultant is M/s. M.N Dastur & Co. Pvt. Ltd. 

The  case  was  put  up   for   consideration   in   the  60th  meeting  held  on  24.10.2011.  After   carefully considering the proposal and presentation the committee recommended Terms of Reference (ToR) for conducting EIA. The ToR is annexed as Annexure 3.

2. Proposed  Residential  Complex   by   M/s.   Fortune   Park   Housing   Projects   Pvt.   Ltd.   at   168 Krishnanagar Road, Vill. – Paschim Khilkapur, Mouza – Moynagadi, PS – Barasat, Dist. ­ 24 Parganas (N). Name of the consultant ­ M/s. Centre for Sustainable Development. 

Activity:

This is a proposal for construction of a  Residential Complex having 819 flats (13nos.  G+11 storied buildings and 1no. G+7 storied building) and Club cum Community Building (G+2 storied). 

Page 28 of 36

Page 29: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________Chronology of the event :

Salient features of the proposed project are – 

Land Area  : 5.841 acres (23641.5 sqm.)

Expected Population : 4100 (fixed), 510 (floating)

Total Water requirement : 710 KLD 

Fresh Water requirement : 632 KLD (Panchayat supply / Groundwater)

Domestic Water requirement : 626 KLD

Wastewater generated  : 500 KLD (to be treated in STP)

Wastewater reclaimed  : 450 KLD (after treatment in STP)

Wastewater recycled  : 70 KLD (to be reused after treatment in STP)

Wastewater discharged  : 380 KLD (to be discharged through panchayat drain after treatment in STP)

Solid waste disposal : 2.35 tonnes per day (to be disposed through local panchayat)

Total Built­up Area : 81360.39 sqm. 

Ground Coverage  : 7167.01 sqm. (30.32% of land area) 

Building Ground Coverage    : 6931.06 sqm. (29.32% of land area)

Cantilever Area  : 235 sqm. (1% of land area) 

Landscaped Green Area  : 5574.97 sqm. (23.58% of land area)

Other Soft Area  : 5796.23 sqm. (24.52% of land area)

Total Paved Area  : 5139.23 sqm. (22.58% of land area)

Proposed waterbody : It is not clear whether any waterbody exists or has been proposed

No. of plantations proposed  : 350

No. of Parking spaces proposed 

: 597 (covered – 220, open ­ 377)

Total Power requirement : 3000 KW, WBSEDCL

Backup Power  : DG Sets (4x250 KVA) 

The name of the Consultant is M/s. Centre for Sustainable Development. 

The  case  was  put  up   for   consideration   in   the  60th  meeting  held  on  24.10.2011.  After   carefully considering the proposal and during the presentation the committee  noted that – 

1. The project has been proposed in an arsenic prone zone. As per the provision of MoEF, New Delhi guidelines on large building projects, groundwater abstraction and recharging cannot be allowed in this area.

Further, approx. 632m3/day groundwater is proposed to be abstracted from this arsenic prone zone. However, no information is available about the depth of borewell and impact of abstraction. 

Page 29 of 36

Page 30: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________2. The proponent has mentioned that water requirement will  be met from Panchayat supply. 

Details of water source, quality and quantity of Panchayat water supply should be provided alongwith specific commitment from concerned authority.

3. No information has been provided about the carrying capacity of the adjacent drainage system in which runoff from the project site in addition to 380m3/day of treated wastewater has been proposed to be discharged. The route of transport of stormwater as well as treated wastewater to the final recipient waterbody is also not specified.

Details of stormwater and treated wastewater discharge, conveyance to the final recipient waterbody should be provided alongwith necessary concurrence of concerned authority.

4. Details of solid waste collection, transport and disposal scheme alongwith concurrence of concerned authority.  The copy of Municipal Solid Waste (MSW) authorization should be valid.

5. Existing trees and waterbodies, if any, should be specified.

6. Land conversion certificate should be submitted. The detailed list of landuse classification of dag nos. should be provided.

7. It has been noted that PVC grass cell structure has been proposed with 25% hard area and 75% soft area. Typical design drawing should be provided.

All   such   details   should   be   be   obtained   from   the   competent   and   concerned   authorities   with necessary endorsement and should be submitted to the SEAC. 

It has been decided that the case shall be further considered only  after  submission of the necessary clarification.

3. Proposed construction of Township, Residential & Commercial Complex “URBANA” by M/s. Bengal NRI complex Limited at 782 & 783, Anandapur, PO – EKTP, Kolkata – 700 107. Name of the Consultant – NIL.

Activity:

This   is   a   proposal   for   development   of   a   Township   consisting   of   Residential   and   Commercial Complexes. The Residential Complex shall comprise of 912 dwelling units in 2 Apartment Towers (5nos. G+40 & 2nos. G+45 storied buildings) and 48 Bungalows. The Commercial Complex shall comprise of 2 Office Towers (2B+G+6 Podium+34 storied building & 2B+G+6 Podium+26 storied building). 

Chronology of the event :

The project proponent delivered a powerpoint presentation in the 25th SEAC meeting on 31.10.2008.

The State Level Expert Appraisal Committee (SEAC) granted Provisional Environmental Clearance during 26th SEAC meeting held on 28.11.2008.

The unit submitted on 07.05.2010, the copy of the building plan sanctioned by KMC on 09.04.2010 & 24.04.2010 for  PHASE I  of   the  proposed  project.  The  modified   features  of   the  proposed  project (PHASE I) was placed in the 44th SEAC meeting held on 12.07.2010. The observations of the SEAC 

Page 30 of 36

Page 31: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________in the 44th SEAC meeting held on 12.07.2010 and the consequent response from the unit submitted on 02.09.2010 are prescribed in the following table :

Recommendations / Directions of the Committee

Response of the Proponent 

1. Area of waterbody should be mentioned. The status of the water body (existing or proposed) should be mentioned explicitly alongwith supporting documents. 

1. The   PP  has   mentioned   that   the   area   of   the proposed   waterbody   will   be   same   as   that specified   in   the   provisional   environmental clearance.   The   PP   has   also   mentioned   that there   is   no   existing   waterbody   within   the premises.

2. The   rationale   for   assuming   per   capita water consumption of 175 lpcd should be mentioned   and   scope   for   minimization should also be explored and reported.

2. The PP has mentioned that they have assumed per capita water consumption of 175 lpcd as per   the   Manual   on   Water   Supply   and Treatment. 

3. Quantity   of   wastewater   recycled   and discharged should be mentioned.

3. The   PP   has   mentioned   the   quantity   of wastewater to be recycled and discharged.

4. Clearance for the height of the building from   the   Airport   Authority   of   India should be submitted. 

4. The PP has mentioned that obtaining Height clearance from AAI was not a requirement for plan sanction by KMC. 

5. Considering   the   condition   of   water availability   in   that   locality   and   the dimension of the project, the SEAC also decided that the project proponent should obtain   the   permission   for   water abstraction   from   concerned   authorities and   submit   the   same   to   the   SEAC  for further processing of this project.

5. The  PP has  mentioned   that  SWID will   take necessary  decision  on  the  basis  of   technical report to be submitted by Jadavpur University. The PP has enclosed the permit  for  one no. existing tubewell with rate of withdrawal 20 m3/hr. The rate of withdrawal of the proposed tubewell   will   be   50   m3/hr.   The   PP   has mentioned   that   the   water   requirement   for PHASE I shall be met from 2nos. tubewells (one existing and one proposed).

6. Status of the project at present should be stated.

6. The PP has mentioned that work on test piles installation, conducting pile load test and site preparation works are in progress.

The proponent has also submitted mouza maps of Madurdaha mouza. 

The committee scrutinized the submission in the 46th SEAC meeting held on 06.09.2010 and it was agreed that considering the typical ground water condition in that particular area and also the status of proposed municipal water supply, the project proponent should first ensure availability of adequate water atleast for operation of Phase­I and in support of their claim they should submit the permission from the competent authority for ground water abstraction. 

The proponent submitted a letter on 17.08.2011 alongwith the permission of SWID dated 11.07.2011, which was  considered in  the  58th  SEAC meeting held on 19.08.2011.  The SEAC noted that  the 

Page 31 of 36

Page 32: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________proponent  has  obtained permission from the SWID for  sinking one no.   tube well  of  capacity  50 cum/hr. Accordingly, they have restructured your PHASE – I development. Further, the committee recommended that following information may be submitted – 

a) detailed comparative statement of salient features for the proposed restructured PHASE – I development.

b) NOC for height clearance from the Airport Authority of India, if applicable.

However, the proponent has submitted on 12.09.2011 revised parameters and sought amendment of Provisional Environmental Clearance earlier granted by the SEAC. The modified building profile is as follows –

  Earlier proposal as mentioned in PEC Revised proposalResidential  Complex having 912 dwelling units   (5nos.   G+40  &   2nos.   G+45   storied buildings) and 48 Bungalows. The  Commercial  Complex   shall   comprise of  2  Office Towers  (2B+G+6 Podium+34 storied   building   &   2B+G+6   Podium+26 storied building).

Residential Complex 5nos. G+45 storied buildings (tower no. 2,3,4,5&6) and 2nos. G+40 storied buildings (tower no. 1 & 7) Other components will remain unchanged.

In the previous letter submitted on 17.08.2011 the proponent mentioned that PHASE I development shall consist of 4 towers (1, 2, 6 & 7) only. 

Further,   the   proponent   submitted   on   14.09.2011   comparative   statement   of   earlier   PHASE   I development and the proposed PHASE I development. The revised parameters and the comparative statement could not be scrutinised in detail. 

The   letters   dated   09.09.2011   and   13.09.2011   were   placed   in   the  59th  SEAC   meeting   held   on 20.09.2011. The committee noted that ­

1. In   the   earlier   letter   submitted   on   17.08.2011,   the   proponent   mentioned   that   PHASE   I development shall consist of 4 towers (1, 2, 6 & 7) only. 

2. However,   the proponent has submitted revised parameters for  the entire Township in  the letter   dated   09.09.2011   and   sought   amendment   of   Provisional   Environmental   Clearance earlier granted by the SEAC for the modified proposal.

The  SEAC requested   the  proponent   to  deliver  a  detailed  powerpoint  presentation  on   the   revised proposal for the overall Township project.  

The case was put up for consideration in the  60th  meeting held on 24.10.2011.  The name of the Consultant is not mentioned. The SEAC in tune with the decisions taken in the 59th meeting held on 20.09.2011 (vide serial no. 3 & 4 of the Miscellaneous Section)  in connection to the MoEF Office Memorandum dated 30.06.2011 and the 30th September deadline as well as the decisions taken in this meeting considered the proposal and during the presentation the committee noted that construction has been started. The water quality tests report for the approved capacity of water is not available. 

The  SEAC requested   the  project  proponent   for   submission  of  detailed   information   regarding   the borewell depth as well as quantity of water available, water requirement for the proposed project, the 

Page 32 of 36

Page 33: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________water  quality   test   report  and corrected water  balance diagram.  The comparative statement  for   the greenbelt should also be submitted. Considering the current status of permission of water abstraction, the SEAC not in a position to consider any further amendment for increasing the construction area (Total   Built­up   Area)   in   the   communication   dated  13.02.2009   in   which   the   conditions   for Environmental Clearance was stipulated by the SEAC, West Bengal (erstwhile termed as Provisional Environmental Clearance earlier). 

It has been decided that the case shall be further considered only  after  submission of the necessary clarification.

Summaries of above decisions are also provided in Table­1.

Table­1 : List of the projects which were placed before the SEAC in the sixtieth meeting held on 24.10.2011 at 12:00 hrs. and the Summary Decisions thereof:

A Cases placed for consideration of Environment Clearance Sl.  No.

 Name of the unit  Summary Decision

1. M/s. Salasar Cements 

Proposed   Cement   Grinding   Unit   at   Plot   No.   –   G10,   Mangalpur Industrial Estate, PS – Raniganj, PO – Baktarnagar, Dist. ­ Burdwan, Pin – 713 321, West Bengal

AAS

2. M/s. Birla Corporation Ltd., Unit : Durgapur Cement Works 

Proposed   expansion   of   the   existing   Cement   Grinding   Unit   and installation of CBM based Captive Power Plant at Jl. No. – 62 & 63, Vill.  –  Sujara,  Near  DSP Slag Bank,  Durgapur  ­  713203,  Dist.   ­ Burdwan, West Bengal

REC

3. M/s. Balaji Paper & Newsprint Private Limited 

Proposed Waste paper based plant and Cogeneration Captive Power Plant   at   Jl.   No.   –   561,   562,   649,   650,   Vill.   ­   Manikpara,   PS   – Jhargram, Dist. – Pashim Medinipur, Pin – 721513, West Bengal

AAS

4. M/s. Maa Gouri Cement Industries 

Proposed expansion of the Cement Grinding Unit at Plot No. – 391 (P), 392, Jl. No. – 53, Vill. & PO – Kuldiha, SD ­ Durgapur, PS – Kanksa, Dist. ­ Burdwan, Pin – 713212, West Bengal.

AAS

5. M/s. Shivam Meltech Pvt. Ltd. 

Proposed expansion project for installation of Induction Furnace and Continuous   Casting   Machine   at   Jl.   No.   –   58,   Vill.   –   Gopalpur, Mouza ­ Bamunara, PS – Kanksa, SD – Durgapur, Dist. ­ Burdwan, West Bengal.

AAS

Page 33 of 36

Page 34: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

A Cases placed for consideration of Environment Clearance Sl.  No.

 Name of the unit  Summary Decision

6. M/s. VSP Udyog Pvt. Ltd.

Proposed expansion project for installation of Induction Furnace at Jl. No. – 58, 65, Banskopa More, Vill. & Mouza – Gopalpur, PO ­ Bamunara, PS – Kanksa, SD – Durgapur, Dist.  ­  Burdwan, Pin – 713212, West Bengal

AAS

7. M/s. Strongbonds Polyseal Pvt. Ltd. 

Proposed   expansion   project   for   enhancement   of   production   of Unsaturated Polyester Resins at Plot No. – 26/C, 26/D/1 & 26/D/2, Kalyani Industrial Estate Phase I, Block – D, Dist. – Nadia, Pin – 741235, West Bengal

REC

8. M/s. Oriental Sales Agencies (India) Pvt. Ltd.

Proposed  Residential   Complex   &   Hospital   at   2,   Jessore   Road, Holding No. – 380 (N), 1108 (O), Cal­Jessore Road, Jl. No. – 19, Mouza – Dum Dum House,  South Dum Dum Municipality Ward No.   ­  07,  PO & PS – Dum Dum, Kolkata  –  700028,  Dist.  –  24 Parganas (North).

AAS

9. M/s. Designer Real Estate India Pvt. Ltd. 

Proposed  Residential Complex  “UJAAS”  at Plot No. 69, Holding No. – 152 (new), 97 (old), S.K. Deb Road, Jl. No. ­ 25, Mouza – Dakshindari, PS – Lake Town, South Dum Dum Municipality Ward No. 31, Dist – 24 Parganas (North) West Bengal.

REC

10. M/s. Avani Projects and Infrastructure Limited 

Proposed project including expansion of the Commercial Complex “AVANI RIVERSIDE MALL”  at 32, Jagat Banerjee Ghat Road, Howrah.

AAS

11. M/s. West Bengal Infrastructure Development Finance Corporation Ltd.

Proposed Residential Complex “SANKALPA II” at Prem. No. – 36, MAR (Plot No. – BF/1,  BF/2,  BF/3),  Action Area I,  New Town, Rajarhat, Kolkata, Dist. – 24 Parganas (North), West Bengal. 

AAS

12. M/s. Strand Properties Ltd. 

Proposed   renovation   and   reconstruction   project  "DIAMOND HERITAGE"  at   16, Strand Road, KMC Ward No. 45, PS ­ Hare Street, Kolkata ­ 700 001, West Bengal.

To be forwarded to SEIAA, West 

Bengal

Page 34 of 36

Page 35: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

A Cases placed for consideration of Environment Clearance Sl.  No.

 Name of the unit  Summary Decision

13. M/s. Bengal Peerless Housing Development Company Limited 

Proposed Residential Complex "AVIDIPTA” at R.S. Dag Nos. 125 (Part)  and 126 (Part),   J.L.  No.  21,  Premises  No. –  401,  Mouza  ­ Barakhola,  PS – Purba Jadavpur,  KMC Ward  No. 109,  Dist.    24 Parganas (S)

REC

14. ESIC Hospital & ODC (EZ)

Proposed  Medical  College  & PGI   at   JL No.  21,  Mouza  ­   Joka, Diamond   Harbour   Road,   PS   –   Thakurpukur,   Kolkata   –   700104, West Bengal. 

Provisions to be informed with no prior construction 

direction

15. M/s. DELTA PV Pvt. Ltd.

Proposed Software Park at Plot No. A1­3, Block ­ GP, Sector – V, Salt Lake, Kolkata – 700 091, Dist. – 24 Parganas (North).

REC

16. National Institute of Biomedical Genomics 

Proposed construction project of "National Institute of Biomedical Genomics" at Holding No. 34/1, Dag No. 7 & 29, Khatian No. 5, JL No. 75, Gayeshpur Municipality Ward No. 19, Mouza – Gopalpur, PS – Kalyani, Dist – Nadia, West Bengal.

SCEC Finalized

17. M/s. Bengal Ambuja Housing Development Limited 

Proposed   Commercial   cum   Residential   project   at   City   Centre, Haldia, West Bengal.

REC

18. M/s. Lingraj Properties Pvt. Ltd. 

Proposed Residential Complex at JL No. 48, Mouza – Kumrakhali, PO – Narendrapur, PS –  Sonarpur, Rajpur­Sonarpur Municipality, Kolkata – 700 103, Dist – South 24 Parganas.

SCEC Finalized

B Miscellaneous cases

Sl.  No.

Name of the unit & Project address Summary Decision

1. Relevant Circulars / Notification of the Ministry of Environment & Forests, Government of India

30.09.2011 onwards the MoEF – Office Memorandum shall be strictly followed.

Page 35 of 36

Page 36: Avidipta CESE Power Water Inlands

Minutes of the sixtieth meeting of the State Level Expert Appraisal Committee, West Bengal held on 24.10.2011 at    12:00    hrs. at the Conference Room, Paribesh Bhawan, Salt Lake.   

___________________________________________________________________

C Cases placed for presentationSl.  No.

Name of the unit & Project address Summary  Decision

1. M/s. West Bengal Power Development Corporation Ltd.

Proposed  modernization of   the existing 5th  unit  of  Bandel Thermal Power Station at Bandel, Dist – Hooghly, West Bengal.

ToR Finalized

2. M/s. Fortune Park Housing Projects Pvt. Ltd.

Proposed  Residential  Complex   at  168   Krishnanagar   Road,   Vill.   – Paschim Khilkapur,  Mouza – Moynagadi,  PS – Barasat,  Dist.   ­  24 Parganas (N). 

AAS

3. M/s. Bengal NRI complex Limited 

Proposed  construction   of   Township,   Residential   &   Commercial Complex  “URBANA”  at   782   &   783,   Anandapur,   PO   –   EKTP, Kolkata – 700 107. 

AAS

REC: Recommended Environmental Clearance, SCEC: Stipulated Conditions for Environmental Clearance, AAS: Asked for Additional Submission / Clarification

The meeting ended with a note of thanks to the Chair.

Page 36 of 36