Cap Ex Op Ex Feasibility

Embed Size (px)

Citation preview

  • 8/3/2019 Cap Ex Op Ex Feasibility

    1/42

    CapEx, OpEx, FeasibilityHouston Workshop

    Nov. 29, 2007

    Uwe Roeper, President, ORTECH

  • 8/3/2019 Cap Ex Op Ex Feasibility

    2/42

    ORTECH Power

    Wind Consulting: Technical & Financial Advisors

    Affiliated with DEWI

    German Wind Energy Institute

    Wind Resource Assessment

    Development Plans

    Operations Support Feasibility & Sector Analysis

    Due Diligence / Independent Engineers.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    3/42

    Outline

    Estimating CapEx Turbines

    Construction

    Other

    Estimating OpEx O&M Fixed & Variable Parts

    Analyzing Feasibility Revenue / Costs IRR

    Cost of Funds

  • 8/3/2019 Cap Ex Op Ex Feasibility

    4/42

    CapEx(Example 100 MW, $200 million)

    Development Costs Land, Wind, Grid, Permits

    Financing Costs

    Cost of Funds, Construction Interest

    Construction Costs

    Turbines, Commissioning, BOP

  • 8/3/2019 Cap Ex Op Ex Feasibility

    5/42

    Development Costs(Illustration)

    Land $100k Wind $200k

    Grid $100k

    Permits $200k

    Sub-total $600k (0.3% of Capital)

    Pre-Constr. $1,400k (0.7% of Capital)

    Total $2,000k (1.0% of Capital)

  • 8/3/2019 Cap Ex Op Ex Feasibility

    6/42

    Financing Costs(Illustration)

    Due Diligence $500k Equity Fee $2,500k

    Debt Fee $2,000k

    Constr. Int. $12,000k

    Total $16,500k (8.3% of Capital)

  • 8/3/2019 Cap Ex Op Ex Feasibility

    7/42

    Construction Costs(Illustration)

    Turbines $150mill. BOP $40mill.

    Financing $17mill.

    Development $2mill.

    Developer Fee $5mill.

    Total (2010) $214mill.

    ($2.1mill./MW)

  • 8/3/2019 Cap Ex Op Ex Feasibility

    8/42

    CapEx Summary

    CapEx (100MW, $214mill.)

    Turbines70%

    Dev.Fee

    2%

    BOP

    19%

    Financing

    8%

    Dev.Cost1%

    Turbines majority cost, rapid increases BOP site dependent, modest increases

    Financing going up due to project timing.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    9/42

    Balance of Plant Portion

    BOP Cost Make-up

    Ship

    Crane

    Found.

    Trnsf

    Substation

    CollectorRoads

    GridInstall

    Foundations are the often the largest BOP cost. BOPcosts can very widely depending on connection costsand the site location.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    10/42

    Turbine Costs

    Very large increase 2004 to 2007 Latest figure for 2009 delivery, could be special circumstance

    Several factors, currency, input costs, global market.

    Turbine Price Increase

    $1.0

    $1.5

    $2.0

    $2.5

    0% 3% 7% 17% 31% 52%

    Sample Quotations 2004 to 2007 (1.5MW Units)

    $Mill.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    11/42

    Changes in Euro exchange

    US$ - Euro Exchange

    1.00

    1.10

    1.20

    1.30

    1.40

    1.50

    FX Jan 04 to Nov 07

    US$

    Euro exchange is significant because many turbinecomponents come from Europe. Recent weakening ofthe US $ could put addition pressure on turbinepricing. However, not main recent for price incrs.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    12/42

    US Steel Price Index

    Steel prices and other commodities have increased substantially.This contributes to the price pressure, but does not account for allthe increases. Bulk is due to supply demand of turbines on theglobal market.

    US Steel Price Index

    100

    120

    140

    160

    180

    200

    Jan 04 - Oct 07

  • 8/3/2019 Cap Ex Op Ex Feasibility

    13/42

    Historical & Projected Wind Energy Costs

    0

    5

    10

    15

    20

    25

    30

    1980 1985 1990 1995 2000 2005 2010

    Year

    ce

    ntsUS/kWh

    Not attainable

    Adapted from: CanWEA 2004

    Price Reduction

    Due to

    Technology Innovation

    Recent

    Trend

  • 8/3/2019 Cap Ex Op Ex Feasibility

    14/42

    Key Issue

    What impact will the significant increases inturbine prices have on prices of wind power,

    and how could this affect the continued

    expansion of the wind industry in the US in thecoming years?

  • 8/3/2019 Cap Ex Op Ex Feasibility

    15/42

    OpEx

    Turbine design life 20 years, op. experience

  • 8/3/2019 Cap Ex Op Ex Feasibility

    16/42

    Cost of Warranty, ServiceMaintenance Contracts

    Example of price variability in WMS contracts.

    Hi quotes related to remote sites.

    Large WTGs typically have slightly higher $/WTG-yr. We will use $39,000/WTG-yr as typical for 1.5 MW turbine

    (limited ext. wty. + srvc.)

    $/WTG - O&M + Warranty (Yr. 3-5)

    $20

    $40

    $60

    $80

    1 2 3 4 5 6 7 8 9

    Thousands

    Selected Price Quotations by OEMs

  • 8/3/2019 Cap Ex Op Ex Feasibility

    17/42

    Wty. portion of WMSO&M Contract, $39,000/WTG-yr

    Service, $26,000

    Warranty, $13,000

    Warranty cost seldom broken out.

    Contractual exclusion vary. 1/3 Assumed as wty. portion of contracts.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    18/42

    WMS as part of total O&M

    WMS typically amounts to approx. 60% Largely market based, not indicative of actual.

    Avail. only for early years (few repairs).

    Warranty O&M - $(000)/WTG-yr

    O&M, $26

    Warranty, $13Reserve, $0

    Ins, $7

    Land, $5

    M-Tax, $9

    BOP, $5

    Adm, $5

  • 8/3/2019 Cap Ex Op Ex Feasibility

    19/42

    Post wty. Costs

    Post O&M - $(000)/WTG-yr

    Service, $25

    Maintenance, $4

    Repair Reserve, $16

    Ins, $7

    Land, $5

    M-Tax, $9BOP, $5

    Adm, $5

  • 8/3/2019 Cap Ex Op Ex Feasibility

    20/42

    Wty. Vs. Post Comparison

    Warranty vs Post O&M

    $0

    $10

    $20

    $30

    C$(000)/WTG-yr

    Warranty $26 $13 $0 $7 $24

    Post $25 $4 $16 $7 $24

    Service Wty/Mtc Reserve Ins. other

    Repair

    Maintenance is the expensed portion (recurringannully), Reserve is the capital portion.

    Mtc. + Reserve = $20,000/WTG-yr.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    21/42

    Service

    Routine day to day operation 24/7 Remote monitoring

    Scheduled maintenance

    On-site services

  • 8/3/2019 Cap Ex Op Ex Feasibility

    22/42

    Unscheduled Maintenance

    Unscheduled minor maintenance highlyvariable by site / model.

    Budget figure meant to refer to minorrecurring small part replacement.

    Excludes major component repairs.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    23/42

    Unscheduled Maintenance

    Unscheduled extension of on-site service. Relies on parts inventory or readily available

    parts that can be replaced by on-site service

    team. Involves recurring outages of short duration

    due to minor parts.

    Is tracked as operating expense, not as capitalreplacement expense.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    24/42

    FAILURE FREQUENCY & DOWNTIMECourtesy: B. Hahn, ISET: Wind Energy Report Germany 2006 (draft)

    Drive Train

    Structurals

    Generator

    Gearbox

    Rotor Hub

    Mech. Brakes

    Rotor Blades

    Yaw/Pitch Sys.

    Hydraulics

    Sensors

    Electronics

    Electrical

    Down time per failure [days]Annual failure frequency [-]

    1 0,75 0,5 0,25 0 2 4 6

    Maintenance

  • 8/3/2019 Cap Ex Op Ex Feasibility

    25/42

    Repair Reserve

    Planned or unplanned major repairs.

    Highly variable by site / model / age. Best to track as Capital Account Repair Reserve.

    Expected to occur only a few times during 20 year life.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    26/42

    FAILURE FREQUENCY & DOWNTIMECourtesy: B. Hahn, ISET: Wind Energy Report Germany 2006 (draft)

    Drive Train

    Structurals

    Generator

    Gearbox

    Rotor Hub

    Mech. Brakes

    Rotor Blades

    Yaw/Pitch Sys.

    Hydraulics

    Sensors

    Electronics

    Electrical

    Down time per failure [days]Annual failure frequency [-]

    1 0,75 0,5 0,25 0 2 4 6

    Major Repair

  • 8/3/2019 Cap Ex Op Ex Feasibility

    27/42

    Variable Annual Repair Costs

    Annual Repair & Maintenance Expenditure (illustration)

    $0

    $10

    $20

    $30

    $40

    $50

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Thousands

    Operating Year

    C$/WTG-yr

    Major repair costs will vary from year to year, occur inintervals and increase in cost with age.

    Wty.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    28/42

    Total life cycle costCumulative Repair Expenditure (w/o CPI)

    $0

    $100

    $200

    $300

    $400

    $500

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Thousands

    Operating Year

    C$/WTG-yr

    The operating goal is minimize the cumulative total throughpreventative maintenance, early detection, reduction of outagetimes etc.

    Small expenditure now may save big later.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    29/42

    Capital Account

    Purpose of the capital account is to ensure that the cost has been budgeted and thefunds are available, regardless of the year in which the repair occurs.

    In early years, repairs are less than $16,000/WTG-yr, excess is saved. In later yearsthe reverse happens.

    Capital Repair Reserve Account (w/o CPI)

    $0

    $20

    $40

    $60

    $80

    $100

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Thousands

    Operating Year

    C$/WTG-yr

  • 8/3/2019 Cap Ex Op Ex Feasibility

    30/42

    Accounting for InflationImpact of 2.5% Annaul Inflation

    $0

    $50

    $100

    $150

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

    Thousands

    Operating Year ($/WTG)

    Service Repair Ins. other

    Wty.

    Budgets can be inflation project forward by assuming inflationrate.

    Parts and labour costs may move differently than inflation.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    31/42

    Key Issue

    What is the financial risk related to theuncertainty of long term repair costs ofwind turbines?

  • 8/3/2019 Cap Ex Op Ex Feasibility

    32/42

    Feasibility

    Typical project feasibility CapEx, OpEx, Revenue

    Wind project feasibility

    CapEx, OpEx, Revenue, Tax

    Revenue market complex

    Tax driven structure complex Revenue / tax structure unique to U.S.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    33/42

    Composite Revenue(PPA, REC, Merchant, Hedges)

    Composite Revenue Example

    $0

    $5

    $10$15

    $20

    $25

    $30

    $35

    $40

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    Operating Year

    millions/year

    Merchant Revenue REC Revenue PPA Revenue

    Part Year

    PPA Ends

    Various market structures by State / Region.

    Revenue subject to complex policies / rules.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    34/42

    Net Revenue (EBITDA)

    Net Revenue / EBITDA

    0

    5

    10

    15

    20

    25

    30

    35

    40

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    Operating Year

    Million/Year

    Net Revenue Expenses

    EBITDA = earnings before interest, tax, depreciation,

    amortization (and before PTC) (but after OpEx)

    Basis for cash flow feasibility (IRR = internal rate of return)

  • 8/3/2019 Cap Ex Op Ex Feasibility

    35/42

    Earnings Perspective

    1525Adj. EBITDA

    04Gross up

    08PTC1513EBITDA

    -10-7OpEx

    2520Revenue

    Yr 15Yr 2

  • 8/3/2019 Cap Ex Op Ex Feasibility

    36/42

    Adjusted EBITDA

    PTC and PTC Gross-up create large earnings shift tofirst of project life.

    $0

    $5

    $10

    $15

    $20

    $25

    $30

    $35

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    Operating Year

    Million/Year

    EBITDA PTC Gross up

  • 8/3/2019 Cap Ex Op Ex Feasibility

    37/42

    Tax Perspective

    9-31Income a. tax

    8PTC

    -521Taxes14-59Taxable

    -1-72Tax DA

    1513EBITDA

    Yr 15Yr 2

  • 8/3/2019 Cap Ex Op Ex Feasibility

    38/42

    After Tax (incl. PTC & tax benefit)

    Wind projects generate large tax benefits in earlyyears. PTC add-back creates large after tax income inyear 7 to 11.

    Income after Tax

    -$40

    -$30

    -$20

    -$10

    $0

    $10

    $20

    $30

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    Operating Year

    Million/Year

  • 8/3/2019 Cap Ex Op Ex Feasibility

    39/42

    Cash Flow Perspective

    1042Cash F. a. tax

    -521Taxes8PTC

    (first yr. only)CapEx

    1513EBITDA

    Yr 15Yr 2

  • 8/3/2019 Cap Ex Op Ex Feasibility

    40/42

    Cash Flow after tax (unlevered)CFaftTax

    $5.0

    $10.0

    $15.0

    $20.0

    $25.0

    $30.0

    $35.0

    $40.0

    $45.0

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    Operating Year

    Large after tax CF in early years reduces long termrisk.

  • 8/3/2019 Cap Ex Op Ex Feasibility

    41/42

    Additional Feasibility Drivers

    Cost of debt / long term int. rates Cost of equity

    Wind resource compared to competing

    projects in the region

    Access to grid connections

  • 8/3/2019 Cap Ex Op Ex Feasibility

    42/42

    Conclusions

    CapEx Highly predictable On rise, concern to project economics

    OpEx

    Difficult to estimate long term costs Repair uncertainty managed by capital reserve

    Feasibility Revenue and tax issues more complex than other

    types of projects. In U.S. project feasibility is highly dependent on tax,

    energy and environment policy.