Ch05 Proj Plan

Embed Size (px)

Citation preview

  • 8/18/2019 Ch05 Proj Plan

    1/41

  • 8/18/2019 Ch05 Proj Plan

    2/41

    Project Planning

     There are several reasons to useconsiderable care when planning

    projects:  The primary purpose of planning is to

    establish a set of directions in enough detail

    to tell the project team exactly what must

    be done

     The purpose of planning is to facilitate later

    accomplishment

    Chapter 5-1

  • 8/18/2019 Ch05 Proj Plan

    3/41

    Initial Project Coordination

    It is crucial that the projects objectives beclearly tied to the overall mission of the

    !rm " project launch meeting is an initial

    coordinating meeting that serves as a visiblesymbol of top managements commitment to

    the project  The project launch meetings success is

    absolutely dependent on the existence of awell-de!ned set of objectives

    Chapter 5-#

  • 8/18/2019 Ch05 Proj Plan

    4/41

    Project Launch Meeting

    $hould not allow plans% schedules% andbudgets to go beyond the most aggregated

    level at the launch meeting  The outcomes should be:

    1& Technical $cope is established

    #& 'asic areas of performance responsibility

    are accepted by the participants

    (& $ome tentative overall schedules and

    budgets are spelled out

    Chapter 5-(

  • 8/18/2019 Ch05 Proj Plan

    5/41

    Composite Plan

    )ach individual*unit accepting responsibility for a

    portion of the project should agree to deliver a

    preliminary plan about how that responsibility will be

    accomplished

     These plans should contain descriptions of the re+uired

    tas,s% and estimates of the budgets and schedules

     These plans are then scrutinied by the group and

    combined into a composite project plan

    Chapter 5-.

  • 8/18/2019 Ch05 Proj Plan

    6/41

    Composite Plan

     The composite plan% still not completely !rm% is

    approved by each participating group% by the

    project manager% and then by senior

    organiational management

    )ach subse+uent approval hardens the plan% and

    when senior management has endorsed it% any

    further changes in the projects scope must be

    made by processing a formal change order 

    Chapter 5-5

  • 8/18/2019 Ch05 Proj Plan

    7/41

    Project Plan

     The !nal approved result of this procedure is theproject plan% also ,nown as a Master  or Baseline plan

    /nce planning phase is complete% it is bene!cial tohold a post-planning review

     The major purpose of the review is to ensure that allnecessary elements of a project plan have beenproperly developed and communicated

    Chapter 5-0

  • 8/18/2019 Ch05 Proj Plan

    8/41

    Project Plan Elements

     The process of developing the project planvaries among organiations% but any projectplan must contain the following elements:

    Overview - a short summary of the objectivesand scope of the project

    Objectives - " more detailed statement of thegeneral goals noted in the overview section

    General Approach - describes both themanagerial and technical approaches to the wor,

    Chapter 5-

  • 8/18/2019 Ch05 Proj Plan

    9/41

    Project Plan Elements

    Contractual Aspects - includes a complete listand description of all reporting re+uirements%customer supplied resources% liaison arrangements%

    advisory committees% project review andcancellation procedures% etc&

    Schedules - this section outlines the variousschedules and lists all the milestone events

    Resources - this includes the budget 2bothcapital and expense re+uirements3 as well as costmonitoring and control procedures

    Chapter 5-4

  • 8/18/2019 Ch05 Proj Plan

    10/41

    Project Plan Elements

    Personnel - this section lists the expected personnelre+uirements of the project including special s,ills%training needs% and security clearances

    Evaluation Methods - every project should beevaluated against standards and by methodsestablished at the projects inception

    Potential Problems -this section should include

    any potential diculties such as subcontractor default%technical failure% tight deadlines% resource limitationsand the li,e& 6replanning may avert some crises

    Chapter 5-7

  • 8/18/2019 Ch05 Proj Plan

    11/41

    Project Planning in Action

    6roject plans are usually constructed bylisting the se+uence of activities re+uiredto carry the project from start to

    completion% and developing an action planto complete the activities

     This helps the planner decide thenecessary se+uence of things

    $e+uencing is a necessary considerationfor determining the project schedule andduration

    Chapter 5-18

  • 8/18/2019 Ch05 Proj Plan

    12/41

    Project Planning in Action

    $oftware and hardware developerscommonly use a planning process

    oriented around the life cycle events: Concept evaluation

    9e+uirements identi!cation

    esign Implementation

     Test

    Chapter 5-11

  • 8/18/2019 Ch05 Proj Plan

    13/41

    Project Planning in Action

    $oftware and hardware developmentplanning process 2cont&3

    Integration

    ;alidation

    Customer test and evaluation

    /perations and maintenance

    Chapter 5-1#

  • 8/18/2019 Ch05 Proj Plan

    14/41

    Systems Integration

    Systems Integration is one part ofintegration management  and plays a crucialrole in the performance aspect of the project

     This includes any technical specialist in thescience or art of the project who is capableof integrating the technical disciplines toachieve the customers objectives

    Chapter 5-1(

  • 8/18/2019 Ch05 Proj Plan

    15/41

    Systems Integration

    Systems Integration is concerned withthree major objectives:

    Performance - what a system does

    Eectiveness - achieve desired performancein an optimal manner

    9e+uires no component speci!cations unlessnecessary to meet one or more systems re+uirements

    )very component re+uirement should be traceable to

    one or more systems re+uirements

    esign components to optimie system performance%

    not the performance of subsystems

    Cost Sstems - cost is a design parameter

    Chapter 5-1.

  • 8/18/2019 Ch05 Proj Plan

    16/41

    Hierarchical Planning

    System

    "ll activities re+uired to complete a project

    must be precisely delineated% and coordinated

    $ome activities must be done se+uentially%and some simultaneously

  • 8/18/2019 Ch05 Proj Plan

    17/41

    Sorting Out the Project

     The importance of careful planning can scarcely

    be overemphasied

    6into and $levin developed a list of ten factors

    that should be associated with success in

    implementation projects

     The factors were split into strategic and tactical

    clusters

    Chapter 5-10

  • 8/18/2019 Ch05 Proj Plan

    18/41

    Sorting Out the Project

    $trategic $uccess ?actors:

    Project Mission - spell out clearly de!ned and

    agreed-upon objectives in the project plan

    !op Mana"ement Support - it is necessary for

    top management to get behind the project at the

    outset% and ma,e clear to all personnel involved

    that they support successful completion Project#s Action Plan - detailed plan of the

    re+uired steps in the implementation process

    needs to be developed including all resource

    re+uirements Chapter 5-1

  • 8/18/2019 Ch05 Proj Plan

    19/41

    The or! "rea!do#n Structure

     The @or, 'rea,down $tructure 2@'$3 can

    ta,e a variety of forms that serve a variety

    of purposes

     The @'$ often appears as an outline with

    Aevel I tas,s on the left and successive

    levels appropriately indented

     The @'$ may also picture a projectsubdivided into hierarchical units of tas,s%

    subtas,s% wor, pac,ages% etc&

    Chapter 5-14

  • 8/18/2019 Ch05 Proj Plan

    20/41

    The or! "rea!do#n Structure

     The @'$ is an important document and can betailored for use in a number of diBerent ways

    It may illustrate how each piece of the project

    contributes to the whole in terms of performance%responsibility% schedule% and budget

    It may list the vendors or subcontractors associatedwith speci!c tas,s

    It may serve as the basis for ma,ing cost estimates orestimates of tas, duration

    It may be used to document that all parties havesigned oB on their various commitments to the project

    Chapter 5-17

  • 8/18/2019 Ch05 Proj Plan

    21/41

    The or! "rea!do#n Structure

    eneral steps for designing and using the @'$:

    1&

  • 8/18/2019 Ch05 Proj Plan

    22/41

    The or! "rea!do#n Structure

    eneral steps for designing and using the @'$ 2cont&3: .& The total project budget should consist of four elements:

    direct budgets from each tas,D an indirect cost budget for theprojectD a =contingency> reserve for unexpected emergenciesD

    and any residual% which includes the pro!t derived from theproject

    5& The project master schedule integrates the many diBerentschedules relevant to the various parts of the project

    Items 1-5 focus on the @'$ as a planning tool but itmay also be used to monitor and control the project

    Chapter 5-#1

  • 8/18/2019 Ch05 Proj Plan

    23/41

    The or! "rea!do#n Structure

    Items 0 and focus on the @'$ as an aid tomonitor and control a project:

    0& The project manager can examine actual resource

    use% by wor, element% wor, pac,age% tas,% up to thefull project level& The project manager can identifyproblems% harden the estimates of !nal cost%

    and ma,e sure that relevant corrections have beendesigned and are ready to implement

    & The project schedule may be subjected to the samecomparisons as the project budget& "ctual progress

    is compared to scheduled and corrective actioncan be ta,en

    Chapter 5-##

  • 8/18/2019 Ch05 Proj Plan

    24/41

    Inter$ace Coordination through

    Integration Management

     The most dicult aspect of implementing aproject is the coordination and integrationof the various elements of the project

     The intricate process of coordinating thewor, and timing of all inputs is calledintegration management 

    Interface coordination is used to denotethe process of managing this wor, acrossmultiple groups

    Chapter 5-#(

  • 8/18/2019 Ch05 Proj Plan

    25/41

    Approaches to Inter$ace

    Management

    9ecent wor, on managing the interfacefocuses on the use of multifunctionalteams 2ET3

     There is general agreement that ET has afavorable impact on product*service designand delivery

    $uccessfully involving cross-functional teamsin project planning re+uires that somestructure be imposed on the planning process

    Chapter 5-#.

  • 8/18/2019 Ch05 Proj Plan

    26/41

    Approaches to Inter$ace

    Management

    " diBerent attac, on the problem is de!ningand mapping all interdependencies betweenthe various members of the project team

    9ather than mapping interfaces on the !rmsorganiational chart% instead it maps theinterdependencies directly

    oes not ignore the value of the @'$% action plan% or

    6)9T*C6E networ,s% but simply uses interface mapsas a source of the coordination re+uirement tomanage the interdependencies

    Chapter 5-#5

  • 8/18/2019 Ch05 Proj Plan

    27/41

    Summary

     The preliminary wor, plans are important

    because they serve as the basis for personnel

    selection% budgeting% scheduling and control  Top management should be represented in the

    initial coordinating meeting where technical

    objectives are established% participant

    responsibility is accepted% and preliminary

    budgets and schedules are de!ned

    Chapter 5-#0

  • 8/18/2019 Ch05 Proj Plan

    28/41

    Summary

    Common elements of the project plan are the

    overview% statement of objectives% general

    approach% contractual re+uirements%

    schedules% budget% cost control procedures%

    evaluation procedures% and potential problems

    $ystem integration concerns the smooth

    coordination of project systems in terms of

    cost% performance% and eBectiveness

    Chapter 5-#

  • 8/18/2019 Ch05 Proj Plan

    29/41

    Summary

     The wor, brea,down structure 2@'$3 relates the

    details of each subtas, to its tas, and provides

    the !nal basis !r the project budget% schedule%

    personnel% and control

    @hen multifunctional teams are used to plan

    complex projects their wor, must be integratedand coordinated& Interface maps are a useful

    way of identifying the interdependencies that

    must be managedChapter 5-#4

  • 8/18/2019 Ch05 Proj Plan

    30/41

    Project Planning

    FuestionsG

    Chapter 5-#7

  • 8/18/2019 Ch05 Proj Plan

    31/41

    Project Planning

    6icture ?iles

  • 8/18/2019 Ch05 Proj Plan

    32/41

    Project Planning

    Figure 5-1

  • 8/18/2019 Ch05 Proj Plan

    33/41

    Project Planning

    Figure 5-2

  • 8/18/2019 Ch05 Proj Plan

    34/41

    Project Planning

    Figure 5-4

  • 8/18/2019 Ch05 Proj Plan

    35/41

    Project Planning

    Figure 5-6

  • 8/18/2019 Ch05 Proj Plan

    36/41

    Project Planning

    Figure 5-11

  • 8/18/2019 Ch05 Proj Plan

    37/41

  • 8/18/2019 Ch05 Proj Plan

    38/41

    Project Planning

     Table ?iles

  • 8/18/2019 Ch05 Proj Plan

    39/41

    Project Planning

  • 8/18/2019 Ch05 Proj Plan

    40/41

    Project Planning

  • 8/18/2019 Ch05 Proj Plan

    41/41

    Copyright H #888 ohn @iley J $ons% Inc& "ll rightsreserved& 9eproduction or translation of this wor,beyond that permitted in $ection 11 of the 170