Upload
phamthien
View
215
Download
0
Embed Size (px)
Citation preview
ADDENDUM
Bid No.: 7584 Addendum No.: 3 Issued: March 6, 2018 Opening Date and Time: March 21, 2018 at 2:00 P.M. Title: Rehabilitation of Bridge No. 04745 Pleasant Street Over Yantic River, F.A.P. #6103(009). State Project No. 103-270 Bidders Note: This addendum is issued to accomplish the following: 1. Revise the Special Provisions for Item #5210003A – Bearing Replacement with Elastomeric Bearing Pads. 2. Add to the Special Provisions new Item #0904990A – Metal Bridge Rail, which replaces original Item #0904990 – Metal Bridge Rail (which had no associated Special Provision). 3. Provide a new Schedule of Prices, which has been updated to reflect replacement of the original Item #0904990 with new Item #040990A, in accordance with 2. Above. All other terms and conditions remain the same.
City of Norwich
Department of Finance – Purchasing Agent Phone: (860)823-3706 100 Broadway, Room No. 105 Fax: (860)823-3812 Norwich, CT 06360 E-mail: [email protected]
Note:
Item Approximate Amounts
Numbers Items Units Quantities Figures Words (Figures)
0020903A Lead Compliance for Miscellaneous Exterior Tasks l.s. 1
0201001 Clearing and Grubbing l.s. 1
0201214A Reset Sign ea. 3
0202000 Earth Excavation c.y. 55
0202100 Rock Excavation c.y. 5
0202452A Test Pit ea. 1
0202512A Cut Concrete Sidewalk l.f. 5
0202529 Cut Bituminous Concrete Pavement l.f. 210
0209001 Formation of Subgrade s.y. 90
0212000 Subbase c.y. 30
0219001 Sedimentation Control System l.f. 282
0304002 Processed Aggregate Base c.y. 20
0305000 Processed Aggregate ton 30
0406171 HMA S0.5 ton 106
0406173 HMA S0.25 ton 23
0406236 Material for Tack Coat gal. 45
0406272A Milling of Bituminous Concrete (0" to 4") s.y. 310
0503151A Removal of Superstructure (Site No. 1) l.s. 1
0503887A Jacking Existing Superstructure (Site No. 1) l.s. 1
0511203A Polyvinyl Chloride Plastic Pipe Weepholes ea. 2
0520036A Asphaltic Plug Expansion Joint System c.f. 23
0521003A Bearing Replacement with Elastomeric Bearing Pads ea. 16
0522178A Construct Concrete Keeper Blocks ea. 3
0601070A Class "S" Concrete c.y. 1
0601097A Variable Depth Patch c.f. 2
0601201A Class ''F'' Concrete c.y. 175
0602006 Deformed Steel Bars - Epoxy Coated lb. 27,500
0707009A Membrane Waterproofing (Cold Liquid Elastomeric) s.y. 401
0811001 Concrete Curbing l.f. 40
0814008 Reset Granite Stone Transition Curbing l.f. 39
0815001 Bituminous Concrete Lip Curbing l.f. 90
0822001 Temporary Precast Concrete Barrier Curb l.f. 100
0904990A Metal Bridge Rail l.f. 245
0910173 R-B 350 Bridge Attachment - Vertical Shaped Parapet ea. 3
0910300 Metal Beam Rail (R-B Mash) l.f. 170
0911923 R-B End Anchorage - Type I ea. 2
0911924 R-B End Anchorage - Type II ea. 1
0912503 Remove Metal Beam Rail l.f. 260
0921001 Concrete Sidewalk s.f. 109
0921005 Concrete Sidewalk Ramp s.f. 35
0921039 Detectable Warning Strip ea. 1
0944000 Furnishing and Placing Topsoil s.y. 50
0950019A Turf Establishment - Lawn s.y. 50
0969060A Construction Field Office, Small mo. 8
0970006 Trafficperson (Municipal Police Officer) (Estimated Cost) est. 1 15,000.00$ Fifteen Thousand Dollars and No Cents 15,000.00$
0971001A Maintenance and Protection of Traffic l.s. 1
0975004 Mobilization and Project Closeout l.s. 1
0976002 Barricade Warning Lights - High Intensity day 1,000
0979003 Construction Barricade Type III ea. 16
0980001 Construction Staking l.s. 1
1208932 Sign Face - Sheet Aluminum (Type IV Retroreflective Sheeting) s.f. 16
1210102 4" Yellow Epoxy Resin Pavement Markings l.f. 500
1210105 Epoxy Resin Pavement Markings, Symbols and Legends s.f. 150
1220027 Construction Signs s.f. 330
1803060A Type B Impact Attenuation System (Non-Gating) ea. 1
BID OPENING DATE: ________________________________________________________________ TIME: _______________________________ NO BIDS WILL BE ACCEPTED AFTER _________________________________ "NO EXCEPTIONS"
Kindly insert here the total amount of your Bid $ _ _ _ _ _ _ _ _ _ _ _ _
It is understood that the unit prices shall govern in case of discrepancy between the unit-prices and this amount.
This bid includes Addendum(a) No(s).: 1, 2 and 3
CITY OF NORWICH
SCHEDULE OF PRICES
FOR THE CONSTRUCTION OF
STATE PROJECT NO. 103-270, FA #6103(009)
Unit Prices Bid
The bidder shall fill in, under the column "Unit Prices Bid," the unit prices, written in figures and in words, for which he proposes to perform the various items of work called for, and under the column headed "Amounts," the total amount for each of the
items at the unit price bid. After the proposal is opened and read, the quantities will be extended and totaled in accordance with the bid prices written in words and the bid will be verified or corrected.
REHABILITATION OF BRIDGE NO. 04745
PLEASANT STREET OVER YANTIC RIVER
IN THE
CITY OF NORWICH
B.
D.
E.
G.
H.
A Contract will not be awarded until the above requirements have been fulfilled and approved.
Please be aware that the City, prior to awarding the Contract, may require further financial and other information from the the low bidder.
Proposal Guaranty (Bid Bond): Except when otherwise specified, no proposal will be considered unless accompanied by a proposal guaranty in the form of a bond furnished by a surety
company, satisfactory to the Engineer, in an amount equal to at least 30% of the amount of the bid, or unless the bidder has on file with the City, an annual bid bond in the proper amount.
The surety must be a corporate surety licensed to sign surety bonds in the State of Connecticut.
A.
F. Statement of Bidder's Qualifications: Each bidder is required to submit to the City a recent sworn statement of the bidder's qualifications on the form furnished by the City for this purpose.
The low bidder is required to submit to the City, on or before the signing of the Contract, both a Certificate of Insurance and a Workers' Compensation Certificate.
This bid includes Addendum(a) No(s).: 1, 2 and 3
CONTRACT TIME AND LIQUIDATED DAMAGES:
One Hundred Forty-six (146) calendar days will be allowed for completion of all work as described in the contract documents for Federal Project No. 6103(009), State Project No. 103-270, and theliquidated damages charge to apply will be Two Thousand One Hundred Dollars ($2,100.00) per calendar day.
PRIME CONTRACTOR'S REQUIREMENTS:
Not less than 13% of the total Contract value shall be subcontracted to, performed by, and paid to Disadvantaged Business Enterprise(s) (DBE).
Kindly insert here the total amount of your Bid $ _ _ _ _ _ _ _ _ _ _ _ _
It is understood that the unit prices shall govern in case of discrepancy between the unit-prices and this amount.
C. If the Contractor is unable to fulfill the DBE percentage requirement, he may request an exception to the above percentage by completing and submitting to the City, the "Application for
Review of Pre-award Good Faith Efforts," as contained in the General Special Provisions.
Contractors must ensure that, at the time of bidding, they have an approved Affirmative Action Plan on file with the State of Connecticut, Department of Transportation.
CITY OF NORWICH
SCHEDULE OF PRICES
FOR THE CONSTRUCTION OF
STATE PROJECT NO. 103-270, FA #6103(009)
REHABILITATION OF BRIDGE NO. 04745
PLEASANT STREET OVER YANTIC RIVER
IN THE
CITY OF NORWICH
BID OPENING DATE: ________________________________________________________________ TIME: _______________________________ NO BIDS WILL BE ACCEPTED AFTER _________________________________ "NO EXCEPTIONS"
Rev. 02-27-18
ITEM #0521003A
103-270 ADDENDUM NO. 3
ITEM #0521003A - BEARING REPLACEMENT WITH ELASTOMERIC
BEARING PADS
Description: Work under this item shall consist of the removal and disposal of existing bearing assemblies,
furnishing and installing new elastomeric bearing pads and sole plates, and removal of existing
galvanized coating from the bottom flange at the bearing location so as to install the new sole
plates, removal of the hot dipped galvanized coating from the new sole plates to complete field
welding and applying a coat of zinc rich primer over the field welds, in accordance with the plans
and these specifications, and as directed by the Engineer. Contractor is alerted to the presence of lead wool within the slotted holes of the existing bearing
masonry plate. The handling and disposal of lead wool encountered during the bearing
replacement work shall be performed in accordance with the special provisions for
Item #020903A - Lead Compliance for Miscellaneous Exterior Tasks. Materials:
1. Elastomer: The elastomeric compound used in the construction of the bearings, shall
contain only virgin polychloroprene (Neoprene) as the raw polymer. It shall conform to the
requirements of Section 18.2 of the AASHTO LRFD Bridge Construction Specifications and
AASHTO M 251. The elastomer shall be low-temperature Grade 3 as defined by ASTM D
4014.
Each steel-laminated elastomeric bearing shall have marked on it, with indelible ink, the
following: the Manufacturer's identification code or symbol, the month and year of
manufacture, the orientation, order number, lot number, bearing identification number, and
elastomer type and grade (Neoprene, Grade 3). The markings should be placed on a side of
the bearing that is visible after installation.
The Contractor shall furnish test bearings in addition to the bearings shown on the plans for
each type (size and thickness) of bearings for destructive testing. The furnished test bearings
shall not include sole plates or load plates.
The Contractor shall furnish a Certified Test Report, confirming that the elastomeric bearings
satisfy the requirements of these specifications, in conformance with the requirements set forth
in Article 1.06.07. 2. Steel Laminae: The internal steel laminae shall conform to the requirements of ASTM A
1011 Grade 36. The internal steel laminae edges shall be ground smooth or otherwise
rounded before molding the bearing. 3. Steel Sole Plates: Steel sole plates shall conform to the requirements of AASHTO M270,
Grade 36 and Article M.06.02 and shall be galvanized to meet the requirements of ASTM A123.
Rev. 02-27-18
ITEM #0521003A
103-270 ADDENDUM NO. 3
Adhesive bonding of the elastomer portion of the bearings to the external steel plates or
concrete is not permitted. 4. Elastomeric Shims: The elastomer for shims shall conform to the same requirements as the
bearing elastomer and be 1/16 inches and 1/8-inches thick. 5. Adhesive: The adhesive for bonding the shims shall consist of a long lasting, high strength,
cold applied, air cured, water and heat resistant material specifically formulated for bonding
neoprene and shall meet the following requirements:
Property Requirement ASTM Test Procedure
Adhesion 30 # per inch D 429, Method B
Hardness 50 ± 5 Shore A points D 2240
Tensile Strength, min. 1,800 psi D 412
Elongation before breaking, min. 750% D 412
6. Non-Shrink Grout: Non-shrink grout shall conform to Sub-Article M.03.01-12. Construction Methods: The Contractor shall notify the Engineer before submitting shop drawings if, after taking
field measurements of the existing bearing assembly height, it is determined the proposed sole
plate thickness will be less than the minimum value shown on the plans. The Contractor shall submit shop drawings to the Engineer, for review and approval, in
accordance with Article 1.05.02. These drawings shall include but not be limited to the
following information: Manufacturer's name, complete details of the bearings, material
designations, nominal hardness of the elastomer, the quantity of bearings required, including test
bearings, and the location of the bearing identification. A minimum of thirty (30) days prior to the installation of the elastomeric bearings, the
Contractor shall deliver to the job site, the required number of bearings for installation plus the
required number of test bearings. The Contractor shall pack the bearings in containers
holding no more than 10 bearings. Bearings in one container shall contain the same type and
size of bearing required for one structure only. The Contractor shall mark the container with the
project number, the bridge number, the number of bearings, the intended location on the
structure, the name of the Manufacturer, and the lot number. The Contractor shall remove the
existing bearing assemblies using methods that do not damage them or the existing beam.
Existing welds shall be removed by machining, grinding, chipping, or air carbon-arc gouging,
and in such a manner that the remaining base metal is not wicked or undercut. A minimum of
1/8 inch of weld metal shall be left in place if arc gouging is the selected removal method
and the remaining weld metal shall be removed by grinding. Welders who perform arc gouging
shall be SMAW certified. Use of flame cutting equipment to cut the anchor bolts is not
allowed. The Contractor shall remove the bolts by sawing the anchor bolt unless another
method is approved by the Engineer. The Contractor shall grind smooth the portion of welds
remaining after removal of the existing sole plate.
Rev. 02-27-18
ITEM #0521003A
103-270 ADDENDUM NO. 3
Lead wool present in the slotted holes of the existing bearing masonry plate shall be handled as
stated in the special provisions for Item #020903A - Lead Compliance for Miscellaneous
Exterior Tasks.
The Engineer will inspect the concrete bearing pads before the installation of the elastomeric
bearings. Portions of protruding anchor bolts shall be cut off below the surface of the concrete
and the holes filled in with non-shrink grout. All other cracks, spalls, or deterioration shall
be repaired as ordered by the Engineer.
The concrete bearing pads shall have smooth, even and level surface. They shall show no
variation from a true plane greater than 1/16 inches over the entire area upon which the
elastomeric bearings are to rest. The Contractor shall grind the concrete as required to achieve
these requirements.
Before installing the elastomeric bearings, the Contractor shall clean the concrete bearing pad of
dirt, grease, oil or other foreign material.
The Contractor shall install the elastomeric bearings as shown on the plans. The Contractor shall
install the elastomeric bearings when the superstructure surface temperature of the second
interior girder and the exterior girder is between 40º F to 80º F, and has been within this range
for at least 2 hours. The superstructure surface temperature shall be determined from the average
of three (3) or more surface temperature readings taken at different locations on the girder
surfaces by the Contractor, as directed by the Engineer. The difference between the average
surface temperature of the exterior girder and second interior girder shall be less than 10º F.
Temperature measurements of the superstructure shall be taken by the Contractor with a
calibrated hand-held digital infrared laser-sighted thermometer on the surfaces of the interior
steel girder, or interior concrete girder protected from direct sunlight. The infrared thermometer
to be supplied by the Contractor for this purpose shall meet certification requirements of
EN61326-1, EN61010-1, and EN60825-1, maintained by the European Committee for
Electrotechnical Standardization (CENELEC). The thermometer shall have a minimum
distance-to-spot ratio of 50:1, and shall have adjustable emissivity control. The thermometer
shall have a minimum accuracy level of ±1% of reading or ±2º F, whichever is greater. The
thermometer shall be used in strict accordance with the manufacturer's written directions. An
additional infrared thermometer satisfying the same standards to be used in this application shall
also be provided to the Engineer for quality assurance purposes.
Welding with the elastomeric bearings in place will not be permitted unless there is more than
1½ inches of steel between the weld and the elastomer. In no case shall the elastomer be
exposed to temperatures greater than 400º F. Temperature Indicating Crayons shall be used
during field welding to ensure that these temperature restrictions are not exceeded.
Welding details, procedures and testing methods shall conform to the latest ANSI/AASHTO/
AWS D1.5: Bridge Welding Code, unless otherwise noted.
Rev. 02-27-18
ITEM #0521003A
103-270 ADDENDUM NO. 3
The Contractor's welding and inspection procedures for each type of field weld and field tacking
must be submitted to the Engineer on the form designated by the Department. All procedures
must be approved by the Division Chief of Material Testing prior to any work and must be
adhered to at all times.
Quality control is the responsibility of the Contractor. The Contractor must provide an AWS
Certified Welding Inspector (CWI) in accordance with AWS D1.5. The CWI must be qualified
and certified in accordance with the provisions of AWS Q1, Standard for Qualification and
Certification of Welding Inspectors.
The CWI shall make a visual inspection of all welds. The Contractor will perform magnetic
particle inspection, ultrasonic testing inspection, or radiographic testing inspection of field welds
if required on the plans. Each test must be witnessed by an authorized representative of the
Engineer.
Welds or sections of welds containing imperfections determined to be unacceptable by either the
CWI or the Engineer shall be removed and re-welded by the Contractor at his expense. Welds so
removed and replaced shall be reinspected by the CWI. All costs for reinspection or testing of
such welds shall be borne by the Contractor.
Upon completion of the field welding and inspection of the welds between the girder bottom
flange and the bearing sole plate, the Contractor shall grind the welded surface smooth and
remove any protrusions or burrs from the welds and apply a coat of zinc rich primer over the
field welds and neighboring surfaces. Repair and touch-up of damaged galvanized steel surfaces
shall be performed in accordance with ASTM A780.
The elastomeric bearings shall rest uniformly on the concrete bearing pads when the bearings are
under the full dead load of the superstructure. If uniform contact is not present, the
Contractor shall fill the gaps beneath the bearing by inserting elastomeric shims that are slightly
thinner than the gaps. The Contractor, in the presence of the Engineer, shall measure the gaps
to determine the locations and sizes of the shims.
The Contractor shall bond the individual shims to the elastomer portion of the bearing with
adhesive applied over the entire shim interface. The surface preparation, application and curing
of the adhesive shall comply with the Manufacturer's recommendations. If shims in excess of
1/8 inch are required, bonding of multiple shims is permitted. In areas that vary in thickness, the
Contractor shall shim by stepping shims.
The Contractor shall provide the Engineer with safe access to the work for inspection purposes.
Method of Measurement:
This work shall be measured for payment by the actual number of elastomeric expansion
bearings installed and accepted. Test bearings will not be measured for payment.
Rev. 02-27-18
ITEM #0521003A
103-270 ADDENDUM NO. 3
Basis of Payment:
This work shall be paid for at the Contract unit price each for "Bearing Replacement with
Elastomeric Bearing Pads" complete, in place and accepted, which price shall include obtaining
field measurements, non-shrink grout, vulcanizing, removal of existing galvanized coating, sole
plates, galvanizing of sole plates, application of zinc rich primer, test bearings, shims, adhesive,
furnishing and installing elastomeric bearings, disposal of the existing bearings, cutting existing
anchor bolts, field welding, furnishing and installing steel plates, and all materials, equipment,
tools, labor and work incidental thereto.
Pay Item Pay Unit
Bearing Replacement with Elastomeric Bearing Pads Ea.
02/27/18
ITEM #0904990A
103-270 ADDENDUM NO. 3
ITEM #0904990A – METAL BRIDGE RAIL
Description: Work under this item shall consist of fabricating and installing a steel open bridge railing,
consisting of steel wide flange shapes for posts and steel rectangular tube shapes for rails, as
shown on the plans or as directed by the Engineer and in accordance with this specification. Materials: Materials for this work shall conform to the following requirements:
The steel rails shall be fabricated from structural steel tubing meeting the requirements of
ASTM A500, Grade B and meeting the longitudinal CVN requirements of 15 ft-lbs. at
0 degrees Fahrenheit.
Rail posts, shims, plates and other shapes shall be fabricated from steel meeting the
requirements of AASHTO M270, Grade 50.
All posts, railing, rail splices, shims, base plates and other shapes shall be galvanized after
fabrication in conformance with ASTM A123 and powder coated with a duplex coating
system.
Button head and domed hex head bolts, embedded threaded rods, deflected thread-type lock
nuts, washers and cap screws shall conform to the requirements of ASTM A307.
Bolts, deflected thread-type lock nuts and washers for splices shall conform to the
requirements of ASTM A307.
All hardware, including bolts, threaded rods, lock nuts, nuts, cap screws and washers shall be
galvanized in conformance with ASTM A153.
Anchor plates shall conform to the requirements of AASHTO M270, Grade 50 and shall be
galvanized in conformance with ASTM A123.
Molded pads shall be manufactured from new un-vulcanized elastomer and unused synthetic
fibers, with a weight proportion of fiber content equal to approximately one-half of the total
weight of the pad. The pads shall be formed into single sheets of 1/8-inch minimum
thickness, with a tolerance of plus or minus 10 percent. Pads shall have a shore 'A' Durometer
hardness within the range of 70 to 90, and shall have a minimum compressive breakdown of
7,000 psi.
Chemical anchoring material shall conform to M.03.07.
The Contractor shall furnish a Materials Certificate in conformance with the requirements of
Article 1.06.07 for the following materials: rail posts, rails, post connection devices, rail
splices, preset anchorages, bolts, nuts, washers and molded pads.
02/27/18
ITEM #0904990A
103-270 ADDENDUM NO. 3
Construction Methods:
Before fabricating any materials, the Contractor shall submit shop drawings to the Engineer for
approval in accordance with Subarticle 1.05.02-3. These drawings shall include but not be
limited to the following information: a layout plan showing post spacing, rail to post
connections, anchorage details, expansion joint locations, material designations and the name
and telephone number of a person to contact who can answer questions about the shop drawings.
Repair of damaged galvanized steel surfaces shall be in accordance with ASTM A780.
Welding details and procedures shall conform to AWS D1.1 - Structural Welding Code - Steel.
See the contract drawings for rail post layout and spacing.
The posts shall be fabricated and installed plumb. If required, steel shims shall be installed to
plumb the posts. One 1/8" and two 1/16" steel shims shall be provided for 25% of the posts.
The shims shall be the same dimensions as the base plate.
The rails and the holes in the posts shall be constructed parallel to the roadway. Holes may be
field drilled in rails. All field-drilled holes shall be coated with an approved zinc rich paint
before erection.
The rails shall be carefully adjusted prior to fixing in place to ensure proper matching at abutting
joints and correct alignment and curvature throughout their length.
Lengths of rails shall be sufficient to be attached to at least two rail posts.
After installation, all rails and posts shall be free of burrs, sharp edges and irregularities.
Method of Measurement:
This work will be measured for payment by the actual number of linear feet of open bridge rail
completed and accepted, measured along the rail from one rail end anchorage to the other rail
end anchorage.
Basis of Payment:
This work will be paid for at the contract unit price per linear foot for "Metal Bridge Rail”,
complete and accepted in place, which price shall include all materials, anchorages, coatings,
equipment, tools, labor and work incidental thereto.
Pay Item Pay Unit
Metal Bridge Rail L.F.