21
Clamp Prototype Install and Schedules RIKEN/RBRC Itaru Nakagawa

Clamp Prototype Install and Schedules

  • Upload
    jacie

  • View
    17

  • Download
    0

Embed Size (px)

DESCRIPTION

Clamp Prototype Install and Schedules. RIKEN/RBRC Itaru Nakagawa. APR. Deadline : Feb. 8. Muon Arm Upgrade for W boson Detection ( 含む Absorber effect 、 S/N) - ラルフ - PowerPoint PPT Presentation

Citation preview

Page 1: Clamp Prototype Install and Schedules

Clamp Prototype Install and Schedules

RIKEN/RBRCItaru Nakagawa

Page 2: Clamp Prototype Install and Schedules

APR

• Muon Arm Upgrade for W boson Detection ( 含む Absorber effect 、 S/N) - ラルフ

• Muon Trigger Performance (efficiency w/ cosmic 等 Run10 データ解析) - 深尾- MuTr Cross Talk and Recapacitation effect - 今津- Recap clamp R&D - ケンタロー、中川

Deadline : Feb. 8

Page 3: Clamp Prototype Install and Schedules

Clamp Schedule

2010 2011

12 1 2 3 4 5 6 7 8 9 10

Dry Air Cover Install

Prototype-1 Delivery

DeliveryInstall & Test50 more

Clamps

300 Clamps

Delivery

Install

Supply Parts

Page 4: Clamp Prototype Install and Schedules

Road To Be Approved Clamp Install

• Evaluate X-Talk Quench Effect (Jan) -> Tsutomu’s Code

• Prove HV Performance (~July)• Budget• Production Schedule to be fit in by End of

October• Scaffold Construction

Page 5: Clamp Prototype Install and Schedules

Cramp Production Schedule• 60 個(2ヶ月)– 発注:4月末  -> 納品6月末

• 320個(2〜4ヶ月?)– 発注 : 6月〜8月 -> 納品9月+10月末(分納)– インストール4〜8週間

Bottom Line6月のパフォーマンスを確認後プロダクションへ(遅くて7月第一週)

部品調達2〜3週間を6月中に依頼すれば間に合うかも?クランプ取り付けのユーティリティーは満足できるレベル。プリント基板は Fix でよいか?基盤の製作を前倒しすればさらに speed up 。変更の可能性がある部分は•プローブ(ピン/ゴム)•コーティング剤の材質や塗り方?•電圧読み出しプローブ

Page 6: Clamp Prototype Install and Schedules

Octant-8 Clamp Install

Octant 8

38103810

38103811

38113811

38123812

38133813

1-pin type

4-pin type

Page 7: Clamp Prototype Install and Schedules

Installed Clamps (Octant-8)

Page 8: Clamp Prototype Install and Schedules

Octant-7 Clamp Install

Octant 7

37103710

37103711

37113711

37123712

37133713

Conductive Rubber type

Dead in Run9Wire 192-223But fixed in Run10

Page 9: Clamp Prototype Install and Schedules

Installed Clamps (Octant-7)

Page 10: Clamp Prototype Install and Schedules

Clamp Prototype Install Summary

• 3 types of clamps (3 each are installed to North Station-3, Octant-7 and 8, Gap-0.

• Nearly 100% electrical contacts were achieved by the clamps without removing coating. -> Clamp works well!

• Will test with HV up to 1.5k with Ar/Co2 gas this week before closing the hatch.

• Observing relieved cross talk effect may be difficult because of partial coverage (only 30% of all anode wires in Oct-8, 15% in Oct-7).

Page 11: Clamp Prototype Install and Schedules

Improving HV performance

1. Better Coating2. Dry air cover to Station-3

1. need to evaluate cost-effectiveness2. Can be kept as back up if the prototype clamps

behave poorly against HV

Page 12: Clamp Prototype Install and Schedules

coating

• Turned out present anodes are mostly exposed to air. The existing coating is not isolating HV circuit from air well.

• Redo coating with higher viscosity type

Page 13: Clamp Prototype Install and Schedules

Dry Air Cover Support

Page 14: Clamp Prototype Install and Schedules

Dry Air Cover • Mechanical Design by REPIC

• First 2~3 Prototypes Delivery by Dec.28?

• Install in Maintenance Day

Dry Air Line Available @Oct8

Page 15: Clamp Prototype Install and Schedules

Expert Shift MuTrig-FEE Please Sign Up!

your_ccount@rcf2:/phenix/WWW/run/11/contacts/mutrg_experts.html Edit by Yourself

Page 16: Clamp Prototype Install and Schedules

Expert Shift MuTrPlease sign up!

Page 17: Clamp Prototype Install and Schedules

Muon Trigger Event Display

Developed by TsutomuShould Add RPC?

Page 18: Clamp Prototype Install and Schedules

Task List• Run Plan

– Special Data Taking– Low B-field (Yoshi) – Zero suppression off run (different luminosity?) How many statistics needed?– MuTr HV Scan (Cosmic/Beam?)

• Dump Important parameters into Database (Yoshi+Katsuro) • Threshold, Latency, BCLK window, Logic, (Delta_s?, LUT?)

• Optimization of Parameters (Yoshi+Katsuro+Itaru)– Threshold .vs multiplicity– Logic– BCLK Window

• Low Level Online Monitor (Katsuro)• Stability monitor (Seoul)

• Low Level• Physics (J/psi) mass width, position, S/N, etc…

• Semi-Online Track Monitoring (Yoshi?)– Rejection power .vs rate– Efficiency .vs rate – Efficiency map

Page 19: Clamp Prototype Install and Schedules
Page 20: Clamp Prototype Install and Schedules
Page 21: Clamp Prototype Install and Schedules